This is the third and final Progress Report to the Board of Executive Directors (the Board) on the implementation of the Management Action Plan (MAP) in response to the Inspection Panel Investigation Report...
On November 13, 2014, a request for inspection, submitted by members and representatives of a Maasai community that was resettled due to the project-supported geothermal developments in the Greater Olkaria...
The Electricity Expansion Project of Kenya had a moderately satisfactory outcome, a moderately satisfactory performance by the Bank and the monitoring and evaluation quality was substantial. The lessons...