PROCUREMENT PLAN (Textual Part) Project information: Sao Tome and Principe - WACA Resilience Investment Project - P162337 Project Implementation agency: Ministry of Public Works and Natural Resources, Directorate General of Environment Date of the Procurement Plan: July 2017 Period covered by this Procurement Plan: July 1st 2017 to June 30th, 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento de Licitação e Contratações Publicas such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables: Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables: Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables Other Relevant Procurement Information.: Not Applicable PROCUREMENT Western Africa : West Africa Coastal Areas Resilience investment Project PLAN General Information Country: Western Africa Bank’s Approval Date of the Original Procurement Plan: 2018-10-04 2019-08-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162337 GPN Date: 2017-12-29 Project Name: West Africa Coastal Areas Resilience investment Project Loan / Credit No: IDA / D2880 Executing Agency(ies): Ministry of Environment and Sustainable Development WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74186-CW-RFQ / Component 3: Strengthening Mise en place d'une clôture Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-10 2019-01-05 2019-07-04 grillagée autour de la marre Envelope d'exécution Investments à Spartines MR-MEDD-74188-CW-RFQ / Component 3: Strengthening Single Stage - One En attente Aménagement du site de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-20 2019-01-15 2019-07-14 Envelope d'exécution l'éco-loge Investments MR-MEDD-74189-CW-RFQ / Component 3: Strengthening Single Stage - One En attente Travaux de construction de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-02-09 2019-04-06 2019-10-03 Envelope d'exécution l'éco-loge Investments MR-MEDD-74202-CW-RFQ / Travaux d'entretien des Component 3: Strengthening Single Stage - One En attente couloirs de pare-feux du IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-12-30 2019-02-24 2019-08-23 Envelope d'exécution Typha au niveau de Investments Diawling MR-MEDD-74205-CW-RFB / Component 4: National Single Stage - Two En attente Construction des sièges de IDA / D2880 A posteriori Appel d'offres Open - National 0.00 2018-09-03 2018-09-08 2018-10-20 2019-01-02 2019-02-06 2019-08-05 Coordination Envelope d'exécution l'Observatoire et de l'UGP MR-MEDD-75951-CW-RFQ / Component 3: Strengthening Travaux pour passages de Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-01-15 2019-03-12 2019-09-08 piétons sur le cordon Envelope d'exécution Investments dunaire de NKTT MR-MEDD-75953-CW-RFQ / Component 3: Strengthening Mise en place de de bacs à Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-12-17 2019-02-11 2019-08-10 fleurs pour la sécurisation Envelope d'exécution Investments du littoral MR-MEDD-75955-CW-RFB / Component 3: Strengthening Single Stage - One En attente Colmatage des brèches du IDA / D2880 National Physical and Social A posteriori Appel d'offres Open - National 0.00 2018-11-05 2018-11-10 2018-12-22 2019-01-21 2019-02-25 2019-08-24 Envelope d'exécution littoral de NKTT Investments MR-MEDD-75986-CW-RFQ / Component 3: Strengthening Single Stage - One En attente Travaux pour la fixation des IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-10-06 2018-12-01 2019-05-30 Envelope d'exécution dunes au niveau de Chami Investments MR-MEDD-75993-CW-RFQ / Travaux de restauration des Component 3: Strengthening paysages des carrières de Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-12-05 2019-01-30 2019-07-29 coquillages en frange Envelope d'exécution Investments continentale du cordon dunaire du littoral Page 1 MR-MEDD-76006-CW-RFQ / Component 3: Strengthening Restauration des éco- Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-20 2019-01-15 2019-07-14 systèmes du Parc National Envelope d'exécution Investments