PROCUREMENT PLAN (Textual Part) Project information: Burkina Faso Local Government Support Project - P162742 Project Implementation agency: Unité de Coordination du Programme d’Appui aux Collectivités Territoriales Date of the Procurement Plan: 23 September 2017 Period covered by this Procurement Plan: 13 September to 31 December 2017 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in LOI N° 039-2016/AN portant règlementation générale de la commande publique, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable PROCUREMENT Burkina Faso : Local Government Support Project PLAN General Information Country: Burkina Faso Banks Approval Date of the Original Procurement Plan: 2017-10-19 Revised Plan Date(s): (comma delineated, leave blank if none) 2017-10-24 Project ID: P120517 GPN Date: Project Name: Local Government Support Project Loan / Credit No: IDA / H7360 Executing Agency(ies): Unite de Coordination du Programme d Appui aux Collectivites Territoriales WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-29596-GO-RFB / Component 4: Project Single Stage - One Pending Matériel informatique et péri- IDA / H7360 Post Request for Bids Open - National 100,000.00 0.00 2017-11-15 2017-11-20 2017-12-20 2017-12-31 2018-01-24 2018-03-25 management and evaluation Envelope Implementation informatique BF-PACT-29716-GO-RFQ / Component 4: Project Request for Single Stage - One Pending Fournitures de bureau, de IDA / H7360 Post Limited 10,000.00 0.00 2017-11-20 2017-12-29 2018-01-29 management and evaluation Quotations Envelope Implementation consommables informatiques BF-PACT-29722-GO-RFQ / Component 4: Project Request for Single Stage - One Pending IDA / H7360 Post Limited 25,000.00 0.00 2017-11-20 2017-12-21 2018-01-21 Matériel et mobilier de bureau management and evaluation Quotations Envelope Implementation BF-PACT-29717-GO-RFB / Component 4: Project Single Stage - One Pending IDA / H7360 Post Request for Bids Open - National 300,000.00 0.00 2017-11-15 2017-11-20 2017-12-20 2017-12-27 2018-01-24 2018-04-24 Matériel roulant management and evaluation Envelope Implementation BF-PACT-29723-GO-DIR / Component 4: Project Pending Fourniture de services IDA / H7360 Post Direct Selection Direct 300,000.00 0.00 2018-01-15 2018-01-29 2018-02-19 2018-02-26 management and evaluation Implementation dassurance NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-29760-CS-QCBS / Component 4: Project Quality And Cost- Pending Audit financier et comptable de IDA / H7360 Post Open - National 90,000.00 0.00 2018-03-10 2018-03-15 2018-04-03 2018-05-08 2018-05-13 2018-06-04 2018-06-28 2019-03-01 management and evaluation Based Selection Implementation trois exercices BF-PACT-29763-CS-QCBS / Component 4: Project Quality And Cost- Pending Audit des marchés des IDA / H7360 Post Open - National 150,000.00 0.00 2018-01-10 2018-01-15 2018-02-06 2018-03-15 2018-03-22 2018-04-15 2018-05-13 2018-06-27 management and evaluation Based Selection Implementation communes pour cinq exercices Component 3 - Improving BF-PACT-29746-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Plateau Central citizens Component 3 - Improving BF-PACT-29732-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre citizens Component 3 - Improving BF-PACT-29749-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre Est citizens Component 3 - Improving BF-PACT-29734-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C du IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation Centre Ouest citizens Component 3 - Improving BF-PACT-29728-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-29 2019-04-29 local level policy makers and Based Selection Implementation région du Sud-Ouest citizens Component 3 - Improving BF-PACT-29726-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région des Hauts-Bassins citizens Component 3 - Improving BF-PACT-29736-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région de lEst citizens Component 3 - Improving BF-PACT-29729-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Sahel citizens Page 1 Component 3 - Improving BF-PACT-29730-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Boucle du Mouhoun citizens Component 3 - Improving BF-PACT-29747-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre Sud citizens Component 3 - Improving BF-PACT-29737-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Centre Nord citizens Component 3 - Improving BF-PACT-29743-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région des Cascades citizens Component 3 - Improving BF-PACT-29745-CS-CQS / Mise accountability linkages between Quality And Cost- Pending en Suvre de la composante C IDA / H7360 Prior Open - International 1,000,000.00 0.00 2017-11-20 2017-12-04 2018-01-03 2018-02-02 2018-02-16 2018-04-01 2018-04-30 2019-04-30 local level policy makers and Based Selection Implementation région du Nord citizens INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PACT-29766-CS-INDV / Component 4: Project Individual Consultant Pending Relecture, suivi et hébergement IDA / H7360 Post Limited 5,000.00 0.00 2017-11-05 2017-11-10 2017-11-20 2017-12-14 2018-01-14 management and evaluation Selection Implementation du site web du PACT BF-PACT-29770-CS-INDV / Component 4: Project Individual Consultant Pending Elaboration dune base de IDA / H7360 Post Limited 5,000.00 0.00 2017-10-20 2017-10-25 2017-11-05 2017-11-27 2017-12-27 management and evaluation Selection Implementation données BF-PACT-29815-CS-INDV / Audits municipaux et Assistance Component 2 - Strengthening Individual Consultant Pending à lélaboration des Plans de IDA / H7360 capacity of municipalities to Post Limited 55,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Selection Implementation Développements Institutionnels manage local development (PDI) de 11 communes BF-PACT-29816-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 1) BF-PACT-29789-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 2) BF-PACT-29790-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 3) BF-PACT-29779-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 4) BF-PACT-29817-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 5) BF-PACT-29795-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 6) BF-PACT-29799-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 7) BF-PACT-29787-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 8) BF-PACT-29791-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 9) Page 2 BF-PACT-29809-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 10) BF-PACT-29793-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 11) BF-PACT-29797-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 12) BF-PACT-29796-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 13) BF-PACT-29813-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 14) BF-PACT-29792-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 15) BF-PACT-29785-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 16) BF-PACT-29802-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 17) BF-PACT-29788-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 18) BF-PACT-29804-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 19) BF-PACT-29805-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 20) BF-PACT-29818-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 21) BF-PACT-29812-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 22) BF-PACT-29806-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 23) BF-PACT-29798-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 24) BF-PACT-29814-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 25) Page 3 BF-PACT-29808-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 26) BF-PACT-29781-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 27) BF-PACT-29807-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 28) BF-PACT-29794-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 29) BF-PACT-29753-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 30) BF-PACT-29786-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 31) BF-PACT-29800-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 32) BF-PACT-29811-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 33) BF-PACT-29801-CS-INDV / Audits municipaux et assistance Component 2 - Strengthening à lélaboration des Plans de Individual Consultant Pending IDA / H7360 capacity of municipalities to Post Limited 50,000.00 0.00 2017-11-25 2017-11-30 2017-12-14 2018-01-28 2018-03-14 Développements Institutionnels Selection Implementation manage local development (PDI) de 10 communes (groupe 34) Component 3 - Improving BF-PACT-29819-CS-CDS / accountability linkages between Pending Collecte de données finales du IDA / H7360 Post Direct Selection Direct - National 153,507.00 0.00 2017-09-18 2017-10-11 2017-10-30 2018-01-28 local level policy makers and Implementation Projet au niveau citoyen citizens Page 4