P128534 Safety Nets Project Procurement Plan June 1st 2017 I. General 1. Bank’s approval Date of the procurement Plan: February 5, 2013 (initial): Revision 12 of Updated Procurement Plan, April 20, 2017 2. Date of General Procurement Notice: Nov 24, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year November 2016 to March 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. NCB (Goods) Above or equal US$ 10 million 2. NCB (Works) Above or equal US$ 10 million 3. NCB (Non-Consultant Services) Above or equal US$ 2 million 4. Individual (Goods) Above or equal Justification to be included US$ 10 million in the PP 5. Individual (Non Consultant Above or equal Justification to be included Services) US$ 2 million in the PP 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for the Safety Nets Project issued on January 2014 by Project Coordination Unit. 5. Any Other Special Procurement Arrangements: Not Applicable 1 6. Summary of the Procurement Packages planned during the 18 months of the current Procurement Plan-November 2016 to March 2018 (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) 1 Summary of 0 0 No No the ICB (Works) 2 Summary of 0 0 No No the ICB (Goods) 3 Summary of 0 0 No No the NCB (Works) 4 Summary of 1.5 18 No Post the NCB (Goods) 5 Summary of 0.74 2 No Prior the NCB (Non- Consultant Services) 6 Summary of 0.51 16 No Post the NCB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above or equal US$ 1 million 2 Competitive Methods (Individual) Above or equal US$ 0.3 million 3 Single Source (Firms) Above or equal Justification to be US$ 1 million included in the PP 4 Single Source (Individual) Above or equal Justification to be US$ 0.3 million included in the PP 2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US$_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 1.7 8 Prior LCS; SSS; number of CQS; contracts that Individual; will be let under other methods 2 Summary of 2 72 Post SSS; CQS; number of Individual contracts that will be let under other methods 3 PROCUREMENT Cameroon : Cameroon Social Safety Nets PLAN General Information Country: Cameroon Banks Approval Date of the Original Procurement Plan: 2017-02-14 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-06-27 Project ID: P128534 GPN Date: Project Name: Cameroon Social Safety Nets Loan / Credit No: IDA / 52240 Executing Agency(ies): UNITE DE GESTION DU PROJET FILETS SOCIAUX WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-26069-CW-RFQ / Laying the Foundations of a Request for Single Stage - One Pending Aménagement des bureaux de IDA / 52240 Safety Net System and Post Limited 8,300.00 0.00 2018-04-01 2018-04-24 2018-05-15 Quotations Envelope Implementation l'antenne régionale du Nord ouest Supporting Project Management GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-5831-GO-RFB / fourniture du matériel Laying the Foundations of a Single Stage - One é honie, et informatique, de télp IDA / 52240 Safety Net System and Post Request for Bids Open - National 253,000.00 243,616.43 Completed 2017-01-24 2017-02-01 2017-01-29 2017-03-12 2017-01-24 2017-04-11 2017-02-10 2017-05-16 2017-04-17 2017-11-12 2017-05-08 Envelope d'équipement de bureau (en 3 Supporting Project Management lots distincts) CM-UGP-PFS-6172-GO-RFQ / Fourniture du matériel de la phase 3 des THIMO dans 2 Request for Single Stage - One Pending IDA / 52240 Public Works Program Pilot Post Limited 188,000.00 0.00 2017-02-18 2017-04-15 2017-05-15 communes de la région de Quotations Envelope Implementation l'Extrême Nord et 2 communes de la région de l'EST CM-UGP-PFS-6231-GO-RFQ / Fourniture des boîtes à pharmacie de la phase 3 des Request for Single Stage - One IDA / 52240 Public Works Program Pilot Post Limited 29,000.00 31,172.51 Completed 2017-02-20 2017-03-03 2017-04-17 2017-04-07 2017-05-01 2017-04-14 THIMO pour 2 communes de la Quotations Envelope région de l'Extrême Nord et 2 communes de la région de l'Est CM-UGP-PFS-6307-GO-RFQ / Laying the Foundations of a Request for Single Stage - One Pending Fourniture des fournitures de IDA / 52240 Safety Net System and Post Limited 60,000.00 0.00 2017-03-20 2017-05-15 2018-05-10 Quotations Envelope Implementation bureau au Projet Filets Sociaux Supporting Project Management CM-UGP-PFS-7392-GO-RFQ / Laying the Foundations of a Single Stage - One Fourniture des consommables IDA / 52240 Safety Net System and Post Request for Bids Open - National 130,000.00 0.00 Canceled 2017-05-31 2016-12-12 2017-06-05 2017-07-17 2017-08-16 2017-09-20 2017-10-20 Envelope informatiques Supporting Project Management CM-UGP-PFS-16931-GO-RFQ / Laying the Foundations of a fourniture des pièces de Request for Single Stage - One IDA / 52240 Safety Net System and Post Open - National 37,500.00 32,502.70 Completed 2017-06-19 2017-08-14 2017-07-17 2017-08-28 2017-08-17 rechange pour véhicules et Quotations Envelope Supporting Project Management motos du Projet Filets Sociaux CM-UGP-PFS-23000-GO-RFQ / fourniture des boites à pharmacie pour la phase 4 des THIMO dans Request for Single Stage - One IDA / 52240 Public Works Program Pilot Post Limited 25,100.00 21,014.35 Signed 2017-08-15 2017-09-04 2017-10-13 2017-10-16 2018-04-11 2 communes de la région de Quotations Envelope l'Adamaoua et 1 commune de la région du Nord CM-UGP-PFS-25708-GO-RFQ / Laying the Foundations of a Request for Single Stage - One Pending Fourniture du mobilier de bureau IDA / 52240 Safety Net System and Post Limited 8,300.00 0.00 2017-11-09 2017-12-12 2018-01-02 Quotations Envelope Implementation de l'antenne du Nord-Ouest Supporting Project Management CM-UGP-PFS-25990-GO-RFQ / Fourniture des boites à pharmacie de la phase 5 des Request for Single Stage - One IDA / 52240 Public Works Program Pilot Post Limited 25,100.00 20,966.02 Signed 2017-10-12 2018-03-01 2017-11-10 2018-04-03 2017-12-01 THIMO pour 2 communes de la Quotations Envelope région de l'Est et 2 communes de la région du Nord ouest CM-UGP-PFS-26037-GO-RFQ / Laying the Foundations of a Fourniture des autocollants pour Request for Single Stage - One Pending IDA / 52240 Safety Net System and Post Limited 2,000.00 0.00 2017-09-27 2017-10-16 2017-10-30 voitures et motos au Projet Filets Quotations Envelope Implementation Supporting Project Management Sociaux CM-UGP-PFS-23003-GO-RFQ / Fourniture du matériel et des matériaux de travail pour la Request for Single Stage - One IDA / 52240 Public Works Program Pilot Post Limited 100,000.00 90,128.08 Signed 2017-09-11 2017-09-04 2017-10-03 2017-10-16 2017-10-24 phase 4 des THIMO dans 2 Quotations Envelope communes de la région de l'Adamaoua CM-UGP-PFS-25561-GO-RFB / Laying the Foundations of a Fourniture du matériel roulant Single Stage - One IDA / 52240 Safety Net System and Post Request for Bids Open - National 162,000.00 143,614.65 Signed 2017-09-01 2017-04-28 2017-09-01 2017-09-01 2017-06-29 2017-09-01 2017-07-07 2017-09-08 2017-08-31 2017-10-08 autos et motos au projet Filets Envelope Supporting Project Management Sociaux en deux lots distincts CM-UGP-PFS-25477-GO-RFQ / Cash Transfer Program with Request for Single Stage - One Under Fourniture des seaux au Projet IDA / 52240 Accompanying Measures to Post Limited 38,000.00 0.00 2017-10-09 2017-11-10 2017-11-06 2017-11-27 Quotations Envelope Implementation Filets Sociaux Boost