PROCUREMENT PLAN (Textual Part) Project information: Mali – Urban Local Government Support Project – P116602 Project Implementation agency: Ministry of Housing and Urban planning Date of the Procurement Plan: December 22, 2017 Period covered by this Procurement Plan: January 1st, 2018 – June 30, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT Mali : Urban Local Government Support Project PLAN General Information Country: Mali Bank’s Approval Date of the Original Procurement Plan: 2018-01-31 2019-08-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P116602 GPN Date: Project Name: Urban Local Government Support Project Loan / Credit No: IDA / 49660, IDA / Q7360 Executing Agency(ies): Urban Local Government Support Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF27 / Construction Component 4: Project Single Stage - One En attente d'une salle d'archivage du IDA / 49660 Management, Monitoring A posteriori Demande de prix Open - National 77,786.00 0.00 2019-01-02 2019-02-27 2019-08-26 Envelope d'exécution PACUM and Evaluation CS-REF28 / Extension du Component 1: Performance- réseau d'eau potable à Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 575,108.00 0.00 2017-10-01 2017-10-06 2017-11-17 2017-12-17 2018-01-21 2018-07-20 Plateau-Bencounda Envelope d'exécution Grants for Secondary Cities Lafiabougou et Kayes N'DI CS-REF29 / Construction de 36 salles de classes 3 Bencouda 6 à Kayes Ndi A 9 à Abdramane Gueye à 3 Component 1: Performance- Single Stage - One En attente Plateau 3 Kayes Ndi B 3 IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 1,016,780.00 0.00 2017-12-20 2017-12-25 2018-02-05 2018-03-07 2018-04-11 2018-10-08 Envelope d'exécution Kasso 3 Legal Ségou 3 à Grants for Secondary Cities Lafiabougou 3 à Liberté et es travaux de construction du CSCOM à Légal ségou CS-REF30 / Construction de 6 salles de classes Component 1: Performance- équipées deux bureaux et Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 146,683.00 0.00 2017-06-30 2017-07-05 2017-08-16 2017-09-15 2017-10-20 2018-04-18 deux blocs de trois Envelope d'exécution Grants for Secondary Cities Latrines à Kôfoulabè et Doumbacoura CS-REF31 / Construction de 12 salles de classes Component 1: Performance- équipées quatre bureaux et Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 286,743.00 0.00 2017-12-20 2017-12-25 2018-02-05 2018-03-07 2018-04-11 2018-10-08 quatre blocs de trois Envelope d'exécution Grants for Secondary Cities Latrines à Niafala Kouleko Kita-Gare et Kolibougou CS-REF32 / Réalisation de feux tricolores solaires aux Component 1: Performance- carrefours du gouvernorat Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 344,483.00 0.00 2018-01-09 2018-01-14 2018-02-25 2018-03-27 2018-05-01 2018-10-28 du cimetière du stade de Envelope d'exécution Grants for Secondary Cities koulikoro des monuments de la mairie et de la préfecture Component 1: Performance- CS-REF33 / Réalisation de Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 310,346.00 0.00 2017-06-16 2017-06-21 2017-08-02 2017-09-01 2017-10-06 2018-04-04 la 2ème phases du Mamelon Envelope d'exécution Grants for Secondary Cities CS-REF35 / Aménagement Component 1: Performance- des voies Rue 579 et Rue Single Stage - One En cours IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 775,642.00 0.00 2018-05-05 2018-05-10 2018-06-21 2018-07-21 2018-08-25 2019-02-21 CSCOM d'accès au CSCOM Envelope d'exécution Grants for Secondary Cities de Sido Soninkoura Page 1 CS-REF36 / Construction et équipement de trois salles Component 1: Performance- Single Stage - One En attente de classes à N’GOLOBALA IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 237,804.00 0.00 2017-06-16 2017-06-21 2017-08-02 2017-09-01 2017-10-06 2018-04-04 Envelope d'exécution et 3 trois salles de classes à Grants for Secondary Cities Djékorobougou CS-REF37 / Construction et équipement de 24 salles de Component 1: Performance- Single Stage - One En attente classes et 8 bureaux IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 467,452.00 0.00 2018-01-16 2018-01-21 2018-03-04 