Sint Marteen - Sint Maarten Hospital Resiliency and Preparedness Project : Second Additional Financing - Restructuring (Inglés)

The development objective of Second Additional Financing for the Sint Maarten Hospital Resiliency and Preparedness Project is to improve the preparedness and capacity of hospital services in Sint Maarten. This restructuring requires approval for second additional financing to cover a cost over-run of component 1 of the project, resulting from a substantial increase in the costs of construction activities. It also requires to modify project component...
Vea más