West Bank and Gaza - Electricity Sector Performance Improvement Project (Inglés)

Ratings for the Electricity Sector Performance Improvement Project for West Bank and Gaza were as follows: outcome and Bank performance was satisfactory. Some lessons learned included: a well-structured yet flexible project design can support defined responsibilities between entities and scalable activities such as solar photovoltaic (PV) systems and smart meters deployment. The Bank policy and team have been adaptive in supporting Palestinian Energy...