Ratings for the Emergency Electricity Access Project for Yemen were as follows: outcome and Bank performance was satisfactory, and monitoring and evaluation (M and E) quality was substantial. Some lessons learned included: partnership with a United Nation (UN) agency and multilayered responsibility provides effective implementation support and oversight during conflict. Allowing flexibility to address changes in project costing (that is, health facilities)...
Vea más
INFORMACIÓN
-
2023/06/28
-
Informe final de ejecución y resultados
-
ICR6168
-
1
-
2023/07/06
-
Disclosed
-
Yemen - Emergency Electricity Access Project