PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive Bidding 1. 3M and above All contracts (ICB) (Goods) National Competitive Bidding (NCB) 2. less than 3M 2M and above (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated: May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 LN 8421 PH Procurement Plan Updated June 2018 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Ref. No. Description g ent Comments US$1= Source nce by Bank Opening Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review Threshold No. Selection Method Method Threshold US$ US$ 1. Competitive Methods 0.3M & above (may be used for also less 1m and above (QCBS, QBS, FBS) (Firms) than 0.3M) 2. Competitive Method CQS less than 0.3M None (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to justification Firms: 1M and above; Individuals) in accordance with paras. 3.9 and 5.4 Individuals 0.3M and respectively of Consultant Guidelines at above. the Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref. Description of Estimated Cost (USD Funding Procuring Expected Bid Comme Selection Method No. Contract Package million) Source Agency Opening Date nts Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 million) LP/GoP Selection US$1,042,75 Single Source Luzon A ( Php59.152 million) LP/GoP Selection US$1,042,75 Single Source Luzon B ( Php48.614 million) LP/GoP Selection US$1,042,75 Single Source Visaya ( Php29.612 million) LP/GoP Selection US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: LN 8421 PH Procurement Plan Updated June 2018 ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2019-03-11 2019-10-11 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 88160 Executing Agency(ies): Department of Agriculture-Philippine Rural Development Project PSO Luzon A WORKS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IB-RCAR-BEN-013- Pending LAT-001-2016-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 207,000.00 0.00 Implementat 2018-09-01 2018-09-06 2018-10-18 2018-12-31 2019-02-04 2019-08-03 Construction of Slope Infrastructure Development Envelope ion Protection of Puguis PRDP-IB-RCAR-BEN-016- Pending BOK-001-2018-AF / Component 2: Request for Single Stage - One IBRD / 88160 Post Open - National 90,784.31 0.00 Implementat 2018-09-06 2018-11-01 2019-04-30 Construction of Salat-Surek Infrastructure Development Quotations Envelope ion Tramline PRDP-IB-RCAR-BEN-017- Pending BOK-002-2018-AF / Component 2: Request for Single Stage - One IBRD / 88160 Post Open - National 93,137.25 0.00 Implementat 2018-09-06 2018-11-01 2019-04-30 Construction of Wakal Infrastructure Development Quotations Envelope ion Tramline PRDP-IB-RCAR-IFU-015- Pending BAN-006-2017-AF / Component 2: Single Stage - Two IBRD / 88160 Prior Request for Bids Open - National 2,449,764.71 0.00 Implementat 2018-09-01 2018-09-06 2018-10-18 2018-12-31 2019-02-04 2019-08-03 Improvement of Viewpoint- Infrastructure Development Envelope ion San Fernando FMR PRDP-IB-RCAR-KAL-004- Pending 000-000-2015-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 4,523,529.41 0.00 Implementat 2018-09-01 2018-09-06 2018-10-18 2018-12-31 2019-02-04 2019-08-03 Improvement of Bado Infrastructure Development Envelope ion Dangwa-Guilayon FMR PRDP-IB-RCAR-IFU-021- BAN-011-2018-AF / Pending Component 2: Single Stage - Two Construction of Anaba- IBRD / 88160 Post Request for Bids Open - National 4,823,549.02 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Infrastructure Development Envelope Ducligan-Banao FMR with ion Bridge PRDP-IB-RCAR-IFU-020- Pending 000-000-2018-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,754,823.53 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Improvement of Junction Infrastructure Development Envelope ion Alimit Nattum FMR Improvement PRDP-IB-RCAR-ABR-009- Pending 000-000-2016-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 194,156.86 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Construction of Warehouse Infrastructure Development Envelope ion of Lapaz, abra PRDP-IB-RCAR-APA-001- Pending 000-000-2015-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 3,884,509.80 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Improvement of Sta. Maria- Infrastructure Development Envelope ion Mallig-Upper Atok FMR PRDP-IB-RCAR-ABR-010- Pending 000-000-2016-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 151,117.65 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Construction of Slope Infrastructure Development Envelope ion Stabilization at Tineg, Abra PRDP-IB-RCAR-IFU-004- Pending 000-000-2016-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 118,274.51 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Construction of Slope Infrastructure Development Envelope ion Protection of Asipulo, Ifugao PRDP-IB-RCAR-APA-002- Pending 000-000-2015-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,254,901.96 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Improvement of Cabatacan- Infrastructure Development Envelope ion San Jose-San Mariano FMR PRDP-IB-RCAR-BEN-006- Pending KAB-001-2016-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,198,454.04 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Improvement of Balang- Infrastructure Development Envelope ion Bocao FMR with Bridge PRDP-IB-R001-LAU-006-000- Pending 000-2015-AF / Rehabilitation Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 1,403,686.27 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 of Parasapas FMR with Infrastructure Development Envelope ion Bridge PRDP-IB-R001-ILN-024- Pending PAO-002-2017-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,480,588.24 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Rehabilitation of Paoay Infrastructure Development Envelope ion Communal Irrigation System PRDP-IB-R001-ILS-007-TAG- Pending 001-2017-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,352,941.18 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 of Jardin-Sawat Bridge with Infrastructure Development Envelope ion Approaches PRDP-IB-R002-ISA-027-000- Pending 000-2016-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 239,529.41 0.00 Implementat 2018-09-01 2018-09-06 2018-10-18 2018-12-31 2019-02-04 2019-08-03 of Warehouse with Solar Infrastructure Development Envelope ion Dryer at Echague, Isabela PRDP-IB-R002-ISA-021-000- Pending 000-2016-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 240,509.80 0.00 Implementat 2018-09-01 2018-09-06 2018-10-18 2018-12-31 2019-02-04 2019-08-03 of Warehouse with Solar Infrastructure Development Envelope ion Dryer at Gamu, Isabela PRDP-IB-R002-ISA-022-000- Pending 000-2016-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 245,921.57 0.00 Implementat 2018-09-01 2018-09-06 2018-10-18 2018-12-31 2019-02-04 2019-08-03 of Warehouse with Solar Infrastructure Development Envelope ion Dryer at Roxas, Isabela PRDP-IB-R002-ISA-028-000- Pending 000-2016-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 246,509.80 0.00 Implementat 2018-09-01 2018-09-06 2018-10-18 2018-12-31 2019-02-04 2019-08-03 of Warehouse with Solar Infrastructure Development Envelope ion Dryer at Mallig, Isabela Page 1 PRDP-IB-R002-NUV-004- Pending AMB-001-2018-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,623,490.20 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Rehabilitation of Tiblac-Dulli Infrastructure Development Envelope ion FMR PRDP-IB-R002-QUI-007-000- 000-2015-AF / Rehabilitation Pending Component 2: Single Stage - Two of National Road Junction- IBRD / 88160 Post Request for Bids Open - National 2,551,940.22 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Infrastructure Development Envelope Ricarte Sur-Magsaysay ion Farm to Market Road PRDP-IB-R002-QUI-008-000- Pending 000-2015-AF / Rehabilitation Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 1,038,451.74 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 