Ratings for the Dam Operational Improvement and Safety Project (DOISP) for Indonesia were as follows: outcome was satisfactory, Bank performance was moderately satisfactory, and monitoring and evaluation (M and E) quality was modest. Some lessons learned included: even though the project decided against programmatic loan instruments at the outset, there was a clear intention from the start for follow-on engagement, which allowed the project to incrementally...
Vea más
INFORMACIÓN
-
2024/06/27
-
Informe final de ejecución y resultados
-
ICR6592
-
1
-
2024/07/10
-
Disclosed
-
Indonesia - Dam Operational Improvement and Safety Project (DOISP)