PHILIPPINE RURAL DEVELOPMENT PROJECT LN 8421-PH ORIGINAL LOAN Procurement Plan As of June 2018 I. General 1. Bank’s approval Date of the Procurement Plan : September 9, 2014 2. Date of General Procurement Notice : September 25, 2012 3. Period covered by this procurement plan : July 2018 – June 2019 II. Goods and Works and non-consulting services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Method Threshold Prior Review No. Procurement Method US$ Threshold US$ International Competitive Bidding 1. 3M and above All contracts (ICB) (Goods) National Competitive Bidding (NCB) 2. less than 3M 2M and above (Goods) packages 3. Shopping (Goods) less than 0.2M None 4. ICB (Works) packages 15M and above All contracts 5. NCB (Works) packages less than 15M 10M and above 6. Shopping (Works) less than 0.2M None Subject to justification in accordance with para. 3.7 of 5. Direct Contracting (Goods) 2M and above Procurement Guidelines at the Procurement Plan stage 6. Commercial Practice less than 0.1M None 7. Community Participation less than 0.05M None 2. Reference to Project Operational/Procurement Manual including Community Participation: Original version dated: May 2014 To be updated by : July 2018 (Revised Operations Manual submitted September 4, 2017) 3. Summary of the Procurement Packages (with international competition, direct contracting, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition, Direct Contracting requiring Bank’s prior review) 1 2 3 4 5 6 7 8 9 10 LN 8421 PH Procurement Plan Updated June 2018 Domest Estimated ic Expected Procurin Procurem Cost Funding Prefere Review Bid Ref. No. Description g ent Comments US$1= Source nce by Bank Opening Agency Method Php 50) (yes/no Date ) No subprojects for Bank’s prior review III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines on Selection and Employment of Consultants: Prior Review Threshold No. Selection Method Method Threshold US$ US$ 1. Competitive Methods 0.3M & above (may be used for also less 1m and above (QCBS, QBS, FBS) (Firms) than 0.3M) 2. Competitive Method CQS less than 0.3M None (Firms) 3. Individuals Competitive regardless of amount 0.3M and above 2. Single Source (Firms & on exceptional basis subject to justification Firms: 1M and above; Individuals) in accordance with paras. 3.9 and 5.4 Individuals 0.3M and respectively of Consultant Guidelines at above. the Procurement Plan stage 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Summary of the Consultancy Assignments/Packages (using international competition, single/sole source selection, requiring Bank’s prior review): PHILIPPINE RURAL DEVELOPMENT PROJECT Summary of the Procurement Packages (with International Competition) 1 2 3 4 5 6 7 8 Ref. Description of Estimated Cost (USD Funding Procuring Expected Bid Comme Selection Method No. Contract Package million) Source Agency Opening Date nts Various PRDP Technical Consultant and Staff (provided with No Objection December 22, 2017) US$1,042,75 Single Source NPCO ( Php53.178 million) LP/GoP Selection US$1,042,75 Single Source Luzon A ( Php59.152 million) LP/GoP Selection US$1,042,75 Single Source Luzon B ( Php48.614 million) LP/GoP Selection US$1,042,75 Single Source Visaya ( Php29.612 million) LP/GoP Selection US$1,042,75 Single Source Mindanao ( Php million) LP/GoP Selection Prepared by: Reviewed by: LN 8421 PH Procurement Plan Updated June 2018 ENGR. ROMEO L. MALONG ENGR. CHRISTOPHER V. MORALES Alternate Procurement Unit Head Procurement Unit Head LN 8421 PH Procurement Plan Updated June 2018 PROCUREMENT Philippines : Philippine Rural Development Project PLAN General Information Country: Philippines Bank’s Approval Date of the Original Procurement Plan: 2019-03-11 2019-09-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P132317 GPN Date: Project Name: Philippine Rural Development Project Loan / Credit No: IBRD / 84210, IBRD / 88160 Executing Agency(ies): PRDP PSO Visayas, Department of Agriculture WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IB-R006-NOC-008-000- Under 000-2015-AF / Rehabilitation Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 953,274.51 0.00 Implementati 2018-09-07 2018-09-12 2018-10-24 2018-11-23 2018-12-28 2019-06-26 of Brgy. 1-A to Brgy. Punta Development Envelope on Salong FMR PRDP-IB-R008-LEY-005- DAG-001-2014-AF / Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 524,156.86 515,997.76 Signed 2018-08-28 2018-09-02 2018-10-14 2018-11-13 2018-12-18 2019-06-16 Concreting of Brgy. Abaca - Development Envelope Pandan Farm-to-Market Road PRDP-IB-R008-NOS-007-ROS- 001-2015-AF / Concreting of Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 978,392.16 957,606.49 Signed 2018-08-20 