2018-04-03 2018-05-08 2018-11-04 Envelope d'exécution magasins et 8 blocs de Grants for Secondary Cities latrines CS-REF38 / Construction Component 1: Performance- l’école de N piena et mûr Single Stage - One En cours IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 141,127.00 0.00 2018-01-16 2018-01-21 2018-03-04 2018-04-03 2018-05-08 2018-11-04 de clôture du groupe scolaire Envelope d'exécution Grants for Secondary Cities de Bla CS-REF39 / Construction de 20 salles de classes Component 1: Performance- Single Stage - One En attente équipées avec magasin et IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 666,741.00 0.00 2018-01-15 2018-01-20 2018-03-03 2018-04-02 2018-05-07 2018-11-03 Envelope d'exécution Latrine dans la Commune Grants for Secondary Cities Urbaine de Mopti CS-REF40 / Aménagement Component 1: Performance- Single Stage - One En attente du 2ème tronçon de la rue IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 888,988.00 0.00 2018-01-31 2018-02-05 2018-03-19 2018-04-18 2018-05-23 2018-11-19 Envelope d'exécution 50 à Sévaré II Grants for Secondary Cities CS-REF41 / Aménagement Component 1: Performance- Single Stage - One En attente de trois terrains sportifs IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 462,274.00 0.00 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Envelope d'exécution nivèlement clôture et forage Grants for Secondary Cities CS-REF42 / Construction Component 1: Performance- de 6 salles de classes à Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 200,022.00 0.00 2017-06-17 2017-06-22 2017-08-03 2017-09-02 2017-10-07 2018-04-05 Gadaye premier Cycle dans Envelope d'exécution Grants for Secondary Cities la commune de Gao CS-REF43 / Travaux de construction de 6 salles de classes 3 à l’école de Sosso- Component 1: Performance- Single Stage - One En attente koira 3 à l’école de Djidara IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 468,941.00 0.00 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Envelope d'exécution un CSCOM à Djidara et Grants for Secondary Cities forage au marché dAljanabandjan ML-PACUM-62100-CW-RFB / Travaux de constructions Component 1: Performance- de 36 classes équipées, 12 Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 861,268.00 0.00 2018-05-09 2018-05-10 2018-05-25 2018-05-26 2018-05-29 2018-09-26 bureaux magasins et 24 Envelope d'exécution Grants for Secondary Cities blocs de trois latrines à Sikasso ML-PACUM-62106-CW-RFB / Travaux de réalisation de Component 1: Performance- 3 AES à Longorola, Single Stage - One En attente IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 906,053.00 0.00 2018-05-09 2018-05-10 2018-05-25 2018-05-28 2018-06-05 2018-09-03 Kouloussandougou, Magan Envelope d'exécution Grants for Secondary Cities DIASSA, Commune Urbaine de Sikass ML-PACUM-62110-CW-RFQ Component 1: Performance- Single Stage - One En attente / Travaux d'achèvement des IDA / 49660 Based and Capacity Support A posteriori Demande de prix Limited 208,405.00 0.00 2018-05-11 2018-07-06 2018-11-03 Envelope d'exécution caniveaux à Sikasso Grants for Secondary Cities Page 2 ML-PACUM-68359-CW-RFB / Travaux de construction des murs de clotures des Component 1: Performance- Single Stage - One En cours écoles Hamdallaye et IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 507,563.00 0.00 2018-06-29 2018-06-30 2018-07-02 2018-07-17 2018-08-09 2019-02-05 Envelope d'exécution Wayerma II et des Grants for Secondary Cities cimétières de Hamdalaye et Sanoubougou II CS-REF34 / Construction Component 1: Performance- de 20 km de collecteurs de Single Stage - One IDA / 49660 Based and Capacity Support A posteriori Appel d'offres Open - National 2,089,121.00 0.00 Annulé 2018-02-15 2018-02-20 2018-04-03 2018-05-03 2018-06-07 2018-12-04 Sanoubougou II Hamdallaye Envelope Grants for Secondary Cities et médine et wayèrema ML-PACUM-97651-CW-RFB / Construction et réhabilitation d'infrastructures scolaires à Component 1: Performance- Single Stage - One En attente Samédougou, Farabala, IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 