of Lusod-Sto Nińo Farm to Infrastructure Development Envelope ion Market Road PRDP-IB-R002-ISA-010-SAO- Pending 001-2015-AF / Rehabilitation Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,966,215.69 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 of Calaocan-Batal Farm to Infrastructure Development Envelope ion Market Road PRDP-IB-R002-ISA-011-SAO- Pending 002-2015-AF / Rehabilitation Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 1,624,313.73 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 of Baluarte-Sinili Farm to Infrastructure Development Envelope ion Market Road PRDP-IB-R002-ISA-031-000- Pending 000-2016-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 786,235.29 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 of Sinalugan Communal Infrastructure Development Envelope ion Pump Irrigation Project PRDP-IB-R002-ISA-029-000- Pending 000-2016-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 796,078.43 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 of Gangalan Communal Infrastructure Development Envelope ion Pump Irrigation Project PRDP-IB-R002-ISA-033- Pending RAM-001-2017-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,489,372.55 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Rehabilitation of Oscariz- Infrastructure Development Envelope ion Nagbacalan Farm to Market Road PRDP-IB-R003-NUE-021- Pending PAL-001-2017-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 3,763,091.45 0.00 Implementat 2019-01-02 2019-01-07 2019-02-18 2019-05-03 2019-06-07 2019-12-04 Construction of Cold Infrastructure Development Envelope ion Storage PRDP-IB-R003-NUE-017- CAR-006-2016-AF / Pending Improvement of Poblacion Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 749,873.53 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 Sur, La Torre, Bantug and Infrastructure Development Envelope ion Mamandil Farm to Market Road PRDP-IB-R003-BUL-005-000- Pending 000-2015-AF / Improvement Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 983,392.16 0.00 Implementat 2018-11-01 2018-11-06 2018-12-18 2019-03-02 2019-04-06 2019-10-03 of Sumandig-Bubulong Infrastructure Development Envelope ion Malaki FMR PRDP-IB-R003-PAM-001- Pending 000-000-2014-AF / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 1,217,705.88 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Construction of Calantas- Infrastructure Development Envelope ion Planas-San Jose FMR PRDP-IB-R003-ZAM-004- Pending Component 2: Single Stage - Two 000-000-2015-AF / IBRD / 88160 Post Request for Bids Open - National 1,994,078.43 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 Infrastructure Development Envelope Construction of Dirita-San ion Agustine FMR PRDP-IB-R003-BAT-006-000- Pending 000-2017-AF / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 51,372.55 0.00 Implementat 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 of Multi Commodity Solar Infrastructure Development Envelope ion Tunnel Dryers PRDP-IB-R002-NUV-004- Pending AMB-001-2018 / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 2,524,490.57 0.00 Implementat 2019-08-05 2019-08-10 2019-09-21 2019-12-04 2020-01-08 2020-07-06 Rehabilitation of Tiblac Duli Infrastructure Development Envelope ion Farm To Market Road PRDP-IB-R003-NUE-008- Pending TAL-001-2015 / Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 721,566.04 0.00 Implementat 2019-08-05 2019-08-10 2019-09-21 2019-12-04 2020-01-08 2020-07-06 Improvement of Poblacion Infrastructure Development Envelope ion Sur-La Torre-Mamandil FMR PRDP-IB-R003-PAM-001- Pending 000-000-2015 / Construction Component 2: Single Stage - Two IBRD / 88160 Post Request for Bids Open - National 1,188,641.51 0.00 Implementat 2019-12-01 2019-12-06 2020-01-17 2020-03-31 2020-05-05 2020-11-01 of Calantas - Planas Farm Infrastructure Development Envelope ion to Market Road PRDP-IB-RCAR-BEN-006- Pending Component 2: Single Stage - Two 000-000-2015 / Improvement IBRD / 88160 Post Request for Bids Open - National 2,132,075.47 0.00 Implementat 2019-12-01 2019-12-06 2020-01-17 2020-03-31 2020-05-05 2020-11-01 Infrastructure Development Envelope of Balang-Bocao with bridge ion GOODS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Process Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Amount Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal (US$) Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Page 2 Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual PRDP-IS-PSO-IB-002-000- Component 4: Project Pending IBRD / 88160 Post Consultant Open 7,058.82 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 2018-AF / Water Specialist Implementation Support Implementation Selection PRDP-IS-PSO-IB-004-003- Component 4: Project Pending 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Implementation Infrastructure Engineer PRDP-IS-PSO-DPD-001-000- Component 2: Pending 2018-AF / Executive IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Infrastructure Development Implementation Assistant PRDP-IS-PSO-PROC-002- Individual Component 4: Project Pending 003-2018-AF / Project IBRD / 88160 Post Consultant Open 4,235.29 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection PRDP-IS-PSO-MAE-001-002- Individual Component 4: Project Pending 2018-AF / Monitoring and IBRD / 88160 Post Consultant Open 6,352.94 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Evaluation Officer Selection PRDP-IS-PSO-GGU-002-003- Individual Component 4: Project Pending 2018-AF / Project IBRD / 88160 Post Consultant Open 4,235.29 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-RCAR-ADM-001- Component 4: Project Pending IBRD / 88160 Post Consultant Open 2,117.65 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 000-2018-AF / Cash Clerk Implementation Support Implementation Selection PRDP-IS-RCAR-ODP-001- Individual Component 4: Project Pending 002-2018-AF / Project IBRD / 88160 Post Consultant Open 3,529.41 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection PRDP-IS-RCAR-DPD-003- Component 4: Project Pending 000-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Implementation Development Associate PRDP-IS-RCAR-SES-001- Individual Component 4: Project Pending 003-2018-AF / Project IBRD / 88160 Post Consultant Open 3,529.41 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection PRDP-IS-RCAR-GGU-001- Individual Component 4: Project Pending 002-2018-AF / Project IBRD / 88160 Post Consultant Open 3,529.41 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection PRDP-IS-RCAR-GGU-001- Individual Component 4: Project Pending 003-2018-AF / Project IBRD / 88160 Post Consultant Open 3,529.41 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection PRDP-IS-RCAR-ADM-002- Individual Component 4: Project Pending 001-2018-AF / IBRD / 88160 Post Consultant Open 2,117.65 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Administrative Staff Selection PRDP-IS-RCAR-ADM-002- Individual Component 4: Project Pending 002-2018-AF / IBRD / 88160 Post Consultant Open 2,117.65 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Administrative Staff Selection PRDP-IS-RCAR-IB-001-005- Individual Component 4: Project Pending 2018-AF / Rural IBRD / 88160 Post Consultant Open 5,647.06 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-RCAR-IB-001-006- Component 4: Project Pending 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Implementation Infrastructure Engineer PRDP-IS-R001-GGU-002- Component 4: Project Pending 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Implementation Development Associate Individual PRDP-IS-R002-ADM-003- Component 4: Project Pending IBRD / 88160 Post Consultant Open 1,411.76 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 000-2018-AF / Chauffer Implementation Support Implementation Selection Individual PRDP-IS-R002-ADM-004- Component 4: Project Pending IBRD / 88160 Post Consultant