2018-08-25 2018-10-06 2018-11-05 2018-12-10 2019-06-08 Salhag - Kailingan Farm-to- Development Envelope Market Road PRDP-IB-R006-ILO-006-000- 000-2015-AF / Component 2: Infrastructure Single Stage - One Rehabilitation/Concreting of IBRD / 88160 Post Request for Bids Open - National 3,632,179.92 3,755,092.75 Signed 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Development Envelope Bongol - Tambal - Quipot Farm to Market Road PRDP-IB-R006-AKL-003-000- Under 000-2015-AF / Rehabilitation Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 1,228,392.16 0.00 Implementati 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 and Improvement of Lalab - Development Envelope on Bay-ang - Magpag-ong Road PRDP-IB-R006-NOC-013-000- Pending 000-2018-AF / Construction Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 1,347,435.88 0.00 Implementati 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 of Ninety (90) L.M. Himoga- Development Envelope on an Bridge III PRDP-IB-R007-SIQ-002-000- Under 000-2017-AF / Construction Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 605,000.00 0.00 Implementati 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 of Siquijor Provincial AA Development Envelope on Abattoir PRDP-IB-R007-NOR-001-000- 000-2017-AF / Rehabilitation Under Component 2: Infrastructure Single Stage - One and Improvement of Hilaitan IBRD / 88160 Post Request for Bids Open - National 6,403,024.97 0.00 Implementati 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Development Envelope to Trinidad Farm to Market on Road PRDP-IB-R008-NOS-004-000- 000-2015-AF / Under Construction/Rehabilitation of Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 2,738,568.63 0.00 Implementati 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Camparanga - Manahaw - Development Envelope on San Ramon - Canjumadal Farm-to-Market Road Page 1 PRDP-IB-R008-NOS-005- BOB-001-2015-AF / Construction/Improvement of Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 678,796.34 743,676.13 Signed 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Brgy. Dancalan - Sitio Development Envelope Inamburacay Farm-to-Market Road PRDP-IB-R008-SAM-010-000- 000-2015-AF / Pending Component 2: Infrastructure Single Stage - One Improvement/Concreting of IBRD / 88160 Post Request for Bids Open - National 1,726,362.52 0.00 Implementati 2018-11-02 2018-11-07 2018-12-19 2019-01-18 2019-02-22 2019-08-21 Development Envelope Brgy. Cogon - Brgy. Villa on Aurora FMR PRDP-IB-R006-ILO-008-000- Pending 000-2018-AF / Construction Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 738,176.47 0.00 Implementati 2019-10-01 2019-10-06 2019-11-17 2019-12-17 2020-01-21 2020-07-19 of Sixty (60) L.M. PSCG Development Envelope on Cabacanan Bridge PRDP-IB-R007-BOH-005-000- Under 000-2014-AF / Rehabilitation Component 2: Infrastructure Single Stage - One IBRD / 88160 Post Request for Bids Open - National 1,432,607.84 0.00 Implementati 2019-10-01 2019-10-06 2019-11-17 2019-12-17 2020-01-21 2020-07-19 of Dagnawan to Dagohoy Development Envelope on Farm to Market Road PRDP-IB-R007-LEY-006-HIL- 001-2016-AF / Concreting of Pending Component 2: Infrastructure Single Stage - One Brgy. Concepcion - IBRD / 88160 Post Request for Bids Open - National 2,591,784.31 0.00 Implementati 2018-08-01 2018-08-06 2018-09-17 2018-10-17 2018-11-21 2019-05-20 Development Envelope Bagumbayan - Hampangan on Farm-to-Market Road GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRDP-IS-VIS-DPD-006-000- Individual Component 4: Project Pending 2018-AF / Project IBRD / 84210 Post Consultant Open 8,470.59 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-PRO-003-000- Individual Component 4: Project Pending 2018-AF / Procurement IBRD / 84210 Post Consultant Open 12,705.88 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 Implementation Support Implementation Officer Selection Page 2 PRDP-IS-VIS-PRO-004-000- Individual Component 4: Project Pending 2018-AF / Procurement IBRD / 84210 Post Consultant Open 12,705.88 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 Implementation Support Implementation Officer Selection PRDP-IS-VIS-SES-003-000- Individual Component 4: Project Pending 2018-AF / Project IBRD / 84210 Post Consultant Open 8,470.59 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 Implementation Support Implementation Development Associate Selection Individual PRDP-IS-VIS-BUD-001-000- Component 4: Project Pending IBRD / 84210 Post Consultant Open 14,117.65 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 2018-AF / Budget Specialist Implementation Support Implementation Selection PRDP-IS-VIS-ADM-003-000- Individual Component 4: Project Pending 2018-AF / Administrative IBRD / 84210 Post Consultant Open 9,882.35 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 Implementation Support Implementation Officer III Selection PRDP-IS-VIS-ADM-008-000- Individual Component 4: Project Pending 2018-AF / Administrative IBRD / 84210 Post Consultant Open 5,647.06 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 Implementation Support Implementation Staff Selection Individual PRDP-IS-VIS-ADM-009-000- Component 4: Project Pending IBRD / 84210 Post Consultant Open 5,647.06 0.00 2018-07-01 2018-08-19 2018-09-09 2018-10-14 2019-04-12 2018-AF / Cash Clerk Implementation Support Implementation Selection Individual PRDP-IS-VIS-R008-ECO-001- Component 4: Project Pending IBRD / 84210 Post Consultant Open 8,470.59 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 2018-AF / Economist Implementation Support Implementation Selection PRDP-IS-VIS-R008-ACC-001- Individual Component 4: Project Pending 2018-AF / Financial Analyst IBRD / 84210 Post Consultant Open 9,882.35 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Implementation Support Implementation I Selection PRDP-IS-VIS-R008-PRO-001- Individual Component 4: Project Pending 2018-AF / Procurement IBRD / 84210 Post Consultant Open 11,294.12 0.00 2018-01-01 2018-02-19 2018-03-12 2018-04-16 2018-10-13 Implementation Support Implementation Officer Selection PRDP-IS-VIS-PRO-001-000- Component 4: Project 2018-AF / Procurement Unit IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Head PRDP-IS-VIS-BUD-003-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-R006-GGU-002- Component 4: Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / GIS Data Officer Implementation Support PRDP-IS-VIS-GGU-002-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R006-IB-004- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-MAE-002-000- Component 4: Project 2018-AF / Monitorig & IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Evaluation Officer PRDP-IS-VIS-MAE-003-000- Component 4: Project 2018-AF / Monitorig & IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Evaluation Officer PRDP-IS-VIS-INF-001-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Writer / InfoAce Implementation Support Page 3 PRDP-IS-VIS-PRO-002-000- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-VIS-R006-FIN-002- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-R006-ADM-003- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Cash Clerk Implementation Support PRDP-IS-VIS-R008-SES-001- Component 4: Project 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Safeguard Officer PRDP-IS-VIS-R008-BUD-001- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-R008-ADM-003- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Cash Clerk Implementation Support PRDP-IS-VIS-ADM-005-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Staff PRDP-IS-VIS-R006-MAE-004- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R008-SES-002- Component 4: Project 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Safegusrd Officer PRDP-IS-VIS-R006-MAE-001- Component 4: Project 2018-AF / Monitoring and IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Evaluation Officer PRDP-IS-VIS-R006-FIN-004- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R008-GGU-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / GIS Data Officer Implementation Support PRDP-IS-VIS-R008-ADM-002- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Driver Implementation Support PRDP-IS-VIS-INF-002-000- Component 4: Project 2018-AF / Layout Artist / IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Videographer PRDP-IS-VIS-SES-001-000- Component 4: Project 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Safeguard Officer PRDP-IS-VIS-BUD-002-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-FIN-003-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support II PRDP-IS-VIS-R006-IB-008- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate Page 4 PRDP-IS-VIS-R006-PRO-001- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist PRDP-IS-VIS-R006-PRO-002- Component 4: Project 2018-AF / Procurement IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer PRDP-IS-VIS-R006-PRO-003- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R006-BUD-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Budget Specialist Implementation Support PRDP-IS-VIS-R008-000-003- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-DPD-004-000- Component 4: Project 2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Assistant PRDP-IS-VIS-GGU-001-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / GIS Data Officer Implementation Support PRDP-IS-VIS-R006-OPD-001- Component 4: Project 