PROCUREMENT PLAN (Textual Part) Project information: Central African Backbone SOP5 (P132821) Project Implementation agency: SOCOF Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January 2018 – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Africa : AFR RI-Central African Backbone SOP5 PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2018-02-10 2019-12-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132821 GPN Date: Project Name: AFR RI-Central African Backbone SOP5 Loan / Credit No: IDA / H9810 Executing Agency(ies): Centrale Central African Backbone WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component B - CAB5-REF-13 / Construction, Management Réhabilitation du Siège de Single Stage - One IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 500,000.00 0.00 Annulé 2018-09-27 2018-11-22 2019-02-20 la SOCOF SA (bâtiment Envelope the CAB5 Infrastructure affecté par le Gouvernement) through a PPP Scheme Component B - CAB5-REF-15 / Travaux de Construction, Management Open - Single Stage - One construction-Carrier Hôtel IDA / H9810 and Commercialization of A posteriori Appel d'offres 1,200,000.00 0.00 Annulé 2018-05-22 2018-05-27 2018-07-26 2018-08-25 2018-09-29 2019-03-28 International Envelope Cluster 1 à Kinshasa the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-16 / Construction, Management Aménagement des bureaux Single Stage - One IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 20,000.00 0.00 Annulé 2018-01-27 2018-03-24 2018-04-23 de la SOCOF SA Envelope the CAB5 Infrastructure (cloisonnement) through a PPP Scheme CAB5-REF-12 / Travaux et fournitures relatifs à la Component A - Emergence Passation de réahabilitation de la FO de IDA / H9810 of an Inclusive Digital A posteriori marché de gré à Direct 600,000.00 0.00 Annulé 2018-08-15 2018-08-20 2018-10-24 2019-05-22 la SCPT-Axe Muanda- Economy gré Kinshasa (avec HUAWEI) CAB5-REF-11 / Travaux de Component A - Emergence Single Stage - One construction du Centre de IDA / H9810 of an Inclusive Digital A posteriori Appel d'offres Open - National 3,000,000.00 0.00 Annulé 2018-07-30 2018-08-04 2018-09-15 2018-10-15 2018-11-19 2019-05-18 Envelope traitement D3E Economy CAB5-REF-14 / Travaux et Fournitures relatifs à la Component B - construction de la FO-Axe Construction, Management Open - Single Stage - One LUBUMBASHI-TENKE- IDA / H9810 and Commercialization of A priori Appel d'offres 50,000,000.00 0.00 Annulé 2018-03-15 2018-03-20 2018-06-18 2018-07-18 2018-08-22 2019-08-22 International Envelope DILOLO et TENKE-KABALO- the CAB5 Infrastructure KALEMIE-GOMA (Cluster through a PPP Scheme Sud et Est) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component B - CAB5-REF-3 / Acquisitions Construction, Management Single Stage - One des tablettes et logiciels IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 53,000.00 0.00 Annulé 2018-04-20 2018-06-15 2018-07-30 Envelope informatiques the CAB5 Infrastructure through a PPP Scheme Page 1 Component B - Construction, Management CAB5-REF-4 / Fournitures Single Stage - One IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 10,000.00 4,527.55 Achevé 2018-01-27 2018-03-24 2018-04-23 de bureau SOCOF 2018 Envelope the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-7 / Acquisition Construction, Management Single Stage - One d'un véhicule tout terrain IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 42,000.00 0.00 Annulé 2018-02-17 2018-04-14 2018-05-29 Envelope pour le suivi des travaux the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-8 / Acquisition Construction, Management Single Stage - One En cours du matériel audio visuel IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 12,000.00 0.00 2018-01-27 2018-03-24 2018-04-23 Envelope d'exécution pour la SOCOF SA the CAB5 Infrastructure through a PPP Scheme CAB5-REF-10 / Acquisition du matériel informatique, du Component C - Enabling matériel audio visuel et des Single Stage - One En cours IDA / H9810 Environment and Regulatory A posteriori Appel d'offres Open - National 500,000.00 492,790.59 2018-01-22 2018-01-27 2018-03-13 2018-04-12 2018-05-17 2018-07-16 logiciels pour