The objective of the Second Transmission and Distribution Project is to contribute to the Government of Vietnam (GOV) poverty alleviation program in the rural areas by providing basic infrastructure services i.e. electricity. Negative impacts of the project: permanent land acquisition, permanent impact on houses, structures, crops, and other assets. Mitigation measures include: 1) acquisition of land and other assets, and resettlement of people will...
Vea más
INFORMACIÓN
-
2010/11/02
-
Plan de reasentamiento
-
RP862
-
3
-
2010/12/22
-
Disclosed
-
Resettlement plan for Thap Cham 220kV substation and connecting branches
-
land area