2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Assistant PRDP-IS-VIS-R006-BUD-002- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R006-FIN-001- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support II PRDP-IS-VIS-R006-ADM-004- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Driver Implementation Support PRDP-IS-VIS-R008-MAE-001- Component 4: Project 2018-AF / Monitoring and IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Evaluation Officer PRDP-IS-VIS-R006-IB-001- Component 4: Project 2018-AF / Alternate I-BUILD IBRD / 84210 Post Direct Selection Direct 16,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Component Head PRDP-IS-VIS-R006-SES-003- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R006-SES-001- Component 4: Project 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Safeguard Specialist PRDP-IS-VIS-R006-GGU-001- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R008-IB-005- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R008-ADM-001- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate Page 5 PRDP-IS-VIS-ECO-001-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 14,117.65 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Economist Implementation Support PRDP-IS-VIS-R008-000-002- Component 4: Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Planning Officer Implementation Support PRDP-IS-VIS-R006-MAE-002- Component 4: Project 2018-AF / Monitoring and IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Evaluation Specialist PRDP-IS-VIS-R006-ADM-005- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Driver Implementation Support PRDP-IS-VIS-ADM-014-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 4,235.29 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Utility Staff Implementation Support PRDP-IS-VIS-R006-MAE-003- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-ADM-013-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,082.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Messengerial Staff Implementation Support PRDP-IS-VIS-FIN-004-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-R008-000-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Planning Officer Implementation Support PRDP-IS-VIS-R006-SES-002- Component 4: Project 2018-AF / Social Safeguard IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Specialist PRDP-IS-VIS-R008-FIN-001- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-OPD-003-000- Component 4: Project 2018-AF / Executive IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Assistant PRDP-IS-VIS-R006-FIN-003- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-R008-PRO-002- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-R006-ADM-002- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 7,058.82 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer I PRDP-IS-VIS-IB-004-000- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-PRO-006-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-ACC-010-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate Page 6 PRDP-IS-VIS-SES-002-000- Component 4: Project 2018-AF / Environmental IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Safeguard Officer PRDP-IS-VIS-R008-IB-001- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-FIN-001-000- Component 4: Project 2018-AF / LGU Finance IBRD / 84210 Post Direct Selection Direct 16,941.18 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Supervisor PRDP-IS-VIS-R006-INF-001- Component 4: Project IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Web Administrator Implementation Support PRDP-IS-VIS-ADM-011-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Driver Implementation Support PRDP-IS-VIS-ADM-006-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Staff PRDP-IS-VIS-FIN-005-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-MAE-004-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-ADM-001-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Unit Head PRDP-IS-VIS-PRO-005-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-OPD-002-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 15,529.41 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Legal Officer Implementation Support PRDP-IS-VIS-ADM-004-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer I PRDP-IS-VIS-R006-IB-002- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-R008-IB-002- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-ADM-012-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Driver Implementation Support PRDP-IS-VIS-FIN-006-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support I PRDP-IS-VIS-R006-IB-007- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-DPD-001-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 