le nouveau Envelope d'exécution Effectiveness système d'information de l'ARPTC Component B - CAB5-REF-2 / Mobilier de Construction, Management Single Stage - One bureau pour nouveau IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 2,000.00 0.00 Annulé 2018-02-27 2018-04-24 2018-05-24 Envelope personnel the CAB5 Infrastructure through a PPP Scheme CAB5-REF-1 / Fournitures des équipements et Component A - Emergence Open - Single Stage - One installations de l'intranet du IDA / H9810 of an Inclusive Digital A priori Appel d'offres 3,250,000.00 0.00 Annulé 2018-08-05 2018-08-10 2018-10-09 2018-11-08 2018-12-13 2019-04-12 International Envelope Gouvernement+Formation des Economy utlisateurs CAB5-REF-9 / Acquisition Component C - Enabling et installation des Open - Single Stage - One IDA / H9810 Environment and Regulatory A priori Appel d'offres 1,500,000.00 0.00 Annulé 2018-06-06 2018-06-11 2018-07-23 2018-08-22 2018-09-26 2019-03-25 équipements de cybersécurité International Envelope Effectiveness et intégrité des réseaux CAB5-REF-42 / Acquisition Component B - du matériel audiovisuel ( 2 Construction, Management Single Stage - One Appareils photo et 1 vidéo IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 2,960.00 0.00 Annulé 2018-02-27 2018-04-24 2018-10-21 Envelope retrojecteur) en faveur de la the CAB5 Infrastructure SOCOF SA through a PPP Scheme NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAB5-REF-5 / Sélection Component B - d'une société de maintenance Construction, Management Single Stage - One des équipements IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2018-03-27 2018-05-22 2019-05-22 Envelope informatiques et the CAB5 Infrastructure bureautiques through a PPP Scheme Component B - CAB5-REF-41 / Connexion Construction, Management Single Stage - One internet des bureaux de la IDA / H9810 and Commercialization of A posteriori Demande de prix Limited 54,000.00 18,685.66 Signé 2018-02-03 2018-03-27 2019-03-27 Envelope SOCOF the CAB5 Infrastructure through a PPP Scheme Page 2 CAB-REF- 70-ASC / Component B - Renouvellement du contrat Construction, Management Passation de d'entretien des bureaux de IDA / H9810 and Commercialization of A posteriori marché de gré à Direct 13,500.00 7,680.00 Signé 2019-10-09 2019-10-14 2019-11-18 2020-05-16 l'UCP CAB- SOCOF SA the CAB5 Infrastructure gré (SOCIETE AFRICAN TRADE through a PPP Scheme AND DEVELOPMENT) CAB-REF-69-ASC-19 / Component B - Renouvellement de contrat Construction, Management Passation de de gardiennage des locaux IDA / H9810 and Commercialization of A posteriori marché de gré à Direct 41,100.00 41,100.00 Signé 2019-10-09 2019-10-14 2019-11-18 2020-05-16 de l'UCP CAB5-SOCOF SA the CAB5 Infrastructure gré (LE GROUPE MAISHA through a PPP Scheme SECURITE PROTECTION) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAB5-REF-17 / Assistance Component A - Emergence Sélection fondée technique-conception de Open - IDA / H9810 of an Inclusive Digital A priori sur la qualité et 500,000.00 268,805.67 Signé 2017-01-15 2017-02-05 2017-03-21 2017-04-18 2017-05-18 2017-06-22 2017-07-27 2018-07-27 l'intranet du Gouvernement International Economy le coût y compris supervision CAB5-REF-24 / Component B - Recrutement d'une firme Construction, Management Sélection fondée chargée de la supervision Open - IDA / H9810 and Commercialization of A priori sur la qualité et 1,500,000.00 809,444.81 Signé 2016-12-15 2017-01-05 2017-02-18 2017-03-18 2017-04-17 2017-05-22 2017-06-26 2018-06-26 des travaux de construction International the CAB5 Infrastructure le coût FO-KINSHASA-MUANDA through a PPP Scheme (Cluster Ouest) CAB5-REF-25 / Recrutement d'une firme Component B - chargée de la supervision Construction, Management Sélection fondée des travaux de construction Open - En cours IDA / H9810 and Commercialization of A priori sur la qualité et 1,500,000.00 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 FO-LUBUMUBASHI-TENKE- International d'exécution the CAB5 Infrastructure le coût DILOLO et TENKE-KABALO- through a PPP Scheme KALEMIE-GOMA (Cluster Sud et Est) Component B - Sélection fondée CAB5-REF-26 / Elaboration