Household Productivity CM-UGP-PFS-25475-GO-RFQ / Fourniture du matériel et des matériaux de travail pour la Request for Single Stage - One Under IDA / 52240 Public Works Program Pilot Post Limited 61,000.00 0.00 2017-09-02 2017-09-04 2017-09-24 2017-10-15 phase 4 des THIMO dans la Quotations Envelope Implementation région du nord , commune de Touboro Page 1 CM-UGP-PFS-47595-GO-RFQ / Fourniture du matériel de la phase 6 des THIMO du Projet Request for Single Stage - One Pending IDA / 52240 Public Works Program Pilot Post Limited 80,275.00 0.00 2018-06-18 2018-07-30 2018-08-29 Filets Sociaux dans les Quotations Envelope Implementation communes de Dembo et Bashéo, région du Nord CM-UGP-PFS-47597-GO-RFQ / Fourniture des boîtes à Request for Single Stage - One Pending IDA / 52240 Public Works Program Pilot Post Limited 4,360.00 0.00 2018-06-11 2018-07-23 2018-08-06 pharmacie de la phase 6 des Quotations Envelope Implementation THIMO du Projet Filets Sociaux CM-UGP-PFS-47606-GO-RFB / Fourniture et paramétrage d'un progiciel de gestion intégré pour Cash Transfer Program with Single Stage - One Pending la planification, la IDA / 52240 Accompanying Measures to Post Request for Bids Open - National 167,500.00 0.00 2018-06-21 2018-06-26 2018-07-27 2018-08-17 2018-09-14 2019-03-13 Envelope Implementation programmation, la budgétisation, Boost Household Productivity é aluation et la production le suivi v des rapports et indicateurs CM-UGP-PFS-47608-GO-RFQ / Cash Transfer Program with Fourniture des logiciels Request for Single Stage - One Pending IDA / 52240 Accompanying Measures to Post Limited 48,400.00 0.00 2018-03-27 2018-05-08 2018-05-29 informatiques au projet Filets Quotations Envelope Implementation Boost Household Productivity Sociaux CM-UGP-PFS-16933-GO-RFQ / Fourniture des seaux, Tee shirt, Cash Transfer Program with Request for Single Stage - One casquettes autocollants pour IDA / 52240 Accompanying Measures to Post Open - National 193,700.00 0.00 Canceled 2017-06-20 2017-08-15 2017-09-14 Quotations Envelope véhicules estampillés Projet Boost Household Productivity Filets Sociaux CM-UGP-PFS-25989-GO-RFQ / Fourniture du matériel et des matériaux de travail pour la Request for Single Stage - One IDA / 52240 Public Works Program Pilot Post Limited 80,275.00 72,952.92 Signed 2018-04-06 2018-03-01 2018-05-05 2018-04-03 2018-06-04 phase 5 des THIMO dans 2 Quotations Envelope communes de la région du Nord ouest (Oku et Ako) CM-UGP-PFS-25987-GO-RFQ / Fourniture du matériel et des matériaux de travail pour la Request for Single Stage - One IDA / 52240 Public Works Program Pilot Post Limited 80,275.00 65,815.47 Signed 2018-04-06 2018-03-01 2018-05-05 2018-04-03 2018-06-04 phase 5 des THIMO dans 2 Quotations Envelope communes de la région de l'EST (Bétaré OYA et Batouri) CM-UGP-PFS-25491-GO-RFQ / Laying the Foundations of a Request for Single Stage - One Pending Fourniture du matériel de pause IDA / 52240 Safety Net System and Post Limited 30,000.00 0.00 2018-04-19 2018-05-24 2019-05-24 Quotations Envelope Implementation café au Projet Filets Sociaux Supporting Project Management CM-UGP-PFS-47578-GO-RFQ / Cash Transfer Program with Fourniture des pneus de Request for Single Stage - One Pending IDA / 52240 Accompanying Measures to Post Limited 28,400.00 0.00 2018-06-04 2018-07-16 2018-08-06 recharge pour des autos et Quotations Envelope Implementation Boost Household Productivity motos du Projet CM-UGP-PFS-25476-GO-RFQ / Cash Transfer Program with Fourniture des tee-shirts et Request for Single Stage - One IDA / 52240 Accompanying Measures to Post Limited 99,000.00 68,943.69 Signed 2017-12-02 2018-01-24 2017-12-26 2018-03-01 2018-01-16 casquettes estampillés au Projet Quotations Envelope Boost Household Productivity Filets Sociaux CM-UGP-PFS-25488-GO-RFQ / Laying the Foundations of a Request for Single Stage - One Pending fourniture des encres pour IDA / 52240 Safety Net System and Post Limited 100,000.00 0.00 2018-01-03 2018-02-10 2019-02-10 Quotations Envelope Implementation imprimantes et photocopieurs Supporting Project Management CM-UGP-PFS-25487-GO-RFQ / Laying the Foundations of a Request for Single Stage - One Pending Fourniture des fournitures de IDA / 52240 Safety Net System and Post Limited 60,000.00 0.00 2017-09-16 2017-10-11 2018-10-11 Quotations Envelope Implementation bureau au Projet Filets sociaux Supporting Project Management CM-UGP-PFS-67485-GO-RFQ / Fourniture du matériel Laying the Foundations of a Request for Single Stage - One Pending informatique et de bureautique de IDA / 52240 Safety Net System and Post Limited 8,250.00 0.00 2018-07-15 2018-08-19 2018-09-02 Quotations Envelope Implementation l'antenne régionale du projet du Supporting Project Management Nord Ouest CM-UGP-PFS-67490-GO-RFQ / Laying the Foundations of a Fourniture des polices Request for Single Stage - One Pending IDA / 52240 Safety Net System and Post Limited 8,250.00 0.00 2018-07-10 2018-08-14 2019-08-14 d'assurance aux 40 premières Quotations Envelope Implementation Supporting Project Management motos du projet NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6232-NC-RFQ / Recrutement des agences de Request for Single Stage - One IDA / 52240 Public Works Program Pilot Post Limited 60,000.00 61,263.97 Signed 2017-02-15 2017-02-10 2017-04-12 2017-04-24 2017-12-08 paiement pour les phases 3 et 4 Quotations Envelope des THIMO en lots CM-UGP-PFS-6233-NC-RFQ / Recrutement des agences de paiement pour le paiement de 19500 ménages bénf é iciaires du Cash Transfer Program with cycle 2 des transferts monétaires Request for Single Stage - One Pending IDA / 52240 Accompanying Measures to Prior Limited 351,000.00 0.00 2017-03-07 2017-05-05 2019-04-25 dont 7500 dans la région de Quotations Envelope Implementation Boost Household Productivity l'Extrême Nord, 5500 dans les régions du Nord et de l'Adamaoua, et 6500 dans les régions de l'Est, du Nord CM-UGP-PFS-6315-NC-RFQ / Cash Transfer Program with Request for Single Stage - One Impression des documents du IDA / 52240 Accompanying Measures to Post Limited 70,000.00 22,001.63 Completed 2017-02-25 2017-04-21 2017-04-22 2017-05-26 2017-05-06 2017-06-19 Quotations Envelope Projet Boost Household Productivity CM-UGP-PFS-6306-NC-RFQ / Laying the Foundations of a Request for Single Stage - One fourniture des polices IDA / 52240 Safety Net System and Post Limited 123,900.00 58,410.90 Signed 2017-03-03 2017-03-06 2017-04-28 2017-06-07 2018-04-23 Quotations Envelope d'assurance maladie Supporting Project Management Page 2 CM-UGP-PFS-7385-NC-RFQ / Laying the Foundations of a Request for Single Stage - One Fourniture des polices IDA / 52240 Safety Net System and Post Limited 31,100.00 18,329.45 Signed 2017-03-03 2017-03-06 2017-04-28 2017-06-15 2018-04-23 Quotations Envelope d'assurance automobile Supporting Project Management CM-UGP-PFS-14464-NC-RFQ / Laying the Foundations of a Renouvellement du contrat Request for Single Stage - One Pending IDA / 52240 Safety Net System and Post Limited 8,250.00 0.00 2017-06-13 2017-06-19 2018-06-14 d'assurance des 40 motos en Quotations Envelope Implementation Supporting Project Management circulation CM-UGP-PFS-25608-NC-RFQ / Laying the Foundations of a Request for Single Stage - One Maintenance Autos UGP pour 1 IDA / 52240 Safety Net