Lao - First Phase of the Rural Electrification Project (Inglés)

Ratings for the Rural Electrification Project for Lao were as follows: outcomes were satisfactory, global environment objectives (GEO) were satisfactory, risk to development outcome was moderate, risk to GEO outcome was moderate, Bank performance was satisfactory, and Borrower performance was moderately satisfactory. Some lessons learned include: Government of Laos (GoL) has played an irreplaceable role in terms of making unwavering commitment, getting...