Uttar Pradesh Sodic Lands Reclamation III Project PROCUREMENT PLAN I. General 1. Project information: • Project: Uttar Pradesh Sodic Lands Reclamation III Project • Country: India • Project Code: P112033 2. Bank’s approval Date of the procurement Plan Draft Procurement Plan dated March 17, 2017 Revision 0 agreed by the Bank on March 17, 2017 3. Implementing Agencies: UPBSN, Irrigation Department, Agriculture Department 4. Period covered by this procurement plan: 18 months 5. Risk Rating for the Implementing Agency: Substantial 6. Original Procurement Risk Rating for the Project: Substantial 7. Current Procurement Risk Rating for the Project: Substantial II. Works, Non-consulting services and Goods. 1 a) Procurement Methods and Thresholds Category Method of Procurement Threshold (US$ Equivalent) Works International Competitive Bidding (ICB) > 40,000,000 National Competitive Bidding (NCB) Up to 40,000,000 (with NCB conditions) Shopping Up to 100,000 Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) for Works As per paragraph 3.14 of Guidelines Force Account As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Goods and International Competitive Bidding (ICB) > 3,000,000 non- Limited International Bidding (LIB) wherever agreed by Bank consultant National Competitive Bidding (NCB) Up to 3,000,000 (with NCB conditions) services Shopping Up to 100,000 (NCS) Direct Contracting (DC) As per paragraph 3.7 of Guidelines Public-Private Partnership (PPP) As per paragraph 3.14 of Guidelines Force Account (only for NCS) As per paragraph 3.9 of Guidelines Framework Agreement (FA) As per paragraph 3.6 of Guidelines Procurement from United Nations (UN) Agencies As per paragraph 3.10 of Guidelines 1 b) Prior Review Threshold Works: All contracts more than USD 10 million equivalent Goods: All contracts more than USD 2 million equivalent Non-Consultant Services and IT systems: All contracts more than USD 2 million equivalent In addition, the justifications for all contracts to be issued using LIB or direct contracting shall be subject to prior review with procurement plan. First framework agreement will be subject to prior review irrespective of value. For prior review contracts, the amendments for increasing the cost beyond 15% of original value shall also be subject to Bank’s prior review. 2. Pre-qualification – Not envisaged 3. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s "Guidelines: Procurement under IBRD Loans and IDA Credits" dated May 2004 and revised October 2006. 4. Any Other Special Procurement Arrangements: NCB will be conducted in accordance with paragraph 3.3 and 3.4 of the Guidelines and the following provisions: i. Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; ii. Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; iii. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State; iv. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; v. Extension of bid validity shall not be allowed with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/ Employer) vi. Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank vii. The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project; viii. Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures. Such contracts will be acceptable however for any procurement under the Shopping procedures; ix. Two or three envelope system will not be used (except when using e- Procurement system assessed and agreed by the Bank) Other agreed provisions are: • Any discount received from the bidders after bid submission deadline will not be considered either during the bid evaluation or the contract award. • Domestic preference will be applicable for ICB procurement of Goods as per Appendix 2 of the Procurement Guidelines. • Bids received from foreign bidders will not be rejected under NCB. • DGS&D rate contracts may be used as framework agreement (FA) provided: i. Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods. ii. Before issuing the purchasing order, the implementing agency will carry out a price analysis on the specific good that is intended to be purchased. If after this due diligence the implementing agency concludes (and Bank agrees) that the DGS&D rate contracts are more advantageous, DGS&D rate contracts may be used as FA. iii. To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank's right to audit and F&C clauses could be mentioned. 5. Procurement Packages with Methods and Time Schedule – As per procurement plan available in STEP. III. Selection of Consultants 1 a) Selection Methods and Thresholds Method of Procurement Threshold (US$ Equivalent) Selection Based on Consultants’ Qualifications Up to 300,000 (CQS)/Least-Cost Selection (LCS) Single-Source Selection (SSS) As per paragraphs 3.9-3.11 of Guidelines Individuals As per Section V of Guidelines Particular Types of Consultants As per paragraphs 3.15-3.21 of Guidelines Quality- and Cost-Based Selection (QCBS)/ Quality- for all other cases Based Selection (QBS)/ Selection under a Fixed Budget (FBS) 1 b) Prior Review Threshold Consultancy Services: > US$ 1,000,000 for firms; and > US$ 300,000 for individuals In addition, the justifications for all contracts to be issued on the basis of single-source selection will be subject to prior review with procurement plan. For prior review contracts, the amendments for increasing the cost or extension of time beyond 15% of original value shall also be subject to Bank’s prior review. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None. 4. Applicable Guidelines: All the contracts issued under the project will follow the World Bank’s "Guidelines: Selection and Employment of Consultants by World Bank Borrowers" dated May 2004 and revised October 2006. 5. Consultancy Assignments with Selection Methods and Time Schedule – As per procurement plan available in STEP. PROCUREMENT India : Uttar Pradesh Sodic Lands Reclamation III Project PLAN General Information Country: India Banks Approval Date of the Original Procurement Plan: 2016-08-24 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-08-10 Project ID: P112033 GPN Date: Project Name: Uttar Pradesh Sodic Lands Reclamation III Project Loan / Credit No: IDA / 46400 Executing Agency(ies): Uttar Pradesh Bhumi Sudhar Nigam WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-UPBSN-3338-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 19,485.00 19,954.35 Completed 2016-11-21 2016-09-30 2017-01-16 2016-12-16 2017-07-15 2017-06-12 Rehabilitation of Baghadi drain System Quotations Envelope IN-UPBSN-3339-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 20,803.00 17,997.03 Completed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-17 2017-03-16 2016-11-30 2017-04-20 2016-12-18 2017-10-17 2017-03-17 Rehabilitation of Jarauna drain System Envelope IN-UPBSN-3340-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 4,587.00 4,492.53 Completed 2016-11-20 2016-10-04 2017-01-15 2016-12-16 2017-07-14 2017-03-12 Rehabilitation of Pitthoupur Drain System Quotations Envelope IN-UPBSN-3341-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 14,298.00 14,002.57 Signed 2016-11-20 2016-09-28 2017-01-15 2016-12-17 2017-07-14 Rehabilitation of Kailai Drain System Quotations Envelope IN-UPBSN-3342-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Upper Reth IDA / 46400 Post Limited 17,975.00 18,154.77 Signed 2016-11-20 2016-09-28 2017-01-15 2016-12-17 2017-07-14 System Quotations Envelope Drain IN-UPBSN-3344-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 12,290.00 12,468.52 Signed 2016-11-20 2016-09-28 2017-01-15 2016-12-17 2017-07-14 Rehabilitation of Saidanpur Drain System Quotations Envelope IN-UPBSN-3345-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Naiya Ka Purwa IDA / 46400 Post Limited 3,274.00 2,995.21 Completed 2016-11-20 2016-09-27 2017-01-15 2016-12-19 2017-07-14 2017-03-18 System Quotations Envelope Drain IN-UPBSN-3346-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Bhatwa Tal IDA / 46400 Post Limited 3,292.00 2,918.53 Completed 2016-11-20 