PROCUREMENT PLAN Project information: country: The People’s Republic of China Project name: Zhejiang Qiandao Lake and Xin'an River Basin Water Resources and Ecological Environment Protection Project P-number: P159870 Project Implementation agency: Zhejiang Urban Environment Project Leading Group Office; Chun’an Qiandao Lake Construction Group; Jiande Xinshui Construction Co. Ltd. Date of the Procurement Plan: January 13, 2020; Period covered by this Procurement Plan: [2020-2021] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017and August 2018) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. A. The Bank’s Standard Procurement Documents (SPDs): The Bank’s SPDs shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. B. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures (Tendering and Bidding Law of the Peoples’ Republic of China, i.e. TBL promulgated by its Order No. 21 dated August 30, 1999 and the Implementation Regulations of the TBL promulgated by its State Council Order No. 613 dated November 30, 2011 and any amendments thereof) may be used with the following conditions to meet the requirements for open competitive procurement of paragraph 5.4 of the Procurement Regulations: a. All procurement notices shall be published in a national newspaper of wide circulation, or on a widely-used website / electronic portal with free access. b. A minimum of twenty (20) business days shall be given to Bidders between the date of such advertisement (or the date of availability of procurement documents, whichever is later and the deadline for the submission of bids). The advertisement and procurement documents shall specify the deadline for the submission of bids. Potential Bidders shall be allowed to inspect and purchase procurement documents at any time prior to the deadline for the submission of bids. c. Any Bidder/Consultant should be eligible to participate in a procurement process and to be awarded a Bank-financed contract as defined in paragraphs 3.21, 3.22 and 3.23 of the Procurement Regulations. d. Bidders/Consultants shall be allowed to submit bids/proposals by mail or in person. Bidders/consultants shall not be mandatory required to be present at the bid/proposal opening session. e. Bidders should not be required to register as a condition for inspecting or purchasing procurement documents, submitting its bid or receiving contract award. A winner Bidder, shall be given reasonable opportunity of registering (if required) before contract signing without any let or hindrance. Bidding shall not be restricted to any class of contractors. f. The winning bidder shall not be required, as a condition of award, to reduce its bid price No contract negotiation shall be permitted unless agreed in the procurement plan. g. No bid may be rejected solely on the basis that the bid price exceeds any cost estimate. Rejection of all bids or re-bidding shall not be allowed solely because the number of bids is less than three (3). Rebidding shall not take place without any sound justification. h. The Bank’s procurement documents for approaching the national market or any procurement document acceptable to the Bank shall be used. All procurement documents must require that bidders/consultants present a signed acceptance at the time of bidding or submitting a proposal, to be incorporated in any resulting contract, confirming application of and compliance with the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. i. The procurement documents shall disclose the newspaper and / or the electronic means in which the information on contract award shall be published. j. The contract award notification shall identify: (a) name and address of the Borrower’s Project Implementing Unit, (b) name and reference number of the contract being awarded and the selection method used (c) names of all Bidders/Consultants that submitted bids/proposals and their prices as read out at the bid opening meeting and as evaluated (d) names of all Bidders/ Consultants whose bids/proposals were rejected either as nonresponsive or as not meeting qualification criteria or were not evaluated, with the reasons therefor and (e) the name of the successful