Slow disbursement of Public Investments Causes and Key Messages : Policy Note (Inglés)

The note identifies the major causes behind the recent phenomenon of slow disbursement in Vietnam. The emphasis is placed on regulatory and procedural changes that went into effect in and after 2015, when the first notable slowdown in disbursement was observed. The note explores factors that influence the decision making of officials, hence resulting in delay in implementation. Long-standing issues that affect disbursement such as land clearance...
Vea más