d'Awleigatt (PNA) MR-MEDD-82725-CW-RFQ / mise en place d'une Component 2: Strengthening Single Stage - One En attente pépinière pour les besoins de IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-10-27 2018-12-22 2019-06-20 Envelope d'exécution la fixation des dunes du Framework littoral MR-MEDD-75980-CW-RFQ / Component 3: Strengthening Travaux de fixation de Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-10-20 2018-12-15 2019-06-13 dunes du littoral de NKTT Envelope d'exécution Investments sur un premier site pilote MR-MEDD-115356-CW-RFQ / Réalisation de clôture grillagée autour du Component 3: Strengthening Single Stage - One En attente périmètre de 15 ha de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-05-25 2019-06-10 2019-07-20 Envelope d'exécution fixation mécanique et Investments biologique du cordon dunaire de Nouakchott MR-MEDD-115655-CW-RFQ Component 3: Strengthening / Fixation de 15 ha de Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-06-01 2019-06-11 2019-08-10 dunes du littoral de Envelope d'exécution Investments Nouakchott MR-MEDD-115657-CW-RFQ / Travaux d'entretien de Component 3: Strengthening Single Stage - One En attente couloirs de pare-feus pour la IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-05-30 2019-06-12 2019-07-12 Envelope d'exécution restauration des mangroves Investments au niveau de Diawling MR-MEDD-115659-CW-RFQ Component 3: Strengthening Single Stage - One En attente / Réalisation de pépinières IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-06-08 2019-06-21 2019-07-21 Envelope d'exécution de mangroves au Diawling Investments MR-MEDD-124501-CW-RFQ Component 3: Strengthening / mise en place d'une cloture Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-08-26 2019-10-21 2020-04-18 de protectionsur les 2 ha de Envelope d'exécution Investments dunes fixées au PND GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74169-GO-RFQ / Acquisition d'équipements de Component 2: Strengthening Single Stage - One En attente bureaux au profit de IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-10-06 2018-12-01 2019-05-30 Envelope d'exécution l'Autorité de la Zone franche Framework de NDB MR-MEDD-74193-GO-RFQ / Acquisition d'équipements et Component 3: Strengthening Single Stage - One En attente de matériels de protection IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-10-13 2018-12-08 2019-06-06 Envelope d'exécution du cordon dunaire de Investments Diawling Page 2 MR-MEDD-74196-GO-RFQ / Component 3: Strengthening Achat de plants pour la Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-25 2019-01-20 2019-07-19 fixation biologique du cordon Envelope d'exécution Investments dunaire de Diawling MR-MEDD-74201-GO-RFQ / Acquisition de matériel pour Component 3: Strengthening Single Stage - One En attente la surveillance des IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-12-01 2019-01-26 2019-07-25 Envelope d'exécution investissements physiques Investments pour Diawling MR-MEDD-74203-GO-RFQ / Acquisition d'équipement Component 3: Strengthening Single Stage - One En attente pour l'observatoire IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-10-06 2018-12-01 2019-05-30 Envelope d'exécution ornithologique au niveau de Investments Diawling MR-MEDD-74204-GO-RFB / Component 4: National Single Stage - One En attente IDA / D2880 A posteriori Appel d'offres Open - National 0.00 2018-08-30 2018-09-04 2018-10-16 2018-11-15 2018-12-20 2019-06-18 Achat de véhicule Coordination Envelope d'exécution MR-MEDD-75952-GO-RFQ / Component 3: Strengthening Equipements pour passages Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2019-01-20 2019-03-17 2019-09-13 de franchissement du cordon Envelope d'exécution Investments dunaire de NKTT MR-MEDD-75959-GO-RFQ / Component 2: Strengthening Acquisition d'équipements Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-12-10 2019-02-04 2019-08-03 pour l'observatoire national