18 months procurement plan based on both LRTF and Counterpart funds I. General 1. Project information: Liberia Cheesemanburg Landfill & Urban Sanitation Program P159961 2. Bank’s approval Date of the procurement Plan : 3. Date of General Procurement Notice: August 16, 2017 4. Period covered by this procurement plan: June 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. In accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. Not expected for the packages of works/goods packages in the procurement plan. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: The CLUS Project July 2017 Procurement Implementation Manual which forms part of Project Implementation Manual (PIM). 5. Any Other Special Procurement Arrangements: Not applicable July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable July 9, 2010 PROCUREMENT Liberia : Cheesemanburg Landfill and Urban Sanitation Project PLAN General Information Country: Liberia Bank’s Approval Date of the Original Procurement Plan: 2017-09-28 2019-12-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159961 GPN Date: 2017-12-19 Project Name: Cheesemanburg Landfill and Urban Sanitation Project Loan / Credit No: / , TF / A5269 Executing Agency(ies): Monrovia City Corporation WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LR-MCC-26882-CW-RFQ / Waste Collection and Request for Single Stage - One Maintenance of Access Road / Post Open - National 67,594.00 77,015.68 Terminated 2017-10-14 2017-12-09 2018-06-07 Disposal Quotations Envelope for Landfill Construction of the MCC-PIU-REF-3 / Drilling Cheesemanburg Regional Single Stage - One of Boreholes at TF / A5269 Post Request for Bids Open - National 100,000.00 0.00 Canceled 2018-02-19 2018-02-24 2018-04-07 2018-05-07 2018-06-11 2018-12-08 Landfill and Partial Closure Envelope Cheesemanburg of the Whein Town Landfill Construction of the MCC-PIU-REF-1 / Cheesemanburg Regional Open - Single Stage - One Construction of TF / A5269 Prior Request for Bids 4,000,000.00 0.00 Canceled 2019-01-14 2019-01-19 2019-03-02 2019-04-01 2019-05-06 2019-11-02 Landfill and Partial Closure International Envelope Cheesemanburg Landfill of the Whein Town Landfill Construction of the MCC-PIU-REF5 / Whein Cheesemanburg Regional Single Stage - One TF / A5269 Post Request for Bids Open - National 250,000.00 0.00 Canceled 2018-12-05 2018-12-10 2019-01-21 2019-02-20 2019-03-27 2019-09-23 Town Permanent Closure Landfill and Partial Closure Envelope of the Whein Town Landfill MCC-PIU-REF-2 / Construction of the Construction of Road Cheesemanburg Regional Single Stage - One TF / A5269 Post Request for Bids Open - National 200,000.00 0.00 Canceled 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 Extension to the Landfill and Partial Closure Envelope Cheesemanburg Community of the Whein Town Landfill Construction of the MCC-PIU-REF-6 / Cheesemanburg Regional Single Stage - One Rehabilitation Works at the TF / A5269 Post Request for Bids Open - National 225,000.00 0.00 Canceled 2018-07-02 2018-07-07 2018-08-18 2018-09-17 2018-10-22 2019-04-20 Landfill and Partial Closure Envelope existing Transfer Stations of the Whein Town Landfill Construction of the LR-MCC-87126-CW-FCA / Cheesemanburg Regional Rehabilitation works at TF / A5269 Post Force Account Direct 23,500.00 11,579.00 Signed 2018-11-28 2018-12-03 2019-01-07 2019-07-06 Landfill and Partial Closure existing Transfer Stations of the Whein Town Landfill LR-MCC-54480-CW-RFB / Construction of the Under Construction of Road Cheesemanburg Regional Single Stage - One TF / A5269 Post Request for Bids Open - National 200,000.00 0.00 Implementati 2019-04-30 