Procurement Plan Agriculture Development Support Project (P147629) I. General 1. Bank’s approval Date of the procurement Plan Original: October 9, 2014 Revision: June 16, 2016 Revision: April 10, 2017 2. Date of General Procurement Notice: October 13,2015 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Procurement Method Prior Review Threshold Threshold US$ 1. ICB (Goods) Above US$ 500,000 All 2. Shopping (Goods) Below US$ 500,000 Above 200,000 3. ICB (Works) Above US$ 1 million All 4. Shopping (Works) Below US$ 1 million Above 200,000 5. Direct Contracting - All 6. Force Account - All 2. Reference to (if any) Project Operational/Procurement Manual: Procurement will be conducted in line with the provisions of the Project Operation Manual which will provide the detailed procedures including using force account (using Ministry’s own procedures for civil works) 3. Any Other Special Procurement Arrangements: Not applicatble 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 60 1 No Post Force [Type here] Account(Wor ks) Summary of 1.23 1 No Prior the ICB (Goods) Summary of 0.3 5 No Prior the Shopping (Works) Summary of 3 17 No Post the Shopping (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) Above US$10,000 3. Individual All key fiduciary and legal positions 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_50,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: No special selection arrangements are planned for the Project 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 4.5 3 Prior number of contracts that will be let under QCBS 2 Summary of 2 14 Post number of contracts that will be let under other methods [Type here] PROCUREMENT Myanmar : Agricultural Development Support Project PLAN General Information Country: Myanmar Bank’s Approval Date of the Original Procurement Plan: 2016-09-07 2020-01-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147629 GPN Date: Project Name: Agricultural Development Support Project Loan / Credit No: IDA / 56240 Executing Agency(ies): Ministry of Agriculture, Livestock and Irrigation WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ADSP W1 / Rehabilitation 1. Irrigation and Drainage and Upgrading of Irrigation IDA / 56240 Post Force Account Direct 6,000,000.00 0.00 Canceled 2017-03-15 2017-03-20 2017-04-24 2017-10-21 Management Systems (ID) ADSP W2 / Construction of Pending 2. Farm Advisory and Request for Single Stage - One Breeder Seed Store Room IDA / 56240 Prior Limited 50,000.00 0.00 Implementati 2016-12-20 2017-02-14 2017-08-13 Technical Services Quotations Envelope (DAR) on Pending ADSP W3 / Upgrade of the 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 72,000.00 0.00 Implementati 2017-03-20 2017-05-15 2017-11-11 NPT Central Farm (DAR) Technical Services Quotations Envelope on ADSP W4 / Construction of Pending 2. Farm Advisory and Request for Single Stage - One On-Farm Seed Storage IDA / 56240 Post Limited 78,000.00 0.00 Implementati 2016-03-20 2016-05-15 2016-11-11 Technical Services Quotations Envelope Facilities (DOA: 2) on ADSP W5 / Construction of Pending 2. Farm Advisory and Request for Single Stage - One Machinery Buildings on Seed IDA / 56240 Post Limited 36,000.00 0.00 Implementati 2016-03-20 2016-05-15 2016-11-11 Technical Services Quotations Envelope Farms (DOA: 2) on ADSP W6 / Construction of Pending 2. Farm Advisory and Request for Single Stage - One Drying Grounds on Seed IDA / 56240 Post Limited 30,000.00 0.00 Implementati 2016-03-20 2016-05-15 2016-11-11 Technical Services Quotations Envelope Farms (DOA) on W-8 / Open Shelf Building Under 1. Irrigation and Drainage Request for Single Stage - One (4 Shelf) (DAR) IDA / 56240 Post Open - National 17,800.00 0.00 Implementati 2018-01-04 2018-03-01 2018-08-28 Management Quotations Envelope (L48' x W30' x H10') on W-9 / Construction Extension Camps Pending (40'x20'x10') (15 Nos) and 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 300,000.00 0.00 Implementati 2018-01-04 2018-03-01 2018-08-28 Tube well, Electricity, Toilet, Technical Services Quotations Envelope on Water tank (15 Nos) DOA (Extension) W-10 / Village Level Storage (40'x20'x10') (12 Pending 2. Farm Advisory and Request for Single Stage - One Nos) and Tube well, IDA / 56240 Post Open - National 120,000.00 0.00 Implementati 2018-01-04 2018-03-01 2018-08-28 Technical Services Quotations Envelope Electricity (1 No) on DOA (Extension) W-11 / Township Level Pending Storage (40'x20'x10') (7 Nos) 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 71,000.00 0.00 Implementati 2018-01-04 2018-03-01 2018-08-28 and Electricity (7 Nos) Technical Services Quotations Envelope on DOA (Extension) W-12 / Concrete Electric Pending 2. Farm Advisory and Request for Single Stage - One Pole (35) + Cabel (3500') IDA / 56240 Post Open - National 1,500.00 0.00 Implementati 2018-01-04 2018-03-01 2018-08-28 Technical Services Quotations Envelope DOA (Seeds) on Page 1 C1-W1 / Rehabilitation Irrigation Scheme Main 1. Irrigation and Drainage IDA / 56240 Prior Force Account Direct 2,640,000.00 2,620,869.80 Signed 2018-02-16 2018-02-21 2018-03-28 2018-09-24 Canal for North Yamar Management Batch 1 C1-W2 / Rehabilitation 1. Irrigation and Drainage Irrigation Scheme Left Main IDA / 56240 Prior Force Account Direct 2,560,000.00 2,548,443.52 Signed 2018-02-16 2018-02-21 2018-03-28 