Indonesia - Dam Safety Project (Inglés)

Ratings for the Dam Safety Project in Indonesia were as follows: outcomes were moderately unsatisfactory, the risk to development outcome was moderate, the Bank performance was moderately satisfactory, and the borrower performance was also moderately satisfactory. Some lessons learned included: 1) to sustain outcomes in a situation where new concepts and processes are introduced, the focus on institutional development needs to be maintained...