The outcome of the Cash Crop Development Project for Nepal was unsatisfactory. The project did not achieve its main objectives, its impact has been modest, sustainability is unlikely, and both the Bank and Borrower performed unsatisfactorily. Several lessons can be learned from this project. First, in project design, complex institutional arrangements should be avoided to minimize problems of project coordination, management, and monitoring. Second...
Vea más
INFORMACIÓN
-
1991/06/14
-
Informe de terminación de proyecto
-
9659
-
1
-
1
-
2010/06/18
-
Disclosed
-
Nepal - Cash Crop Development Project
-
surface water irrigation system