Open 5,647.06 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 000-2018-AF / Chauffer Implementation Support Implementation Selection PRDP-IS-R002-FIN-002-001- Individual Component 4: Project Pending 2018-AF / Finance Analyst IBRD / 88160 Post Consultant Open 4,117.65 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation I Selection PRDP-IS-R003-PROC-002- Individual Component 4: Project Pending 003-2018-AF / Project IBRD / 88160 Post Consultant Open 3,529.41 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection PRDP-IS-R003-FIN-001-000- Individual Component 4: Project Pending 2018-AF / Finance Analyst IBRD / 88160 Post Consultant Open 4,941.18 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation I Selection PRDP-IS-R003-IB-001-005- Component 4: Project Pending 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Implementation Infrastructure Engineer PRDP-IS-R003-INF-001-000- Individual Component 4: Project Pending 2018-AF / Project IBRD / 88160 Post Consultant Open 3,529.41 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-R003-IB-003-000- Component 4: Project Pending IBRD / 88160 Post Consultant Open 2,823.53 0.00 2017-12-01 2018-01-19 2018-02-09 2018-03-16 2018-09-12 2018-AF / Chaffeur Implementation Support Implementation Selection PRDP-IS-PSO-IB-001-000- Component 4: Project 2018-AF / I-BUILD IBRD / 88160 Post Direct Selection Direct 9,882.35 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Component Head PRDP-IS-PSO-IB-003-000- Component 4: Project 2018-AF / Roads and IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Bridges Specialist PRDP-IS-PSO-IB-004-001- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer Page 3 PRDP-IS-PSO-IB-004-002- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R002-IB-004-001- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-PSO-IB-005-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-DPD-002-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Economist Implementation Support PRDP-IS-R002-IB-004-002- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-PSO-DPD-003-000- Component 4: Project 2018-AF / Compliance IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer PRDP-IS-R002-IB-004-003- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-PSO-INF-001-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Writer Implementation Support PRDP-IS-PSO-INF-002-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Lay-Out Artist Implementation Support PRDP-IS-PSO-PROC-001- Component 4: Project 000-2018-AF / Procurement IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer PRDP-IS-R002-IB-004-004- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-PSO-PROC-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-PROC-002- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R002-IB-004-005- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R002-IB-004-006- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-PSO-MAE-001-001- Component 4: Project 2018-AF / Monitoring and IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Evaluation Officer PRDP-IS-PSO-FIN-001-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support II PRDP-IS-R002-IB-005-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R002-ODP-001-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 8,470.59 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Executive Asst. Implementation Support PRDP-IS-R002-ODP-002-000- Component 4: Project 2018-AF / Compliance IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer PRDP-IS-R002-ADM-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / Admin Implementation Support Officer I PRDP-IS-R002-ADM-002- Component 4: Project 000-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R002-FIN-002-002- Component 4: Project IBRD / 88160 Post Direct Selection Direct 9,882.35 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Finance Analyst Implementation Support I PRDP-IS-PSO-FIN-002-001- Component 4: Project 2018-AF / Financial Analyst IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support I PRDP-IS-R002-FIN-002-003- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-FIN-002-002- Component 4: Project 2018-AF / Financial Analyst IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support I PRDP-IS-PSO-FIN-002-003- Component 4: Project 2018-AF / Financial Analyst IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support I PRDP-IS-R002-FIN-002-004- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-FIN-001-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Budget Analyst Implementation Support PRDP-IS-PSO-GGU-001-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / GIS Data Officer Implementation Support PRDP-IS-R002-PROC-001- Component 4: Project 000-2018-AF / Procurement IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer Page 4 PRDP-IS-PSO-GGU-002-001- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R002-PROC-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R002-MAE-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 001-2018-AF / M&E Officer Implementation Support PRDP-IS-PSO-GGU-002-002- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-SES-001-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 9,882.35 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / SES Unit Head Implementation Support PRDP-IS-R002-MAE-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-SES-002-000- Component 4: Project 2018-AF / Social Safeguards IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Specialist PRDP-IS-R002-MAE-002- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-SES-003-000- Component 4: Project 2018-AF / Environmental IBRD / 88160 Post Direct Selection Direct 6,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Safeguards Officer PRDP-IS-R002-SES-002-000- Component 4: Project 2018-AF / Social Safeguard IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Specialist PRDP-IS-PSO-SES-004-000- Component 4: Project 2018-AF / Program IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R002-SES-003-000- 2018-AF / Social Component 4: Project IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Environmental Safeguard Implementation Support Officer PRDP-IS-PSO-ADM-001-000- Component 4: Project 2018-AF / Administrative IBRD / 88160 Post Direct Selection Direct 4,235.29 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer I PRDP-IS-R002-SES-004-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-ADM-002-001- Component 4: Project 2018-AF / Administrative IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Staff PRDP-IS-PSO-ADM-002-002- Component 4: Project 2018-AF / Administrative IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Staff PRDP-IS-R002-GGU-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / GIS Implementation Support Specialist PRDP-IS-PSO-ADM-003-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Cashier Clerk Implementation Support PRDP-IS-PSO-ADM-004-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Chaffeur Implementation Support PRDP-IS-PSO-ADM-004-002- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Chaffeur Implementation Support PRDP-IS-R002-GGU-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 11,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 001-2018-AF / GIS Officer Implementation Support PRDP-IS-PSO-ADM-004-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Chaffeur Implementation Support PRDP-IS-R002-GGU-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R002-INF-001-000- Component 4: Project 2018-AF / Info & Advocacy IBRD / 88160 Post Direct Selection Direct 12,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Specialist PRDP-IS-R002-INF-002-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 8,470.59 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Layout Artist Implementation Support PRDP-IS-PSO-ADM-006-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Utility