2019-05-05 2019-06-16 2019-07-16 2019-08-20 2020-02-16 Extension to Cheesemenburg Landfill and Partial Closure Envelope on Community of the Whein Town Landfill LR-MCC-87128-CW-FCA / Construction of Conerstone and Demarcation line with Construction of the Sandcree Block and Mass Cheesemanburg Regional Concrete arround the 100 TF / A5269 Post Force Account Direct 8,500.00 0.00 Canceled 2018-11-29 2018-12-04 2019-01-08 2019-07-07 Landfill and Partial Closure acres of land for the of the Whein Town Landfill construction of the new Sanitary Lnadfill at Cheesemanburg Page 1 MCC-PIU-REF-4 / Construction of the Construction of perimeter Cheesemanburg Regional Single Stage - One TF / A5269 Prior Request for Bids Open - National 750,000.00 0.00 Canceled 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-02-01 wall at Whein Town Landfill Landfill and Partial Closure Envelope Site( Fencing) of the Whein Town Landfill LR-MCC-86280-CW-RFP / Construction of the Design and Construction of Cheesemanburg Regional Request for Open - Single Stage - Two Under TF / A5269 Prior 4,300,000.00 0.00 2019-10-10 2019-12-26 2019-12-26 2019-10-15 2020-03-05 2020-05-18 2020-06-22 2021-12-14 the Cheesemnburg Regional Landfill and Partial Closure Proposals International Envelope Review Landfill of the Whein Town Landfill MCC-CLUS /WKS-4/08/19 / Construction of the Construction of Perimeter Under Cheesemanburg Regional Single Stage - One Wall-Fence around the TF / A5269 Post Request for Bids Open - National 75,000.00 0.00 Implementati 2019-10-18 2019-10-23 2019-12-04 2020-01-03 2020-02-07 2020-08-05 Landfill and Partial Closure Envelope Sanitary Landfill at the on of the Whein Town Landfill Whein Town GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MCC-PIU-REF-11 / Supply Waste Collection and Single Stage - One / Post Request for Bids Open - National 273,515.00 0.00 Canceled 2017-09-30 2017-10-05 2017-11-16 2017-12-16 2018-01-20 2018-07-19 and Delivery of Fuel Disposal Envelope MCC-PIU-SWM-F-REF-11 / Waste Collection and Supply and Delivery of fuel TF / A5269 Prior Direct Selection Direct 273,515.00 0.00 Canceled 2017-10-09 2017-10-14 2017-11-18 2018-05-17 Disposal for Solid Waste Equipment MCC-PIU-REF-8 / Supply Waste Collection and Open - Single Stage - One and Delivery of Garbage / Prior Request for Bids 2,000,000.00 0.00 Canceled 2017-10-05 2017-10-10 2017-11-21 2017-12-21 2018-01-25 2018-07-24 Disposal International Envelope Collection Equipment LR-MCC-37773-GO-RFB / Waste Collection and Open - Single Stage - One Supply and Delivery of Solid TF / A5269 Prior Request for Bids 2,000,000.00 1,222,978.00 Signed 2017-11-27 2017-12-02 2018-01-13 2018-02-12 2018-03-19 2018-09-15 Disposal International Envelope Waste Collection Equipment LR-MCC-54497-GO-RFB / Construction of the Supply and Delivery of Solid Cheesemanburg Regional Open - Single Stage - One TF / A5269 Prior Request for Bids 1,054,700.00 0.00 Canceled 2018-04-20 2018-04-25 2018-06-06 2018-07-06 2018-08-10 2019-02-06 Waste Collection Equipment Landfill and Partial Closure International Envelope Phase 2 of the Whein Town Landfill LR-MCC-60200-GO-RFQ / Construction of the Supply , Delivery and Cheesemanburg Regional Request for Single Stage - One TF / A5269 Post Open - National 30,000.00 15,800.00 Signed 2018-05-05 2018-06-30 2018-12-27 Installation of GPS Landfill and Partial Closure Quotations Envelope Trackers (System) of the Whein Town Landfill Construction of the MCC-PIU-REF-9 / Purchase Cheesemanburg Regional Request for Single Stage - One TF / A5269 Post Open - National 27,920.00 5,472.50 Signed 2018-10-23 2018-12-18 2019-06-16 