2016-10-04 2017-01-15 2016-12-19 2017-07-14 2017-03-18 System Quotations Envelope Drain IN-UPBSN-3347-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 6,610.00 6,321.47 Completed 2016-11-20 2016-10-04 2017-01-15 2016-12-19 2017-07-14 2017-03-18 Rehabilitation of Kaidawan Drain System Quotations Envelope IN-UPBSN-3349-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 17,639.00 17,420.66 Completed 2016-11-20 2016-09-27 2017-01-15 2016-12-19 2017-07-14 2017-04-18 Rehabilitation of Jeego Drain System Quotations Envelope IN-UPBSN-3350-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 16,409.00 15,973.11 Completed 2016-11-20 2016-09-27 2017-01-15 2016-12-22 2017-07-14 2017-04-21 Rehabilitation of Jamunipur Drain System Quotations Envelope IN-UPBSN-3351-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Tisakhanapur IDA / 46400 Post Limited 15,949.00 15,670.18 Completed 2016-11-20 2016-09-27 2017-01-15 2016-12-19 2017-07-14 2017-04-18 System Quotations Envelope Drain IN-UPBSN-3352-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 2,817.00 2,384.87 Completed 2016-11-20 2016-10-04 2017-01-15 2016-12-19 2017-07-14 2017-03-18 Rehabilitation of Dharmapur Drain System Quotations Envelope IN-UPBSN-3353-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 15,672.00 16,279.35 Signed 2016-11-20 2016-10-04 2017-01-15 2016-12-22 2017-07-14 Rehabilitation of Sher tal Drain System Quotations Envelope IN-UPBSN-3354-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Basantpur Cut IDA / 46400 Post Limited 14,029.00 14,451.39 Signed 2016-11-20 2016-10-04 2017-01-15 2016-12-24 2017-07-14 System Quotations Envelope Drain IN-UPBSN-3356-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Govindpur IDA / 46400 Post Limited 19,105.00 18,957.11 Completed 2016-11-20 2016-10-04 2017-01-15 2016-12-22 2017-07-14 2017-03-21 System Quotations Envelope Escape IN-UPBSN-3357-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 12,951.00 12,682.87 Completed 2016-11-20 2016-09-27 2017-01-15 2016-12-19 2017-07-14 2017-04-18 Rehabilitation of Gajanipur Drain System Quotations Envelope IN-UPBSN-3359-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Pure Barjor IDA / 46400 Post Limited 12,374.00 12,046.54 Completed 2016-11-20 2016-09-27 2017-01-15 2016-12-19 2017-07-14 2017-04-18 System Quotations Envelope Drain IN-UPBSN-3361-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 10,904.00 10,796.77 Signed 2016-11-20 2016-11-08 2017-01-15 2016-12-19 2017-07-14 Rehabilitation of Adampur Drain System Quotations Envelope IN-UPBSN-3364-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 19,007.00 18,767.56 Signed 2016-11-20 2016-11-08 2017-01-15 2016-12-19 2017-07-14 Rehabilitation of Gopalpur Drain System Quotations Envelope IN-UPBSN-3365-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Rehabilitation of Nagla Danua IDA / 46400 Post Limited 13,115.00 13,096.86 Signed 2016-11-20 2016-11-08 2017-01-15 2016-12-19 2017-07-14 System Quotations Envelope Drain IN-UPBSN-3366-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One IDA / 46400 Post Limited 10,586.00 10,323.71 Completed 2016-11-20 2016-10-26 2017-01-15 2016-12-07 2017-07-14 2017-02-22 Rehabilitation of Behta Drain System Quotations Envelope IN-UPBSN-3368-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 47,481.00 46,733.75 Completed 2016-11-15 2016-09-21 2016-11-20 2017-01-01 2016-11-10 2017-03-16 2016-11-28 2017-04-20 2016-12-21 2017-10-17 2017-03-20 Rehabilitation of Tarhati Drain System Envelope IN-UPBSN-3369-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 118,847.00 121,854.60 Signed 2016-11-15 2016-09-20 2016-11-20 2017-01-01 2016-11-17 2017-03-16 2016-12-05 2017-04-20 2016-12-27 2017-10-17 Rehabilitation of Rasulpur Drain System Envelope IN-UPBSN-3370-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 74,653.00 76,607.13 Signed 2016-11-15 2016-09-20 2016-11-20 2017-01-01 2016-11-17 2017-03-16 2016-12-05 2017-04-20 2016-12-27 2017-10-17 Rehabilitation of Rasulpur-1 Drain