2018-09-24 Management canal Sinthe Batch1 ADSP W1- 18 / Package No.1Rehabilitation of Work for Irrigation Site (Stone Lining RD 0 to 2000, RD 1. Irrigation and Drainage 12850 to 20000, Between RD IDA / 56240 Post Force Account Direct 362,300.00 362,300.00 Signed 2018-06-07 2018-06-07 2018-06-07 2018-06-07 Management 20000 and 72640 ) Construction and Rehabilitation of Stucture 9 nos- North Yammar ADSP W2- 18 / Package No.2 Rehabilitation of Work for Irrigation Site Sinthe Earth Work (Cutting LNC 1. Irrigation and Drainage IDA / 56240 Post Force Account Direct 36,200.00 362,300.00 Signed 2018-06-07 2018-06-07 2018-06-07 2018-06-07 RD 9000 to 10500) - Management Construction and Rehabilitation of Stucture 28 nos ADSP W3- 18 / Package No.3 Rehabilitation of Work for Irrigation Site - Marlae 1. Irrigation and Drainage IDA / 56240 Post Force Account Direct 72,460.00 114,940.00 Signed 2018-06-07 2018-06-07 2018-06-07 2018-06-07 Nat Taung (Stone Lining Management 350 ft) and Canal Crossing Bridge 3 nos ADSP W4- 18 / Rehabilitation of Work for Irrigation Site Swa (DY 7 1. Irrigation and Drainage IDA / 56240 Post Force Account Direct 144,940.00 144,940.00 Signed 2018-06-07 2018-06-12 2018-07-17 2019-01-13 Head Regulator Management Rehabilitation and Stone Lining 1220 ft) ADSP W13- 2018-2019 / Pending 2. Farm Advisory and Request for Single Stage - One Package No.13 Construction IDA / 56240 Post Open - National 82,000.00 0.00 Implementati 2018-12-08 2019-02-02 2019-08-01 Technical Services Quotations Envelope of Extension Camp on ADSP W14- 2018-2019 / Pending 2. Farm Advisory and Request for Single Stage - One Package No.14 Construction IDA / 56240 Post Open - National 12,000.00 0.00 Implementati 2018-12-08 2019-02-02 2019-08-01 Technical Services Quotations Envelope of Village Level Storage on ADSP W15- 2018-2019 / Pending 2. Farm Advisory and Request for Single Stage - One Package No.15 Flooring of IDA / 56240 Post Limited 12,000.00 0.00 Implementati 2018-12-08 2019-02-02 2019-08-01 Technical Services Quotations Envelope 18 Storage on ADSP W16- 2018-2019 / Pending 2. Farm Advisory and Request for Single Stage - One Package No.16 Fencing for IDA / 56240 Post Limited 60,000.00 0.00 Implementati 2018-12-08 2019-02-02 2019-08-01 Technical Services Quotations Envelope 32 Building on ADSP W17- 2018-2019 / Rehabilitation of Work for Irrigation Site - Sinthe Left Main Canal, Earth work from RD 0+000 to RD 59+000 and from DY 1 to 1. Irrigation and Drainage IDA / 56240 Prior Force Account Direct 3,152,000.00 3,152,000.00 Signed 2018-12-17 2018-12-22 2019-01-26 2019-07-25 DY 5, Stone Lining Work Management with Associated Works from RD 2585' to 14000' - RD 17000' to 41000' and DY 1 to DY 5 and 2.3 Structure from Page 2 ADSP W18- 2018-2019 / Rehabilitation of Work for Irrigation Site - North Yamar, Stone Lining Work 1. Irrigation and Drainage IDA / 56240 Prior Force Account Direct 2,655,000.00 2,655,000.00 Signed 2018-12-17 2018-12-22 2019-01-26 2019-07-25 with Associated Works Management (From RD 32+000 to RD 41+000 and RD 48+400 to 52+800) ADSP W19- 2018-2019 / Rehabilitation of Work for Irrigation Site - Marlae Nat Taung, Earth Work of LMC RD 0+000 to RD 28+000 DY RD 0+000 to RD 7+300, 1. Irrigation and Drainage IDA / 56240 Prior Force Account Direct 2,720,000.00 2,720,000.00 Signed 2018-12-17 2018-12-22 2019-01-26 2019-07-25 RMC-1 RD 0+000 to RD Management 44+100 DY RD RD 0+000 to RD 6+900 and RMC-2 RD 0+000 to RD 29+90, Stone Lining LMC RD 0+000 to RD 28+000 ADSP W20 - 2018-2019 / Rehabilitation of Work for Irrigation Site Swa, Main Canal Earth Work (RD 0 to 1. Irrigation and Drainage IDA / 56240 Prior Force Account Direct 2,500,000.00 2,500,000.00 Signed 2019-01-18 2019-01-23 2019-02-27 2019-08-26 86000) and Earth Work ( Management DY 2- RD 0 to 50000), Stone Lining ( Between DY 2- RD 0 to 15105) ADSP W17-A- 2018-2019 / Rehabilitation of work for Irrigation site for Sinthe. DY (1) Earth Work in Cutting, Filling and Slope 1. Irrigation and Drainage Dressing (by Machine), Stone IDA / 56240 Post Force Account Direct 1,254,693.00 1,254,693.00 Signed 2019-05-21 2019-05-26 2019-06-30 2019-12-27 Management Lining RD 2871 to 12027, Structure Work H.R (24 nos), Drop (6 nos), Bridge (7 nos), Spill in (4 nos). DY (2) Earth Work ADSP W18-A- 2018-2019 / Rehabilitation of work for Irrigation site for North Yamar- Earth work and Grass portion Work between RD 20000 to 23000, Stone 1. Irrigation and Drainage IDA / 56240 Post Force Account Direct 1,687,810.00 1,687,810.00 Signed 2019-05-21 2019-05-26 2019-06-30 2019-12-27 Lining Work RD 14900 to Management 15700, RD 37760 to 38500, RD 44100 to 44721, RD 48500 to 49492, RD 49492 to 50592, RD 52500 to 54757 ADSP W19 A - 2018-2019 / Rehabilitation of work for Irrigation site for Marlenat Taung- Dam Safety Work for Cement Grouting Work 1. Irrigation and Drainage Crest Drain, Bern Drain, IDA / 56240 Post Force Account Direct 1,819,024.00 1,819,024.00 Signed 2019-05-21 2019-05-26 2019-06-30 2019-12-27 Management Toe Drain Conduit Repair Work. Improvement of Canal Network for Resection of Canal and Canal Lining @ LMC RD 22010 to 24250 Page 3 ADSP W20-A- 2018-2019 / Rehabilitation of work for Irrigation site for SWA- Stone Lining works at Main canal RD 0 to 2500, RD 1. Irrigation and Drainage 10150 to 11150 and RD IDA / 56240 Post Force