Ratings for the Public Sector Reform for Results Project for Ghana were as follows: outcome and Bank performance were moderately unsatisfactory, and monitoring and evaluation (M and E) quality was modest. Some lessons learned included: project design should include sufficient lead time for implementation and anticipate delays that the Bank does not have control over. The project was later affected by implementation delays resulting from delays in...
Vea más
INFORMACIÓN
-
2025/02/18
-
Informe final de ejecución y resultados
-
ICR00279
-
1
-
2025/02/18
-
Disclosed
-
Ghana - Public Sector Reform for Results Project