Bidder/Consultant, the final contract price, the contract duration and a summary of its scope. k.The Borrower shall implement an effective complaint mechanism allowing bidders or consultants to complain, and have their complaints handled and responded in a timely manner. Procurement documents should indicate the complaint mechanism procedure and provide the professional title and address of the officials to whom such protests should be sent. l. The Bank shall be allowed to review procurement documentation and activities related to the activities included in the procurement plan. C. Other national procurement arrangements: When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. A. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing is not applicable for those contracts identified in the Procurement Plan tables. B. Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations is not applicable. C. Domestic Preference as specified under paragraph 5.51 of the Procurement Regulations: Goods: Domestic Preference is not applicable for those contracts identified in the Procurement Plan tables. Works: Domestic Preference is not applicable. G. Other Relevant Procurement Information: Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table1 according to the Procurement Regulations (dated July 2016, revised November 2017 and August 2018). Table1.Thresholds for Procurement Methods and Prior Review Expenditure Contract Value Prior Review Threshold Procurement Method Category Threshold (US$) (US$) International Open ≥40,000,000 Competitive Procurement All contracts (International + Open) National Open ≥ 500k to 1. Civil works Competitive Procurement All contracts ≥15 million <40,000,000 (National + Open) <500,000 Request for Quotations N/A Any value Direct Selection All contracts ≥15 million International Open ≥10,000,000 Competitive Procurement All contracts (International + Open) 2. Goods/Non- National Open consulting ≥ 500k to Competitive Procurement All contracts ≥4 million services <10,000,000 (National + Open) <500,000 Request for Quotations N/A Any value Direct Selection All contracts ≥4 million Currency Unit = Chinese Yuan (CNY) US$1.00 = CNY 6.70 Procurement Packages with Methods and Time Schedule: Estimated Estimated Review Expected Prequalific- Domestic Contract Cost Cost Procurement Procurement byBank Bid- Ref.No. ContractName Description ation Preference Period Remarks (CNY:10 (USD:10 Category Method (Prior/ Opening (yes/no) (yes/no) (Month) thousand) thousand) Post) Date Component1: Landscape Management Improvement Forest emergency Forest emergency road Open JUHT3 road in Hangtou of 9km in Hangtou 447.04 66.723 Works +National No No Post 2020.3 9 Town Town, width 2.5m + RFB Forest emergency road Forest emergency Open of 13.13km in JUXA4 road in Xin'anjiang 2437.98 363.8773 Works +National No No Post 2020.3 15 Xin'anjiang Street Street + RFB Office, width 4.0m Component 2: Water Resources Management Improvement Chuan'an Rural RFB / WTP 800m3/d and CGPM3 Water Supply: 1958.58 292.33 Works Open / No No Post 2020.4 15 water supply pipe Pingmen WS National Chuan'an Rural RFB / Water water supply pipe and CGPS4 2420.73 361.30 Works Open / No No Post 2020.4 15 Supply:Pingshan related facilities National WS Chuan'an Rural RFB / water supply pipe and CGQB6 Water Supply: 567.44 84.69 Works Open / No No Post 2020.4 15 related facilities Qiaobei WS National Estimated Estimated Review Expected Prequalific- Domestic Contract Cost Cost Procurement Procurement byBank Bid- Ref.No. ContractName Description ation Preference Period Remarks (CNY:10 (USD:10 Category Method (Prior/ Opening (yes/no) (yes/no) (Month) thousand) thousand) Post) Date Chuan'an Rural RFB / water supply pipe and CGLQ8 Water Supply: Linqi 1594.96 238.05 Works Open / No No Post 2020.4 15 related facilities WS National Chuan'an Rural RFB / water supply pipe and CGJS9 Water Supply: 1497.32 223.48 Works Open / No No Post 2020.4 15 related facilities Jieshou WS National Chuan'an Rural RFB / water supply pipe and CGQD10 Water Supply: 1040.46 155.29 Works Open / No No Post 2020.4 15 related facilities Qiandaohu WS National Chuan'an Rural RFB / WTP 2100m3/d