Implementation Support PRDP-IS-R002-INF-003-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 7,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-PSO-ADM-005-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,549.02 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Messenger Implementation Support PRDP-IS-R002-INF-004-000- Component 4: Project 2018-AF / IBRD / 88160 Post Direct Selection Direct 8,470.59 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Photographer/Videographer PRDP-IS-RCAR-ODP-001- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-FIN-001- Component 4: Project 001-2018-AF / Financial IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Analyst 1 Page 5 PRDP-IS-R003-SES-001-000- Component 4: Project 2018-AF / Social Safeguard IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer PRDP-IS-RCAR-FIN-001- Component 4: Project 002-2018-AF / Financial IBRD / 88160 Post Direct Selection Direct 4,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Analyst 1 PRDP-IS-R003-SES-002-001- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-SES-002-002- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-ODP-002- Component 4: Project 000-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-MAE-001- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-MAE-001- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-PROC-001- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-PROC-001- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-PROC-001- Component 4: Project 003-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-SES-001- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-SES-001- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-INF-001- Component 4: Project 000-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-GGU-001- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-RCAR-ADM-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 001-2018-AF / Chauffer Implementation Support PRDP-IS-RCAR-ADM-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 002-2018-AF / Chauffer Implementation Support PRDP-IS-RCAR-ADM-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 003-2018-AF / Chauffer Implementation Support PRDP-IS-RCAR-ADM-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 004-2018-AF / Chauffer Implementation Support PRDP-IS-RCAR-IB-001-001- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R003-GGU-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / GIS Data Implementation Support Officer PRDP-IS-R003-GGU-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-GGU-002- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-PROC-001- Component 4: Project 000-2018-AF / Procurement IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer PRDP-IS-R003-PROC-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-PROC-002- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-MAE-001- Component 4: Project 000-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-MAE-001- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-OFP-001-001- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-OFP-001-002- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-IB-001-001- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer Page 6 PRDP-IS-RCAR-IB-001-002- Component 2: 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Infrastructure Development Infrastructure Engineer PRDP-IS-R003-IB-001-002- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-RCAR-IB-001-003- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R003-IB-001-003- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-RCAR-IB-001-004- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-RCAR-IB-002-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-IB-001-004- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 5,647.06 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R003-IB-002-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-FIN-001-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 4,117.65 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Finance Analyst Implementation Support I PRDP-IS-R001-FIN-002-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-ADM-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / Cashier Clerk Implementation Support PRDP-IS-R001-PROC-001- Component 4: Project 000-2018-AF / Procurement IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Officer PRDP-IS-R003-ADM-002- Component 4: Project 000-2018-AF / IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Administrative Staff PRDP-IS-R003-ADM-003- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / Chaffeur Implementation Support PRDP-IS-R001-PROC-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-OFP-002-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,823.53 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Chaffeur Implementation Support PRDP-IS-R001-PROC-002- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R003-ADM-004- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,117.65 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / Utility Implementation Support PRDP-IS-R001-PROC-002- Component 4: Project 003-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-INF-001-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 4,117.65 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Writer Implementation Support PRDP-IS-R001-INF-002-000- Component 4: Project IBRD / 88160 Post Direct Selection Direct 3,529.41 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 2018-AF / Videographer Implementation Support PRDP-IS-R001-SES-001-000- Component 4: Project 2018-AF / Environmental IBRD / 88160 Post Direct Selection Direct 5,294.12 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Safeguard Specialist PRDP-IS-R001-SES-002-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-SES-002-001- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-MAE-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 3,764.71 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 001-2018-AF / M&E Officer Implementation Support PRDP-IS-R001-MAE-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 588.24 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-MAE-002- Component 4: Project 002-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-GGU-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 4,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / GIS Data Implementation Support Officer PRDP-IS-R001-GGU-002- Component 4: Project 001-2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-OPD-001-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-DPD-001-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate Page 7 PRDP-IS-R001-IB-001-001- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R001-IB-001-002- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R001-IB-001-003- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R001-IB-001-004- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R001-IB-001-005- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R001-IB-001-006- Component 4: Project 2018-AF / Rural IBRD / 88160 Post Direct Selection Direct 4,705.88 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Infrastructure Engineer PRDP-IS-R001-IB-002-000- Component 4: Project 2018-AF / Project IBRD / 88160 Post Direct Selection Direct 2,941.18 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 Implementation Support Development Associate PRDP-IS-R001-ADM-001- Component 4: Project IBRD / 88160 Post Direct Selection Direct 1,058.82 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 000-2018-AF / Cash Clerk Implementation Support PRDP-IS-R001-ADM-002- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 001-2018-AF / Chauffeur Implementation Support PRDP-IS-R001-ADM-002- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 002-2018-AF / Chauffeur Implementation Support