The World Bank Implementation Status & Results Report Central African Republic - LONDO Project (P152512) Central African Republic - LONDO Project (P152512) AFRICA | Central African Republic | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 7 | ARCHIVED on 08-Nov-2018 | ISR34608 | Implementing Agencies: Agence d'Execution des Travaux d'Interet Public en Centrafrique (AGETIP-CAF), Ministry of Economy, Planning, and Cooperation Key Dates Key Project Dates Bank Approval Date: 30-Jul-2015 Effectiveness Date: 29-Sep-2015 Planned Mid Term Review Date: 15-Nov-2017 Actual Mid-Term Review Date: 15-Dec-2017 Original Closing Date: 31-Dec-2018 Revised Closing Date: 31-Dec-2018 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To provide temporary employment to vulnerable people throughout the entire territory of the country. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Local Governance:(Cost $3.40 M) Public Infrastructure:(Cost $8.00 M) Socio-Economic Integration:(Cost $5.00 M) Project Management:(Cost $3.00 M) Contingency (3%): to be allocated to Components 1, 2, and 3:(Cost $0.60 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Highly Satisfactory Highly Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating High High Implementation Status and Key Decisions The overall progress of the project towards achievement of the PDO is highly satisfactory and the overall implementation progress is satisfactory. The grant became effective on Sep 29, 2015 and the disbursement rate is 79%. The aggregated execution rate is about 80%. As of today, the project has benefitted a total of 28,250 beneficiaries in 58 districts and maintained 1,820 km of roads (1.1 million men-days). More than 1.6 billion CFA francs in the form of stipends have been distributed to workers. Phase 5 of the project (4,500 beneficiaries in nine districts) is ongoing. 11/8/2018 Page 1 of 7 The World Bank Implementation Status & Results Report Central African Republic - LONDO Project (P152512) 11/8/2018 Page 2 of 7 The World Bank Implementation Status & Results Report Central African Republic - LONDO Project (P152512) 11/8/2018 Page 3 of 7 The World Bank Implementation Status & Results Report Central African Republic - LONDO Project (P152512) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic Substantial Moderate Substantial Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Sustainability High High High Fiduciary High High High Environment and Social Moderate Moderate Moderate Stakeholders Substantial Substantial Substantial Other -- -- -- Overall High High High Results PDO Indicators by Objectives / Outcomes Improve access IN00579865 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 26,200.00 28,250.00 35,500.00 11/8/2018 Page 4 of 7 The World Bank Implementation Status & Results Report Central African Republic - LONDO Project (P152512) Date 01-Jan-2015 16-Mar-2018 19-Oct-2018 31-Dec-2018 IN00579909 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 35.00 35.00 33.00 Expand public services IN00579902 ►Benefitting districts (sous-prefectures) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 54.00 57.00 71.00 Date 01-Jan-2015 16-Mar-2018 19-Oct-2018 31-Dec-2018 Promote resilience IN00579901 ►Worked days (men-days) (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 976,377.00 1,096,531.00 1,420,000.00 Date 01-Jan-2015 16-Mar-2018 19-Oct-2018 31-Dec-2018 Intermediate Results Indicators by Components Local Governance IN00579903 ►Rapid development assessments (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 58.00 58.00 71.00 Date 01-Jan-2015 16-Mar-2018 19-Oct-2018 31-Dec-2018 IN00579906 ►Grievances registered related to delivery of project benefits addressed (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 100.00 Date 01-Jan-2015 16-Mar-2018 19-Oct-2018 31-Dec-2018 IN00645026 ►Regional AGETIP-CAF teams (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 11/8/2018 Page 5 of 7 The World Bank Implementation Status & Results Report Central African Republic - LONDO Project (P152512) Value 0.00 -- 5.00 5.00 Date 01-Jan-2015 -- 19-Oct-2018 31-Dec-2018 Public Infrastructure IN00579905 ►Road maintenance (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1,509.00 1,814.57 2,840.00 Date 01-Jan-2015 16-Mar-2018 19-Oct-2018 31-Dec-2018 Socio-Economic Integration IN00579907 ►Distribution of stipends (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 205.00 243.00 284.00 Date 01-Jan-2015 16-Mar-2018 19-Oct-2018 31-Dec-2018 IN00579908 ►Community maintenance systems (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 46.00 46.00 71.00 Date 01-Jan-2015 16-Mar-2018 16-Mar-2018 31-Dec-2018 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P152512 IDA-D0800 Effective USD 20.00 20.00 0.00 15.71 4.23 79% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P152512 IDA-D0800 Effective 30-Jul-2015 26-Aug-2015 29-Sep-2015 31-Dec-2018 31-Dec-2018 Cumulative Disbursements 11/8/2018 Page 6 of 7 The World Bank Implementation Status & Results Report Central African Republic - LONDO Project (P152512) Restructuring History There has been no restructuring to date. Related Project(s) P166943-CAR: LONDO + 11/8/2018 Page 7 of 7