and CGXS13 Water Supply: 2160.54 322.47 Works Open / No No Post 2020.4 15 water supply pipe Xiashan WS National Chuan'an Rural RFB / water supply pipe and CGJJ15 Water Supply: 2037.12 304.05 Works Open / No No Post 2020.4 15 related facilities Jiangjia WS National 12 bridges along Qingtan River and Open Bridge rehabilitation JUDT1 Zhenyuan River, with 607.18 90.6241 Works +National No No Post 2020.4 12 in Datong Town rehabilitation area of + RFB 1237.5m2 Prior Review Threshold: The thresholds of procurement methods and the requirements for the Bank’s prior review are shown in Table2 according to the Procurement Regulations (dated July 2016, revised November 2017 and August 2018). Table2.Thresholds for Procurement Methods and Prior Review Expenditure Contract Value Prior Review Threshold Procurement Method Category Threshold (US$) (US$) ≥300,000 QCBS/QBS/LCS/FBS All contracts ≥2 million <300,000 FBS, LCS, CQS Direct Selection for firms All contracts ≥2 million Consultant services Selection of Individual All contracts ≥400,000 Consultant Direct Selection for All contacts ≥ 400,000 individuels Notes: QCBS: Quality- and Cost-Based Selection DS: Direct Selection QBS: Quality-Based Selection IC: Individual Consultant selection FBS: Fixed Budget Selection N/A: Not Applicable LCS: Least Cost Selection CQS: Consultants’ Qualifications-based Selection Currency Unit = Chinese Yuan(CNY) US$1.00 = CNY 6.70 Procurement Packages with Methods and Time Schedule: Estimated Estimated Expected Domestic Reviewby Contract Cost Cost Procurement Procurement Prequalific-ation Bid- Ref.No. ContractName Description Preference Bank Period Remarks (CNY:10 (USD:10 Category Method (yes/no) Opening (yes/no) (Prior/Post) (Month) thousand) thousand) Date Component 3: Institutional Capacity Building, Monitoring and Project Management Study on Near-nature Management Technique of Coniferous Forest Transforming to Coniferous and Broad- leaved mixed Forest, Study on Near-nature Renovation Technique of Pinus Open Study on Three Consulting JLJY1 Massoniana Forest 159.61 23.8224 +National No No Post 2020.3 43 Forestry Issues Service Transforming to + CQS Coniferous and Broad- leaved mixed Forest, Study on Near-natural Management Technique of Secondary Broad-leaved Forest of Soil and Water Conservation Type PROCUREMENT China : Zhejiang Qiandao Lake and Xin'an River Basin Water Resources and Ecological Environment Protection Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2018-12-17 2020-01-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P159870 GPN Date: 2018-09-20 Project Name: Zhejiang Qiandao Lake and Xin'an River Basin Water Resources and Ecological Environment Protection Project Loan / Credit No: IBRD / 88560 Executing Agency(ies): Qiandao Lake PMO WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CLCP1 / No.1 contract section of Chun'an Forest Under Conpontent 1: Landscape Single Stage - One Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 648,200.00 460,516.56 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2021-10-27 Management Improvement Envelope Project:Forest greening and on renovation of 3506mu CLCP2 / No.2 contract section of Chun'an Forest Under Conpontent 1: Landscape Single Stage - One Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 707,500.00 464,781.22 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2021-10-27 Management Improvement Envelope Project:Forest greening and on renovation of 3561mu CLCP3 / No.3 contract section of Chun'an Forest Under Conpontent 1: Landscape Single Stage - One Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 786,200.00 533,808.04 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2021-10-27 Management Improvement Envelope Project:Forest greening and on renovation of 3560mu CLCP4 / No.4 contract section of Chun'an Forest Under Conpontent 1: Landscape Single Stage - One Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 733,600.00 0.00 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2021-10-27 Management Improvement Envelope Project:Forest greening and on renovation of 2243mu CLCP6 / No.6 contract section of Chun'an Forest Under Conpontent 1: Landscape Single Stage - One Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 765,800.00 446,281.59 Implementati 2018-12-20 2018-12-25 2019-02-05 2019-03-07 2019-04-11 2021-10-27 Management Improvement Envelope Project:Forest greening and on renovation of 1127mu CLCP7 / No.7 contract section of Chun'an Forest Under Conpontent 1: Landscape Request for Single Stage - One Ecological Rehabilitation IBRD / 88560 Post Open - National 458,500.00 276,650.66 Implementati 2018-12-25 2019-02-19 2021-09-06 Management Improvement Quotations Envelope Project:Forest greening and on renovation of 1798mu CGWB1 / Wangfu Water Component 2: Water Single Stage - One Plant:WTP 2200m3/d and IBRD / 88560 Resources Management Post Request for Bids Open - National 2,913,900.00 0.00 Canceled 2019-01-15 2019-01-20 2019-03-03 2019-04-02 2019-05-07 2020-07-30 Envelope water supply pipe Improvement CGFS2 / Fengshuling Wate Component 2: Water Under Single Stage - One r Plant:WTP 5000m3/d and IBRD / 88560 Resources Management Post Request for Bids Open - National 8,848,100.00 7,088,245.67 Implementati 2019-01-15 2019-01-20 2019-03-03 2019-04-02 2019-05-07 2020-07-30 Envelope water supply pipe Improvement on CGYJ11 / Yejia Water Plan Component 2: Water Under Single Stage - One t:WTP 1400m3/d and water IBRD / 88560 Resources Management Post Request for Bids Open - National 1,607,200.00 1,676,901.92 Implementati 2019-01-15 2019-01-20 2019-03-03 2019-04-02 2019-05-07 2020-07-30 Envelope supply pipe Improvement on JUHT2 / Construction of Pending Conpontent 1: Landscape Single Stage - One wetland in Hangtou Town: IBRD / 88560 Post Request for Bids Open - National 541,900.00 0.00 Implementati 2019-03-05 2019-03-10 2019-04-21 2019-05-21 2019-06-25 2020-06-19 Management Improvement Envelope 16247.2m2 on Page 1 JSDT4 / Qingtan River in Datong Town (Panshan Component 2: Water Request for Single Stage - One Section): river dredging IBRD / 88560 Resources Management Post Open - National 400,600.00 315,759.74 Signed 2019-01-15 2019-03-12 2019-12-07 Quotations Envelope 1.1km, ecological Improvement embankment 2.2km JSHT14 / Wulong River in Hangtou Town (Pengjia Component 2: Water Request for Single Stage - One Section): river dredging IBRD / 88560 Resources Management Post Open - National 471,300.00 329,678.78 Signed 2019-01-15 2019-03-12 2019-12-07 Quotations Envelope 1.1km, ecological Improvement embankment 2.2km JSHT15 / Wulong River in Component 2: Water Hangtou Town: new Request for Single Stage - One IBRD / 88560 Resources Management Post Open - National 300,400.00 277,402.44 Signed 2019-01-15 2019-03-12 2019-12-07 construction and Quotations Envelope Improvement rehabilitation of 9 dams JSHT16 / Shimuling River Component 2: Water in Hangtou Town: river Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 951,600.00 637,750.93 Signed 2019-01-10 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2020-03-27 dredging 2.3km, ecological Envelope Improvement embankment 4.6km, 1 dam CGWB1-1 / Wangfu WS: Component 2: Water Under Single Stage - One WTP 2200m3/d and water IBRD / 88560 Resources Management Post Request for Bids Open - National 2,647,700.00 2,221,867.53 Implementati 2019-05-15 2019-05-20 2019-07-01 2019-07-31 2019-09-04 2020-10-28 Envelope supply pipe Improvement on JSDT5 / Qingtan River in Datong Town (Xikou Component 2: Water Request for Single Stage - One Section): river dredging IBRD / 88560 Resources Management Post Open - National 143,700.00 0.00 Canceled 2019-01-15 2019-03-12 2019-12-07 Quotations Envelope 0.79km, ecological Improvement embankment 1.57km JSDT1 / DatongRiver in Component 2: Water Request for Single Stage - One Datong Town: ecological IBRD / 88560 Resources Management Post Open - National 220,700.00 0.00 Canceled 2019-01-15 2019-03-12 2019-12-07 Quotations Envelope embankment 9.3km Improvement JSDT1-5 / DatongRiver& Qingtan River(Xikou Section)in Datong Town: Component 2: Water Under Request for Single Stage - One ecological embankment IBRD / 88560 Resources Management Post Open - National 364,500.00 286,326.47 Implementati 2019-08-10 2019-10-05 2020-07-01 Quotations Envelope 9.3km, river dredging Improvement on 0.79km, ecological embankment 