Account Direct 1,547,059.00 1,547,059.00 Signed 2019-05-21 2019-05-26 2019-06-30 2019-12-27 Management 19000 to 20000. Main Canal Structure Direct Outlet DO, Reinforce cement concrete and Deck-Girder Bridge, Box Culvert,Head regulator ADSP W21-18-19 / Preparatory Work for New Spillway and Work for Dam Safety(SWA) Surveying work, Reservoir water test, Geological 1. Irrigation and Drainage IDA / 56240 Post Force Account Direct 685,507.00 685,507.00 Signed 2019-05-24 2019-05-29 2019-07-03 2019-12-30 investigation, Jungle clearing Management for new Spillway, Earth Work for Diversion Channel and Excavation for grouting for foundation new Spillway and C ADSP W31- 2019-2020 / Pending Package No.31 Dried Groung 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 28,870.00 0.00 Implementati 2019-11-17 2020-01-12 2020-07-10 (75'x 65'x 1') for DOA Seed- Technical Services Quotations Envelope on 2 ADSP W32- 2019-2020 / Pending Package No.32 Construction 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 41,203.00 0.00 Implementati 2019-11-17 2020-01-12 2020-07-10 for Celing (40'x20'x10') DOA Technical Services Quotations Envelope on Ext - 32 ADSP W33- 2019-2020 / Pending Package No.33 Providing 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 5,666.00 0.00 Implementati 2019-11-23 2020-01-18 2020-07-16 Iron Work for Warehouse Technical Services Quotations Envelope on (40'x20'x10') DOA Ext - 18 ADSP W34- 2019-2020 / Package No.34 Construction 4'x 4'x 18' Over head Tank with iron Frame (1600) Pending 2. Farm Advisory and Request for Single Stage - One Gallon, 4" dia Tube well, IDA / 56240 Post Limited 131,148.00 0.00 Implementati 2019-11-23 2020-01-18 2020-07-16 Technical Services Quotations Envelope Groung Tank (3600) Galoon, on Submersible Pump, Piping (200') with PVC Pipe (2") for DOA Ext -14 ADSP W35- 2019-2020 / Package No.35 Construction Pending for 2 unit Latrine RCC (10' 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 32,131.00 0.00 Implementati 2019-11-30 2020-01-25 2020-07-23 x 6'x 8') with Septic Tank Technical Services Quotations Envelope on (10' x 8' x 8') for DOA Ext -14 ADSP W36- 2019-2020 / Package No.36 Laying Access Pending 2. Farm Advisory and Request for Single Stage - One Road and Concrete Road, IDA / 56240 Post Limited 825.00 0.00 Implementati 2019-11-30 2020-01-25 2020-07-23 Technical Services Quotations Envelope Thickness 9" Length 50' on Breadth 8' for DOA Ext W 22 2019-20 / Under 1. Irrigation and Drainage Rehabilitation of Work for IDA / 56240 Prior Force Account Direct 973,705.00 0.00 Implementati 2019-11-15 2019-11-20 2019-12-25 2020-06-22 Management Irrigation Site - Sinthe on W 23- 2019-20 / Under Rehabilitation of Work for 1. Irrigation and Drainage IDA / 56240 Prior Force Account Direct 932,033.00 0.00 Implementati 2019-11-15 2019-11-20 2019-12-25 2020-06-22 Irrigation Site - North Management on Yamar Page 4 W 24-2019-20 / Under Rehabilitation of Work for 1. Irrigation and Drainage IDA / 56240 Prior Force Account Direct 1,555,898.00 0.00 Implementati 2019-11-15 2019-11-20 2019-12-25 2020-06-22 Irrigation Site - Marlae Nat Management on Taung W 25-2019-20 / Under 1. Irrigation and Drainage Rehabilitation of Work for IDA / 56240 Prior Force Account Direct 4,570,780.00 0.00 Implementati 2019-11-15 2019-11-20 2019-12-25 2020-06-22 Management Irrigation Site Swa on W 27 2019-20 / Under 1. Irrigation and Drainage Rehabilitation of Work for IDA / 56240 Prior Force Account Direct 1,967,213.00 0.00 Implementati 2019-11-26 2019-12-01 2020-01-05 2020-07-03 Management Irrigation Site - Bawni on W 30 2019-2020 / Under 1. Irrigation and Drainage Rehabilitation of Work for IDA / 56240 Prior Force Account Direct 1,311,475.00 0.00 Implementati 2019-12-03 2019-12-08 2020-01-12 2020-07-10 Management Irrigation Site -Thekaw on W 29 2019-2020 / Pending 1. Irrigation and Drainage Rehabilitation of Work for IDA / 56240 Prior Force Account Direct 1,967,213.00 0.00 Implementati 2020-01-23 2020-01-28 2020-03-03 2020-08-30 Management Irrigation Site -Zeetaw on W 28 2019-2020 / Pending 1. Irrigation and Drainage Rehabilitation of Work for IDA / 56240 Prior Force Account Direct 983,606.00 0.00 Implementati 2020-01-23 2020-01-28 2020-03-03 2020-08-30 Management Irrigation Site -Ngaleik on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ADSP G1 / Package No. 1: 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Prior Limited 146,000.00 0.00 Canceled 2016-12-20 2017-02-14 2017-08-13 Motorbikes Management Quotations Envelope ADSP G2 / Package No. 2: 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Prior Limited 490,000.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Vehicles Management Quotations Envelope ADSP G3 / Package No. 3: 2. Farm Advisory and Open - Single Stage - One IDA / 56240 Prior Request for Bids 1,230,000.00 601,331.33 Signed 2016-09-15 2016-09-20 2016-11-01 2016-12-01 2017-01-05 2017-07-04 Tractors Technical Services International Envelope ADSP G5 / Package No. 5: Other Machines and 2. Farm Advisory and Request for Single Stage - One Equipment for AMD IDA / 56240 Prior Limited 325,222.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Technical Services Quotations Envelope Stations, MTC, and DOA Seed Farms ADSP G6 / Package No. 6: 2. Farm Advisory and Request for Single Stage - One Small Equipment for AMD IDA / 56240 Post Limited 82,880.