System and Post Limited 8,300.00 0.00 Canceled 2017-10-04 2017-10-31 2018-10-31 Quotations Envelope an Supporting Project Management CM-UGP-PFS-25616-NC-RFQ / Laying the Foundations of a Maintenance matériel Request for Single Stage - One IDA / 52240 Safety Net System and Post Limited 8,300.00 0.00 Canceled 2017-10-07 2017-11-07 2018-11-07 bureautique et informatique UGP Quotations Envelope Supporting Project Management pour 1 an CM-UGP-PFS-25623-NC-RFQ / Laying the Foundations of a Request for Single Stage - One Maintenance froid et IDA / 52240 Safety Net System and Post Limited 8,300.00 0.00 Canceled 2017-10-11 2017-11-09 2018-11-09 Quotations Envelope climatisation UGP pour 1 an Supporting Project Management CM-UGP-PFS-25711-NC-RFQ / Laying the Foundations of a Fourniture du service de Request for Single Stage - One Pending IDA / 52240 Safety Net System and Post Limited 6,000.00 0.00 2017-12-09 2018-01-09 2019-01-09 gardiennage pour l'antenne Quotations Envelope Implementation Supporting Project Management régionale du Nord Ouest CM-UGP-PFS-25729-NC-RFQ / Laying the Foundations of a Fourniture des systèmes de Request for Single Stage - One IDA / 52240 Safety Net System and Post Limited 4,000.00 1,315.18 Signed 2017-10-15 2018-02-20 2017-11-15 2018-03-12 2017-12-15 sécurité et de GPS et du service Quotations Envelope Supporting Project Management de tracking pour les autos CM-UGP-PFS-25892-NC-RFQ / Laying the Foundations of a Confection et la pose des Request for Single Stage - One IDA / 52240 Safety Net System and Post Open - National 4,000.00 7,636.09 Signed 2017-09-30 2017-11-10 2018-02-08 2017-12-01 plaques signalétiques (7 plaques Quotations Envelope Supporting Project Management directionnelles + 3 panneaux) CM-UGP-PFS-25980-NC-RFQ / Laying the Foundations of a Avenant au contrat de l'agence Request for Single Stage - One Pending IDA / 52240 Safety Net System and Post Limited 6,000.00 0.00 2017-09-11 2017-09-23 2018-09-23 de gardiennage de l'antenne Quotations Envelope Implementation Supporting Project Management régionale du Nord CM-UGP-PFS-25981-NC-RFQ / Laying the Foundations of a Avenant au contrat de l'agence Request for Single Stage - One Pending IDA / 52240 Safety Net System and Post Limited 5,000.00 0.00 2017-09-11 2017-09-23 2018-09-23 de gardiennage de l'antenne Quotations Envelope Implementation Supporting Project Management régionale de l'Extrême Nord CM-UGP-PFS-25983-NC-RFQ / Avenant au contrat d'assurance Laying the Foundations of a Request for Single Stage - One Pending du personnel en vu de la prise en IDA / 52240 Safety Net System and Post Limited 39,000.00 0.00 2017-09-15 2017-10-16 2018-08-12 Quotations Envelope Implementation compte du personnel Supporting Project Management nouvellement recruté CM-UGP-PFS-30748-NC-DIR / recrutement d'une agence de paiement chargée d'assurer les Cash Transfer Program with transferts monétaires des IDA / 52240 Accompanying Measures to Post Direct Selection Direct 36,000.00 30,643.76 Signed 2017-10-04 2018-01-04 2017-10-09 2017-11-27 2017-11-16 2018-02-13 2018-11-16 é iciaires de la phase 2 des bénf Boost Household Productivity transferts monétaires d'urgence du Projet Filets Sociaux CM-UGP-PFS-37510-NC-RFQ / avenant Lettre de Marché N°009/LM/MINEPAT/CTS/PFS/U GP/CAPM/2017 du 26 mai 2017 de l'agence de paiement pour la IDA / 52240 Public Works Program Pilot Post Direct Selection Direct 6,000.00 22,354.79 Signed 2017-12-18 2018-01-04 2017-12-25 2018-01-08 2018-01-15 2018-02-13 2018-05-15 réalisation des paiements des 6000 bénf é iciaires des THIMO 5 dont 3000 dans le Nord-Ouest et 3000 dans l'Est CM-UGP-PFS-37511-NC-RFQ / Avenant au contrat d'assurance Laying the Foundations of a véhicule LETTRE DE MARCHE IDA / 52240 Safety Net System and Post Direct Selection Direct 4,000.00 1,207.48 Signed 2017-12-18 2017-12-22 2017-12-23 2017-12-22 2018-01-09 2018-02-13 2018-07-08 N°011/LM/MINEPAT/CTS/PFS/U Supporting Project Management GP/CAPM/2017 DU 08 JUIN 2017 CM-UGP-PFS-25853-NC-DIR / Avenant au contrat de l'agence de paiement chargée des transferts monetaires du cycle 2 Request for Single Stage - One à l'Est, le Nord ouest, Douala et IDA / 52240 Public Works Program Pilot Post Limited 23,400.00 22,232.85 Signed 2017-09-25 2018-01-08 2017-11-20 2018-02-13 2018-05-19 Quotations Envelope Yaoundé pour la phase 5 des THIMO dont 3000 dans la région de l'Est et 3000 dans la région du Nord Ouest CM-UGP-PFS-47580-NC-RFQ / Cash Transfer Program with Fourniture de polices Request for Single Stage - One Pending IDA / 52240 Accompanying Measures to Post Limited 28,000.00 0.00 2018-03-31 2018-05-26 2019-05-26 d'assurance autos au projet Quotations Envelope Implementation Boost Household Productivity Filets Sociaux CM-UGP-PFS-47582-NC-RFQ / Confection et pause des plaques Cash Transfer Program with Request for Single Stage - One Under signalétiques des réalisations du IDA / 52240 Accompanying Measures to Post Limited 8,250.00 0.00 2018-04-30 2018-01-02 2018-06-11 2018-07-11 Quotations Envelope Implementation Projet Filets Sociaux dans les Boost Household Productivity communes CM-UGP-PFS-47593-NC-RFQ / Agence de paiement chargée d'assurer le paiement des 3000 Cash Transfer Program with Request for Single Stage - One Pending é iciaires de la phase 3 des IDA / 52240 bénf Accompanying Measures to Post Limited 19,170.00 0.00 2018-05-23 2018-07-18 2019-07-18 Quotations Envelope Implementation transferts monétaires d'urgence Boost Household Productivity du du Projet Filets Sociaux dans le Nord Ouest Page 3 CM-UGP-PFS-47602-NC-DIR / Avenant au contrat de l'agence de paiement chargée d'assurer les paiement des transfert monétaires du cycle 2 dans le Pending IDA / 52240 Public Works Program Pilot Post Direct Selection Direct 11,700.00 0.00 2018-06-21 2018-06-26 2018-07-31 2019-01-27 Nord et l'Adamaoua pour les Implementation é iciaire paiements de 3000 bénf de la phase 6 des THIMO dans la région du Nord, communes de Dembo et Bashéo CM-UGP-PFS-25707-NC-RFQ / Laying the Foundations of a Maintenance froid et Request for Single Stage - One IDA / 52240 Safety Net System and Post Limited 5,000.00 0.00 Canceled 2017-10-09 2017-11-07 2018-11-07 climatisation EN et NO pour 1 Quotations Envelope Supporting Project Management an CM-UGP-PFS-25610-NC-RFQ / Laying the Foundations of a Request for Single Stage - One Maintenance des Autos et Motos IDA / 52240 Safety Net System and Post Limited 5,000.00 0.00 Canceled 2017-10-04 2017-10-31 2018-10-31 Quotations Envelope de l'Extrême-Nord Supporting Project Management CM-UGP-PFS-25612-NC-RFQ / Laying the Foundations of a Request for Single Stage - One Maintenance des Autos et Motos IDA / 52240 Safety Net System and Post Limited 5,000.00 0.00 Canceled 2017-09-03 2017-09-30 2018-09-30 Quotations Envelope du Projet du Nord Supporting Project Management CM-UGP-PFS-25618-NC-RFQ / Laying the Foundations of a Maintenance matériel Request for Single Stage - One IDA / 52240 Safety Net System and Post Limited 5,000.00 0.00 Canceled 2017-10-07 2017-11-03 2018-11-03 bureautique et informatique EN et Quotations Envelope Supporting Project Management NO pour 1 an CM-UGP-PFS-47255-NC-RFQ / Cash Transfer Program with Production et multiplication des Request for Single Stage - One IDA / 52240 Accompanying Measures to Post Limited 7,567.00 