1.57km JLFH8 / Forest fire Pending Conpontent 1: Landscape Request for Single Stage - One pool:building 20 forest fire IBRD / 88560 Post Open - National 166,900.00 0.00 Implementati 2019-08-10 2019-10-05 2020-04-02 Management Improvement Quotations Envelope pools in project area on JLDT1 / No.1contract section of Datong Town Under Forest Greening and Conpontent 1: Landscape Single Stage - One IBRD / 88560 Post Request for Bids Open - National 1,607,900.00 1,104,134.94 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2022-12-09 Renovation Project: forest Management Improvement Envelope on greening and renovation of 3834 mu JLDT2 / No.2 contract section of Datong Town Under Forest Greening and Conpontent 1: Landscape Single Stage - One IBRD / 88560 Post Request for Bids Open - National 1,910,800.00 1,077,204.01 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2022-12-09 Renovation Project: forest Management Improvement Envelope on greening and renovation of 4488 mu JLDT3 / No.3 contract section of Datong Town Under Forest Greening and Conpontent 1: Landscape Single Stage - One IBRD / 88560 Post Request for Bids Open - National 1,490,600.00 1,102,447.01 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2022-12-09 Renovation Project: forest Management Improvement Envelope on greening and renovation of 2920 mu Page 2 JLSC4 / Shouchang Town Forest Greening and Under Conpontent 1: Landscape Request for Single Stage - One Renovation Project: forest IBRD / 88560 Post Open - National 432,900.00 342,283.69 Implementati 2019-08-10 2019-10-05 2022-10-19 Management Improvement Quotations Envelope greening and renovation of on 1671 mu JLHT5 / Hangtou Town Forest Greening and Under Conpontent 1: Landscape Single Stage - One Renovation Project: forest IBRD / 88560 Post Request for Bids Open - National 1,511,500.00 983,362.36 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2022-12-09 Management Improvement Envelope greening and renovation of on 5839 mu JLLC6 / Shouchang Forest Farm & Xin’anjiang Forest Farm Forest Greening and Renovation Project: Under Conpontent 1: Landscape Single Stage - One shouchang forest farm:forest IBRD / 88560 Post Request for Bids Open - National 1,076,300.00 1,121,777.22 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2022-12-09 Management Improvement Envelope greening and renovation of on 3382 mu;Xin’anjiang forest farm:forest greening and renovation of 1801 mu CLCP8 / CLCP8: Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 800,000.00 486,499.33 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 3376 mu CLCP9 / CLCP9:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 680,000.00 441,230.91 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 2464 mu CLCP10 / CLCP10:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 650,000.00 403,362.30 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 2251 mu CLCP11 / CLCP11:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 790,000.00 495,355.48 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 4106 mu CLCP12 / CLCP12: Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 780,000.00 478,471.53 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 3453 mu CLCP13 / CLCP13:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 780,000.00 476,424.74 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 2048 mu CLCP14 / CLCP14:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 810,000.00 493,997.41 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 1297 mu CLCP15 / CLCP15:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 790,000.00 486,566.57 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 1172 mu Page 3 CLCP16 / CLCP16:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 730,000.00 411,140.65 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 2218 mu CLCP17 / CLCP17:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 730,000.00 460,355.12 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 2258 mu CLCP18 / CLCP18:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 790,000.00 441,234.49 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 2709 mu CLCP19 / CLCP19:Chun'an Forest Ecological Under