435,708.00 0.00 2019-02-04 2019-02-09 2019-03-11 2019-03-21 2019-04-03 2019-08-01 Envelope d'exécution Doumbacoura, Kofoulabe, Grants for Secondary Cities Niafala, Darsalam, Kita gare dans la Commune Urbaine de Kita ML-PACUM-97656-CW-RFB / Construction de Clôture des écoles fondamentales de Kayo et Souban, Plateau III et Katibougou Second Cycle, Component 1: Performance- Single Stage - One En attente de construction d'un (1) bloc IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 457,626.00 0.00 2019-02-04 2019-02-09 2019-03-11 2019-03-21 2019-03-31 2019-07-29 Envelope d'exécution de trois (3) salles de classe Grants for Secondary Cities (Second cycle) et de clôture de l'Ecole de Kolèbougou et la construction et l'équipemen ML-PACUM-97658-CW-RFB / Réalisation de forages Component 1: Performance- équipés dans les villages de Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 85,343.00 0.00 2019-02-04 2019-02-09 2019-03-11 2019-03-21 2019-04-02 2019-07-01 : Yèrèlonziéra, Flazanbougou, Envelope d'exécution Grants for Secondary Cities Niagassoni, Badabala, Niprodioula, Konsanso Dioula ML-PACUM-97659-CW-RFQ Component 1: Performance- / construction d'un mur de Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Demande de prix Open - National 46,996.00 0.00 2019-02-09 2019-03-05 2019-06-03 soutènement à la colline du Envelope d'exécution Grants for Secondary Cities Mamelon ML-PACUM-98933-CW-RFQ Component 1: Performance- / Construction de la clôture Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Demande de prix Open - National 31,732.00 0.00 2019-02-10 2019-02-28 2019-05-29 du Mur de l'école B Envelope d'exécution Grants for Secondary Cities Hamdallaye ML-PACUM-98934-CW-RFB / réhabilitation de 4 terrains Component 1: Performance- Single Stage - One En attente de Basket Ball (Hamdallaye- IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 127,459.00 0.00 2019-02-11 2019-02-16 2019-03-18 2019-03-28 2019-04-09 2019-07-08 Envelope d'exécution Bananissabakoro-Bougoufié- Grants for Secondary Cities Darsalam) ML-PACUM-98935-CW-RFB / construction de salles de classes équipées, bureaux Component 1: Performance- Single Stage - One En attente magasins équipés et de blocs IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 432,352.00 0.00 2019-02-12 2019-02-17 2019-03-19 2019-03-29 2019-04-10 2019-07-09 Envelope d'exécution de 3 latrines dans des Grants for Secondary Cities écoles de la Commune Urbaine de Niono Page 3 ML-PACUM-98936-CW-RFB / construction d'un CSCOM à Komouna construction d'un Component 1: Performance- bloc de trois salles de Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 477,446.00 0.00 2019-02-12 2019-02-17 2019-03-19 2019-03-29 2019-04-08 2019-07-07 classes équipés un bureau Envelope d'exécution Grants for Secondary Cities magasin et deux blocs de trois latrine à Noumouna sécond cycle et Sorofing ML-PACUM-98937-CW-RFB / construction d' un Kit Scolaire à Komoguel II et Component 1: Performance- réalisation des clôtures des Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 189,752.00 0.00 2019-02-12 2019-02-17 2019-03-19 2019-03-29 2019-04-12 2019-07-11 écoles de Komoguel 2, Envelope d'exécution Grants for Secondary Cities Madina Coura, Sévaré I dans la Commune Urbaine de Mopti ML-PACUM-98939-CW-RFB Component 1: Performance- Single Stage - One En attente / Réalisation de forages dans IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 268,025.00 0.00 2019-02-13 2019-02-18 2019-03-20 2019-03-30 2019-04-11 2019-07-10 Envelope d'exécution les quartiers de Gao Grants for Secondary Cities ML-PACUM-99037-CW-RFB Component 1: Performance- / Réalisation de projet pilote Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Appel d'offres Open - National 319,731.00 0.00 2019-02-11 2019-02-16 2019-03-18 2019-04-02 2019-04-22 2019-08-20 d'aménagement d'espaces Envelope d'exécution Grants for Secondary Cities publics à Bamako ML-PACUM-121798-CW-DIR / Convention avec Cellule des TRavaux Routier d’Urgence (CETRU)pour la Component 1: Performance- Passation de réalisation des travaux En cours