Construction, Management sur les du Plan en faveur des IDA / H9810 and Commercialization of A posteriori Open - National 150,000.00 160,018.20 Signé 2017-06-20 2017-07-11 2017-08-24 2017-09-23 2017-10-28 2017-12-27 qualifications des Populations Autocthones the CAB5 Infrastructure consultants through a PPP Scheme CAB5-REF-28 / Proposition de la structure Component B - Sélection fondée organisationnelle et Construction, Management sur les élaboration du manuel de IDA / H9810 and Commercialization of A posteriori Open - National 70,000.00 0.00 Annulé 2018-02-15 2018-03-08 2018-04-21 2018-05-21 2018-06-25 2018-09-23 qualifications des procédures de gestion the CAB5 Infrastructure consultants administrative, fiancière et through a PPP Scheme comptable Component B - CAB5-REF-33 / Sélection fondée Construction, Management Recrutement d'un Cabinet sur les IDA / H9810 and Commercialization of A posteriori Open - National 30,000.00 0.00 Annulé 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2019-07-23 d'Avocats pour assistance qualifications des the CAB5 Infrastructure juridique consultants through a PPP Scheme CAB5-REF-37 / Component B - Recrutement d'un cabinet Sélection fondée Construction, Management pour la mesure de l'impact sur les Open - IDA / H9810 and Commercialization of A posteriori 100,000.00 0.00 Annulé 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-08-24 du déploiement de la Fibre qualifications des International the CAB5 Infrastructure sur l'axe MUANDA- consultants through a PPP Scheme KINSHASA Page 3 CAB5-REF-39 / Etudes de faisabiloité et assistance à Component C - Enabling Sélection fondée Open - l'acquisition du matériel pour IDA / H9810 Environment and Regulatory A priori sur la qualité et 500,000.00 162,150.00 Signé 2017-11-15 2017-12-06 2018-01-19 2018-02-16 2018-03-18 2018-04-22 2018-05-27 2019-05-27 International l'intégrité et la sécurité du Effectiveness le coût réseau Component B - CAB5-REF-30 / Construction, Management Sélection fondée Recrutement Auditeur CAB5, En cours IDA / H9810 and Commercialization of A posteriori sur la qualité et Open - National 30,000.00 0.00 2018-06-15 2018-07-06 2018-08-19 2018-09-16 2018-10-16 2018-11-20 2018-12-25 2020-05-13 Exercices 2018 - 2019 et d'exécution the CAB5 Infrastructure le coût clôture through a PPP Scheme CAB5-REF-19 / Formation Sélection fondée Component A - Emergence des cadres du MINIPTNTIC sur les Open - IDA / H9810 of an Inclusive Digital A posteriori 50,000.00 0.00 Annulé 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2018-09-21 en recyclage des déchets qualifications des International Economy électriques et électroniques consultants Sélection fondée Component A - Emergence CAB5-REF-18 / Etudes sur les Open - IDA / H9810 of an Inclusive Digital A posteriori 100,000.00 0.00 Annulé 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-07-24 EIES du Centre D3E qualifications des International Economy consultants CAB-REF-C-67-19 / Recrutement d'une ONG Component B - spécialisée dans la Construction, Management cartographie et évaluation Organisations à IDA / H9810 and Commercialization of A posteriori Direct 50,000.00 49,255.00 Signé 2019-12-30 2020-02-08 2020-03-14 2020-09-10 des risques VBG en faveur but non lucratif the CAB5 Infrastructure du projet CAB5 ( CARITAS through a PPP Scheme – DEVELOPPEMENT BOMA) Component B - Sélection fondée CAB-REF-71-SQC-19 / Construction, Management sur les En attente Recrutement d'un agence de IDA / H9810 and Commercialization of A posteriori Open - National 200,000.00 0.00 2020-02-25 2020-03-17 2020-04-30 2020-05-30 2020-07-04 2020-12-31 qualifications des d'exécution communication the CAB5 Infrastructure consultants through a PPP Scheme INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAB5-REF-23 / Protocole d'Accord avec l'Agence Component B - Congolaise de Construction, Management Sélection de l'Environnement pour le En cours IDA / H9810 and Commercialization of A priori consultants par Direct 100,000.00 0.00 2018-05-15 2018-06-12 2018-08-31 2019-08-31 Suivi Environnemental des d'examen the CAB5 Infrastructure entente directe activités du Projet CAB5- through