7,132.71 Signed 2018-03-16 2018-02-23 2018-04-10 2018-03-08 2018-04-24 documents des Pratiques Quotations Envelope Boost Household Productivity familiales essentielles CM-UGP-PFS-26101-NC-RFQ / Laying the Foundations of a Request for Single Stage - One Maintenance des Autos et Motos IDA / 52240 Safety Net System and Post Limited 5,000.00 0.00 Canceled 2017-10-11 2017-11-13 2018-11-13 Quotations Envelope du Nord-Ouest Supporting Project Management CM-UGP-PFS-6311-NC-RFQ / Laying the Foundations of a Request for Single Stage - One Fourniture de police d'assurance IDA / 52240 Safety Net System and Post Limited 8,250.00 3,228.19 Signed 2018-04-06 2018-03-02 2018-05-11 2018-03-26 2019-05-06 Quotations Envelope pour 20 motos Supporting Project Management CM-UGP-PFS-26060-NC-RFQ / Laying the Foundations of a Fourniture des Systèmes de Request for Single Stage - One IDA / 52240 Safety Net System and Post Limited 8,500.00 1,867.92 Signed 2018-05-01 2018-03-05 2018-06-01 2018-03-26 2018-06-22 sécurité pour les motos du projet Quotations Envelope Supporting Project Management (20) CM-UGP-PFS-37512-NC-RFQ / Avenant N°2 au contrat d'assurance du personnel pour la Cash Transfer Program with prise en compte des relais Under IDA / 52240 Accompanying Measures to Post Direct Selection Direct 30,000.00 0.00 2018-03-30 2018-03-19 2018-04-06 2018-05-04 2018-10-31 communautaires recrutés dans le Implementation Boost Household Productivity cadre de la sensibilisation sur les pratiques familiales essentielles CM-UGP-PFS-47572-NC-RFB / Cash Transfer Program with Fourniture des polices Request for Single Stage - One Pending IDA / 52240 Accompanying Measures to Post Limited 130,000.00 0.00 2018-05-07 2018-07-02 2019-07-02 d'assurance au personnel du Quotations Envelope Implementation Boost Household Productivity Projet Filets Sociaux CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6358-CS-CQS / ONG pour THIMO: 7000 é iciaires dans 2 communes bénf de l'Extrême Nord, 2 communes Consultant Under de l'Est pour la phase 3 et 6000 IDA / 52240 Public Works Program Pilot Post Qualification Open - National 429,190.00 0.00 2017-02-07 2016-10-07 2017-02-28 2017-04-13 2017-02-22 2017-05-13 2017-03-17 2017-06-17 2017-12-14 Implementation bénfé iciaires: 2 communes Selection Adamaoua, 1 commune Nord pour la phase 4 en 2017 (1 ONG par région) CM-UGP-PFS-54735-CS-CQS / Consultant pour le Cash Transfer Program with Consultant développement d'un progiciel de Under IDA / 52240 Accompanying Measures to Post Qualification Open - National 167,500.00 0.00 2018-05-30 2018-05-11 2018-06-20 2018-08-03 2018-09-02 2018-10-07 2019-04-05 gestion intégré pour le système Implementation Boost Household Productivity Selection d'information du Projet Filets Sociaux INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CM-UGP-PFS-6328-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,950.00 10,372.40 Signed 2017-02-06 2016-12-20 2017-03-27 2017-04-17 2017-05-19 2017-05-22 2017-01-19 2017-06-16 l'enregistrement à Blangoua du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6334-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,950.00 10,368.36 Signed 2017-02-06 2017-05-15 2017-03-27 2017-04-17 2017-01-13 2017-05-22 2017-01-19 2017-06-16 l'enregistrement à Goulfey du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6337-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 15,500.00 12,422.62 Signed 2017-02-06 2017-05-15 2017-03-27 2017-04-17 2017-06-13 2017-05-22 2017-01-19 2017-06-21 l'enregistrement à Makari du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6339-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 10,372.40 Signed 2017-02-06 2017-05-17 2017-03-27 2017-04-17 2017-05-19 2017-05-22 2017-01-19 2017-06-16 l'enregistrement à GOBO du Selection Boost Household Productivity cycle 2 des transferts monetaires Page 4 CM-UGP-PFS-6340-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 10,379.07 Signed 2017-02-06 2017-05-15 2017-03-27 2017-04-17 2017-05-16 2017-05-22 2017-01-19 2017-06-16 l'enregistrement à BOURRHA du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6341-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 10,379.07 Signed 2017-02-06 2017-05-15 2017-03-27 2017-04-17 2017-05-16 2017-05-22 2017-01-19 2017-06-16 l'enregistrement à Koza du cycle Selection Boost Household Productivity 2 des transferts monetaires CM-UGP-PFS-6342-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 10,372.40 Signed 2017-02-06 2017-05-16 2017-02-13 2017-02-14 2017-05-18 2017-02-24 2017-01-19 2017-03-21 l'enregistrement à Mogodé du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6344-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 15,500.00 11,613.54 Signed 2017-02-06 2017-05-15 2017-02-13 2017-02-14 2017-05-17 2017-02-24 2017-01-26 2017-03-26 l'enregistrement à Banyo du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6346-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 10,381.76 Signed 2017-02-06 2017-05-29 2017-02-13 2017-02-14 2017-06-28 2017-02-24 2017-01-19 2017-03-21 l'enregistrement à Tcheboa du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6347-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 9,829.76 Signed 2017-02-06 2017-05-15 2017-02-13 2017-02-14 2017-02-24 2017-01-26 2017-03-21 l'enregistrement à Mayo Oulo du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6348-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 9,707.50 Signed 2017-02-06 2017-05-16 2017-02-24 2017-02-26 2017-05-24 2017-02-28 2017-01-26 2017-03-25 l'enregistrement à Rey Bouba du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6349-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 9,716.26 Signed 2017-02-06 2017-05-22 2017-02-09 2017-02-10 2017-05-26 2017-02-12 2017-01-26 2017-03-09 l'enregistrement à Touboro du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6350-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 11,772.77 Signed 2017-02-06 2016-12-20 2017-02-18 2017-02-28 2017-03-04 2017-03-14 2017-03-29 l'enregistrement à Kette du cycle Selection Boost Household Productivity 2 des transferts monetaires CM-UGP-PFS-6351-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 12,500.00 9,713.75 Signed 2017-02-06 2017-05-15 2017-02-18 2017-02-28 2017-05-17 2017-03-04 2017-03-14 2017-03-29 l'enregistrement à Belo du cycle Selection Boost Household Productivity 2 des transferts monetaires CM-UGP-PFS-6352-CS-INDV / Consultant pour le ciblage et Cash Transfer Program with Individual Consultant l'enregistrement à Menchum IDA / 52240 Accompanying Measures to Post Open 12,500.00 9,703.73 Signed 2017-02-06 2017-05-15 2017-02-18 2017-02-28 2017-05-16 2017-03-04 2017-03-14 2017-03-29 Selection Valley du cycle 2 des transferts Boost Household Productivity monetaires CM-UGP-PFS-6353-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant Under IDA / 52240 Accompanying Measures to Post Open 15,500.00 0.00 2017-02-06 2017-02-18 2017-02-28 2017-03-04 2017-03-29 l'enregistrement à Douala 3 du Selection Implementation Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6354-CS-INDV / Cash Transfer Program with Consultant pour le ciblage et Individual Consultant IDA / 52240 Accompanying Measures to Post Open 15,500.00 9,264.24 Signed 2017-02-06 2017-05-17 2017-02-18 2017-02-28 2017-05-24 2017-03-04 