IDA / 49660 Based and Capacity Support A posteriori marché de gré à Direct 266,696.00 0.00 2019-07-08 2019-07-13 2019-07-28 2019-09-02 d’aménagement d’ouvrages d'exécution Grants for Secondary Cities gré d’assainissement pour le compte de la commune urbaine de Kayes dans le cadre du PACUM GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF44 / Acquisition de Component 4: Project Single Stage - One En attente fournitures de bureau et de IDA / 49660 Management, Monitoring A posteriori Demande de prix Open - National 15,557.00 0.00 2018-01-13 2018-03-10 2018-09-06 Envelope d'exécution consommables informatiques and Evaluation ML-PACUM-62107-GO-RFQ Component 1: Performance- Single Stage - One En attente / Equipement de la IDA / 49660 Based and Capacity Support A posteriori Demande de prix Limited 554.00 0.00 2018-05-10 2018-07-05 2018-09-03 Envelope d'exécution Maternité Grants for Secondary Cities ML-PACUM-99042-GO-RFQ / Choix de l'entreprise pour la Fourniture de 15 Component 1: Performance- lampadaires solaires dans les Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Demande de prix Open - National 28,325.00 0.00 2019-02-16 2019-04-13 2019-08-11 quartier de Fama et Envelope d'exécution Grants for Secondary Cities Bougoula Ville et de 8 panneaux solaires au marché Sanoubougou I ML-PACUM-99051-GO-RFQ Component 1: Performance- / Achat d'une Machine Single Stage - One En attente IDA / Q7360 Based and Capacity Support A posteriori Demande de prix Open - National 17,157.00 0.00 2019-02-17 2019-03-31 2019-04-30 Tondeuse pour le Stade Envelope d'exécution Grants for Secondary Cities Municipal Sory I KONANDJI Page 4 Component 2: Priority ML-PACUM-99059-GO-RFQ Infrastructure Investment, / Acquisition du logiciel pour Single Stage - One En attente IDA / Q7360 Institutional Restructuring A posteriori Demande de prix Open - National 61,133.00 0.00 2019-03-23 2019-04-30 2019-05-30 la gestion du patrimoine Envelope d'exécution and Capacity Support du District de Bamako Grants for Bamako ML-PACUM-99063-GO-RFQ Component 4: Project / Acquisition de fournitures Single Stage - One En attente IDA / Q7360 Management, Monitoring A posteriori Demande de prix Open - National 15,557.00 0.00 2019-03-24 2019-04-29 2019-05-29 de bureau et de Envelope d'exécution and Evaluation consommables informatiques ML-PACUM-99323-GO-RFQ Component 1: Performance- Single Stage - One En attente / Acquisition de tables bancs IDA / Q7360 Based and Capacity Support A posteriori Demande de prix Open - National 35,560.00 0.00 2019-03-31 2019-05-26 2019-06-25 Envelope d'exécution pour les écoles de Kita Grants for Secondary Cities ML-PACUM-113724-GO-RFQ / Edition d'un guide Component 3: Institutional Single Stage - One En attente méthodologique d'élaboration IDA / 49660 A posteriori Demande de prix Open - National 33,337.00 0.00 2019-05-19 2019-06-21 2019-07-21 Capacity Strengthening Envelope d'exécution des PDESEC des Collectivités Territoriales ML-PACUM-113725-GO-RFQ / Edition d'un guide pratiques sur les rôles et Component 3: Institutional Single Stage - One En attente IDA / 49660 A posteriori Demande de prix Open - National 22,225.00 0.00 2019-06-02 2019-07-07 2019-08-06 responsabilités en matière de Capacity Strengthening Envelope d'exécution mobilisation sociale et d'engagement citoyens ML-PACUM-113727-GO-RFQ / Fournir à la DGCT des équipements informatiques Component 3: Institutional Single Stage - One En attente IDA / 49660 A posteriori Demande de prix Open - National 33,337.00 0.00 2019-06-01 2019-07-06 2019-08-05 en appui à Capacity Strengthening Envelope d'exécution l'opérationalisation de la Base OISE nouvelle version NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF1 / Etude sur la Sélection fondée mise en œuvre d’un Component 3: Institutional sur les En attente dispositif de contrôle à IDA / 49660 A posteriori Open - National 100,011.00 0.00 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 Capacity Strengthening qualifications des d'exécution postériori dans les consultants collectivités territoriales CS-REF4 