PRDP-IS-R001-ADM-002- Component 4: Project IBRD / 88160 Post Direct Selection Direct 2,352.94 0.00 Canceled 2017-12-01 2017-12-11 2018-02-14 2018-08-13 003-2018-AF / Chauffeur Implementation Support Individual PRDP-IS-NLU-002-DPD-001- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,207.55 0.00 2019-04-01 2019-04-11 2019-05-02 2019-06-06 2019-12-03 2019-AF / Economist Implementation Support Implementation Selection PRDP-IS-NLU-004-DPD-003- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Open 6,113.21 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer II Selection PRDP-IS-NLU-005-DPD-004- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Direct 5,094.34 0.00 2019-04-01 2019-04-11 2019-05-02 2019-06-06 2019-12-03 Implementation Support Implementation Officer I Selection PRDP-IS-NLU-006-DPD-005- Individual Component 4: Project Pending 2019-AF / Compliance IBRD / 88160 Post Consultant Direct 12,452.83 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection Individual PRDP-IS-NLU-007-ACE-001- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,962.26 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-NLU-009-ACE-003- Individual Component 4: Project Pending 2019-AF / Media Production IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-010-PRO-001- Individual Component 4: Project Pending 2019-AF / Procurement Unit IBRD / 88160 Post Consultant Open 11,773.58 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Head Selection PRDP-IS-NLU-011-PRO-002- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Direct 11,207.55 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-NLU-012-PRO-003- Individual Component 4: Project Pending 2019-AF / Procurement IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-013-PRO-004- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,358.49 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-014-PRO-005- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,358.49 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-015-PRO-006- Individual Component 4: Project Pending 2019-AF / Associate IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NLU-016-MNE- Individual Component 4: Project Pending 001-2019-AF / M&E IBRD / 88160 Post Consultant Open 10,188.68 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Specialist Selection Individual PRDP-IS-NLU-017-MNE- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,207.55 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 002-2019-AF / M&E Officer Implementation Support Implementation Selection Individual PRDP-IS-NLU-018-MNE- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 003-2019-AF / M&E Officer Implementation Support Implementation Selection PRDP-IS-NLU-019-FIN-001- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Open 10,188.68 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation III Selection PRDP-IS-NLU-020-FIN-002- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation II Selection PRDP-IS-NLU-021-FIN-003- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation II Selection PRDP-IS-NLU-022-FIN-004- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 2,037.74 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation II Selection Page 8 PRDP-IS-NLU-023-ACT-001- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation II (Accountant) Selection PRDP-IS-NLU-024-ACT-002- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 1,811.32 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation I Selection PRDP-IS-NLU-025-ACT-003- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 1,811.32 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation I Selection PRDP-IS-NLU-026-ACT-004- Individual Component 4: Project Pending 2019-AF / Financial Analyst IBRD / 88160 Post Consultant Direct 9,962.26 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation I Selection Individual PRDP-IS-NLU-027-BUD-001- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,962.26 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / Budget Analyst Implementation Support Implementation Selection Individual PRDP-IS-NLU-028-GGU-001- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,207.55 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / GIS Data Officer Implementation Support Implementation Selection Individual PRDP-IS-NLU-029-GGU-002- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 2019-AF / GIS Data Officer Implementation Support Implementation Selection PRDP-IS-NLU-030-GGU-003- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,358.49 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-031-GGU-004- Individual Component 4: Project Pending 2019-AF / Project IBRD / 88160 Post Consultant Direct 1,358.49 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-NLU-032-SES-001- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 16,188.68 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 2019-AF / SES Unit Head Implementation Support Implementation Selection PRDP-IS-NLU-033-SES-002- Individual Component 4: Project Pending 2019-AF / Social Safeguards IBRD / 88160 Post Consultant Direct 2,264.15 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Specialist Selection PRDP-IS-NLU-034-SES-003- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Open 10,188.68 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Environmental Safeguard Implementation Support Implementation Selection Specialist PRDP-IS-NLU-035-SES-004- Individual Component 4: Project Pending 2019-AF / Environmental IBRD / 88160 Post Consultant Direct 2,037.74 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Safeguards Officer Selection PRDP-IS-NLU-036-SES-005- Individual 2019-AF / Social and Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Environemental Safeguards Implementation Support Implementation Selection Officer PRDP-IS-NLU-037-SES-006- Individual Component 4: Project Pending 2019-AF / PSO Project IBRD / 88160 Post Consultant Direct 1,358.49 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate SES Selection PRDP-IS-NLU-038-SES-007- Individual Component 4: Project Pending 2019-AF / Associate SES IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-01-03 2019-02-21 2019-03-14 2019-04-18 2019-10-15 Implementation Support Implementation Officer Selection PRDP-IS-NLU-039-ADM- Individual Component 4: Project Pending 001-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Administrative Officer III Selection PRDP-IS-NLU-040-ADM- Individual Component 4: Project Pending 002-2019-AF / IBRD / 88160 Post Consultant Direct 7,471.70 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Administrative Officer II Selection PRDP-IS-NLU-049-ISP-011- Individual Component 4: Project Pending 2019-AF / Administrative IBRD / 88160 Post Consultant Open 5,094.34 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer II Selection PRDP-IS-NLU-050-ISP-001- Individual Component 4: Project Pending 2019-AF / ISUPPORT IBRD / 88160 Post Consultant Direct 17,433.96 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Component Head Selection PRDP-IS-NLU-051-IB-001- Individual 2019-AF / Rural Component 4: Project Pending IBRD / 88160 Post Consultant Direct 12,452.83 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Infrastracture Specialist - Implementation Support Implementation Selection Roads and Bridges PRDP-IS-NLU-052-IB-002- Individual 2019-AF / Rural Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,207.55 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Infrastructure Engineer Implementation Support Implementation Selection (RIE) PRDP-IS-NLU-053-IB-003- Individual 2019-AF / Rural Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,207.55 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Infrastructure Engineer Implementation Support Implementation Selection (RIE) PRDP-IS-NLU-054-IB-004- Individual 2019-AF / Rural Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Infrastructure