a PPP Scheme Cluster Est et Sud (Phase 1) CAB5-REF-29 / Component B - Recurutement d'un Construction, Management Consultant individuel chargé IDA / H9810 and Commercialization of A posteriori Individuel Open 48,000.00 0.00 Annulé 2017-01-15 2017-03-05 2017-03-26 2017-04-30 2018-04-30 de communication du Projet the CAB5 Infrastructure CAB5 through a PPP Scheme Component B - CAB5-REF-31 / Construction, Management Recrutement d'un deuxième IDA / H9810 and Commercialization of A posteriori Individuel Limited 14,000.00 0.00 Annulé 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2019-05-15 chauffeur the CAB5 Infrastructure through a PPP Scheme CAB5-REF-34 / Component B - Recrutement d'un consultant Construction, Management individuel pour appuyer la IDA / H9810 and Commercialization of A posteriori Individuel Limited 15,000.00 22,034.00 Achevé 2018-01-15 2018-01-20 2018-02-10 2018-03-17 2018-05-16 revue à mi-parcours du the CAB5 Infrastructure Projet CAB5 through a PPP Scheme Page 4 CAB5-REF-35 / Component B - Recrutement de deux Construction, Management consultants individuels IDA / H9810 and Commercialization of A posteriori Individuel Open 96,000.00 0.00 Annulé 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2019-06-28 ingénieurs des the CAB5 Infrastructure télécommunications through a PPP Scheme Component B - Construction, Management CAB5-REF-36 / IDA / H9810 and Commercialization of A posteriori Individuel Limited 15,000.00 0.00 Annulé 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2019-05-15 Recurutement d'un Archiviste the CAB5 Infrastructure through a PPP Scheme CAB5-REF-38 / Recrutemet Component B - d'un consultant individuel Construction, Management architecte pour les études de IDA / H9810 and Commercialization of A posteriori Individuel Limited 15,000.00 0.00 Annulé 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-08-13 réhabilitation du bâtiment the CAB5 Infrastructure de la SOCOF SA through a PPP Scheme CAB5 -REF-40 / Renforcement des capacités sur l'utilisation et la Component C - Enabling Sélection de maintenance des IDA / H9810 Environment and Regulatory A priori consultants par Direct 500,000.00 0.00 Annulé 2018-07-15 2018-07-25 2018-09-28 2019-09-28 équipements de gestion des Effectiveness entente directe spectres de fréquences radioélectriques ( avec LS TELECOM) CAB5-REF-20 / Formation des cadres du MINIPTNTIC en gestion de projets de Component A - Emergence Sélection de mise en place des IDA / H9810 of an Inclusive Digital A posteriori consultants par Direct 100,000.00 94,700.00 Achevé 2017-11-15 2017-11-25 2018-01-29 2018-03-30 infrastructures à fibres Economy entente directe optiques+ intranet (avec ST2i CONSULTING) CAB5-REF-22 / Protocole d'Accord avec l'Agence Component B - Congolaise de Construction, Management Sélection de l'Environnement pour le IDA / H9810 and Commercialization of A posteriori consultants par Direct 50,000.00 23,000.00 Signé 2018-01-15 2018-02-12 2018-04-18 2019-04-18 Suivi Environnemental des the CAB5 Infrastructure entente directe activités du Projet CAB5-Axe through a PPP Scheme Kinshasa-Muanda CAB5-REF-27 / Protocole d'accord avec COPIREP pour Component B - la mise en œuvre de la Construction, Management Sélection de feuille de route de IDA / H9810 and Commercialization of A posteriori consultants par Direct 250,000.00 0.00 Annulé 2018-03-15 2018-03-25 2018-05-29 2019-05-29 restructuration de la SCPT the CAB5 Infrastructure entente directe et la mise en œuvre des through a PPP Scheme PPP Component B - CAB5-REF-32 / Construction, Management Recrutement d'un auditeur IDA / H9810 and Commercialization of A posteriori Individuel Open 36,000.00 0.00 Annulé 2017-10-13 2017-12-01 2017-12-22 2018-01-26 2019-01-26 interne the CAB5 Infrastructure through a PPP Scheme CAB5-REF-21 / Contractualisation avec la firme IDEA CONSULT Component B - INTERNATIONAL pour les Construction, Management Sélection de Etudes complémentaires IDA / H9810 and Commercialization of A posteriori consultants par Direct 400,000.00 395,550.00 Signé 2017-12-15 2017-12-25 2018-02-28 2018-05-29 d'impact environnemental et the CAB5 Infrastructure entente