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 71,263.76 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Kayes consultants CS-REF5 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 71,263.76 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Kita consultants Page 5 CS-REF6 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 71,263.76 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Koulikoro consultants CS-REF7 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 64,619.15 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Sikasso consultants CS-REF8 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 70,225.26 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Ségou consultants CS-REF9 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 70,225.26 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Niono consultants CS-REF10 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 70,225.26 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Bla consultants CS-REF11 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 65,297.47 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Mopti consultants CS-REF12 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les IDA / 49660 A posteriori Open - National 88,899.00 65,297.47 Signé 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 de la société civile dans la Capacity Strengthening qualifications des commune de Gao consultants CS-REF13 / ONG pour Sélection fondée accompagner la dynamisation Component 3: Institutional sur les En attente IDA / 49660 A posteriori Open - National 444,494.00 0.00 2018-01-20 2018-02-10 2018-03-26 2018-04-25 2018-05-30 2018-11-26 de la société civile dans le Capacity Strengthening qualifications des d'exécution District de Bamako consultants CS-REF17 / Contrôle et la Sélection fondée survaillance des d'extension Component 1: Performance- sur les En attente du réseau d'eau potable à IDA / 49660 Based and Capacity Support A posteriori Open - National 377,782.00 0.00 2017-08-13 2017-09-03 2017-10-17 2017-11-16 2017-12-21 2018-06-19 qualifications des d'exécution Plateau Bencounda Grants for Secondary Cities consultants Lafiabougou et Kayes N DI CS-REF18 / Etude des Component 1: Performance- Sélection fondée travaux de bitumage des En attente IDA / 49660 Based and Capacity Support A posteriori sur la qualité et Open - National 100,011.00 0.00 2017-03-13 2017-04-03 2017-05-17 2017-06-14 2017-07-14 2017-08-18 2017-09-22 2018-09-22 rues 340 457 420 à d'exécution Grants for Secondary Cities le coût lafiabougou sud CS-REF21 / Etudes le contrôle et la surveillance Sélection fondée Component 1: Performance- des travaux d'aménagement sur les En cours IDA / 49660 Based and Capacity Support A posteriori Open - National 88,899.00 0.00 2017-12-20 2018-01-10 2018-02-23 2018-03-25 2018-04-29 2018-10-26 des voies Rue 579 et Rue qualifications des d'exécution Grants for Secondary Cities CSCOM d accès au CSCOM consultants de Sido Soninkoura CS-REF15 / Evaluation des résultats impacts audit Component 4: Project Sélection fondée technique etc à mener dans IDA / 49660 Management, Monitoring A priori sur la qualité et Open - National 200,022.00 0.00 Annulé 2017-12-28 2018-01-18 2018-03-03 2018-03-31 2018-04-30 2018-06-04 2018-07-09 2019-07-09 le cadre de la clôture du and Evaluation le coût projet et la pérennisation des acquis CS-REF16 / Agence de Component 4: Project Sélection fondée communication pour la mise IDA / 49660 Management, Monitoring A posteriori sur la qualité et Open - National 286,699.00 38,821.82 Signé 2018-01-05 2018-01-26 2018-03-11 2018-04-08 2018-05-08 2018-06-12 2018-07-17 2019-07-17 en œuvre du plan de and Evaluation le coût communication du projet Page 6 CS-REF24 / Contrôle et Sélection fondée Surveillance des travaux Component 1: Performance- sur les d'aménagement de trois IDA / 49660 Based and Capacity Support A posteriori Open - National 24,447.00 0.00 Annulé 2018-01-12 2018-02-02 2018-03-18 2018-04-17 2018-05-22 2018-11-18 qualifications des terrains sportifs nivèlement Grants for Secondary Cities consultants clôture