14,117.65 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Compliance Officer Implementation Support Page 7 PRDP-IS-VIS-IB-002-000- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-IB-005-000- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-R008-IB-003- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-ADM-007-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Staff PRDP-IS-VIS-R006-IB-005- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-ADM-002-000- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 9,882.35 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer III PRDP-IS-VIS-MAE-001-000- Component 4: Project 2018-AF / Monitorig & IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Evaluation Unit Head PRDP-IS-VIS-R008-IB-004- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-R006-IB-006- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-ADM-010-000- Component 4: Project IBRD / 84210 Post Direct Selection Direct 5,647.06 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 2018-AF / Driver 1 Implementation Support PRDP-IS-VIS-R006-IB-003- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 11,294.12 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-FIN-002-000- Component 4: Project 2018-AF / Financial Analyst IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support II PRDP-IS-VIS-R006-ADM-001- Component 4: Project 2018-AF / Administrative IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Officer III PRDP-IS-VIS-DPD-005-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-IB-006-000- Component 4: Project 2018-AF / Project IBRD / 84210 Post Direct Selection Direct 8,470.59 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Development Associate PRDP-IS-VIS-IB-003-000- Component 4: Project 2018-AF / Rural IBRD / 84210 Post Direct Selection Direct 12,705.88 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Infrastructure Engineer PRDP-IS-VIS-IB-001-000- Component 4: Project 2018-AF / I-BUILD IBRD / 84210 Post Direct Selection Direct 19,764.71 0.00 Canceled 2018-01-01 2018-01-11 2018-03-17 2018-09-13 Implementation Support Component Head Page 8 Individual PRDP-VIS-DPD-AF-2019-001 Component 4: Project Pending IBRD / 88160 Post Consultant Open 11,764.71 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 / Compliance/Legal Officer Implementation Support Implementation Selection Individual PRDP-VIS-DPD-AF-2019-002 Component 4: Project Pending IBRD / 88160 Post Consultant Open 7,058.82 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 / Administrative Officer II Implementation Support Implementation Selection Individual PRDP-VIS-DPD-AF-2019-004 Component 4: Project Pending IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 / Economist Implementation Support Implementation Selection Individual PRDP-VIS-INF-AF-2019-005 Component 4: Project Pending IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 / Media Production Officer Implementation Support Implementation Selection Individual PRDP-VIS-INF-AF-2019-006 Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 / Writer Implementation Support Implementation Selection Individual PRDP-VIS-IB-AF-2019-001 / Component 4: Project Pending IBRD / 88160 Post Consultant Direct 19,764.71 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 I-BUILD Component Head Implementation Support Implementation Selection PRDP-VIS-IB-AF-2019-002 / Individual Component 4: Project Pending Rural Infrastructure IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Engineer - 1 Selection PRDP-VIS-IB-AF-2019-003 / Individual Component 4: Project Pending Rural Infrastructure IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Engineer - 2 Selection PRDP-VIS-IB-AF-2019-004 / Individual Component 4: Project Pending Rural Infrastructure IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Engineer - 3 Selection PRDP-VIS-IB-AF-2019-005 / Individual Component 4: Project Pending Project Development IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Associate Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project Pending 001 / Procurement Unit IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Head Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project Pending 002 / Procurement Officer - IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation 1 Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project Pending 003 / Procurement Officer - IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation 2 Selection PRDP-VIS-IS-PRO-AF-2019- Individual Component 4: Project Pending 004 / Associate Procurement IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection PRDP-VIS-IS-MAE-AF-2019- Individual