2017-03-14 2017-03-29 l'enregistrement à Yaoundé du Selection Boost Household Productivity cycle 2 des transferts monetaires CM-UGP-PFS-6355-CS-INDV / Consultant chargé d'améliorer les modules du volet c é onomique notamment formation en AGR ( Cash Transfer Program with Individual Consultant Pending agriculture, petit commerce, IDA / 52240 Accompanying Measures to Post Open 26,260.00 0.00 2017-02-10 2017-02-25 2017-03-02 2017-03-12 2017-04-17 Selection Implementation gestion de l'argent, l é evage) et Boost Household Productivity é iciaires dans ces former les bénf modules à l'Extrême Nord dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6356-CS-INDV / Consultant chargé d'améliorer les modules du volet c é onomique : formation en AGR ( Cash Transfer Program with agriculture,petit commerce, Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 28,460.00 0.00 2017-02-10 2017-02-25 2017-03-02 2017-03-12 2017-04-17 gestion de l'argent, l é evage) et Selection Implementation Boost Household Productivity é iciaires dans ces former les bénf modules dans le Nord et l'Adamaoua dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6357-CS-INDV / Consultant chargé d'améliorer les modules du volet c é onomique : formation en AGR ( Cash Transfer Program with agriculture,petit commerce, Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 31,400.00 0.00 2017-02-10 2017-02-25 2017-03-02 2017-03-12 2017-04-17 gestion de l'argent, l é evage) et Selection Implementation Boost Household Productivity é iciaires dans ces former les bénf modules dans le Nord O, Est, Dla, Ydé dans le cadre de la phase 2 du cycle 1 CM-UGP-PFS-6421-CS-INDV / Individual Consultant Under Expert environnemental et social IDA / 52240 Public Works Program Pilot Prior Open 63,840.00 0.00 2017-02-17 2017-07-13 2017-04-07 2017-03-29 2017-04-28 2017-06-02 2017-11-29 Selection Implementation du PFS Laying the Foundations of a CM-UGP-PFS-6423-CS-INDV / Individual Consultant Under IDA / 52240 Safety Net System and Prior Open 1,920.00 0.00 2017-02-07 2017-07-13 2017-03-28 2017-04-18 2017-05-23 2017-06-28 Assistant Comptable Selection Implementation Supporting Project Management Laying the Foundations of a CM-UGP-PFS-6424-CS-INDV / Individual Consultant Under IDA / 52240 Safety Net System and Prior Open 1,920.00 0.00 2017-02-07 2017-07-13 2017-03-28 2017-05-04 2017-04-18 2017-05-23 2017-06-28 Assistant SPM Selection Implementation Supporting Project Management Page 5 CM-UGP-PFS-6327-CS-CDS / Cash Transfer Program with protocole d'accord avec l'INS Pending IDA / 52240 Accompanying Measures to Prior Direct Selection Direct 900,000.00 0.00 2017-02-06 2017-02-16 2017-03-03 2017-09-29 pour le dénombrement et Implementation Boost Household Productivity l'enquête PMT du cycle 2 CM-UGP-PFS-14406-CS-INDV / Opérateur Terrain commune Cash Transfer Program with Individual Consultant Under Mayo Moskota (Extrême Nord) IDA / 52240 Accompanying Measures to Post Open 12,960.00 0.00 2017-05-19 2017-06-26 2017-06-04 2017-10-23 2017-06-11 2017-06-21 2019-06-21 Selection Implementation pour les transferts monetaires Boost Household Productivity d'urgence CM-UGP-PFS-14407-CS-INDV / Laying the Foundations of a Renouvellement du contrat de Individual Consultant IDA / 52240 Safety Net System and Post Open 24,000.00 22,835.28 Signed 2017-05-08 2015-01-09 2017-05-09 2017-05-05 2017-05-10 2017-06-13 2017-05-10 2017-06-09 2019-05-10 l'Assistante du Coordonnateur du Selection Supporting Project Management Projet CM-UGP-PFS-14409-CS-INDV / Laying the Foundations of a Renouvellement du contrat de la Individual Consultant IDA / 52240 Safety Net System and Post Open 19,200.00 18,268.22 Signed 2017-05-05 2015-01-09 2017-05-06 2017-05-05 2017-05-07 2017-06-14 2017-05-07 2017-06-09 2019-05-07 Secrétaire de l'Unité de Gestion Selection Supporting Project Management du Projet CM-UGP-PFS-14410-CS-INDV / Laying the Foundations of a Renouvellement contrat Individual Consultant IDA / 52240 Safety Net System and Post Open 16,800.00 15,984.70 Signed 2017-05-05 2015-01-09 2017-05-06 2017-05-05 2017-05-07 2017-06-09 2017-05-07 2017-06-09 2019-05-07 Chauffeur 1 de l'Unité de Gestion Selection Supporting Project Management du Projet CM-UGP-PFS-14411-CS-INDV / Laying the Foundations of a Renouvellement contrat Individual Consultant IDA / 52240 Safety Net System and Post Open 16,800.00 15,984.70 Signed 2017-05-05 2015-06-09 2017-05-06 2015-05-05 2017-05-07 2017-06-09 2017-05-07 2017-06-09 2019-05-07 Chauffeur 2 Unité de Gestion du Selection Supporting Project Management Projet CM-UGP-PFS-14412-CS-INDV / Laying the Foundations of a Renouvellement du contrat de Individual Consultant IDA / 52240 Safety Net System and Post Open 16,800.00 15,984.70 Signed 2017-05-05 2015-01-09 2017-05-06 2017-05-05 2017-05-07 2017-05-31 2017-05-07 2017-06-09 2019-05-07 l'Agent de liaison de l'Unité de Selection Supporting Project Management Gestion du Projet CM-UGP-PFS-14463-CS-INDV / Laying the Foundations of a Individual Consultant Pending Avenant au contrat de l'operateur IDA / 52240 Safety Net System and Post Open 12,960.00 0.00 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2019-06-15 Selection Implementation de terrain de Yaoundé 7 Supporting Project Management CM-UGP-PFS-14460-CS-INDV / Laying the Foundations of a Avenant au contrat de l'opératrice Individual Consultant Pending IDA / 52240 Safety Net System and Post Open 3,240.00 0.00 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2017-12-12 de terrain de la commune de Selection Implementation Supporting Project Management Douala 2 CM-UGP-PFS-14490-CS-INDV / Laying the Foundations of a Avenant au contrat de Individual Consultant Pending IDA / 52240 Safety Net System and Post Open 16,800.00 0.00 2017-06-15 2017-06-23 2017-06-25 2017-06-29 2019-06-29 Technicienne de surface de Selection Implementation Supporting Project Management l'UGP CM-UGP-PFS-14454-CS-INDV / Laying the Foundations of a Individual Consultant Avenant au contrat du point focal IDA / 52240 Safety Net System and Post Open 19,200.00 34,575.36 Terminated 2017-06-09 2017-10-27 2017-06-12 2017-06-13 2015-06-15 2017-06-15 2015-06-17 2019-06-15 Selection de la ville de Douala Supporting Project Management CM-UGP-PFS-16811-CS-INDV / Laying the Foundations of a renouvellement de contrat Individual Consultant Pending IDA / 52240 Safety Net System and Post Direct 12,960.00 0.00 2017-06-09 2017-06-11 2017-06-12 2017-06-13 2019-06-03 opérateur de terrain 1 commune Selection Implementation Supporting Project Management de MOKOLO CM-UGP-PFS-16814-CS-INDV / Laying the Foundations of a renouvellement contrat opérateur Individual Consultant Pending IDA / 52240 Safety Net System and Post Direct 12,960.00 0.00 2017-06-09 2017-06-12 2017-06-13 2017-06-14 2019-06-04 de terrain 2 commune de Selection Implementation Supporting Project Management MOKOLO CM-UGP-PFS-16821-CS-INDV / Laying the Foundations of a Renouvellement de contrat de Individual Consultant Pending IDA / 52240 Safety Net System and Post Direct 12,960.00 0.00 2017-06-09 2017-06-12 2017-06-13 2017-06-15 2019-06-05 l'opérateur de terrain de la Selection Implementation Supporting Project Management commune de MAGA CM-UGP-PFS-16823-CS-INDV / Laying the Foundations of a Renouvellement du contrat de Individual Consultant Pending IDA / 