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Technical Services Quotations Envelope Stations ADSP G7 / Package No. 7: 2. Farm Advisory and Request for Single Stage - One Teaching and Learning IDA / 56240 Prior Limited 355,826.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Technical Services Quotations Envelope Materials for MTC ADSP G8 / Package No. 8: 2. Farm Advisory and Request for Single Stage - One Seed Laboratory Equipment IDA / 56240 Prior Limited 355,700.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Technical Services Quotations Envelope for DAR Farms ADSP G9 / Package No. 9: 2. Farm Advisory and Request for Single Stage - One Laboratory Equipment for IDA / 56240 Post Limited 109,200.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Technical Services Quotations Envelope LUD and DAR Page 5 ADSP G10 / Package No. 2. Farm Advisory and Request for Single Stage - One 10: Equipment for DOA IDA / 56240 Prior Limited 250,900.00 0.00 Canceled 2016-12-20 2017-02-14 2017-08-13 Technical Services Quotations Envelope Seed Farms ADSP G11 / Accounting 3. Project Coordination and Request for Single Stage - One IDA / 56240 Post Limited 25,000.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Software (PMU) Management Quotations Envelope ADSP G12 / Satellite 1. Irrigation and Drainage IDA / 56240 Post Direct Selection Direct 8,000.00 6,045.92 Signed 2016-12-15 2016-12-20 2017-01-24 2017-07-23 Images (DALMS) Management ADSP G13 / Software for 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Post Limited 20,000.00 20,332.21 Signed 2016-12-20 2017-02-14 2017-08-13 Land Maps (DALMS) Management Quotations Envelope ADSP G14 / Package No. 1. Irrigation and Drainage Request for Single Stage - One 10: Computers, Printers and IDA / 56240 Post Limited 77,700.00 0.00 Canceled 2016-12-20 2017-02-14 2017-08-13 Management Quotations Envelope Scanners ADSP G15 / Package No. 2. Farm Advisory and Request for Single Stage - One 11: Other Computers and IDA / 56240 Post Limited 168,000.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 Technical Services Quotations Envelope Printers ADSP G16 / Other office 3. Project Coordination and Request for Single Stage - One IDA / 56240 Post Limited 100,000.00 0.00 Canceled 2016-12-20 2017-02-14 2017-08-13 equipment Management Quotations Envelope ADSP G17 / Generator 3. Project Coordination and Request for Single Stage - One IDA / 56240 Post Limited 3,000.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 (PMU) (1) Management Quotations Envelope ADSP G18 / AC Unit 3. Project Coordination and Request for Single Stage - One IDA / 56240 Post Limited 2,000.00 0.00 Canceled 2016-09-20 2016-11-15 2017-05-14 (PMU) (1) Management Quotations Envelope ADSPG19 / Office Equipment for PMU Office; Lot-1 and Lot2 Office 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Post Limited 37,675.00 21,912.74 Signed 2017-01-04 2017-03-01 2017-08-28 Equipment, Lot-3 Office Management Quotations Envelope Furniture, Lot4 Office Stationary ADSP G4 / Package No. 4: 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Prior Limited 338,520.00 268,812.94 Signed 2016-09-20 2016-11-15 2017-05-14 Combine Harvesters Technical Services Quotations Envelope G-20 / Laboratory 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 326,699.00 224,082.23 Signed 2018-01-04 2018-03-01 2018-08-28 Equipment for DOA (PPD) Technical Services Quotations Envelope G-21 / Machineries & 1. Irrigation and Drainage Request for Single Stage - One Equipments ,Hydraulic IDA / 56240 Post Open - National 450,000.00 0.00 Canceled 2018-01-04 2018-03-01 2018-08-28 Management Quotations Envelope Excavator (7 ton) (6) G-22 / Teaching and 1. Irrigation and Drainage Request for Single Stage - One Learning Materials for IDA / 56240 Post Open - National 300,000.00 0.00 Canceled 2018-01-04 2018-03-01 2018-08-28 Management Quotations Envelope IWUMD,Workshop Tools G-23 / Tractor Set for 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 499,700.00 112,051.52 Signed 2018-01-04 2018-03-01 2018-08-28 AMD Technical Services Quotations Envelope G-24 / Implements 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 150,920.00 107,068.17 Signed 2018-01-04 2018-03-01 2018-08-28 Materials for AMD Technical Services Quotations Envelope G-25 / Combine Harvester 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 292,600.00 0.00 Canceled 2018-01-04 2018-03-01 2018-08-28 and Transplanter for AMD Technical Services Quotations Envelope G-27 / Office Equipment for 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 9,105.00 7,316.53 Signed 2018-01-04 2018-03-01 2018-08-28 DAR Technical Services Quotations Envelope Page 6 2. Farm Advisory and Request for Single Stage - One G-28 / Furniture for DAR IDA / 56240 Post Open - National 9,040.00 0.00 Canceled 2018-01-04 2018-03-01 2018-08-28 Technical Services Quotations Envelope G-29 / Lab Equipment for 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Prior Open - National 470,000.00 0.00 Canceled 2018-01-04 2018-03-01 2018-08-28 LUD (Non Control Items) Technical Services Quotations Envelope G-30 / Distribution of 2. Farm Advisory and Request for Single Stage - One printed Extension material IDA / 56240 Post Open - National 14,044.00 0.00 Canceled 2018-01-04 2018-03-01 2018-08-28 Technical Services Quotations