of Office Supplies Landfill and Partial Closure Quotations Envelope of the Whein Town Landfill LR-MCC-73837-GO-RFB / Supply and Delivery of Waste Collection and Single Stage - One TF / A5269 Post Request for Bids Open - National 650,000.00 639,265.00 Signed 2018-08-31 2018-09-05 2018-10-17 2018-11-16 2018-12-21 2019-06-19 Solid Waste Collection Disposal Envelope Equiment Phase II MCC-PIU-REF-10 / Waste Collection and Request for Single Stage - One Purchase of Office TF / A5269 Post Open - National 17,920.00 0.00 Canceled 2019-04-02 2019-05-28 2019-11-24 Disposal Quotations Envelope Furniture Page 2 LR-MCC-40785-GO-RFQ / Supply and Delivery of Waste Collection and Request for Single Stage - One Chemicals for the TF / A5269 Post Open - National 10,000.00 0.00 Canceled 2019-07-03 2019-08-28 2020-02-24 Disposal Quotations Envelope Maintenance of Landfill facility MCC-CLUS/GDS-17-08/19 / Motorola for the improvement of Waste Collection and Request for Single Stage - One TF / A5269 Post Open - National 45,000.00 0.00 Canceled 2019-09-28 2019-11-23 2020-05-21 communication in support of Disposal Quotations Envelope Solid Waste Collection and Coordination of Equipment LR-MCC-139692-GO-RFQ / Supply and Delivery of Parts Waste Collection and Request for Single Stage - One for the upgrading of TF / A5269 Post Open - National 60,000.00 0.00 Canceled 2019-10-23 2019-12-18 2020-06-15 Disposal Quotations Envelope Weighbridges at the Transfer Stations and Landfill. LR-MCC-142288-GO-RFQ / Supply and Delivery of Parts Under Waste Collection and Request for Single Stage - One for the upgrading of TF / A5269 Post Limited 60,000.00 0.00 Implementati 2019-10-30 2019-12-25 2020-02-12 Disposal Quotations Envelope Weighbridges at the Transfer on Stations and Landfill NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Construction of the MCC-PIU-REF-14 / Cheesemanburg Regional Single Stage - One Operations and Management / Post Request for Bids Open - National 161,280.00 0.00 Canceled 2017-10-05 2017-10-10 2017-11-21 2017-12-21 2018-01-25 2018-07-24 Landfill and Partial Closure Envelope of Weighbridges of the Whein Town Landfill MCC-PIU-REF-13 / Pushing Waste Collection and Single Stage - One and Compacting Solid Waste / Post Request for Bids Open - National 336,000.00 417,380.28 Terminated 2017-10-03 2017-10-08 2017-11-19 2017-12-19 2018-01-23 2018-07-22 Disposal Envelope at Landfill Construction of the MCC-PIU-REF-12 / Public Cheesemanburg Regional Single Stage - One Awareness and Citizens / Post Request for Bids Open - National 70,000.00 0.00 Canceled 2017-10-30 2017-11-04 2017-12-16 2018-01-15 2018-02-19 2018-08-18 Landfill and Partial Closure Envelope Engagement of the Whein Town Landfill MCC-PIU-REF-15 / Supply Waste Collection and Single Stage - One and Delivery Equipment / Post Request for Bids Open - National 158,400.00 0.00 Canceled 2017-10-06 2017-10-11 2017-11-22 2017-12-22 2018-01-26 2018-07-25 Disposal Envelope Rental Services Construction of the LR-MCC-36212-NC-RFB / Cheesemanburg Regional Single Stage - One Public Awareness and TF / A5269 Post Request for Bids Open - National 70,000.00 0.00 Canceled 2019-07-31 2019-08-05 2019-09-16 2019-10-16 2019-11-20 2020-05-18 Landfill and Partial Closure Envelope Citizens Engagement of the Whein Town Landfill CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Construction of the LR-MCC-36206-CS-CQS / Consultant Cheesemanburg Regional Hydro geological and Geo TF / A5269 Prior Qualification Open - National 190,000.00 322,740.00 Signed 2017-11-20 2017-12-11 2018-01-24 2018-02-23 2018-03-30 2018-09-26 Landfill and Partial Closure technical