The principal ratings for the Argentina National Highways Rehabilitation and Maintenance Project are as follows: the outcome was moderately satisfactory, the risk to development outcome was moderate, the Bank performance was satisfactory, and the borrower performance was moderately satisfactory. Some of the lessons learned from the project include the following: performance-based contracts for road maintenance, such as the CREMA contracts, are an...
Vea más
INFORMACIÓN
-
2007/07/01
-
Informe de evaluación de proyecto
-
40154
-
1
-
1
-
2004/10/03
-
Disclosed
-
Argentina - National Highways Rehabilitation and Maintenance Project
-
vehicles per day