Engineer Implementation Support Implementation Selection (RIE) PRDP-IS-NLU-055-IB-005- Individual 2019-AF / Project Component 4: Project Pending IBRD / 88160 Post Consultant Direct 7,471.70 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Development Associate Implementation Support Implementation Selection (PDA) PRDP-IS-NLU-R001-001- Individual Component 4: Project Pending OPD-001-2019-AF / Project IBRD / 88160 Post Consultant Direct 7,471.70 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-003- Individual Component 4: Project Pending DPD-001-2019-AF / Project IBRD / 88160 Post Consultant Open 4,075.47 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-005- Individual Component 4: Project Pending DPD-003-2019-AF / Admin IBRD / 88160 Post Consultant Open 5,094.34 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer II Selection Page 9 PRDP-IS-NLU-R001-006-IB- Individual 001-2019-AF / Rural Component 4: Project Pending IBRD / 88160 Post Consultant Open 4,075.47 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Infrastructure Specialist- Implementation Support Implementation Selection Road & Bridges PRDP-IS-NLU-R001-007-IB- Individual Component 4: Project Pending 002-2019-AF / Rural IBRD / 88160 Post Consultant Direct 9,169.81 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-008-IB- Individual Component 4: Project Pending 003-2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,811.32 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-009-IB- Individual Component 4: Project Pending 004-2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,811.32 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-010-IB- Individual Component 4: Project Pending 005-2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,811.32 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-011-IB- Individual Component 4: Project Pending 006-2019-AF / Rural IBRD / 88160 Post Consultant Direct 1,811.32 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-012-IB- Individual Component 4: Project Pending 007-2019-AF / Rural IBRD / 88160 Post Consultant Open 1,811.32 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-013-IB- Individual Component 4: Project Pending 008-2019-AF / Rural IBRD / 88160 Post Consultant Open 7,698.11 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-014-IB- Individual Component 4: Project Pending 009-2019-AF / Rural IBRD / 88160 Post Consultant Open 7,698.11 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-015-IB- Individual Component 4: Project Pending 010-2019-AF / Rural IBRD / 88160 Post Consultant Open 7,698.11 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R001-016-IB- Individual Component 4: Project Pending 011-2019-AF / Project IBRD / 88160 Post Consultant Direct 7,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-017-IB- Individual Component 4: Project Pending 012-2019-AF / Project IBRD / 88160 Post Consultant Open 566.04 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-022- Individual Component 4: Project Pending GGU-002-2019-AF / GIS IBRD / 88160 Post Consultant Open 1,811.32 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R001-023- Individual Component 4: Project Pending GGU-003-2019-AF / GIS IBRD / 88160 Post Consultant Direct 8,150.94 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R001-024- Individual Component 4: Project Pending GGU 004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,132.08 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-025- Individual Component 4: Project Pending PRO-001-2019-AF / IBRD / 88160 Post Consultant Open 1,811.32 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NLU-R001-026- Individual Component 4: Project Pending PRO-002-2019-AF / Project IBRD / 88160 Post Consultant Direct 8,150.94 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-027- Individual Component 4: Project Pending PRO-003-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,132.08 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-028- Individual Component 4: Project Pending PRO-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,132.08 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-029- Individual Component 4: Project Pending PRO-005-2019-AF / Project IBRD / 88160 Post Consultant Open 1,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R001-030- Individual Component 4: Project Pending PRO-006-2019-AF / IBRD / 88160 Post Consultant Direct 7,132.08 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Associate Procurement Selection Officer PRDP-IS-NLU-R001-031- Individual Component 4: Project Pending MNE-001-2019-AF / M&E IBRD / 88160 Post Consultant Open 1,811.32 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R001-032- Individual Component 4: Project Pending MNE-002-2019-AF / M&E IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R001-032- Individual Component 4: Project Pending MNE-003-2019-AF / PDA - IBRD / 88160 Post Consultant Open 1,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation M&E Selection PRDP-IS-NLU-R001-033- Individual Component 4: Project Pending MNE-004-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate M&E Officer Selection PRDP-IS-NLU-R001-034- Individual Component 4: Project Pending SES-001-2019-AF / IBRD / 88160 Post Consultant Direct 2,037.74 0.00 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 Implementation Support Implementation Environmental Safeguards Selection Specialist PRDP-IS-NLU-R001-035- Individual Component 4: Project Pending SES-002-2019-AF / SES IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R001-036- Individual Component 4: Project Pending SES-003-2019-AF / Associate IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation SES Officer Selection PRDP-IS-NLU-R001-037- Individual Component 4: Project Pending SES-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,132.08 0.00 2018-01-01 2018-01-11 2018-02-01 2018-03-08 2018-09-04 Implementation Support Implementation Development Associate Selection Page 10 PRDP-IS-NLU-R001-038- Individual Component 4: Project Pending SES-005-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,132.08 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-NLU-R001-039- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 1,584.91 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 ACE-001-2019-AF / Writer Implementation Support Implementation Selection Individual PRDP-IS-NLU-R001-040- Component 4: Project Pending IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 ACE-002-2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-NLU-R001-042- Individual Component 4: Project Pending FIN-001-2019-AF / Finance IBRD / 88160 Post Consultant Open 1,584.91 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst I Selection PRDP-IS-NLU-R001-043- Individual Component 4: Project Pending ACT-001-2019-AF / Finance IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst I Selection PRDP-IS-NLU-R001-044- Individual Component 4: Project Pending ACT-002-2019-AF / Project IBRD / 88160 Post Consultant Open 1,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-003- Individual Component 4: Project Pending DPD-003-2019-AF / IBRD / 88160 Post Consultant Direct 3,056.60 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Compliance Officer Selection PRDP-IS-NLU-R002-004- Individual Component 4: Project Pending DPD-004-2019-AF / IBRD / 88160 Post Consultant Open 5,094.34 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Administrative Officer II Selection PRDP-IS-NLU-R002-005- Individual Component 4: Project Pending DPD-005-2019-AF / IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Administrative Officer I Selection PRDP-IS-NLU-R002-006- Individual Component 4: Project Pending DPD-006-2019-AF / IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Economist Selection PRDP-IS-NLU-R002-007-IB- Individual Component 4: Project Pending 