Arab Republic of Egypt : Integrated Irrigation Improvement and Management Project and Farm-Level Irrigation Modernization Project (Inglés)

Ratings for the Integrated Irrigation Improvement and Management Project are as follows: Outcome was moderately satisfactory, Risk to development outcome was modest, Bank performance was moderately satisfactory, and Borrow performance was moderately satisfactory. Ratings for the Farm-Level Irrigation Modernization Project are as follows: Outcome was moderately satisfactory, Risk to development outcome was modest, and Bank performance was moderately...
Vea más

INFORMACIÓN

  • 2022/07/05

  • Informe de evaluación de proyecto

  • 173462

  • 1

  • Arab Republic of, Egipto, República Árabe de,

  • Oriente Medio y Norte de África,

  • 2022/08/19

  • Disclosed

  • Arab Republic of Egypt : Integrated Irrigation Improvement and Management Project and Farm-Level Irrigation Modernization Project