Investigation Selection of the Whein Town Landfill Page 3 Institutional Capacity Consultant LR-MCC-40764-CS-CQS / TF / A5269 Development and Project Post Qualification Open - National 15,000.00 15,000.00 Signed 2017-12-29 2018-01-19 2018-03-04 2018-04-03 2018-05-08 2018-11-04 Project Financial Audit Management Selection Construction of the Consultant MCC-PIU-REF-27 / Design Cheesemanburg Regional TF / A5269 Post Qualification Open - National 300,000.00 0.00 Canceled 2018-10-26 2018-11-16 2018-12-30 2019-01-29 2019-03-05 2019-09-01 of Cheesemanburg Landfill Landfill and Partial Closure Selection of the Whein Town Landfill MCC-PIU-REF-24 / Construction of the Consultant Supervision of the Cheesemanburg Regional Pending TF / A5269 Post Qualification Open - National 80,000.00 0.00 2019-11-12 2019-12-03 2020-01-16 2020-02-15 2020-03-21 2020-09-17 Chesemanburg Landfil Landfill and Partial Closure Implementation Selection Construction of the Whein Town Landfill MCC-CLUS/CS-16/09/09 / Construction of the Consultant Partial Closure Studies of Cheesemanburg Regional Under TF / A5269 Post Qualification Limited 150,000.00 0.00 2019-09-27 2019-10-11 2019-11-10 2019-12-15 2020-06-12 the Sanitary Landfill at Landfill and Partial Closure Implementation Selection Whein Town of the Whein Town Landfill MCC-CLUS/CS-15/09/19 / Construction of the Feasibility Study for an Consultant Cheesemanburg Regional improved Solid Waste TF / A5269 Post Qualification Limited 100,000.00 0.00 Under Review 2019-10-18 2019-11-01 2019-12-01 2020-01-05 2020-07-03 Landfill and Partial Closure Management Strategies for Selection of the Whein Town Landfill Greater Monrovia INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Construction of the MCC-PIU-REF-23 / Individual Cheesemanburg Regional Cheesemanburg Community / Post Consultant Open 30,000.00 0.00 Canceled 2017-09-30 2017-11-18 2017-12-09 2018-01-13 2018-07-12 Landfill and Partial Closure Liason Officer Selection of the Whein Town Landfill Institutional Capacity Individual MCC-PIU-REF-22 / / Development and Project Post Consultant Open 100,000.00 3,200.00 Terminated 2017-10-03 2017-11-21 2017-12-12 2018-01-16 2018-07-15 Safeguard Officer Management Selection Construction of the Individual MCC-PIU-REF-21 / Civil Cheesemanburg Regional / Post Consultant Limited 39,600.00 0.00 Canceled 2017-10-06 2017-10-11 2017-11-01 2017-12-06 2018-06-04 Engineer Landfill and Partial Closure Selection of the Whein Town Landfill Construction of the Individual MCC-PIU-REF-19 / Cheesemanburg Regional / Post Consultant Limited 27,000.00 0.00 Canceled 2017-10-06 2017-10-11 2017-11-01 2017-12-06 2018-06-04 Procurement Specialist Landfill and Partial Closure Selection of the Whein Town Landfill Construction of the MCC-PIU-REF-20 / Individual Cheesemanburg Regional Administrative and Accounts / Post Consultant Limited 27,000.00 0.00 Canceled 2017-10-06 2017-10-11 2017-11-01 2017-12-06 2018-06-04 Landfill and Partial Closure Officer Selection of the Whein Town Landfill Construction of the Individual MCC-PIU-REF-18 / Project Cheesemanburg Regional / Post Consultant Limited 54,000.00 0.00 Canceled 2017-10-10 2017-10-15 2017-11-05 2017-12-10 2018-06-08 Coordinator Landfill and Partial Closure Selection of the Whein Town Landfill MCC-PIU-REF-25 / Construction of the Individual Hydrogeological and Cheesemanburg Regional / Post Consultant Open 80,000.00 0.00 Canceled 2017-09-29 2017-11-17 2017-12-08 2018-01-12 2018-07-11 Geotechnical Study at Landfill and Partial Closure Selection Cheesemanburg of the Whein Town Landfill Page 4 Institutional Capacity LR-MCC-36777-CS-CDS / TF / A5269 Development