Envelope d'exécution Framework du littoral mauritanien MR-MEDD-75977-GO-RFQ / Acquisition d'équipements de Component 2: Strengthening Single Stage - One En attente surveillance et de secourisme IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-10-30 2018-12-25 2019-06-23 Envelope d'exécution au profit de la Direction de Framework la Protection Civile MR-MEDD-75978-GO-RFQ / Component 2: Strengthening Single Stage - One En attente Acquisition d'équipements au IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-10-20 2018-12-15 2019-06-13 Envelope d'exécution profit de l'ONM Framework MR-MEDD-75979-GO-RFQ / Component 2: Strengthening Acquisition d'équipements Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-11-20 2019-01-15 2019-07-14 pour l'opérationnalisation du Envelope d'exécution Framework plan POLMAR MR-MEDD-75988-GO-RFQ / Component 3: Strengthening Acquisition d'équipements Single Stage - One En attente IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-20 2019-01-15 2019-07-14 pour la fixation des dunes Envelope d'exécution Investments au niveau de Chami MR-MEDD-75990-GO-RFQ / Component 3: Strengthening Single Stage - One En attente Mise en place de pépinières IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-10 2019-01-05 2019-07-04 Envelope d'exécution de mangroves à Nouamghar Investments MR-MEDD-75995-GO-RFQ / Acquisition d'équipements Component 2: Strengthening Single Stage - One En attente pour le réseau des IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-12-10 2019-02-04 2019-08-03 Envelope d'exécution Parlementaires et élus Framework locaux de l'environnement MR-MEDD-75997-GO-RFQ / Component 2: Strengthening Acquisition de matériel pour Single Stage - One En attente IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-12-04 2019-01-29 2019-07-28 la coordination du Master Envelope d'exécution Framework Gaed Page 3 MR-MEDD-75998-GO-RFQ / Acquisition d'équipements Component 2: Strengthening Single Stage - One En attente pour l'opérationnalisation de IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-11-04 2018-12-30 2019-06-28 Envelope d'exécution la base de données du Framework MEED MR-MEDD-76001-GO-RFQ / Acquisition d'équipements Component 2: Strengthening Single Stage - One En attente pour le laboratoire des IDA / D2880 the Policy and Institutional A posteriori Demande de prix Limited 0.00 2018-11-04 2018-12-30 2019-06-28 Envelope d'exécution études environnementales et Framework de géographie (LEERG) MR-MEDD-76866-GO-RFQ / Component 3: Strengthening Single Stage - One En attente Acquisition de matériel pour IDA / D2880 National Physical and Social A posteriori Demande de prix Open - National 0.00 2018-10-15 2018-12-10 2019-06-08 Envelope d'exécution les AGR Investments NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74195-NC-RFQ / Collecte et transport sur Component 3: Strengthening Single Stage - One En cours sites de matériaux de IDA / D2880 National Physical and Social A posteriori Demande de prix Limited 0.00 2018-11-13 2019-01-08 2019-07-07 Envelope d'exécution fixation mécanique de dunes Investments au niveau de Diawling CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74182-CS-QCBS Sélection fondée Component 2: Strengthening / Elaboration de la directive sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-25 2018-10-16 2018-11-29 2018-12-29 2019-02-02 2019-08-01 d'aménagement du littoral de qualifications des d'exécution Framework NDB consultants Sélection fondée MR-MEDD-74184-CS-QCBS Component 2: Strengthening sur les En attente / Etude sur le classement de IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 qualifications des d'exécution la Baie de l'Etoile de NDB Framework consultants MR-MEDD-74207-CS-QCBS / Analyse du rapport EIE du Sélection fondée Component 2: Strengthening projet Ahmeyin/Guembeul sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-05 2018-09-26 2018-11-09 2018-12-09 2019-01-13 2019-07-12 