52240 Safety Net System and Post Direct 3,240.00 0.00 2017-06-09 2017-06-10 2017-06-11 2017-06-12 2017-12-09 l'opérateur de terrain de la Selection Implementation Supporting Project Management commune de Kar Hay CM-UGP-PFS-16925-CS-INDV / Laying the Foundations of a Individual Consultant Avenant au contrat du SPM du IDA / 52240 Safety Net System and Prior Open 63,840.00 0.00 Canceled 2017-06-12 2017-06-15 2017-06-19 2017-06-21 2019-06-11 Selection Projet Supporting Project Management CM-UGP-PFS-14451-CS-INDV / Laying the Foundations of a Individual Consultant Renouvellement du contrat IDA / 52240 Safety Net System and Prior Open 46,000.00 0.00 Canceled 2017-06-09 2017-07-19 2017-06-10 2017-06-14 2017-06-15 2019-06-15 Selection Comptable Supporting Project Management CM-UGP-PFS-14446-CS-INDV / Laying the Foundations of a Renouvellement du contrat de Individual Consultant IDA / 52240 Safety Net System and Prior Open 63,840.00 0.00 Canceled 2017-06-09 2017-07-19 2017-06-09 2017-06-10 2017-06-15 2019-06-15 l'Expert Informatique et Selection Supporting Project Management Responsable SIG du Projet CM-UGP-PFS-14452-CS-INDV / Laying the Foundations of a Renouvellement du contrat du Individual Consultant IDA / 52240 Safety Net System and Prior Direct 38,400.00 0.00 Canceled 2017-06-09 2017-06-12 2017-06-13 2017-06-13 2017-06-15 2019-06-15 Responsable Régional Extrême Selection Supporting Project Management Nord CM-UGP-PFS-25501-CS-INDV / Laying the Foundations of a Recrutement du responsable Individual Consultant Under IDA / 52240 Safety Net System and Post Open 19,200.00 0.00 2017-08-31 2017-08-28 2017-09-26 2017-10-25 2017-10-03 2017-11-06 2017-10-13 2018-10-13 régional du Nord ouest du projet Selection Implementation Supporting Project Management Filets Sociaux CM-UGP-PFS-25504-CS-INDV / Consultant chargé de la Laying the Foundations of a Individual Consultant Conception et l' appui à la mise IDA / 52240 Safety Net System and Post Open 21,500.00 14,972.00 Signed 2017-09-01 2017-09-06 2017-09-29 2017-10-02 2017-10-06 2017-11-03 2017-10-16 2017-11-03 2018-04-19 Selection en Suvre du plan de Supporting Project Management communication Page 6 CM-UGP-PFS-25520-CS-INDV / Recrutement de 4 consultants é iciaires pour le ciblage des bénf de la phase 2 des transferts monetaires d'urgence dans les Laying the Foundations of a Individual Consultant Under département du Logone et Chari IDA / 52240 Safety Net System and Post Open 36,400.00 0.00 2017-09-07 2017-10-09 2017-10-12 2017-10-19 2017-10-27 2017-11-16 Selection Implementation (Communes de Blangoua, Supporting Project Management Goulfey, Makari) et dans le département du Mayo Tsanaga(commune de Mayo Moskota CM-UGP-PFS-25782-CS-INDV / Laying the Foundations of a Avenant N°01 au contrat de Individual Consultant IDA / 52240 Safety Net System and Post Open 38,095.25 35,736.96 Signed 2017-09-06 2014-10-10 2017-09-09 2017-06-13 2017-09-10 2017-06-15 2017-09-11 2017-08-17 2018-09-11 l'Expert informatique et Selection Supporting Project Management responsable SIG UGP CM-UGP-PFS-25786-CS-INDV / Laying the Foundations of a Avenant N°02 au contrat du Individual Consultant IDA / 52240 Safety Net System and Post Open 38,095.25 71,473.92 Signed 2017-09-06 2013-05-29 2017-09-09 2017-06-19 2017-09-10 2017-06-22 2017-09-11 2017-08-17 2018-09-11 Spécialiste en passation des Selection Supporting Project Management Marchés de l'UGP CM-UGP-PFS-25787-CS-INDV / Laying the Foundations of a Individual Consultant Avenant N°1 au contrat du IDA / 52240 Safety Net System and Post Open 35,555.57 33,354.50 Signed 2017-09-06 2014-10-14 2017-09-09 2017-06-13 2017-09-10 2017-06-15 2017-09-11 2017-08-17 2018-09-11 Selection Comptable de l'UGP Supporting Project Management CM-UGP-PFS-25794-CS-INDV / Avenant N°1 au contrat du Laying the Foundations of a Individual Consultant Responsable régional du Projet IDA / 52240 Safety Net System and Post Open 19,200.00 18,099.26 Signed 2017-09-06 2015-04-14 2017-09-09 2017-06-13 2017-09-10 2017-06-16 2017-09-11 2017-08-17 2018-09-11 Selection Filets Sociaux dans l'Extrême Supporting Project Management Nord CM-UGP-PFS-25517-CS-INDV / Consultant chargé de la sensibilisation des bénfé iciaires Cash Transfer Program with Individual Consultant du Cycle 2 (i) à l'Extrême Nord, IDA / 52240 Accompanying Measures to Post Open 58,180.00 43,182.70 Signed 2017-09-07 2017-09-06 2017-10-12 2017-10-25 2017-10-19 2017-11-01 2017-10-27 2017-11-01 2018-02-24 Selection (ii) au Nord et à l'Adamaoua, (iii) Boost Household Productivity à l'Est, au Nord-ouest, à Douala et à Yaoundé CM-UGP-PFS-6326-CS-CDS / Cash Transfer Program with Protocole d'accord avec l'INS IDA / 52240 Accompanying Measures to Prior Direct Selection Direct 500,000.00 391,776.36 Signed 2017-08-31 2017-09-05 2017-08-31 2017-09-16 2017-09-28 2018-05-14 pour la réalisation de l'enquête de Boost Household Productivity base CM-UGP-PFS-25509-CS-INDV / Recrutement de 34 relais Cash Transfer Program with communautaires dans la Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 40,800.00 0.00 2017-11-30 2017-12-30 2018-01-06 2018-01-14 2019-01-14 commune de Koza, département Selection Implementation Boost Household Productivity du Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25508-CS-INDV / Recrutement de 34 relais Cash Transfer Program with communautaires dans la Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 40,800.00 0.00 2017-12-30 2018-01-29 2018-02-03 2018-02-11 2019-02-11 commune de Bourrha, Selection Implementation Boost Household Productivity département du Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25512-CS-INDV / Recrutement de 34 relais Cash Transfer Program with communautaires dans la Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 40,800.00 0.00 2017-11-30 2017-12-30 2018-01-06 2018-01-14 2019-01-14 commune de Mogode, Selection Implementation Boost Household Productivity département du Mayo Tsanaga, Région de l'Extrême Nord CM-UGP-PFS-25515-CS-INDV / Recrutement de 34 relais Cash Transfer Program with communautaires dans la Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 40,800.00 0.00 2017-11-30 2018-01-02 2018-01-09 2018-01-17 2019-01-17 commune de Mayo-Oulo, Selection Implementation Boost Household Productivity département du Mayo Louti, Région du Nord CM-UGP-PFS-25516-CS-INDV / Recrutement de 34 relais Cash Transfer Program with communautaires dans la Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 40,800.00 0.00 2017-11-30 2018-01-04 2018-01-11 2018-01-19 2019-01-19 commune de Tcheboa, Selection Implementation Boost Household Productivity département de la Bénoué, Région du Nord CM-UGP-PFS-37431-CS-INDV / Laying the Foundations of a Individual Consultant Pending Chauffeur de l'antenne régionale IDA / 52240 Safety Net System and Post Open 6,840.00 0.00 2017-12-27 2018-01-20 2018-01-22 2018-01-29 2019-01-29 Selection Implementation du Projet du Nord- Ouest Supporting Project Management CM-UGP-PFS-37432-CS-INDV / Laying the Foundations of a Individual Consultant Under Secrétaire de l'antenne régionale IDA / 52240 Safety Net System and Post Open 9,600.00 0.00 2017-12-28 2018-01-11 2018-01-23 2018-02-28 2018-01-28 2018-03-06 2018-02-04 2019-02-04 Selection Implementation du Projet du Nord Ouest Supporting Project Management CM-UGP-PFS-37434-CS-INDV / Laying the Foundations of a Individual Consultant Pending Point focal du Projet de la ville de IDA / 52240 Safety Net System and Post Open 9,600.00 0.00 2017-11-30 2017-12-22 2017-12-26 2017-12-28 2018-12-28 Selection Implementation Douala Supporting Project Management CM-UGP-PFS-25972-CS-CQS / Avenant au contrat N°001/MINEPAT/CTS/PFS/CAP M/2017 du 23 mars 2017 de l'ONG chargée de la mise en Suvre des THIMO 3 dans IDA / 52240 Public Works Program Pilot Post Direct Selection Direct 99,042.50 93,748.34 Signed 2017-12-18 2017-12-21 2017-12-25 2017-12-22 2018-01-18 2018-02-13 2018-07-17 l'Extrême Nord avec 4000 é iciaires pour la mise en bénf Suvre des THIMO 5 avec 3000 bénfé iciaires dans la région du Nord-ouest CM-UGP-PFS-25907-CS-CQS / Avenant au contrat N°002/MINEPAT/CTS/PFS/CAP M/2017 du 23 mars 2017 de l'ONG chargée de la mise en Suvre des THIMO 3 dans la IDA / 52240 Public Works Program Pilot Post Direct Selection Direct 99,042.50 92,937.44 Signed 2017-12-18 2017-12-21 2017-12-25 2017-12-22 2018-01-18 2018-02-13 2018-07-17 région de l'Est avec 3000 bénfé iciaires pour la mise en Suvre des THIMO 5 avec 3000 bénf é iciaires dans la région de l'Est Page 7 CM-UGP-PFS-47367-CS-INDV / Consultant individuel chargé Individual Consultant Pending IDA / 52240 Public Works Program Pilot Post Limited 8,250.00 0.00 2018-03-30 2018-04-04 2018-04-18 2018-04-28 2018-05-28 d'actualiser la carte des THIMO Selection Implementation du Projet Filets Sociaux CM-UGP-PFS-47368-CS-INDV / Consultants individuels (3) Cash Transfer Program with chargés du ciblage des Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 20,256.00 0.00 2018-04-06 2018-05-09 2018-05-23 2018-06-02 2018-07-17 é iciaires de la phase 3 des bénf Selection Implementation Boost Household Productivity transferts monétaires d'urgence dans la région du Nord Ouest CM-UGP-PFS-47363-CS-INDV / Consultants individuels (03) chargés de compléter et Cash Transfer Program with d'améliorer les manuels de Individual Consultant Under IDA / 52240 Accompanying Measures to Post Open 63,040.00 0.00 2018-03-09 2018-02-02 2018-04-14 2018-04-06 2018-04-28 2018-04-13 2018-05-12 2019-05-12 formation et de former les Selection Implementation Boost Household Productivity é iciaires sur les AGR pour le bénf cycle 2 des transferts monétaires du Projet Filets CM-UGP-PFS-47362-CS-INDV / Cash Transfer Program with Consultant individuel chargé de la Individual Consultant IDA / 52240 Accompanying Measures to Post Open 8,250.00 0.00 Under Review 2018-03-15 2018-03-29 2018-04-17 2018-04-24 2018-04-30 2019-04-30 traduction des documents du Selection Boost Household Productivity projet en anglais CM-UGP-PFS-25526-CS-INDV / Consultant chargé de Laying the Foundations of a l'accompagnement en Individual Consultant IDA / 52240 Safety Net System and Post Open 12,000.00 0.00 Canceled 2017-09-15 2017-10-11 2017-10-16 2017-10-24 2018-10-24 TOM2PRO, TOM2PAIE, Selection Supporting Project Management TOM2MONITORING et TOM2MARCHE CM-UGP-PFS-25881-CS-INDV / Laying the Foundations of a Individual Consultant Under Consultant chargé du IDA / 52240 Safety Net System and Post Open 8,250.00 0.00 2018-04-17 2018-04-26 2018-05-13 2018-05-20 2018-06-17 2018-12-14 Selection Implementation développement du site WEB Supporting Project Management CM-UGP-PFS-16899-CS-INDV / Laying the Foundations of a Individual Consultant Avenant au contrat de l'auditeur IDA / 52240 Safety Net System and Post Open 76,190.00 71.57 Signed 2017-10-02 2014-10-14 2017-10-13 2017-10-18 2017-09-08 2017-10-23 2017-11-01 2019-10-13 Selection interne Supporting Project Management Cash Transfer Program with CM-UGP-PFS-47928-CS-INDV / Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 12,000.00 0.00 2018-04-20 2018-05-30 2018-06-13 2018-07-04 2019-07-04 é aluation Assistant au suivi v Selection Implementation Boost Household Productivity CM-UGP-PFS-47923-CS-INDV / Cash Transfer Program with Individual Consultant Pending Recrutement d'un Spécialiste en IDA / 52240 Accompanying Measures to Post Open 12,000.00 0.00 2018-04-04 2018-05-07 2018-05-21 2018-06-18 2019-06-18 Selection Implementation Passation des Marché Assistant Boost Household Productivity CM-UGP-PFS-54610-CS-INDV / consultant individuel pour Cash Transfer Program with l'assistance à la migration Individual Consultant Under IDA / 52240 Accompanying Measures to Post Limited 8,250.00 0.00 2018-04-16 2018-03-26 2018-04-21 2018-05-12 2018-06-16 2018-12-13 comptable vers le nouveau Selection Implementation Boost Household Productivity é entiel comptable réfr SYSCOHADA révisé CM-UGP-PFS-54615-CS-INDV / consultant pour assister l'UGP à Cash Transfer Program with Individual Consultant Pending l'utilisation optimale des logiciels IDA / 52240 Accompanying Measures to Post Limited 8,250.00 0.00 2018-04-20 2018-04-25 2018-05-16 2018-06-20 2019-06-20 Selection Implementation TOM2PRO, TOM2PAIE et Boost Household Productivity TOM2MARCHE CM-UGP-PFS-54616-CS-INDV / Consultant pour la conception du Cash Transfer Program with masque de saisie, la supervision Individual Consultant Under IDA / 52240 Accompanying Measures to Post Limited 8,250.00 0.00 2018-04-25 2018-05-15 2018-04-30 2018-05-21 2018-06-25 2018-12-22 de la saisie et l'analyse des Selection Implementation Boost Household Productivity données de la première é aluation interne du Projet IDA v CM-UGP-PFS-47366-CS-INDV / Consultant individuel chargé Cash Transfer Program with Individual Consultant Pending d'actualiser la carte de pauvreté IDA / 52240 Accompanying Measures to Post Limited 8,250.00 0.00 2018-04-30 2018-05-05 2018-05-19 2018-05-29 2018-06-28 Selection Implementation pour les transferts monétaires du Boost Household Productivity Projet Filets Sociaux CM-UGP-PFS-47370-CS-INDV / Cash Transfer Program with Avenant au contrat du point focal IDA / 52240 Accompanying Measures to Post Direct Selection Direct 3,600.00 3,181.63 Signed 2018-04-20 2016-01-11 2018-04-27 2018-02-28 2018-05-03 2018-02-28 2018-10-30 du Projet dans le Département Boost Household Productivity du Mberé, région de l'Adamaoua CM-UGP-PFS-25974-CS-CQS / Contrat ONG pour la phase 6 des Pending é iciaires THIMO pour 3000 bénf IDA / 52240 Public Works Program Pilot Post Direct Selection Direct 99,042.50 0.00 2018-05-30 2018-06-09 2018-07-30 2019-01-26 Implementation dans 2 communes de la région du Nord CM-UGP-PFS-47376-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain de la commune de la IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,169.08 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 commune de la commune de kai Boost Household Productivity kai département du Mayo Danay, région de l'extrême Nord CM-UGP-PFS-47377-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain de la commune de IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 Méri, département du Diamaré, Boost Household Productivity région de l'Extrême Nord CM-UGP-PFS-47378-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain de la commune de IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 Ndoukoula, département du Boost Household Productivity Diamaré, région de l'Extrême Nord CM-UGP-PFS-47379-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain de la commune de IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,169.08 