and Project Prior Direct Selection Direct 108,000.00 108,000.00 Under Review 2017-06-16 2017-09-26 2017-09-29 2018-03-28 Project Coordinator Management Institutional Capacity LR-MCC-36784-CS-CDS / TF / A5269 Development and Project Prior Direct Selection Direct 54,000.00 54,000.00 Under Review 2017-06-16 2017-09-26 2017-09-29 2018-03-28 Procurement Specialist Management Institutional Capacity MCC-REF-3 / Account TF / A5269 Development and Project Prior Direct Selection Direct 54,000.00 54,000.00 Signed 2017-06-16 2017-09-26 2017-09-29 2018-03-28 Officer Management Institutional Capacity LR-MCC-36791-CS-CDS / TF / A5269 Development and Project Prior Direct Selection Direct 79,200.00 79,200.00 Signed 2017-06-16 2017-09-26 2017-09-29 2018-03-28 Solid Waste Engineer Management Construction of the Individual MCC-PIU-REF-26 / Urban Cheesemanburg Regional TF / A5269 Post Consultant Open 80,000.00 0.00 Canceled 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2018-10-10 Management Studies Landfill and Partial Closure Selection of the Whein Town Landfill MCC-PIU-REF-30 / Construction of the Individual Quarterly Groundwater and Cheesemanburg Regional TF / A5269 Post Consultant Open 75,000.00 16,000.00 Signed 2017-12-28 2018-02-15 2018-03-08 2018-04-12 2018-10-09 Leachate Sampling at the Landfill and Partial Closure Selection Cheesemanburg Landfill of the Whein Town Landfill Construction of the MCC-PIU-REF-32 / Design Individual Cheesemanburg Regional of Road exension to the TF / A5269 Post Consultant Open 10,000.00 13,200.00 Signed 2019-04-15 2019-06-03 2019-06-24 2019-07-29 2020-01-25 Landfill and Partial Closure Cheesemanburg community Selection of the Whein Town Landfill Construction of the Individual MCC-PIU-REF-37 / Cheesemanburg Regional / Post Consultant Open 60,000.00 0.00 Canceled 2018-01-23 2018-03-13 2018-04-03 2018-05-08 2018-11-04 Financial Audits Landfill and Partial Closure Selection of the Whein Town Landfill MCC-PIU-REF-29 / Construction of the Individual Quarterly Groundwater and Cheesemanburg Regional / Post Consultant Open 75,000.00 0.00 Canceled 2018-03-25 2018-05-13 2018-06-03 2018-07-08 2019-01-04 Leachate Sampling at the Landfill and Partial Closure Selection Whein Town Landfill of the Whein Town Landfill LR-MCC-64546-CS-INDV / Institutional Capacity Individual Local Project Consultant for TF / A5269 Development and Project Post Consultant Open 24,000.00 0.00 Canceled 2018-06-14 2018-08-02 2018-08-23 2018-09-27 2019-03-26 the Monrovia City Management Selection Corporation LR-MCC-64548-CS-INDV / Institutional Capacity Individual Legal & Safety Consultant TF / A5269 Development and Project Post Consultant Open 24,000.00 0.00 Canceled 2018-06-19 2018-08-07 2018-08-28 2018-10-02 2019-03-31 for the City of Monrovia Management Selection Construction of the LR-MCC-80461-CS-INDV / Individual Cheesemanburg Regional Under Cheesemanburg Community TF / A5269 Post Consultant Open 30,000.00 0.00 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2019-09-11 Landfill and Partial Closure Implementation Liaison Officer (CCLO) Selection of the Whein Town Landfill Construction of the Individual LR-MCC-26957-CS-INDV / Cheesemanburg Regional TF / A5269 Post Consultant Open 50,000.00 0.00 Canceled 2018-12-20 2019-02-07 2019-02-28 2019-04-04 2019-10-01 Whein Town Closure Design Landfill and Partial Closure Selection of the Whein Town Landfill LR-MCC-93652-CS-INDV / Institutional Capacity Individual Consultancy Service for TF / A5269 Development and Project Post Consultant Open 25,000.00 0.00 Canceled 2019-01-30 2019-03-20 2019-04-10 2019-05-15 2019-11-11 Financial Assessment