Envelope for DOA (Extension) G-31 / Distribution on of 2. Farm Advisory and Request for Single Stage - One printed Extension IDA / 56240 Post Open - National 15,167.00 4,138.69 Signed 2018-01-04 2018-03-01 2018-08-28 Technical Services Quotations Envelope material for DOA (LUD) G-32 / Office Equipment for 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 60,519.00 29,989.99 Signed 2018-01-04 2018-03-01 2018-08-28 DOA (Extension) Technical Services Quotations Envelope G-33 / Goods & Equipment 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 200,500.00 87,367.39 Signed 2018-01-04 2018-03-01 2018-08-28 for DOA (Seeds) Technical Services Quotations Envelope G-34 / Office Equipment for 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 6,650.00 60,923.55 Signed 2018-01-04 2018-03-01 2018-08-28 DOA (Seeds) Technical Services Quotations Envelope G-35 / Gliricida for DOA 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 50,000.00 0.00 Canceled 2018-01-04 2018-03-01 2018-08-28 (Extension) Technical Services Quotations Envelope G-36 / Goods and 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 153,800.00 29,082.69 Signed 2018-01-04 2018-03-01 2018-08-28 Equipment for DOA (Seeds) Technical Services Quotations Envelope G-37 / Equipment for DOA 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 127,500.00 60,402.51 Signed 2018-01-04 2018-03-01 2018-08-28 Seed Farm Technical Services Quotations Envelope G 26-2 / Machinery and Under 2. Farm Advisory and Single Stage - One Equipment for DAR ( IDA / 56240 Post Request for Bids Open - National 773,056.00 0.00 Implementati 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 2018-06-20 Technical Services Envelope Combine Harvester) on G 26-3 / Machinery 2. Farm Advisory and Single Stage - One Equipment for DAR ( IDA / 56240 Post Request for Bids Open - National 773,056.00 60,924.51 Signed 2017-09-05 2017-09-10 2017-10-22 2017-11-21 2017-12-26 2018-06-24 Technical Services Envelope Equipment ) G 26-6 / Machinery and 2. Farm Advisory and Request for Single Stage - One Equipment for DAR IDA / 56240 Post Open - National 26,157.63 0.00 Canceled 2017-11-14 2018-01-09 2018-07-08 Technical Services Quotations Envelope (Microscopes) G 26-5 / Machinery and 2. Farm Advisory and Request for Single Stage - One equipment for DAR IDA / 56240 Post Open - National 313,120.30 315,043.83 Signed 2017-10-21 2017-12-16 2018-06-14 Technical Services Quotations Envelope (Laboratory Equipment) G 26-4 / Machinery and 2. Farm Advisory and Request for Single Stage - One Eqipment for DAR IDA / 56240 Post Open - National 55,555.56 0.00 Canceled 2017-10-21 2017-12-16 2018-06-14 Technical Services Quotations Envelope (Implements) G-26-1 / Machinery and 2. Farm Advisory and Request for Single Stage - One Equipment for DAR ( IDA / 56240 Post Open - National 275,555.60 86,800.64 Signed 2018-01-04 2018-03-01 2018-08-28 Technical Services Quotations Envelope Tractor for DAR) G 38 / IT and Office 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Post Open - National 19,000.00 10,972.97 Signed 2017-12-09 2018-02-03 2018-08-02 Equipment for DALMS Management Quotations Envelope G 40 / Seed Laboratory 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 33,450.00 0.00 Canceled 2017-12-09 2018-02-03 2018-08-02 Equipment for DOA Seed Technical Services Quotations Envelope G 39 / Seed Laboratory 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 73,050.00 0.00 Canceled 2017-12-09 2018-02-03 2018-08-02 Machines for DOA Seed Technical Services Quotations Envelope Page 7 ADSP G1R / Package No. 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Post Limited 146,000.00 62,322.10 Signed 2017-10-31 2017-12-26 2018-06-24 1: Motorbikes Management Quotations Envelope ADSP G2R / Package No. 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Post Limited 490,000.00 118,154.93 Signed 2017-10-31 2017-12-26 2018-06-24 2: Vehicles Management Quotations Envelope ADSP G29R / Lab 2. Farm Advisory and Request for Single Stage - One Equipment for LUD (Non IDA / 56240 Post Limited 470,000.00 381,237.90 Signed 2017-11-29 2018-01-24 2018-07-23 Technical Services Quotations Envelope Control Items) ADSP G5R / Package No. 5: Other Machines and 2. Farm Advisory and Request for Single Stage - One Equipment for AMD IDA / 56240 Post Limited 20,000.00 12,874.61 Signed 2017-08-19 2017-10-14 2018-04-12 Technical Services Quotations Envelope Stations, MTC, and DOA Seed Farms ADSP G6R / Package No. 2. Farm Advisory and Request for Single Stage - One 6: Small Equipment for IDA / 56240 Post Limited 82,880.00 176,500.52 Signed 2017-02-05 2017-04-02 2017-09-29 Technical Services Quotations Envelope AMD Stations ADSP G7R / Package No. 2. Farm Advisory and Request for Single Stage - One 7: Teaching and Learning IDA / 56240 Post Limited 355,826.00 94,614.41 Signed 2017-08-19 2017-10-14 2018-04-12 Technical Services Quotations Envelope Materials for MTC G 41 / Machinery and 1. Irrigation and Drainage Open - Single Stage - One IDA / 56240 Prior Request for Bids 5,500,000.00 3,116,012.00 Signed 2018-10-10 2018-10-15 2018-11-26 2018-12-26 2019-01-30 2019-07-29 Equipment for IWUMD Management International Envelope ADSP G42- 2018- 2019 / Package No. 42 Seed 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 100,000.00 73,370.42 Signed 2018-11-17 2019-01-12 2019-07-11 