Conpontent 1: Landscape Single Stage - One Rehabilitation Project: Forest IBRD / 88560 Post Request for Bids Open - National 820,000.00 0.00 Implementati 2019-08-05 2019-08-10 2019-09-21 2019-10-21 2019-11-25 2020-05-23 Management Improvement Envelope greening and renovation of on 3393 mu CLCP5 / No.5 contract section of Chun'an Forest Under Conpontent 1: Landscape Single Stage - One Ecological Rehabilitation IBRD / 88560 Post Request for Bids Open - National 640,800.00 423,598.19 Implementati 2019-08-02 2019-08-07 2019-09-18 2019-10-18 2019-11-22 2022-06-09 Management Improvement Envelope Project:Forest greening and on renovation of 1237mu JSHT12 / Hangchuan section of Shouchang River Component 2: Water Single Stage - One in Hangtou Town: river IBRD / 88560 Resources Management Post Request for Bids Open - National 1,258,200.00 893,255.41 Signed 2019-08-02 2019-08-07 2019-09-18 2019-10-18 2019-11-22 2020-10-17 Envelope dredging 3.3km, ecological Improvement embankment 3.5km, 3 dams CGLC12 / Langchuan Wate Component 2: Water Under r Supply Extention Networks Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 831,343.28 556,508.26 Implementati 2019-08-20 2019-08-25 2019-10-06 2019-11-05 2019-12-10 2021-03-04 :water supply pipe and rela Envelope Improvement on ted facilities CGPM3 / Chuan'an Rural Component 2: Water Pending Water Supply: Pingmen WS: Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 2,923,253.73 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-10-29 WTP 800m3/d and water Envelope Improvement on supply pipe CGPS4 / Chuan'an Rural Component 2: Water Pending Water Supply:Pingshan WS: Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 3,613,029.85 0.00 Implementati 2020-04-15 2020-04-19 2020-05-31 2020-06-30 2020-08-04 2021-10-28 water supply pipe and Envelope Improvement on related facilities CGQB6 / Chuan'an Rural Component 2: Water Pending Water Supply:Qiaobei WS: IBRD / 88560 Resources Management Post Request for Bids 846,925.37 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-10-29 water supply pipe and Improvement on related facilities CGLQ8 / Chuan'an Rural Component 2: Water Pending Water Supply:Linqi WS: Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 2,380,537.31 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-10-29 water supply pipe and Envelope Improvement on related facilities CGJS9 / Chuan'an Rural Component 2: Water Pending Water Supply:Jieshou WS: Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 2,234,805.97 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-10-29 water supply pipe and Envelope Improvement on related facilities Page 4 CGQD10 / Chuan'an Rural Water Supply: Component 2: Water Pending Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 1,552,925.37 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-10-29 Envelope Qiandaohu WS: water supply Improvement on pipe and related facilities CGXS13 / Chuan'an Rural Water Supply: Component 2: Water Pending Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 3,224,686.57 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-10-29 Envelope Xiashan WS: WTP 2100m3/d Improvement on and water supply pipe CGJJ15 / Chuan'an Rural Water Supply: Component 2: Water Pending Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 3,040,477.61 0.00 Implementati 2020-04-15 2020-04-20 2020-06-01 2020-07-01 2020-08-05 2021-10-29 Envelope Jiangjia WS: water supply Improvement on pipe and related facilities JUHT3 / Forest emgerency Pending Conpontent 1: Landscape Single Stage - One road of 9km in Hangtou IBRD / 88560 Post Request for Bids Open - National 667,230.00 0.00 Implementati 2020-02-09 2020-02-14 2020-03-27 2020-04-26 2020-05-31 2021-02-25 Management Improvement Envelope Town, width 2.5m on JUXA4 / Forest emgerency Pending road of 13.13km in Conpontent 1: Landscape Single Stage - One IBRD / 88560 Post Request for Bids Open - National 3,638,773.00 0.00 Implementati 2020-02-09 2020-02-14 2020-03-27 2020-04-26 2020-05-31 2021-08-24 Xin'anjiang Street Office, Management Improvement Envelope on width 4.0m JUDT1 / Bridge rehabilitation in Datong Component 2: Water Pending Town: 12 bridges along Single Stage - One