Component 4: Project Pending 001 / Monitorig & IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Evaluation Unit Head Selection PRDP-VIS-IS-MAE-AF-2019- Individual Component 4: Project Pending 002 / Monitorig & IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Evaluation Officer - 1 Selection PRDP-VIS-IS-MAE-AF-2019- Individual Component 4: Project Pending 003 / Monitorig & IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Evaluation Officer - 2 Selection Page 9 Individual PRDP-VIS-IS-GGU-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 001 / GIS Officer - 1 Implementation Support Implementation Selection Individual PRDP-VIS-IS-GGU-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 002 / GIS Officer - 2 Implementation Support Implementation Selection Individual PRDP-VIS-IS-SES-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Open 11,764.71 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 001 / SES Specialist Implementation Support Implementation Selection Individual PRDP-VIS-IS-SES-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 002 / SES Officer - 1 Implementation Support Implementation Selection Individual PRDP-VIS-IS-SES-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 003 / SES Officer - 2 Implementation Support Implementation Selection Individual PRDP-VIS-IS-BUD-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 001 / Budget Analyst Implementation Support Implementation Selection PRDP-VIS-IS-FIN-AF-2019- Individual Component 4: Project Pending 001 / Finance Analyst III / IBRD / 88160 Post Consultant Open 11,764.71 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Finance Specialist Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 12,705.88 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 002 / Finance Analyst II - 1 Implementation Support Implementation Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 003 / Finance Analyst II - 2 Implementation Support Implementation Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 004 / Finance Analyst II - 3 Implementation Support Implementation Selection Individual PRDP-VIS-IS-FIN-AF-2019- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 005 / Finance Analyst I Implementation Support Implementation Selection PRDP-VIS-IS-ADM-AF-2019- Individual Component 4: Project Pending 001 / Administrative Unit IBRD / 88160 Post Consultant Direct 18,352.94 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Head Selection PRDP-VIS-IS-ADM-AF-2019- Individual Component 4: Project Pending 002 / Administrative Officer IBRD / 88160 Post Consultant Direct 8,470.59 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation III Selection PRDP-IS-VIS-OPD-003-000- Individual Component 4: Project Pending 2018-AF-E / Executive IBRD / 88160 Post Consultant Direct 823.53 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Assistant Selection PRDP-IS-VIS-DPD-001-000- Individual Component 4: Project Pending 2018-AF-E / Compliance IBRD / 88160 Post Consultant Direct 2,352.94 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer Selection Individual PRDP-IS-VIS-OPD-002-000- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 2,588.24 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 2018-AF-E / Legal Oficer Implementation Support Implementation Selection PRDP-IS-VIS-DPD-004-000- Individual Component 4: Project Pending 2018-AF-E / Executive IBRD / 88160 Post Consultant Direct 1,647.06 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Assistant Selection Page 10 PRDP-IS-VIS-DPD-005-000- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-GGU-002-000- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-INF-002-000- Individual Component 4: Project Pending 2018-AF-E / Graphic Layout IBRD / 88160 Post Consultant Direct 1,647.06 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Artist Selection PRDP-IS-VIS-IB-005-000- Individual Component 4: Project Pending 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer Selection PRDP-IS-VIS-PRO-005-000- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-PRO-006-000- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-MAE-003-000- Individual Component 4: Project Pending 2018-AF-E / Monitoring & IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Evaluation Officer Selection PRDP-IS-VIS-SES-002-000- Individual Component 4: Project Pending 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Safeguard Officer Selection PRDP-IS-VIS-SES-001-000- Individual Component 4: Project Pending 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Safeguard Officer Selection PRDP-IS-VIS-FIN-002-000- Individual Component 4: Project Pending 2018-AF-E / Budget IBRD / 88160 