Laboratory Equipment for Technical Services Quotations Envelope DOA Seeds ADSP G43- 2018- 2019 / Package No. 43 Machineries 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Open - National 250,000.00 173,338.29 Signed 2018-11-17 2019-01-12 2019-07-11 and Equipments for DOA Technical Services Quotations Envelope Seed ADSP G44- 2018- 2019 / 2. Farm Advisory and Request for Single Stage - One Package No.44 Computer & IDA / 56240 Post Open - National 23,000.00 20,230.48 Signed 2018-11-20 2019-01-15 2019-07-14 Technical Services Quotations Envelope Printer DOA LUD &Seed ADSP G45- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.45 Laboratory IDA / 56240 Post Open - National 35,000.00 18,964.86 Signed 2018-11-25 2019-01-20 2019-07-19 Technical Services Quotations Envelope Equipments for LUD ADSP G46- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.46 Lab IDA / 56240 Post Open - National 300,000.00 202,894.28 Signed 2018-11-25 2019-01-20 2019-07-19 Technical Services Quotations Envelope Equipment DOA PPD ADSP G47- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.47 Microscope IDA / 56240 Post Open - National 49,000.00 32,068.99 Signed 2018-12-05 2019-01-30 2019-07-29 Technical Services Quotations Envelope for (DAR) ADSP G48- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.48 Machineries IDA / 56240 Post Open - National 260,000.00 232,409.05 Signed 2019-01-12 2019-03-09 2019-09-05 Technical Services Quotations Envelope & Equipments for (DAR) ADSP G49- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.49 Office IDA / 56240 Post Open - National 37,000.00 32,226.32 Signed 2019-01-12 2019-03-09 2019-09-05 Technical Services Quotations Envelope Furniture for (DAR) ADSP G50- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.50 Office IDA / 56240 Post Open - National 23,000.00 0.00 Canceled 2019-01-12 2019-03-09 2019-09-05 Technical Services Quotations Envelope Furniture (DOA Ext) Page 8 ADSP G51- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.51 IT & Office IDA / 56240 Post Open - National 50,000.00 14,331.14 Signed 2019-01-19 2019-03-16 2019-09-12 Technical Services Quotations Envelope Equipment (DOA Ext) ADSP G52- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.52 Combine IDA / 56240 Post Open - National 485,000.00 0.00 Canceled 2019-01-19 2019-03-16 2019-09-12 Technical Services Quotations Envelope Harvester for DOA Ext ADSP G53- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.53 Other IDA / 56240 Post Open - National 160,000.00 0.00 Canceled 2019-01-19 2019-03-16 2019-09-12 Technical Services Quotations Envelope Equipments for DOA Ext ADSP G54- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.54 Tractors for IDA / 56240 Post Open - National 330,000.00 0.00 Canceled 2019-01-26 2019-03-23 2019-09-19 Technical Services Quotations Envelope DOA Ext ADSP G55- 2018-2019 / 2. Farm Advisory and Request for Single Stage - One Package No.55 Lab IDA / 56240 Post Open - National 28,000.00 11,897.50 Signed 2019-01-26 2019-03-23 2019-09-19 Technical Services Quotations Envelope Equipment DOA Ext ADSP G 41 A / Teaching Under 1. Irrigation and Drainage Open - Single Stage - One and Learning Material for IDA / 56240 Prior Request for Bids 1,875,220.00 0.00 Implementati 2019-02-05 2019-02-10 2019-03-24 2019-04-23 2019-05-28 2019-11-24 Management International Envelope IWUMD (Lot 2) on G 56 / Teaching and 1. Irrigation and Drainage Request for Single Stage - One Learning Materials for IDA / 56240 Post Open - National 485,000.00 380,393.87 Signed 2019-04-08 2019-06-03 2019-11-30 Management Quotations Envelope IWUMD ADSP G 57 / Laboratory 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 75,188.00 76,408.93 Signed 2019-06-26 2019-08-21 2020-02-17 Equipment for DOA (LUD) Technical Services Quotations Envelope ADSP G58- 2019- 2020 / Pending Package No. 58 IT 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Post Limited 106,100.00 0.00 Implementati 2020-01-11 2020-03-07 2020-09-03 Equipment and GPS for Management Quotations Envelope on DALMS ADSP G59- 2019- 2020 / Pending Package No. 59 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 39,685.00 0.00 Implementati 2019-12-11 2020-02-05 2020-08-03 LaboratoryMaterials for DOA Technical Services Quotations Envelope on LUD ADSP G60- 2019- 2020 / Package No.60 Seed Pending 2. Farm Advisory and Request for Single Stage - One Processing Plants and Other IDA / 56240 Post Limited 212,687.00 0.00 Implementati 2019-12-11 2020-02-05 2020-08-03 Technical Services Quotations Envelope Equipment for DOA on Extension ADSP G61- 2019-2020 / Pending 2. Farm Advisory and Request for Single Stage - One Package No.61 Machinery for IDA / 56240 Post Limited 461,608.00 0.00 Implementati 2019-12-16 2020-02-10 2020-08-08 Technical Services Quotations Envelope Bean and Pulses for AMD on ADSP G62- 2019-2020 / Pending Package No.62 Machinery 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 320,500.00 0.00 Implementati 2019-12-16 2020-02-10 2020-08-08 Input Application for Paddy Technical Services Quotations Envelope on for AMD ADSP G63- 2019-2020 / Pending Package No.63 Machinery for 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 369,350.00 0.00 Implementati 2019-12-21 2020-02-15 2020-08-13 Straw Management & Laser Technical Services Quotations Envelope on Levelling for AMD ADSP G64- 2019-2020 / Pending Package No.64 Machinery for 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 397,426.00 0.00 Implementati 2019-12-21 2020-02-15 2020-08-13 Transplanting & Harvesting Technical Services Quotations Envelope on for AMD Page 9 ADSP G65- 2019-2020 / Pending Package No.65 Tresher and 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 184,416.00 0.00 Implementati 2020-01-11 2020-03-07 2020-09-03 Other Machinery Equipment Technical Services Quotations Envelope on for AMD ADSP G66- 2019-2020 / Pending Package No.66 Teaching 2. Farm Advisory and Request for Single Stage - One IDA / 56240 Post Limited 312,300.00 0.00 Implementati 2020-01-11 2020-03-07 2020-09-03 Aids (Machinery Equipment) Technical Services Quotations Envelope on for AMD ADSP G67- 2019-2020 / Pending Package No.67 Teaching and 1. Irrigation and Drainage Request for Single Stage - One IDA / 56240 Post Limited 440,600.00 0.00 Implementati 2019-11-16 2020-01-11 2020-07-09 Learninig Materials for Two Management Quotations Envelope on Training Center IWUMD ADSP G68- 2019-2020 / Pending 1. Irrigation and Drainage Request for Single Stage - One Package No.68 Desktop IDA / 56240 Post Limited 36,100.00 0.00 Implementati 2019-11-09 2020-01-04 2020-07-02 Management Quotations Envelope Computer for IWUMD on ADSP G69- 2019-2020 / Package No.69 11 KV 100 Pending 2. Farm Advisory and Request for Single Stage - One KVA Transformer and 1700' IDA / 56240 Post Limited 20,329.00 0.00 Implementati 2019-11-13 2020-01-08 2020-07-06 Technical Services Quotations Envelope Electricity Cable Wire for on DOA Seeds ADSP G70- 2019-2020 / Package No.70 Set up Pending 2. Farm Advisory and Request for Single Stage - One Electricity Cable Wire (40' x IDA / 56240 Post Limited 52,459.00 0.00 Implementati 2019-11-09 2020-01-04 2020-07-02 Technical Services Quotations Envelope 20' x 10') for DOA Ext - on 32 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ADSP SC-04 / Design and Consultant 3. Project Coordination and Open - Pending Establishment of M&E IDA / 56240 Prior Qualification 60,000.00 0.00 2016-09-15 2016-10-06 2016-11-19 2016-12-19 2017-01-23 2017-07-22 Management International Implementation System (PMU) Selection ADSP SC-05 / Impact Consultant 3. Project Coordination and Open - Pending Evaluation/Baseline Survey IDA / 56240 Post Qualification 70,000.00 0.00 2017-03-15 2017-04-05 2017-05-19 2017-06-18 2017-07-23 2018-01-19 Management International Implementation (PMU) Selection SC-03 / Feasibillity and 1. Irrigation and Drainage Quality And Cost- Open - Design of Irrigation Schemes IDA / 56240 Prior 2,750,000.00 2,816,670.00 Signed 2016-06-10 2016-07-01 2016-08-14 2016-09-11 2016-10-11 2016-11-15 2016-12-20 2017-12-20 Management Based Selection International and Dam safety (ID) ADSP SC-01 / Training needs assessment, training program development, TOT, 1. Irrigation and Drainage Quality And Cost- Open - IDA / 56240 Prior 1,763,000.00 0.00 Canceled 2016-09-15 2016-10-06 2016-11-19 2016-12-17 2017-01-16 2017-02-20 2017-03-27 2018-03-27 training materials for ID Management Based Selection International and WUG Facilitators/ Irrigation Community Org Page 10 ADSP SC-02 / WUG 1. Irrigation and Drainage Quality And Cost- Open - Facilitators/ Irrigation IDA / 56240 Prior 900,000.00 0.00 Canceled 2016-09-15 2016-10-06 2016-11-19 2016-12-17 2017-01-16 2017-02-20 2017-03-27 2018-03-27 Management Based Selection International Community Org ADSP SC-03 / Feasibility and Design of Irrigation 1. Irrigation and Drainage Quality And Cost- Open - IDA / 56240 Prior 2,750,000.00 0.00 Canceled 2016-09-15 2016-10-06 2016-11-19 2016-12-17 2017-01-16 2017-02-20 2017-03-27 2018-03-27 Schemes and Dam Safety Management Based Selection International (ID) SC 01-B / Training needs assessment, training program 1. Irrigation and Drainage Quality Based Open - IDA / 56240 Prior 863,000.00 0.00 Canceled 2017-09-08 2017-09-29 2017-11-12 2017-12-10 2018-01-09 2018-02-08 2018-03-15 2019-03-15 development, TOT, training Management Selection International materials for ID (SC 01-b) SC-01 C / Strengthening of 1. Irrigation and Drainage Quality Based Open - Irrigation Management IDA / 56240 Prior 1,700,000.00 1,660,962.86 Signed 2017-12-28 2018-01-18 2018-03-03 2018-03-31 2018-04-30 2018-05-30 2018-07-04 2019-07-04 Management Selection International Institutions INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ADSP SC-06 / Lands Individual Records Date Base 1. Irrigation and Drainage Pending IDA / 56240 Post Consultant Open - National 30,000.00 0.00 2016-09-15 2016-11-03 2016-11-24 2016-12-29 2017-06-27 Development (DAMLS) (for 2 Management Implementation Selection months) ADSP SC-07 / Land Individual 1. Irrigation and Drainage Pending Property Valuation (DALMS) IDA / 56240 Post Consultant Limited 60,000.00 0.00 2016-12-15 2016-12-20 2017-01-10 2017-02-14 2017-08-13 Management Implementation (for 2 months) Selection ADSP SC-08 / Soil Individual Identification and 2. Farm Advisory and Pending IDA / 56240 Post Consultant Limited 18,000.00 0.00 2017-03-15 2017-03-20 2017-04-10 2017-05-15 2017-11-11 Classification (DOA) (for 3 Technical Services Implementation Selection months) ADSP SC-09 / Independent Individual verification consultant of 3. Project Coordination and Pending IDA / 56240 Prior Consultant Limited 150,000.00 0.00 2017-03-15 