Lesotho - Second Phase of Water Sector Improvement Adaptable Program Loan Project : Metolong Dam and Water Supply : Lesotho - Second Phase of Water Sector Improvement Project (Inglés)

Ratings for the Second Phase of Water Sector Improvement Adaptable Program Loan Project: Metolong Dam and Water Supply for Lesotho were as follows: outcome and Bank performance was moderately satisfactory and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: the importance of tertiary lines, that is, those transmission lines that branch out from main conveyance lines and connect rural households, should be...