The World Bank Implementation Status & Results Report Modernization and Upgrade of Transmission Substations (P156584) Modernization and Upgrade of Transmission Substations (P156584) EUROPE AND CENTRAL ASIA | Uzbekistan | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 5 | ARCHIVED on 27-Jun-2019 | ISR37867 | Implementing Agencies: Republic of Uzbekistan, UZBEKENERGO Key Dates Key Project Dates Bank Approval Date: 23-Nov-2016 Effectiveness Date: 28-Dec-2017 Planned Mid Term Review Date: 31-Dec-2020 Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2022 Revised Closing Date: 31-Dec-2022 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve the technical efficiency and reliability of the power transmission networks in Uzbekistan. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1. Electricity Transmission System Upgrade:(Cost $191.30 M) Component 2. Institutional Development and Technical Assistance:(Cost $5.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Project became effective on December 28, 2018. The first batch of transformers have arrived into the country, contracts have been signed for several other contracts (#2, #3, #5, #9), and procurement activities for other contracts are making steady progress. Risks 6/27/2019 Page 1 of 5 The World Bank Implementation Status & Results Report Modernization and Upgrade of Transmission Substations (P156584) Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Moderate Moderate Substantial Technical Design of Project or Program Low Low Low Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Low Low Moderate Stakeholders Moderate Moderate Moderate Other -- -- -- Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes Electricity losses per year in the project area IN00723331 ►Electricity losses per year in the project area (target substations) (Sector Core) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.71 0.71 0.71 0.25 Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 Number of electricity outages of major equipment in the substations covered under the project IN00723332 ►Number of electricity outages of major equipment in the substations covered under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 103.00 103.00 103.00 10.00 Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 Average interruption frequency per year in the project area SAIFI IN00723333 ►Average interruption frequency per year in the project area SAIFI (Sector Core) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 6/27/2019 Page 2 of 5 The World Bank Implementation Status & Results Report Modernization and Upgrade of Transmission Substations (P156584) Value 59.00 59.00 59.00 58.00 Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 Direct project beneficiaries IN00723334 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 29.10 Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 IN00723335 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Intermediate Results Indicators by Components Component 1. Electricity Transmission System Upgrade IN00723336 ►Number of substations rehabilitated under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 22.00 Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 Component 2. Institutional Development and Technical Assistance IN00723337 ►UE group transition to IFRS is fully complete (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 IN00723338 ►Percent of registered project-related grievances responded to within stipulated service standards for response times (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 IN00723339 6/27/2019 Page 3 of 5 The World Bank Implementation Status & Results Report Modernization and Upgrade of Transmission Substations (P156584) Percent of registered project-related grievances responded to within stipulated service standards for response times - Disaggregated by gender (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 01-Jul-2016 18-Dec-2018 18-Dec-2018 31-Dec-2022 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P156584 IBRD-86640 Effective USD 92.00 92.00 0.00 0.00 92.00 0% P156584 IDA-59160 Effective USD 39.16 39.16 0.00 18.30 20.86 47% P156584 IDA-59170 Effective USD 18.84 18.84 0.00 2.44 16.40 13% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P156584 IBRD-86640 Effective 23-Nov-2016 20-Sep-2017 28-Dec-2017 31-Dec-2022 31-Dec-2022 P156584 IDA-59160 Effective 23-Nov-2016 20-Sep-2017 28-Dec-2017 31-Dec-2022 31-Dec-2022 P156584 IDA-59170 Effective 23-Nov-2016 20-Sep-2017 28-Dec-2017 31-Dec-2022 31-Dec-2022 Cumulative Disbursements 6/27/2019 Page 4 of 5 The World Bank Implementation Status & Results Report Modernization and Upgrade of Transmission Substations (P156584) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/27/2019 Page 5 of 5