pour la production de gaz qualifications des d'exécution Framework offshore en Mauritanie et au consultants Sénégal MR-MEDD-74256-CS-CQS / Sélection fondée Component 3: Strengthening Etude pour le sur les En attente IDA / D2880 National Physical and Social A posteriori Limited 0.00 2018-10-08 2018-10-22 2018-11-21 2018-12-26 2019-06-24 franchissement du cordon qualifications des d'exécution Investments dunaire de NKTT consultants MR-MEDD-75957-CS-QCBS Sélection fondée Component 2: Strengthening / Evaluation des risques liés sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 aux inondations de la ville qualifications des d'exécution Framework de NKTT consultants MR-MEDD-75958-CS-QCBS Sélection fondée Component 2: Strengthening / Elaboration de la directive sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-28 2018-10-19 2018-12-02 2019-01-01 2019-02-05 2019-08-04 d'aménagement du littoral de qualifications des d'exécution Framework NKTT consultants Page 4 MR-MEDD-75960-CS-QCBS Sélection fondée Component 2: Strengthening / Elaboration d'une stratégie sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-21 2018-10-12 2018-11-25 2018-12-25 2019-01-29 2019-07-28 de gestion intégrée du qualifications des d'exécution Framework littoral mauritanien consultants MR-MEDD-75970-CS-QCBS Sélection fondée Component 2: Strengthening / Evaluation du capital sur les En attente IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-20 2018-10-11 2018-11-24 2018-12-24 2019-01-28 2019-07-27 sédimentologique de la ville qualifications des d'exécution Framework de NKTT consultants MR-MEDD-76863-CS-QBS / élaboration de plans de Component 2: Strengthening Sélection fondée En attente développement communaux IDA / D2880 the Policy and Institutional A posteriori Open - National 0.00 2018-09-26 2018-10-17 2018-11-30 2018-12-28 2019-01-27 2019-02-26 2019-04-02 2020-04-01 sur la qualité d'exécution pour Tevragh Zeine ,sebkha Framework et Elmina MR-MEDD-76873-CS-QCBS Component 2: Strengthening Sélection fondée / Etude sur les pressions et Open - En attente IDA / D2880 the Policy and Institutional A posteriori sur la qualité et 0.00 2018-10-08 2018-10-29 2018-12-12 2019-01-09 2019-02-08 2019-03-15 2019-04-19 2020-04-18 enjeux exercés sur l'espace International d'exécution Framework le coût vital du PNBA MR-MEDD-115364-CS-CQS / Sélection fondée Etude de faisabilité pour la Component 3: Strengthening sur les En attente réhabilitation et l'extension IDA / D2880 National Physical and Social A posteriori Limited 0.00 2019-05-27 2019-06-03 2019-06-07 2019-06-14 2019-07-24 qualifications des d'exécution de la digue de protection au Investments consultants niveau du Diawling MR-MEDD-115676-CS-CQS / Sélection fondée Component 3: Strengthening Etude technique pour le sur les En attente IDA / D2880 National Physical and Social A posteriori Limited 0.00 2018-06-15 2018-06-29 2018-07-13 2018-08-10 2018-09-24 colmatage des brèches du qualifications des d'exécution Investments littoral de Nouakchott consultants MR-MEDD-117326-CS-QCBS / recrutement d'un cabinet Sélection fondée Component 4: National En attente d'audit pour audit extezrne IDA / D2880 A posteriori sur la qualité et Open - National 0.00 2019-05-29 2019-05-31 2019-06-08 2019-06-11 2019-06-14 2019-06-20 2019-06-23 2019-07-13 Coordination d'exécution du projet pour les années le coût 2018 2019 2020 et 2021. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MR-MEDD-74127-CS-INDV / Diagnostic et évaluation de Component 2: Strengthening la capacité de tous les En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-08-17 2018-08-22 2018-09-12 2018-10-17 2019-04-15 organismes concernés avec d'exécution Framework l'OLM (inclus consultations, séminaires, ateliers) MR-MEDD-74130-CS-INDV / Component 2: Strengthening En attente Elaboration des plans de IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-08-20 2018-08-25 2018-09-15 2018-10-20 2019-04-18 d'exécution résilience de N'Diago Framework MR-MEDD-74133-CS-INDV / Identification des actions Component 2: Strengthening prioritaires de l'antenne En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 nationale de la MOLOA d'exécution Framework (inclus consultations, ateliers, séminaires) MR-MEDD-74135-CS-INDV / Component 3: Strengthening Elaboration de textes En attente IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-11-02 2018-11-07 2018-11-28 2019-01-02 2019-07-01 juridiques relatifs aux d'exécution Investments principes pollueur-payeurs Page 5 MR-MEDD-74137-CS-INDV / Conception et mise en place d'une plateforme de gestion Component 2: Strengthening environnementale relative à En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-09-03 2018-09-08 2018-09-29 2018-11-03 2019-05-02 l'évaluation des activités et d'exécution Framework le suivi de leurs impacts environnementaux sur le littoral mauritanien MR-MEDD-74141-CS-INDV / Analyse du cadre foncier Component 2: Strengthening En attente relatif au littoral (inclus IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-15 2018-10-20 2018-11-10 2018-12-15 2019-06-13 d'exécution consultations, séminaires, Framework ateliers) MR-MEDD-74150-CS-INDV / Analyse et révision de Component 2: Strengthening En attente l'ordonnance relative au IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-02 2018-10-07 2018-10-28 2018-12-02 2019-05-31 d'exécution littoral et élaboration des Framework textes d'application MR-MEDD-74152-CS-INDV / Component 2: Strengthening Elaboration de guide des En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 acteurs et des métiers du d'exécution Framework littoral mauritanien MR-MEDD-74153-CS-INDV / Revue et amendement du Component 2: Strengthening En attente système des études d'impact IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-01 2018-10-06 2018-10-27 2018-12-01 2019-05-30 d'exécution environnemental en Framework Mauritanie MR-MEDD-74154-CS-INDV / Rédaction des termes de Component 2: Strengthening référence de l'étude relative En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-03 2018-10-08 2018-10-29 2018-12-03 2019-06-01 aux plans de résilience de d'exécution Framework N'Diago (inclus consultations, ateliers, séminaires) MR-MEDD-74164-CS-INDV / Recrutement d'un assistant Component 2: Strengthening En attente technique au profit de IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-13 2018-11-01 2018-11-22 2018-12-27 2019-06-25 d'exécution l'Autorité de la Zone franche Framework de NDB MR-MEDD-74172-CS-INDV / Component 2: Strengthening Analyse du schéma En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 opérationnel de la Zone d'exécution Framework franche de NDB MR-MEDD-74174-CS-INDV / Component 2: Strengthening Actualisation du schéma En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-12-03 2018-12-08 2018-12-29 2019-02-02 2019-08-01 opérationnel de la Zone d'exécution Framework franche de NDB MR-MEDD-74175-CS-INDV / Component 2: Strengthening Etat des lieux de En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 l'environnement au niveau d'exécution Framework de la Zone franche de NDB MR-MEDD-74185-CS-INDV / Actualisation du plan Component 2: Strengthening En attente d'aménagement et de gestion IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-20 2018-11-08 2018-11-29 2019-01-03 2019-07-02 d'exécution de la Baie de l'Etoile de Framework NDB MR-MEDD-74187-CS-INDV / Component 3: Strengthening En attente Etude relative à la mise en IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2018-09-18 2018-11-06 2018-11-27 2019-01-01 2019-06-30 d'exécution place de l'éco-loge Investments Page 6 MR-MEDD-74191-CS-INDV / Component 2: Strengthening Elaboration d'une carte de En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-11-13 2018-11-18 2018-12-09 2019-01-13 2019-07-12 potentialités de la Zone d'exécution Framework franche de NDB MR-MEDD-74192-CS-INDV / Component 3: Strengthening