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 Guider, département du Mayo Boost Household Productivity Louti, région du Nord Page 8 CM-UGP-PFS-47430-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain de la commune de IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 Lagdo, département de la Boost Household Productivity Bénoué, région du Nord CM-UGP-PFS-47431-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain N° 1 de la commune IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 de Bibemi (ADAMOU Bienvenu), Boost Household Productivity département de la Bénoué, région du Nord CM-UGP-PFS-47432-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain N° 2 de la commune IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 de Bibemi (GOUDOUM GRANA Boost Household Productivity Dieunedort), département de la Bénoué, région du Nord CM-UGP-PFS-47433-CS-INDV / Avenant au contrat de l'opérateur de terrain de la commune de Kar Cash Transfer Program with Pending Hay pour la commune de Makary IDA / 52240 Accompanying Measures to Post Direct Selection Direct 8,100.00 0.00 2018-04-18 2018-04-22 2018-04-28 2019-04-28 Implementation dans le département du Logone Boost Household Productivity et Chari, région de l'Extrême Nord CM-UGP-PFS-47434-CS-INDV / Cash Transfer Program with Avenant au contrat de la IDA / 52240 Accompanying Measures to Post Direct Selection Direct 16,800.00 15,497.59 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2019-12-30 secrétaire de l'antenne régionale Boost Household Productivity de l'Extrême Nord CM-UGP-PFS-47435-CS-INDV / Cash Transfer Program with Individual Consultant Pending Avenant au contrat du chauffeur IDA / 52240 Accompanying Measures to Post Direct 11,340.00 0.00 2018-03-05 2018-03-12 2018-03-17 2018-03-25 2019-12-15 Selection Implementation de l'antenne régionale du Nord Boost Household Productivity CM-UGP-PFS-47369-CS-INDV / Cash Transfer Program with Avenant au contrat du point focal IDA / 52240 Accompanying Measures to Post Direct Selection Direct 3,600.00 3,188.07 Signed 2018-04-25 2016-01-11 2018-04-29 2018-02-28 2018-05-05 2018-02-28 2018-11-01 du département du Diamaré dans Boost Household Productivity la région de l'Extrême Nord CM-UGP-PFS-47371-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain N°1 de la commune de IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 DIR (HEBGASSO Jean Boost Household Productivity Baptiste) département du Mbér, é région de l'Adamaoua CM-UGP-PFS-47372-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain N° 2 de la Commune IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 de Dir (HOULAO Pierre) Boost Household Productivity département du Mbér, é région de l'Adamoua CM-UGP-PFS-47375-CS-INDV / Avenant au contrat de l'opérateur Cash Transfer Program with de terrain N°2 de la commune de IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2018-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 BOGO( Wanie Bernard) Boost Household Productivity département du Diamaré, région de l'Extrême Nord CM-UGP-PFS-47373-CS-INDV / Avenant au contrat de l'opératrice Cash Transfer Program with de terrain N°1 de la commune de IDA / 52240 Accompanying Measures to Post Direct Selection Direct 2,430.00 2,147.60 Signed 2018-04-24 2016-01-11 2018-04-28 2018-02-28 2018-05-04 2018-02-28 2018-10-31 BOGO, département du Diamaré, Boost Household Productivity région de l'Extrême Nord CM-UGP-PFS-59671-CS-CDS / Cash Transfer Program with Opérateur de terrain de la IDA / 52240 Accompanying Measures to Post Direct Selection Direct 3,240.00 2,391.05 Signed 2018-04-30 2016-01-11 2018-05-10 2018-05-30 2018-05-19 2018-05-31 2018-11-15 commune de Douala 4 Boost Household Productivity CM-UGP-PFS-59673-CS-INDV / Cash Transfer Program with Recrutement du Responsable Individual Consultant Pending IDA / 52240 Accompanying Measures to Post Open 19,200.00 0.00 2018-05-04 2018-06-06 2018-06-13 2018-06-22 2019-06-22 régional de l'antenne du Nord du Selection Implementation Boost Household Productivity Projet Filets Sociaux CM-UGP-PFS-59789-CS-CDS / Audit financier et comptable des comptes du Projet de Remise à niveau des Réseaux de Transport Cash Transfer Program with Under d'Electricité et Réforme du IDA / 52240 Accompanying Measures to Post Direct Selection Direct 54,000.00 0.00 2018-04-26 2018-04-20 2018-04-30 2018-03-23 2018-05-14 2020-05-13 Implementation Secteur (PRRTERS): exercices Boost Household Productivity 2017-2018 - 2019 et du Projet Filets Sociaux (PFS) : exercices 2017-2018 CM-UGP-PFS-67474-CS-CDS / Avenant au contrat de l'opérateur Laying the Foundations of a Pending de terrain de la commune de IDA / 52240 Safety Net System and Post Direct Selection Direct 3,240.00 0.00 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Implementation Yaoundé 1er NGO SICK Supporting Project Management ELEANOR RHOLY p é ouse KAM CM-UGP-PFS-67475-CS-CDS / Avenant au contrat de l'opérateur Laying the Foundations of a de terrain de la commune de Pending IDA / 52240 Safety Net System and Post Direct Selection Direct 3,240.00 0.00 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Funfong, département du Boyo Implementation Supporting Project Management région du Nord Ouest AGHA-AH EVARISTUS ALANJI CM-UGP-PFS-67477-CS-CDS / Avenant au contrat de l'opérateur de terrain de la commune de Laying the Foundations of a Pending Balikumbat département du Ngo IDA / 52240 Safety Net System and Post Direct Selection Direct 3,240.00 0.00 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Implementation Ketungja région du Nord Ouest Supporting Project Management TAJIPUKU ALPHONSE TAMIGHANG Page 9 CM-UGP-PFS-67478-CS-CDS / avenant au contrat de l'opérateur de terrain N1 de la commune de Laying the Foundations of a Pending Messamena département du IDA / 52240 Safety Net System and Post Direct Selection Direct 3,240.00 0.00 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Implementation Haut Nyong région de l'Est Supporting Project Management TSALA MVOGO BERNARD JEAN CM-UGP-PFS-67479-CS-CDS / Avenant au contrat du point focal Laying the Foundations of a Pending du département du Haut Nyong IDA / 52240 Safety Net System and Post Direct Selection Direct 4,800.00 0.00 2018-06-29 2018-07-03 2018-07-09 2019-01-05 Implementation région de l'Est MBILLA Pierre Supporting Project Management Valery CM-UGP-PFS-67481-CS-CDS / avenant au contrat de l'opérateur Laying the Foundations of a Pending de terrain N°2 de la commune de IDA / 52240 Safety Net System and Post Direct Selection Direct 2,160.00 0.00 2018-07-02 2018-07-06 2018-07-12 2018-11-09 Implementation Messamena ESSOMBA Supporting Project Management YANNICK ALBERT NGUEM CM-UGP-PFS-67482-CS-CDS / Avenant au contrat de l'opérateur Laying the Foundations of a de terrain N°2 de la commune de Pending IDA / 52240 Safety Net System and Post Direct Selection Direct 540.00 0.00 2018-06-29 2018-07-03 2018-07-08 2018-08-07 Lagdo, département de la Implementation Supporting Project Management Bénoué, région du Nord SIRINA ELVIS CM-UGP-PFS-67517-CS-INDV / Laying the Foundations of a Pending Responsable Administratif et IDA / 52240 Safety Net System and Post Direct Selection Direct 38,095,248.00 0.00 2018-06-29 2018-07-04 2018-07-11 2019-07-11 Implementation Financier du Projet Supporting Project Management Page 10