directe social et plan de through a PPP Scheme réinstalation des popolations du Projet CAB5 Page 5 CAB5-REF-43 / Protocole d'accord avec COPIREP pour Component B - la mise en œuvre de la Construction, Management Sélection de feuille de route de IDA / H9810 and Commercialization of A posteriori consultants par Direct 50,000.00 54,000.00 Signé 2018-08-20 2018-08-30 2018-11-03 2019-05-02 restructuration de la SCPT the CAB5 Infrastructure entente directe et la mise en œuvre des through a PPP Scheme PPP Component B - CAB5-REF-44 / Construction, Management En cours Renouvellement de contrat IDA / H9810 and Commercialization of A priori Individuel Direct 264,000.00 0.00 2019-03-01 2019-03-07 2019-03-12 2019-03-13 2020-03-12 d'examen du Directeur Général the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-45 / Construction, Management Renouvellement de contrat IDA / H9810 and Commercialization of A posteriori Individuel Direct 154,000.00 84,000.00 Signé 2019-03-01 2019-03-07 2019-03-08 2019-03-11 2020-03-10 du Directeur Administratif et the CAB5 Infrastructure Financier through a PPP Scheme Component B - CAB5-REF-46 / Construction, Management Renouvellement de contrat IDA / H9810 and Commercialization of A posteriori Individuel Direct 154,000.00 84,000.00 Signé 2019-03-01 2019-03-07 2019-03-08 2019-03-11 2020-03-10 du Directeur Technique the CAB5 Infrastructure through a PPP Scheme CAB5-REF-48 / Component B - Renouvellement de contrat Construction, Management de l'Assistant DG et Chargé IDA / H9810 and Commercialization of A posteriori Individuel Direct 55,000.00 30,000.00 Signé 2019-03-01 2019-03-07 2019-03-08 2019-03-11 2020-03-10 de Suivi d'exécution des the CAB5 Infrastructure Marchés through a PPP Scheme Component B - CAB5-REF-49 / Construction, Management En cours Renouvellement de contrat IDA / H9810 and Commercialization of A posteriori Individuel Direct 66,000.00 0.00 2019-03-01 2019-03-07 2019-03-08 2019-03-12 2020-03-11 d'examen de la Comptable the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-50 / Construction, Management En cours Recrutement d'un Chargé de IDA / H9810 and Commercialization of A posteriori Individuel Limited 66,000.00 0.00 2019-03-01 2019-03-06 2019-03-27 2019-04-15 2020-04-14 d'exécution Passation des Marchés the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-51 / Construction, Management Recrutement d'un Spécialiste En cours IDA / H9810 and Commercialization of A posteriori Individuel Limited 88,000.00 0.00 2019-03-01 2019-03-06 2019-03-20 2019-04-01 2020-03-31 en sauvegarde d'examen the CAB5 Infrastructure environnementale et sociale through a PPP Scheme Component B - CAB5-REF-52 / Construction, Management En cours Recrutement d'un Spécialiste IDA / H9810 and Commercialization of A posteriori Individuel Limited 88,000.00 0.00 2019-03-01 2019-03-06 2019-03-27 2019-04-21 2020-04-20 d'exécution en Suivi-évaluation the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-53 / Construction, Management En cours Renouvellement de contrat IDA / H9810 and Commercialization of A posteriori Individuel Direct 33,000.00 0.00 2019-03-01 2019-03-07 2019-03-08 2019-03-11 2020-03-10 d'examen de la Trésorière the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-54 / Construction, Management Renouvellement de contrat IDA / H9810 and Commercialization of A posteriori Individuel Direct 29,700.00 16,200.00 Signé 2019-03-01 2019-03-07 2019-03-08 2019-03-11 2020-03-10 de l'Intendant the CAB5 Infrastructure through a PPP Scheme Page 6 Component B - CAB5-REF-55 / Construction, Management Renouvellement de contrat IDA / H9810 and Commercialization of A posteriori Individuel Direct 26,400.00 14,400.00 Signé 2019-03-01 2019-03-07 2019-03-08 2019-03-11 2020-03-10 du chauffeur the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-47 / Construction, Management Renouvellement de contrat IDA / H9810 and Commercialization of A priori Individuel Direct 231,000.00 0.00 Annulé 2019-03-01 2019-03-07 2019-03-12 2019-03-13 2020-03-12 du Spécialiste Principal en the CAB5 Infrastructure Passation des Marchés through a PPP Scheme Component B - CAB5-REF-47B / Construction, Management