Post Consultant Direct 2,352.94 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Specialist Selection PRDP-IS-VIS-FIN-004-000- Individual Component 4: Project Pending 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation I Selection PRDP-IS-VIS-BUD-003-000- Individual Component 4: Project Pending 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation I Selection PRDP-IS-VIS-BUD-002-000- Individual Component 4: Project Pending 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation I Selection PRDP-IS-VIS-FIN-003-000- Individual Component 4: Project Pending 2018-AF-E / Finance Analyst IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation II Selection PRDP-IS-VIS-ADM-003-000- Individual Component 4: Project Pending 2018-AF-E / Administrative IBRD / 88160 Post Consultant Direct 1,607.84 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer III Selection PRDP-IS-VIS-ADM-004-000- Individual Component 4: Project Pending 2018-AF-E / Administrative IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer I Selection PRDP-VIS-R006-IB-AF-2019- Individual Component 4: Project Pending 001 / Rural Infrastructure IBRD / 88160 Post Consultant Open 10,588.24 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Specialist Selection Page 11 PRDP-VIS-R006-IS-MAE-AF- Individual Component 4: Project Pending 2019-002 / Associate M&E IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection Individual PRDP-VIS-R006-IS-SES-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 2019-001 / SES Officer - 1 Implementation Support Implementation Selection Individual PRDP-VIS-R006-IS-SES-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 2019-002 / SES Officer - 2 Implementation Support Implementation Selection PRDP-VIS-R006-IS-SES-AF- Individual Component 4: Project Pending 2019-003 / Associate SES IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection PRDP-VIS-R006-IS-INF-AF- Individual Component 4: Project Pending 2019-001 / Media Production IBRD / 88160 Post Consultant Open 7,058.82 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection PRDP-VIS-R006-IS-PRO-AF- Individual Component 4: Project Pending 2019-002 / Associate IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Procurement Officer Selection PRDP-VIS-R006-IS-ADM-AF- Individual Component 4: Project Pending 2019-001 / Administrative IBRD / 88160 Post Consultant Open 5,882.35 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer II Selection PRDP-VIS-R007-IB-AF-2019- Individual Component 4: Project Pending 001 / Rural Infrastructure IBRD / 88160 Post Consultant Open 9,529.41 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Specialist Selection PRDP-VIS-R007-IS-MAE-AF- Individual Component 4: Project Pending 2019-002 / Associate M&E IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection Individual PRDP-VIS-R007-IS-SES-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 2019-001 / SES Officer Implementation Support Implementation Selection PRDP-VIS-R007-IS-ADM-AF- Individual Component 4: Project Pending 2019-001 / Administrative IBRD / 88160 Post Consultant Open 7,058.82 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer II Selection PRDP-VIS-R008-IB-AF-2019- Individual Component 4: Project Pending 002 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Engineer - 2 Selection PRDP-VIS-R008-IB-AF-2019- Individual Component 4: Project Pending 003 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Engineer - 3 Selection PRDP-VIS-R008-IB-AF-2019- Individual Component 4: Project Pending 004 / Rural Infrastructure IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Engineer - 4 Selection PRDP-VIS-R008-IB-AF-2019- Individual Component 4: Project Pending 005 / Project Development IBRD / 88160 Post Consultant Direct 7,058.82 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Associate Selection Individual PRDP-VIS-R008-IS-GGU-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 11,294.12 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 2019-001 / GIS Data Officer Implementation Support Implementation Selection Individual PRDP-VIS-R008-IS-BUD-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 2019-001 / Budget Analyst I Implementation Support Implementation Selection Page 12 PRDP-VIS-R008-IS-FIN-AF- Individual Component 4: Project Pending 2019-001 / Finance Analyst I IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation - 1 Selection PRDP-VIS-R008-IS-ACC-AF- Individual Component 4: Project Pending 2019-002 / Finance Analyst I IBRD / 88160 Post Consultant Direct 9,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation - 2 Selection PRDP-VIS-R008-IS-PRO-AF- Individual Component 4: Project Pending 2019-001 / Procurement IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection PRDP-VIS-R008-IS-PRO-AF- Individual Component 4: Project Pending 2019-002 / Associate IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Procurement Officer Selection Individual PRDP-VIS-R008-IS-MAE-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 2019-001 / M&E Officer Implementation Support Implementation Selection PRDP-VIS-R008-IS-MAE-AF- Individual Component 4: Project Pending 2019-002 / Associate M&E IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection Individual PRDP-VIS-R008-IS-SES-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Open 9,411.76 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 2019-001 / SES Officer Implementation Support Implementation Selection PRDP-VIS-R008-IS-SES-AF- Individual Component 4: Project Pending 2019-002 / Associate SES IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection Individual PRDP-VIS-R008-IS-INF-AF- Component 4: Project Pending IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 2019-001 / Writer Implementation Support Implementation Selection PRDP-IS-VIS-R006-OPD-001- Individual Component 4: Project Pending 2018-AF-E / Executive IBRD / 88160 Post Consultant Direct 1,411.76 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Assistant Selection PRDP-IS-VIS-R006-OPD-003- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-R006-PRO-003- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-R006-MAE-003- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-R006-SES-001- Individual Component 4: Project Pending 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Safeguard Specialist Selection PRDP-IS-VIS-R006-SES-002- Individual Component 4: Project Pending 2018-AF-E / Social Safeguard IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Specialist Selection PRDP-IS-VIS-R006-SES-003- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-R006-INF-001- Individual Component 4: Project Pending 2018-AF-E / Web IBRD / 88160 Post Consultant Direct 1,647.06 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Administrator Selection Page 13 PRDP-IS-VIS-R006-FIN-004- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-R006-IB-001- Individual Component 4: Project Pending 2018-AF-E / Alternate I- IBRD / 88160 Post Consultant Direct 2,823.53 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation BUILD Component Head Selection PRDP-IS-VIS-R006-IB-003- Individual Component 4: Project Pending 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer - 1 Selection PRDP-IS-VIS-R006-IB-004- Individual Component 4: Project Pending 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer - 2 Selection PRDP-IS-VIS-R006-IB-005- Individual Component 4: Project Pending 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer - 3 Selection PRDP-IS-VIS-R007-IB-001- Individual Component 4: Project Pending 2018-AF-E / Rural IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Infrastructure Engineer - 4 Selection PRDP-IS-VIS-R007-SES-001- Individual Component 4: Project Pending 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Safeguard Officer - 1 Selection PRDP-IS-VIS-R007-SES-002- Individual Component 4: Project Pending 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Safeguard Officer - 2 Selection PRDP-IS-VIS-R007-SES-003- Individual Component 4: Project Pending 2018-AF-E / Social Safeguard IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer Selection PRDP-IS-VIS-R007-MAE-003- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-R007-OPD-003- Individual Component 4: Project Pending 2018-AF-E / Compliance IBRD / 88160 Post Consultant Direct 2,117.65 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Officer Selection PRDP-IS-VIS-R008-SES-001- Individual Component 4: Project Pending 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Safeguard Officer - 1 Selection PRDP-IS-VIS-R008-SES-002- Individual Component 4: Project Pending 2018-AF-E / Environmental IBRD / 88160 Post Consultant Direct 1,882.35 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Safeguard Officer - 2 Selection PRDP-IS-VIS-R008-ADM-001- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-IS-VIS-R008-PRO-002- Individual Component 4: Project Pending 2018-AF-E / Project IBRD / 88160 Post Consultant Direct 1,176.47 0.00 2019-01-01 2019-01-11 2019-02-01 2019-03-08 2019-09-04 Implementation Support Implementation Development Associate Selection PRDP-VIS-R007-IS-SES-AF- Individual Component 4: Project Pending 2019-002 / Associate SES IBRD / 88160 Post Consultant Open 8,235.29 0.00 2019-03-01 2019-04-19 2019-05-10 2019-06-14 2019-12-11 Implementation Support Implementation Officer Selection Page 14