001-2019-AF / Road and IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Bridges Specialist Selection PRDP-IS-NLU-R002-008-IB- Individual Component 4: Project Pending 002-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-009-IB- Individual Component 4: Project Pending 003-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-010-IB- Individual Component 4: Project Pending 004-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-011-IB- Individual Component 4: Project Pending 005-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-012-IB- Individual Component 4: Project Pending 006-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-013-IB- Individual Component 4: Project Pending 007-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-014-IB- Individual Component 4: Project Pending 008-2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-015-IB- Individual Component 4: Project Pending 009-2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R002-016-IB- Individual Component 4: Project Pending 010-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-017-IB- Individual Component 4: Project Pending 011-2019-AF / Project IBRD / 88160 Post Consultant Open 5,094.34 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-019- Individual Component 4: Project Pending GGU-001-2019-AF / GIS IBRD / 88160 Post Consultant Direct 3,056.60 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Specialist Selection PRDP-IS-NLU-R002-020- Individual Component 4: Project Pending GGU-002-2019-AF / GIS IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R002-021- Individual Component 4: Project Pending GGU-003-2019-AF / GIS IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R002-022- Individual Component 4: Project Pending GGU-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-023- Individual Component 4: Project Pending GGU-005-2019-AF / IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NLU-R002-024- Individual Component 4: Project Pending PRO-001-2019-AF / IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-01-03 2019-02-21 2019-03-14 2019-04-18 2019-10-15 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NLU-R002-025- Individual Component 4: Project Pending PRO-006-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate Procurement Selection Officer PRDP-IS-NLU-R002-026- Individual Component 4: Project Pending PRO-007-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Page 11 PRDP-IS-NLU-R002-027- Individual MNE-001-2019-AF / Component 4: Project Pending IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Monitoring & Evaluation Implementation Support Implementation Selection Officer PRDP-IS-NLU-R002-028- Individual MNE-002-2019-AF / Component 4: Project Pending IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Monitoring & Evaluation Implementation Support Implementation Selection Officer PRDP-IS-NLU-R002-029- Individual Component 4: Project Pending MNE-003-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate M & E Officer Selection PRDP-IS-NLU-R002-030- Individual Component 4: Project Pending MNE-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-031- Individual Component 4: Project Pending SES-001-2019-AF / Social IBRD / 88160 Post Consultant Direct 3,056.60 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Safeguard Specialist Selection PRDP-IS-NLU-R002-032- Individual SES-002-2019-AF / Social Component 4: Project Pending IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 and Environment Implementation Support Implementation Selection Safeguards Officer PRDP-IS-NLU-R002-033- Individual SES-003-2019-AF / Social Component 4: Project Pending IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 and Environment Implementation Support Implementation Selection Safeguards Officer PRDP-IS-NLU-R002-034- Individual Component 4: Project Pending SES-004-2019-AF / Associate IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation SES Officer Selection PRDP-IS-NLU-R002-035- Individual Component 4: Project Pending SES-005-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-036- Individual ACE-001-2019-AF / Component 4: Project Pending IBRD / 88160 Post Consultant Direct 3,056.60 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Information & Advocacy Implementation Support Implementation Selection Specialist Individual PRDP-IS-NLU-R002-038- Component 4: Project Pending IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-01-03 2019-02-21 2019-03-14 2019-04-18 2019-10-15 ACE-003-2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-NLU-R002-039- Individual Component 4: Project Pending ACE-004-2019-AF / IBRD / 88160 Post Consultant Direct 2,037.74 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Photographer/Videographer Selection PRDP-IS-NLU-R002-040- Individual Component 4: Project Pending ACE-005-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-041- Individual Component 4: Project Pending FIN-001-2019-AF / Finance IBRD / 88160 Post Consultant Open 2,377.36 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst I Selection PRDP-IS-NLU-R002-042- Individual Component 4: Project Pending FIN-002-2019-AF / Finance IBRD / 88160 Post Consultant Open 2,377.36 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst I Selection PRDP-IS-NLU-R002-043- Individual Component 4: Project Pending FIN-003-2019-AF / Finance IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst I Selection PRDP-IS-NLU-R002-044- Individual Component 4: Project Pending FIN-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-045- Individual Component 4: Project Pending FIN-005-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R002-046- Individual Component 4: Project Pending ACT-001-2019-AF / Finance IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst 1 Selection PRDP-IS-NLU-R002-047- Individual Component 4: Project Pending BUD-001-2019-AF / Budget IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst 1 Selection PRDP-IS-NLU-R003-001- Individual Component 4: Project Pending ADM-006-2019-AF / IBRD / 88160 Post Consultant Open 5,094.34 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Administrative Officer II Selection PRDP-IS-NLU-R003-005- Individual Component 4: Project Pending ADM-010-2019-AF / IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Economist Selection PRDP-IS-NLU-R003-012- Individual Component 4: Project Pending ISP-001-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-013- Individual Component 4: Project Pending ISP-002-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-014- Individual Component 4: Project Pending ISP-003-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-NLU-R003-015- Component 4: Project Pending IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 ACE-001-2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-NLU-R003-016- Individual Component 4: Project Pending ACE-002-2019-AF / PDA - IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation InfoACE Selection PRDP-IS-NLU-R003-017- Individual Component 4: Project Pending FIN-001-2019-AF / Finance IBRD / 88160 Post Consultant Direct 9,509.43 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Analyst 1 Selection Page 12 PRDP-IS-NLU-R003-018- Individual Component 4: Project Pending ACT-001-2019-AF / Finance IBRD / 88160 Post Consultant Open 3,566.04 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst 1 Selection PRDP-IS-NLU-R003-019- Individual Component 4: Project Pending ACT-002-2019-AF / Finance IBRD / 88160 Post Consultant Open 3,566.04 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst 1 Selection PRDP-IS-NLU-R003-020- Individual Component 4: Project Pending BUD-001-2019-AF / Budget IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Analyst Selection PRDP-IS-NLU-R003-021- Individual Component 4: Project Pending PRO-001-2019-AF / IBRD / 88160 Post Consultant Direct 10,867.92 