Evaluation des risques En attente IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-12-17 2018-12-22 2019-01-12 2019-02-16 2019-08-15 d'inondations pour la ville d'exécution Investments de NBD MR-MEDD-74194-CS-INDV / Component 3: Strengthening Etudes de faisabilité des En cours IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-10-01 2018-10-06 2018-10-27 2018-12-01 2019-05-30 travaux de fixation du d'exécution Investments cordon dunaire de Diawling MR-MEDD-74199-CS-INDV / Recrutement d'un consultant Component 3: Strengthening En attente pour le suivi et le contrôle IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-11-05 2018-11-10 2018-12-01 2019-01-05 2019-07-04 d'exécution des travaux du cordon Investments dunaire de Diawling MR-MEDD-74200-CS-INDV / Component 3: Strengthening Elaboration d'une carte En cours IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 d'occupation des éco-systèmes d'exécution Investments de mangroves MR-MEDD-75945-CS-INDV / Component 3: Strengthening Etude pour le En cours IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-10-01 2018-10-06 2018-10-27 2018-12-01 2019-05-30 franchissement du cordon d'exécution Investments dunaire de NKTT MR-MEDD-75972-CS-INDV / Component 2: Strengthening En attente Conception et mise en place IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-11-05 2018-11-10 2018-12-01 2019-01-05 2019-07-04 d'exécution d'un site web pour l'OLM Framework MR-MEDD-76164-CS-INDV / Component 2: Strengthening En attente Recrutement d'un Comptable IDA / D2880 the Policy and Institutional A priori Individuel Open 0.00 2018-08-31 2018-10-19 2018-11-09 2018-12-14 2019-06-12 d'exécution pour le Projet Framework MR-MEDD-76422-CS-INDV / Component 4: National En attente Recrutement d'un auditeur IDA / D2880 A priori Individuel Limited 0.00 2018-09-12 2018-09-17 2018-10-08 2018-11-12 2019-05-11 Coordination d'exécution interne MR-MEDD-76867-CS-INDV / Component 3: Strengthening En attente Mise à jour du SIG de la IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 d'exécution Région de Nouakchott Investments MR-MEDD-76868-CS-INDV / Component 3: Strengthening Adaptation du fonds En attente IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2018-12-04 2019-01-22 2019-02-12 2019-03-19 2019-09-15 d'Investissement communal d'exécution Investments (région de NKTT) MR-MEDD-82696-CS-INDV / Component 2: Strengthening recrutement d'un consultant En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-31 2018-11-05 2018-11-26 2018-12-31 2019-06-29 pour appuyer la cellule d'exécution Framework Changement Climatique MR-MEDD-82701-CS-INDV / recrutement d'un consultant Component 2: Strengthening national pour l'appui à En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-29 2018-11-03 2018-11-24 2018-12-29 2019-06-27 l'étude de faisabilité du d'exécution Framework projet WACA-CCA en Mauritanie Page 7 MR-MEDD-82704-CS-INDV / Component 2: Strengthening En attente réalisation d'un documentaire IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-10-19 2018-10-24 2018-11-14 2018-12-19 2019-06-17 d'exécution sur la baie de l'étoile Framework MR-MEDD-82731-CS-INDV / Component 4: National En attente Maintenance et suivi IDA / D2880 A posteriori Individuel Limited 0.00 2018-11-19 2018-11-24 2018-12-15 2019-01-03 2019-07-02 Coordination d'exécution informatique MR-MEDD-82737-CS-INDV / accompagnement de l'UGP et des structures beneficiaires Component 3: Strengthening dans la mise en oeuvre des En attente IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-11-15 2018-11-20 2018-12-11 2019-01-15 2019-07-14 activitesd d'exécution Investments investissement(identification des sites screening environnemental reporting...) MR-MEDD-76859-CS-NPO / Component 3: Strengthening En attente Mise en place d'un système IDA / D2880 National Physical and Social A posteriori Individuel Limited 0.00 2018-11-01 2018-11-06 2018-11-27 2019-01-01 2019-06-30 