Ratings for the Energy Efficiency Facility for Industrial Enterprises Project for Uzbekistan were as follows: outcomes were satisfactory, the Bank's performance was satisfactory, and the monitoring and evaluation quality was substantial. Some lessons learned included: setting the result indicators targets is a challenging task and efforts should be made to set them at realistic levels. During project preparation, the teams should conduct analysis...
Vea más
INFORMACIÓN
-
2024/11/20
-
Informe final de ejecución y resultados
-
ICR6469
-
1
-
2024/11/21
-
Disclosed
-
Uzbekistan - Energy Efficiency Facility for Industrial Enterprises Project