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NLU-R003-022- Individual Component 4: Project Pending PRO-002-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate Procurement Selection Officer PRDP-IS-NLU-R003-023- Individual Component 4: Project Pending PRO-003-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-024- Individual Component 4: Project Pending PRO-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-025- Individual Component 4: Project Pending MNE-001-2019-AF / M&E IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R003-026- Individual Component 4: Project Pending MNE-002-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate M&E Officer Selection PRDP-IS-NLU-R003-027- Individual Component 4: Project Pending MNE-003-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-028- Individual Component 4: Project Pending MNE-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-029- Individual Component 4: Project Pending SES-001-2019-AF / Social IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Safeguard Officer Selection PRDP-IS-NLU-R003-030- Individual SES-002-2019-AF / Social Component 4: Project Pending IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 and Environmental Implementation Support Implementation Selection Safeguard Officer PRDP-IS-NLU-R003-031- Individual Component 4: Project Pending SES-003-2019-AF / Associate IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation SES Officer Selection PRDP-IS-NLU-R003-032- Individual Component 4: Project Pending SES-004-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-033- Individual Component 4: Project Pending SES-005-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-034- Individual Component 4: Project Pending GGU-001-2019-AF / GIS IBRD / 88160 Post Consultant Direct 10,867.92 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Officer Selection PRDP-IS-NLU-R003-035- Individual Component 4: Project Pending GGU-002-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-036-IB- Individual Component 4: Project Pending 001-2019-AF / Project IBRD / 88160 Post Consultant Direct 1,698.11 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-R003-037-IB- Individual Component 4: Project Pending 002-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-038-IB- Individual Component 4: Project Pending 003-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-039-IB- Individual Component 4: Project Pending 004-2019-AF / Rural IBRD / 88160 Post Consultant Direct 2,716.98 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-040-IB- Individual Component 4: Project Pending 005-2019-AF / Rural IBRD / 88160 Post Consultant Open 9,962.26 0.00 2019-01-03 2019-02-21 2019-03-14 2019-04-18 2019-10-15 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-041-IB- Individual Component 4: Project Pending 006-2019-AF / Rural IBRD / 88160 Post Consultant Open 9,962.26 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-042-IB- Individual Component 4: Project Pending 007-2019-AF / Rural IBRD / 88160 Post Consultant Open 9,962.26 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-043-IB- Individual Component 4: Project Pending 008-2019-AF / Rural IBRD / 88160 Post Consultant Direct 8,150.94 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-044-IB- Individual Component 4: Project Pending 009-2019-AF / Rural IBRD / 88160 Post Consultant Direct 8,150.94 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-R003-045-IB- Individual Component 4: Project Pending 010-2019-AF / Project IBRD / 88160 Post Consultant Direct 6,792.45 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-RCAR-002- Individual Component 4: Project Pending DPD-002-2019-AF / IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Economist Selection Page 13 PRDP-IS-NLU-RCAR-003-IB- Individual Component 4: Project Pending 001-2019-AF / Roads & IBRD / 88160 Post Consultant Open 9,169.81 0.00 2019-01-03 2019-02-21 2019-03-14 2019-04-18 2019-10-15 Implementation Support Implementation Bridges Specialist Selection PRDP-IS-NLU-RCAR-004-IB- Individual Component 4: Project Pending 002-2019-AF / Rural IBRD / 88160 Post Consultant Direct 8,150.94 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-RCAR-005-IB- Individual Component 4: Project Pending 003-2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-RCAR-006-IB- Individual Component 4: Project Pending 004-2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-RCAR-007-IB- Individual Component 4: Project Pending 005-2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-RCAR-008-IB- Individual Component 4: Project Pending 006-2019-AF / Rural IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-NLU-RCAR-009-IB- Individual Component 4: Project Pending 007-2019-AF / Project IBRD / 88160 Post Consultant Open 5,094.34 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Development Associate Selection PRDP-IS-NLU-RCAR-011- Individual Component 4: Project Pending GGU-001-2019-AF / GIS IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Officer Selection PRDP-IS-NLU-RCAR-013- Individual Component 4: Project Pending PRO-001-2019-AF / IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Procurement Officer Selection PRDP-IS-NLU-RCAR-014- Individual Component 4: Project Pending PRO-002-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate Procurement Selection Officer PRDP-IS-NLU-RCAR-015- Individual Component 4: Project Pending PRO-003-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate Procurement Selection Officer PRDP-IS-NLU-RCAR-016- Individual MNE-001-2019-AF / Component 4: Project Pending IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Monitoring & Evaluation Implementation Support Implementation Selection Officer PRDP-IS-NLU-RCAR-017- Individual Component 4: Project Pending MNE-002-2019-AF / IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation Associate M & E Officer Selection PRDP-IS-NLU-RCAR-018- Individual SES-001-2019-AF / Social Component 4: Project Pending IBRD / 88160 Post Consultant Open 8,150.94 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 and Environment Implementation Support Implementation Selection Safeguards Officer PRDP-IS-NLU-RCAR-019- Individual Component 4: Project Pending SES-002-2019-AF / Associate IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 Implementation Support Implementation SES Officer Selection Individual PRDP-IS-NLU-RCAR-021- Component 4: Project Pending IBRD / 88160 Post Consultant Open 7,132.08 0.00 2019-04-01 2019-05-20 2019-06-10 2019-07-15 2020-01-11 ACE-001-2019-AF / Writer Implementation Support Implementation Selection PRDP-IS-NLU-RCAR-023- Individual Component 4: Project Pending FIN-001-2019-AF / Finance IBRD / 88160 Post Consultant Direct 7,132.08 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Analyst Selection PRDP-IS-NLU-RCAR-024- Individual Component 4: Project Pending ACT-001-2019-AF / Finance IBRD / 88160 Post Consultant Direct 7,132.08 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Analyst Selection PRDP-IS-NLU-R002-037- Individual Component 4: Project Pending ACE-002-2019-AF / Layout IBRD / 88160 Post Consultant Direct 2,037.74 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Artist Selection PRDP-IS-NLU-R001-041- Individual Component 4: Project Pending ACE-003-2019-AF / IBRD / 88160 Post Consultant Direct 1,358.49 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Videographer/Photographer Selection PRDP-IS-NLU-R002-002- Individual Component 4: Project Pending DPD-002-2019-AF / IBRD / 88160 Post Consultant Direct 2,037.74 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Executive Assistant Selection PRDP-IS-NLU-008-ACE-002- Individual Component 4: Project Pending 2019-AF / Graphics/Lay-out IBRD / 88160 Post Consultant Direct 2,377.36 0.00 2019-01-03 2019-01-13 2019-02-03 2019-03-10 2019-09-06 Implementation Support Implementation Artist Selection Page 14