et forage CS-REF19 / Contrôle et la surveillance réalisation de Sélection fondée feux tricolores solaires aux Component 1: Performance- sur les carrefours ddu gouvernorat IDA / 49660 Based and Capacity Support A posteriori Open - National 33,337.00 0.00 Annulé 2017-11-07 2017-11-28 2018-01-11 2018-02-10 2018-03-17 2018-09-13 qualifications des du cimetière du stade de Grants for Secondary Cities consultants koulikoro du momument de la mairie et de la préfecture CS-REF20 / Etudes techniques des travaux de Component 1: Performance- Sélection fondée Construction de 20 km de En attente IDA / 49660 Based and Capacity Support A posteriori sur la qualité et Open - National 326,703.00 0.00 2017-08-28 2017-09-18 2017-11-01 2017-11-29 2017-12-29 2018-02-02 2018-03-09 2019-03-09 collecteurs de Sanoubougou d'exécution Grants for Secondary Cities le coût II Hamdallaye et médine et wayèrema ML-PACUM-99072-CS-CQS / Enquete de satisfaction des Sélection fondée Component 4: Project usagers à mener dans le sur les En cours IDA / Q7360 Management, Monitoring A posteriori Open - National 44,449.00 45,063.04 2019-02-19 2019-03-12 2019-04-25 2019-05-25 2019-06-29 2019-07-29 cadre de la clôture du projet qualifications des d'exécution and Evaluation et la pérennisation des consultants acquis ML-PACUM-97398-CS-CDS / Recrutement d'un consultant pour l'audit des comptes Sélection fondée Component 1: Performance- administratifs des villes sur les En cours IDA / Q7360 Based and Capacity Support A posteriori Open - National 58,984.00 0.00 2019-03-04 2019-03-25 2019-04-16 2019-05-01 2019-05-18 2019-06-17 participantes au projet qualifications des d'exécution Grants for Secondary Cities d'appui aux communes consultants urbaines du Mali- pour les exercices 2018 et 2019 ML-PACUM-99067-CS-CQS / Audit technique des Sélection fondée Component 4: Project investissements à mener sur les IDA / Q7360 Management, Monitoring A posteriori Open - National 44,449.00 0.00 Annulé 2019-05-20 2019-06-10 2019-07-24 2019-08-03 2019-09-07 2019-11-06 dans le cadre de la clôture qualifications des and Evaluation du projet et la pérennisation consultants des acquis ML-PACUM-116994-CS- QCBS / Evaluation des Sélection fondée Component 4: Project résultats, impacts à mener sur les IDA / 49660 Management, Monitoring A priori Open - National 111,123.00 0.00 Annulé 2019-06-10 2019-06-24 2019-07-23 2019-08-06 2019-08-30 2019-10-29 dans le cadre de la clôture qualifications des and Evaluation du projet et la pérennisation consultants des acquis ML-PACUM-126652-CS-CQS / Évaluation des résultats, Sélection fondée impacts à mener dans le Component 3: Institutional sur les En attente IDA / 49660 A posteriori Open - National 111,123.00 0.00 2019-08-08 2019-08-15 2019-09-06 2019-09-11 2019-09-26 2019-11-10 cadre de la clôture du projet Capacity Strengthening qualifications des d'exécution et la pérennisation des consultants acquis INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 7 CS-REF2 / Etudes relative au recensement de conservation et de Sélection de Component 3: Institutional En attente valorisations des espaces IDA / 49660 A priori consultants par Direct 300,033.00 0.00 2018-02-19 2018-03-01 2018-05-05 2018-11-01 Capacity Strengthening d'exécution publics et de l’évaluation de entente directe l’offre de services urbains de base Component 4: Project Sélection de ML-PACUM-51338-CS-CDS / En attente IDA / 49660 Management, Monitoring A posteriori consultants par Direct 21,801.00 0.00 2017-12-22 2018-01-01 2018-03-07 2018-09-03 Chef comptable d'exécution and Evaluation entente directe CS-REF3 / Elaboration du programme global de Sélection de Component 3: Institutional renforcement des capacités IDA / 49660 A posteriori consultants par Direct 44,449.00 34,268.18 Signé 2018-03-09 2018-03-19 2018-05-23 2018-11-19 Capacity Strengthening VPP Structures Etat Société entente directe Civil ML-PACUM-51340-CS-CDS / Maitre d Ouvrage Délégué pour les travaux Component 1: Performance- Sélection de En attente d'aménagement des voies IDA / 49660 Based and Capacity Support A