IBRD / 88560 Resources Management Post Request for Bids Open - National 906,241.00 0.00 Implementati 2020-02-16 2020-02-21 2020-04-03 2020-05-03 2020-06-07 2021-06-02 Qingtan River and Zhenyuan Envelope Improvement on River, with rehabilitation area of 1237.5m2 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JNZZ1 / Surface pollution control for planting industry Under Conpontent 1: Landscape Single Stage - One (equipments including solar IBRD / 88560 Post Request for Bids Open - National 647,500.00 0.00 Implementati 2019-01-10 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2024-04-05 Management Improvement Envelope insecticidal light and insect on sticky board) JLFH7 / Procuring of forest fire prenvention GIS Conpontent 1: Landscape Single Stage - One monitoring and early IBRD / 88560 Post Request for Bids Open - National 579,300.00 0.00 Canceled 2019-01-10 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2019-10-29 Management Improvement Envelope warning system and other equipments JLFH7 / Procuring of forest fire prenvention GIS Under Conpontent 1: Landscape Request for Single Stage - One monitoring and early IBRD / 88560 Post Open - National 382,300.00 0.00 Implementati 2019-08-10 2019-10-05 2020-04-02 Management Improvement Quotations Envelope warning system and other on equipments NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAJY2 / Chun'an County: External Environment Monit Component 3: Institutional Consultant Under oring:External environment IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 144,700.00 0.00 2018-12-20 2019-01-10 2019-02-23 2019-03-25 2019-04-29 2024-06-21 Implementation monitoring, preparation of en and Project Management Selection vironment monitoring report JDJY2 / Jiande City: Exter nal Environment Monitoring Component 3: Institutional Consultant Under :External environment moni IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 35,800.00 0.00 2018-12-20 2019-01-10 2019-02-23 2019-03-25 2019-04-29 2024-06-21 Implementation toring, preparation of enviro and Project Management Selection nment monitoring report ZJJY1-6 / Project Management Consulting Services:project management (support for bidding and Component 3: Institutional deal with the complaint, Quality And Cost- Open - Under IBRD / 88560 Capcity Buildting, Monitory Post 500,000.00 0.00 2018-12-30 2019-01-20 2019-03-05 2019-04-02 2019-05-02 2019-06-06 2019-07-11 2024-06-30 contract variation Based Selection International Implementation and Project Management management, construction management and payment review). preparation of the Progress Report for WB. CHJC2 / Chun'an and Jian de Environment Monitoring Project (Result monitoring): Component 3: Institutional Result monitoring for water Quality And Cost- Open - Pending IBRD / 88560 Capcity Buildting, Monitory Post 840,000.00 0.00 2019-06-30 2019-07-21 2019-08-18 2019-09-15 2019-09-22 2019-10-13 2019-11-17 2024-07-13 conservancy project, forest pr Based Selection International Implementation and Project Management oject and agriculture project of Chun'an County and Jian de City Component 3: Institutional Consultant JLJY1 / Study on Three Pending IBRD / 88560 Capcity Buildting, Monitory Post Qualification Open - National 238,224.00 0.00 2020-02-09 2020-03-01 2020-04-14 2020-05-14 2020-06-18 2023-12-31 Forestry Issues Implementation and Project Management Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAJY1 / Chun'an County: External Resettlement Monit Component 3: Institutional Individual oring:External resettlement Under IBRD / 88560 Capcity Buildting, Monitory Post Consultant Limited 143,300.00 0.00 2018-12-20 2018-12-25 2019-01-15 2019-02-19 2024-06-22 and land acquisition monitor Implementation and Project Management Selection ing, preparation of resettlem ent report JDJY1 / Jiande City: Exter nal Resettlement Monitoring Component 3: Institutional Individual :External resettlement and Under IBRD / 88560 Capcity Buildting, Monitory Post Consultant Limited 35,800.00 0.00 2018-12-20 2018-12-25 2019-01-15 2019-02-19 2024-06-22 land acquisition monitoring, Implementation and Project Management Selection preparation of resettlement r eport Page 6