for Management Selection the waste Sector Page 5 LR-MCC-95081-CS-CDS / Construction of the Consultancy Services for the Cheesemanburg Regional TF / A5269 Prior Direct Selection Direct 45,000.00 0.00 Under Review 2019-01-25 2019-02-04 2019-04-10 2019-10-07 Provision of Technical Landfill and Partial Closure Support to PIU of the Whein Town Landfill Construction of the MCC-PIU-REF-31 / Individual Cheesemanburg Regional Safeguard Audit of the TF / A5269 Post Consultant Open 75,000.00 0.00 Canceled 2019-03-29 2019-05-17 2019-06-07 2019-07-12 2020-01-08 Landfill and Partial Closure Whein Town Landfill Selection of the Whein Town Landfill Construction of the Individual Cheesemanburg Regional MCC-PIU-REF-28 / M&E TF / A5269 Post Consultant Open 40,000.00 0.00 Canceled 2019-06-30 2019-08-18 2019-09-08 2019-10-13 2020-04-10 Landfill and Partial Closure Selection of the Whein Town Landfill Construction of the MCC-PIU-REF-33 / Individual Cheesemanburg Regional Preparation of Solid Waste TF / A5269 Post Consultant Open 80,000.00 0.00 Canceled 2018-10-24 2018-12-12 2019-01-02 2019-02-06 2019-08-05 Landfill and Partial Closure Management Strategy Selection of the Whein Town Landfill Construction of the MCC-PIU-REF-36 / Whein Individual Cheesemanburg Regional Town Permanent Closure / Post Consultant Open 50,000.00 0.00 Canceled 2019-06-30 2019-08-18 2019-09-08 2019-10-13 2020-04-10 Landfill and Partial Closure Supervision Selection of the Whein Town Landfill CLUS/CS-8/IC/PAC/09/19 / Institutional Capacity Individual Public Awareness Consultant Under TF / A5269 Development and Project Post Consultant Open 36,000.00 0.00 2019-09-23 2019-11-11 2019-12-02 2020-01-06 2020-07-04 (PAC)/ Communication Implementation Management Selection Specialist Construction of the MCC-PIU-REF-35 / Whein Individual Cheesemanburg Regional Town Partial Closure TF / A5269 Post Consultant Open 50,000.00 0.00 Canceled 2018-12-14 2019-02-01 2019-02-22 2019-03-29 2019-09-25 Landfill and Partial Closure Supervision Selection of the Whein Town Landfill LR-MCC-64547-CS-INDV / Institutional Capacity Individual Financial and Revenue TF / A5269 Development and Project Post Consultant Open 24,000.00 0.00 Canceled 2018-06-15 2018-08-03 2018-08-24 2018-09-28 2019-03-27 Consultant for the City of Management Selection Monrovia CLUS/CS-9/IC/TSWS/09/19 / Institutional Capacity Individual Under Technical Solid Waste TF / A5269 Development and Project Prior Consultant Open 42,000.00 0.00 2019-10-25 2019-12-13 2020-01-03 2020-02-07 2020-08-05 Implementation Specialist Management Selection LR-MCC-139704-CS-CDS / Institutional Capacity Website Development and Pending TF / A5269 Development and Project Post Direct Selection Direct 10,000.00 0.00 2019-10-23 2019-11-02 2020-01-06 2020-07-04 Database System for the Implementation Management CLUS Project LR-MCC-143088-CS-INDV / CONSULTANCY SERVICE Construction of the FOR THE Individual Cheesemanburg Regional Pending ENVIRONMENTAL AND TF / A5269 Post Consultant Open 50,000.00 0.00 2019-10-31 2019-12-19 2020-01-09 2020-02-13 2020-08-11 Landfill and Partial Closure Implementation SOCIAL AUDIT OF WHEIN Selection of the Whein Town Landfill TOWN SANITARY LANDFILL SITE LR-MCC-150242-CS-INDV / Recruitment of a consultant Construction of the for the conduct of an Individual Cheesemanburg Regional Pending environmental and social TF / A5269 Post Consultant Open 50,000.00 0.00 2019-12-16 2020-02-03 2020-02-24 2020-03-30 2020-09-26 Landfill and Partial Closure Implementation audit of the Whein town Selection of the Whein Town Landfill landfill site and the two solid waste transfer stations. Page 6