Recrutement d'un Spécialiste IDA / H9810 and Commercialization of A posteriori Individuel Open 100,000.00 96,000.00 Signé 2019-06-05 2019-07-24 2019-08-14 2019-09-18 2020-03-16 en Passation des Marchés the CAB5 Infrastructure through a PPP Scheme CAB5-REF-64 / Component B - Renouvellement de contrat Construction, Management En cours du Consultant Point focal IDA / H9810 and Commercialization of A posteriori Individuel Direct 49,920.00 0.00 2019-07-31 2019-08-10 2019-08-31 2019-10-05 2020-04-02 d'examen Chef de la composante C du the CAB5 Infrastructure projet CAB5 through a PPP Scheme CAB5- CI-66-19 / Component B - Recrutement du Responsable Construction, Management En cours Administratif, Financier et IDA / H9810 and Commercialization of A posteriori Individuel Open 84,000.00 0.00 2019-09-30 2019-11-18 2019-12-09 2020-01-13 2020-07-11 d'exécution Comptable de CAB5-SOCOF the CAB5 Infrastructure SA through a PPP Scheme CAB5-REF-63 / Component B - Recrutement d'un Construction, Management Sélection de cabinet/ONG spécialisé (e) IDA / H9810 and Commercialization of A posteriori consultants par Direct 150,000.00 0.00 Annulé 2019-07-12 2019-07-22 2019-09-25 2020-03-23 dans la cartographie et the CAB5 Infrastructure entente directe évaluation des risques VBG through a PPP Scheme en faveur du projet CAB5 Component B - Construction, Management CAB5-REF-61 / Secrétaire En attente IDA / H9810 and Commercialization of A posteriori Individuel Limited 18,000.00 0.00 2019-12-30 2020-01-04 2020-01-25 2020-02-29 2021-02-28 Administratif d'exécution the CAB5 Infrastructure through a PPP Scheme CAB5-REF-65 / Component B - Renouvellement de contrat Construction, Management du Consultant Point focal IDA / H9810 and Commercialization of A posteriori Individuel Direct 49,920.00 0.00 Annulé 2019-07-31 2019-08-10 2019-08-31 2019-10-05 2020-04-02 PTNTIC Chef de la the CAB5 Infrastructure composante A du projet through a PPP Scheme CAB5 Component B - Construction, Management CAB5-REF-62 / Chargé des En attente IDA / H9810 and Commercialization of A posteriori Individuel Open 48,000.00 0.00 2019-12-30 2020-02-17 2020-03-09 2020-04-13 2020-10-10 questions juridiques d'exécution the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-REF-60 / Construction, Management Recrutement d'un Spécialiste IDA / H9810 and Commercialization of A posteriori Individuel Open 48,000.00 0.00 Annulé 2019-05-24 2019-07-12 2019-08-02 2019-09-06 2020-03-04 de Violence basée sur le the CAB5 Infrastructure Genre SVGB through a PPP Scheme Component B - CAB-REF- 68-CI-19 / Construction, Management Recrutement d'un Spécialiste En cours IDA / H9810 and Commercialization of A posteriori Individuel Limited 48,000.00 0.00 2019-12-30 2020-01-04 2020-01-25 2020-02-29 2020-08-27 de Violence basée sur le d'exécution the CAB5 Infrastructure Genre SVGB through a PPP Scheme Page 7 Component B - Construction, Management CAB-REF-73-CI-19 / En attente IDA / H9810 and Commercialization of A posteriori Individuel Open 36,000.00 0.00 2020-01-31 2020-03-20 2020-04-10 2020-05-15 2020-11-11 Recrutement d'un Auditeur d'exécution the CAB5 Infrastructure through a PPP Scheme Component B - CAB5-74-CI-19 / Construction, Management En attente Recrutement d'un Spécialiste IDA / H9810 and Commercialization of A posteriori Individuel Open 52,000.00 0.00 2020-01-31 2020-03-20 2020-04-10 2020-05-15 2020-11-11 d'exécution en Communication the CAB5 Infrastructure through a PPP Scheme CAB5-75-CI- 19 / Recrutement d'un Expert Component A - Emergence En cours juridique pour l'analyse IDA / H9810 of an Inclusive Digital A posteriori Individuel Limited 50,000.00 0.00 2019-12-31 2020-01-05 2020-01-26 2020-03-01 2020-08-28 d'exécution critique sur les articles de Economy la loi de Telecom CAB5-75-CI- ED-19 / Recrutement de Ndukuma Adjayi Kodjo Expert Component A - Emergence Sélection de En attente juridique pour l'élaboration IDA / H9810 of an Inclusive Digital A posteriori consultants par Direct 25,000.00 0.00 2020-03-31 2020-04-10 2020-06-14 2020-12-11 d'exécution des mesures d’encadrement Economy entente directe sur certains articles de la loi de Telecom Page 8