2017-03-20 2017-04-10 2017-05-15 2017-11-11 force account (PMU) (for 6 Management Implementation Selection months) ADSP SC-10 / National Individual 3. Project Coordination and Project Manager (PMU) (for IDA / 56240 Prior Consultant Limited 300,000.00 31,400.00 Signed 2016-07-30 2016-08-04 2016-08-25 2016-09-29 2017-03-28 Management 75 months) Selection ADSP SC-11 / National Individual Environmental Safeguards 3. Project Coordination and IDA / 56240 Prior Consultant Open - National 150,000.00 22,800.00 Signed 2016-07-30 2016-09-17 2016-10-08 2016-11-12 2017-05-11 Specialist (PMU) (for 75 Management Selection months) ADSP SC-12 / National Individual 3. Project Coordination and Social Safeguards Specialist IDA / 56240 Prior Consultant Limited 150,000.00 24,000.00 Signed 2016-07-30 2016-08-04 2016-08-25 2016-09-29 2017-03-28 Management (PMU) (for 75 months) Selection ADSP SC-13 / National Individual 3. Project Coordination and M&E Specialist (PMU) (for IDA / 56240 Prior Consultant Limited 150,000.00 24,000.00 Signed 2016-07-30 2016-08-04 2016-08-25 2016-09-29 2017-03-28 Management 75 months) Selection ADSP SC-14 / International Individual Financial Management 3. Project Coordination and Under IDA / 56240 Prior Consultant Limited 300,000.00 0.00 2016-07-30 2016-08-04 2016-08-25 2016-09-29 2017-03-28 Specialist (PMU) (for 12 Management Implementation Selection months) Page 11 ADSP SC-15 / National Individual 3. Project Coordination and Finance Officer (PMU) (for IDA / 56240 Prior Consultant Limited 150,000.00 24,000.00 Signed 2016-07-30 2016-08-04 2016-08-25 2016-09-29 2017-03-28 Management 75 months) Selection ADSP SC-16 / International Individual 3. Project Coordination and Procurement Specialist IDA / 56240 Prior Consultant Limited 300,000.00 199,500.00 Signed 2016-07-30 2016-08-04 2016-08-25 2016-09-29 2017-03-28 Management (PMU) (for 12 months) Selection Individual ADSP SC17 / National 3. Project Coordination and IDA / 56240 Prior Consultant Open 72,000.00 21,600.00 Signed Procurement Officer (PMU) Management Selection 1. Irrigation and Drainage SC-02 / IRRI Consultancy IDA / 56240 Prior Direct Selection Direct 1,750,000.00 0.00 Canceled 2016-12-30 2017-01-09 2017-03-15 2017-09-11 Management SC-18 / Technical 2. Farm Advisory and Assistance for Rice Based IDA / 56240 Prior Direct Selection Direct 1,700,000.00 1,500,000.00 Signed 2017-03-29 2017-04-08 2017-06-12 2017-12-09 Technical Services Farming System Individual ADSP SC 19 / National 1. Irrigation and Drainage IDA / 56240 Post Consultant Limited 12,000.00 12,000.00 Signed 2017-05-30 2017-05-30 2017-05-30 2017-07-04 2017-12-31 Finance Assistant( SC -19 ) Management Selection SC-17-B / National Individual 3. Project Coordination and Procurement Officer- IDA / 56240 Post Consultant Direct 72,000.00 31,075.00 Signed 2017-08-24 2017-09-03 2017-09-24 2017-10-29 2018-04-27 Management Replacement (SC-17) Selection ADSP SC-06 18-19 / Individual Package No.5 Lands Records 1. Irrigation and Drainage IDA / 56240 Post Consultant Open 30,000.00 0.00 Canceled 2018-05-08 2018-06-26 2018-07-17 2018-08-21 2019-02-17 Date Base Development Management Selection (DAMLS) (for 2 months) ADSP SC-07 18-19 / Individual Package No.6 Land Property 1. Irrigation and Drainage IDA / 56240 Post Consultant Limited 60,000.00 0.00 Canceled 2018-05-08 2018-05-13 2018-06-03 2018-07-08 2019-01-04 Valuation (DALMS) (for 2 Management Selection months) ADSP SC-10 18-19 / Package No.7 National 3. Project Coordination and IDA / 56240 Post Direct Selection Direct 300,000.00 0.00 Canceled 2018-05-08 2018-05-18 2018-07-22 2019-01-18 Project Manager (PMU) (for Management 75 months) ADSP SC-16 18-19 / Package No.12 International 3. Project Coordination and IDA / 56240 Post Direct Selection Direct 300,000.00 0.00 Canceled 2018-05-08 2018-05-18 2018-07-22 2019-01-18 Procurement Specialist Management (PMU) (for 12 months) ADSP SC-17 18-19 / Package No.13National 3. Project Coordination and IDA / 56240 Post Direct Selection Direct 72,000.00 0.00 Canceled 2018-05-08 2018-05-18 2018-07-22 2019-01-18 Procurement Officer (PMU) Management (for 24 months) ADSP SC-20 / Package Individual 3. Project Coordination and Pending No.16 National Office IDA / 56240 Post Consultant Open 24,000.00 0.00 2018-05-08 2018-06-26 2018-07-17 2018-08-21 2019-02-17 Management Implementation Assistant (for 24 months) Selection Individual ADSP SC 21 / Independent 1. Irrigation and Drainage IDA / 56240 Post Consultant Limited 100,000.00 67,000.00 Signed 2019-02-28 2019-03-05 2019-03-26 2019-04-30 2019-10-27 Dam Safety Review Expert Management Selection Individual ADSP SC-22 / National 1. Irrigation and Drainage Pending IDA / 56240 Post Consultant Limited 24,000.00 0.00 2019-08-16 2019-08-21 2019-09-11 2019-10-16 2020-04-13 Accountant Management Implementation Selection Page 12 ADSP SC23- 2019-2020 / Individual Package No.23 Benchmark 2. Farm Advisory and Pending IDA / 56240 Post Consultant Limited 30,000.00 0.00 2019-11-23 2019-11-28 2019-12-19 2020-01-23 2020-07-21 Survey Consultant for DOA Technical Services Implementation Selection Ext Individual SC - 24 2019-2020 / 1. Irrigation and Drainage Pending IDA / 56240 Post Consultant Limited 60,000.00 0.00 2019-12-13 2019-12-18 2020-01-08 2020-02-12 2020-08-10 National Accountant Officer Management Implementation Selection Page 13