posteriori consultants par Direct 88,676.00 0.00 2017-12-06 2017-12-16 2018-02-19 2018-08-18 d'exécution Rue 579 et Rue CSCOM d Grants for Secondary Cities entente directe accès au CSCOM de Sido Soninkoura CS-REF23 / Etude des Component 1: Performance- Sélection de En attente travaux de construction de IDA / 49660 Based and Capacity Support A priori consultants par Direct 88,899.00 0.00 2017-10-29 2017-11-08 2018-01-12 2018-07-11 d'exécution 16 km de caniveaux à Niono Grants for Secondary Cities entente directe ML-PACUM-51342-CS-CDS / Component 4: Project Sélection de Trois chauffeurs pour la IDA / 49660 Management, Monitoring A posteriori consultants par Direct 16,002.00 0.00 Annulé 2018-01-02 2018-01-12 2018-03-18 2018-09-14 Cellule de Cordination du and Evaluation entente directe Projet CS-REF14 / Mise en cohérence de trois études PACUM PDUD et expérience Component 3: Institutional IDA / 49660 A priori Individuel Open 33,337.00 0.00 Annulé 2017-12-20 2018-02-07 2018-02-28 2018-04-04 2018-10-01 Niger avec proposition des Capacity Strengthening modalités d’une opération pilote de gestion ML-PACUM-97509-CS-CDS / Reconduction du contrat du groupement de cabinet CAFEC-KA/Convergences Component 4: Project Sélection de En cours audit et Conseils Associes IDA / Q7360 Management, Monitoring A priori consultants par Direct 35,560.00 0.00 2019-02-05 2019-02-15 2019-04-01 2019-05-01 d'exécution pour l'audit des comptes du and Evaluation entente directe projet d'appui aux communes urbaines du Mali- pour les exercices 2018 et 2019 ML-PACUM-97513-CS-CDS / Reconduction des contrats Component 1: Performance- Sélection de En attente des Assistants à la Maîtrise IDA / Q7360 Based and Capacity Support A priori consultants par Direct 29,993.00 0.00 2019-02-04 2019-02-11 2019-02-23 2019-05-24 d'exécution d'Ouvrage à Gao , Kita, Grants for Secondary Cities entente directe Niono, Bla et Koulikoro ML-PACUM-97629-CS-INDV / Recrutement d'un Component 3: Institutional En attente consultant pour l'élaboration IDA / Q7360 A posteriori Individuel Open 22,225.00 0.00 2019-02-11 2019-03-09 2019-03-24 2019-04-07 2019-05-07 Capacity Strengthening d'exécution de manuel de procédure sur les missions de la DNUH Page 8 ML-PACUM-97641-CS-INDV / Recrutement d'un consultant pour l'élaboration Component 3: Institutional En attente IDA / Q7360 A posteriori Individuel Open 22,225.00 0.00 2019-02-18 2019-03-16 2019-03-31 2019-04-14 2019-05-14 d'un manuel de procédure Capacity Strengthening d'exécution d'évaluation des performances des villes ML-PACUM-99317-CS-INDV / consultant individuel pour Component 3: Institutional En attente l'encadrement de la gestion IDA / Q7360 A posteriori Individuel Open 33,337.00 0.00 2019-03-26 2019-05-14 2019-06-04 2019-07-09 2019-08-08 Capacity Strengthening d'exécution des équipements marchands dans les VPP ML-PACUM-102838-CS-CDS / Reconduction du contrat de Sélection de l'Equipe Mobile de Component 3: Institutional En cours IDA / Q7360 A priori consultants par Direct 800,089.00 0.00 2019-02-25 2019-03-07 2019-03-14 2019-11-09 Renforcement des Capacités Capacity Strengthening d'exécution entente directe des Communes Urbaines du Mali ML-PACUM-113732-CS- INDV / Recrutement d'un Component 4: Project En attente consultant pour l'élaboration IDA / 49660 Management, Monitoring A posteriori Individuel Open 33,337.00 0.00 2019-05-30 2019-07-03 2019-07-10 2019-08-01 2019-08-31 d'exécution du document de la rue and Evaluation finale ML-PACUM-113731-CS- Component 4: Project INDV / Recrutement d'un En cours IDA / 49660 Management, Monitoring A posteriori Individuel Open 44,449.00 0.00 2019-05-13 2019-06-16 2019-07-01 2019-07-22 2019-08-21 consultant pour l'audit d'exécution and Evaluation environnemental ML-PACUM-116993-CS- INDV / Audit technique des Component 4: Project investissements à mener En attente IDA / 49660 Management, Monitoring A posteriori Individuel Open 44,449.00 0.00 2019-05-28 2019-06-23 2019-07-08 2019-07-22 2019-09-20 dans le cadre de la clôture d'exécution and Evaluation du projet et la pérennisation des acquis Page 9