d'exécution de Gestion de plaintes Investments MR-MEDD-76166-CS-INDV / Component 2: Strengthening Recrutement d'un En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-09-05 2018-09-10 2018-10-01 2018-11-05 2019-05-04 Responsable de Suivi- d'exécution Framework Evaluation MR-MEDD-76167-CS-INDV / Component 2: Strengthening En attente Recrutement d'un Spécialiste IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 d'exécution en communication Framework MR-MEDD-76173-CS-INDV / Component 2: Strengthening En attente Recrutement en IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 d'exécution Développement Institutionnel Framework MR-MEDD-76168-CS-INDV / Component 2: Strengthening Recrutement d'un Spécialiste En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 en Développement Social, d'exécution Framework sauvegarde sociale et genre MR-MEDD-76158-CS-INDV / Component 2: Strengthening En attente Recrutement Coordinateur du IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-08-29 2018-09-03 2018-09-24 2018-10-29 2019-04-27 d'exécution Projet WACA Framework MR-MEDD-76160-CS-INDV / Component 2: Strengthening Recrutement d'un En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-08-29 2018-09-03 2018-09-24 2018-10-29 2019-04-27 Coordinateur-Adjoint juriste d'exécution Framework pour le Projet WACA MR-MEDD-76162-CS-INDV / Component 2: Strengthening Recrutement d'un En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2018-08-29 2018-09-03 2018-09-24 2018-10-29 2019-04-27 Responsable de Passation d'exécution Framework des Marchés MR-MEDD-74190-CS-INDV / Component 3: Strengthening Elaboration d'un plan de En attente IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-07-01 gestion environnementale et d'exécution Investments sociale du site de l'éco-loge MR-MEDD-115334-CS-INDV / Elaboration des TDR de Component 2: Strengthening l'étude de détermination du En cours IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2019-05-30 2019-06-12 2019-06-14 2019-06-18 2019-07-08 trait de côte du Littoral d'exécution Framework mauritanien par GNSS de N'Diago au Cap blanc Page 8 MR-MEDD-115272-CS-INDV / Etude pour l'élaboration Component 2: Strengthening En cours d'une stratégie et d'un plan IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2019-05-30 2019-06-13 2019-06-15 2019-06-21 2019-08-05 d'exécution de communication pour le Framework Projet MR-MEDD-115327-CS-INDV / L'élaboration d'une étude Component 3: Strengthening En cours d'identification de sous- IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2019-05-30 2019-06-11 2019-06-13 2019-06-17 2019-07-27 d'exécution projets dans les communes Investments littorales MR-MEDD-115350-CS-INDV / Elaboration de cahier de Component 3: Strengthening prescriptions techniques pour En cours IDA / D2880 National Physical and Social A posteriori Individuel Open 0.00 2019-05-30 2019-06-12 2019-06-17 2019-06-20 2019-07-16 le colmatage des brèches du d'exécution Investments cordon dunaire de Nouakchott MR-MEDD-115371-CS-CDS / Component 2: Strengthening Etat des lieux du foncier du En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Open 0.00 2019-05-30 2019-06-11 2019-06-13 2019-06-17 2019-08-16 littoral de N'Diago et de la d'exécution Framework Zone Franche de Nouadhibou MR-MEDD-124785-CS-INDV / etude sur l'état des lieux Component 2: Strengthening et le mapping des bases de En attente IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2019-08-05 2019-08-10 2019-08-15 2019-09-12 2019-10-12 donnees et SIG des zones d'exécution Framework côtières et arides de la mauritanie. MR-MEDD-124792-CS-INDV / Inventaire des textes juridiques relatifs à la Component 2: Strengthening En attente gestion des zones côtières et IDA / D2880 the Policy and Institutional A posteriori Individuel Limited 0.00 2019-08-21 2019-08-26 2019-09-16 2019-10-21 2020-04-18 d'exécution marines et ratifications des Framework protocoles de la convention d'Abidjan. Page 9