System Envelope Page 1 IN-UPBSN-3371-CW-RFB / 2. Improvement of Drainage Single Stage - Two Rehabilitation of Naupur IDA / 46400 Post Request for Bids Open - National 32,292.00 25,442.80 Completed 2016-11-15 2016-09-21 2016-11-20 2017-01-01 2016-11-16 2017-03-16 2016-11-29 2017-04-20 2016-12-28 2017-10-17 2017-05-09 System Envelope Madiyapar Drain IN-UPBSN-3372-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 42,241.00 36,197.55 Signed 2016-11-15 2016-09-21 2016-11-20 2017-01-01 2016-11-16 2017-03-16 2016-11-30 2017-04-20 2016-12-26 2017-10-17 Rehabilitation of Hathauta Drain System Envelope IN-UPBSN-3373-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 24,692.00 23,171.95 Completed 2016-11-15 2016-09-21 2016-11-20 2017-01-01 2016-11-17 2017-03-16 2016-11-29 2017-04-20 2016-12-24 2017-10-17 2017-05-09 Rehabilitation of Katohi Drain System Envelope IN-UPBSN-3374-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 26,653.00 26,961.80 Signed 2016-11-15 2016-09-21 2016-11-20 2017-01-01 2016-11-16 2017-03-16 2016-11-30 2017-04-20 2016-12-21 2017-10-17 Rehabilitation of Sataini Drain System Envelope IN-UPBSN-3375-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 34,412.00 35,251.53 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-09 2017-03-16 2016-11-22 2017-04-20 2016-12-22 2017-10-17 Rehabilitation of Maholiya Drain System Envelope IN-UPBSN-3377-CW-RFB / 2. Improvement of Drainage Single Stage - Two Rehabilitation of Sarai Joga Ext. IDA / 46400 Post Request for Bids Open - National 53,966.00 54,550.97 Signed 2016-11-15 2016-10-14 2016-11-20 2017-01-01 2016-11-30 2017-03-16 2016-12-08 2017-04-20 2016-12-22 2017-10-17 System Envelope Drain IN-UPBSN-3378-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 129,990.00 127,775.73 Signed 2016-11-15 2016-10-08 2016-11-20 2017-01-01 2016-11-22 2017-03-16 2016-12-13 2017-04-20 2016-12-27 2017-10-17 Rehabilitation of Kesrua Drain System Envelope IN-UPBSN-3380-CW-RFB / 2. Improvement of Drainage Single Stage - Two Rehabilitation of Sonthal Ext. IDA / 46400 Post Request for Bids Open - National 89,119.00 88,321.45 Signed 2016-11-15 2016-10-10 2016-11-20 2017-01-01 2016-11-22 2017-03-16 2016-12-13 2017-04-20 2016-12-27 2017-10-17 System Envelope Drain IN-UPBSN-3381-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 47,917.00 50,124.35 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-09 2017-03-16 2016-11-22 2017-04-20 2016-12-22 2017-10-17 Rehabilitation of Kheoli-1 Drain System Envelope IN-UPBSN-3383-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 27,705.00 28,761.56 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-09 2017-03-16 2016-11-22 2017-04-20 2016-12-22 2017-10-17 Rehabilitation of Barethi Drain System Envelope IN-UPBSN-3384-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 35,874.00 22,811.11 Signed 2016-11-15 2016-09-27 2016-11-20 2017-01-01 2016-11-21 2017-03-16 2016-11-28 2017-04-20 2016-12-22 2017-10-17 Rehabilitation of Kursi Drain System Envelope IN-UPBSN-3385-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 25,832.00 23,881.74 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-09 2017-03-16 2016-11-22 2017-04-20 2016-12-22 2017-10-17 Rehabilitation of Meerpur Drain System Envelope IN-UPBSN-3386-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 29,516.00 28,499.34 Signed 2016-11-15 2016-09-27 2016-11-20 2017-01-01 2016-11-21 2017-03-16 2016-11-28 2017-04-20 2016-12-17 2017-10-17 Rehabilitation of Ukhadi Drain System Envelope IN-UPBSN-3388-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 49,644.00 51,889.61 Completed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-09 2017-03-16 2016-11-22 2017-04-20 2016-12-24 2017-10-17 2017-03-25 Rehabilitation of Naiya Nala Drain System Envelope IN-UPBSN-3389-CW-RFB / 2. Improvement of Drainage Single Stage - Two Rehabilitation of Ambar(Kamoli) IDA / 46400 Post Request for Bids Open - National 53,153.00 53,811.24 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-09 2017-03-16 2016-11-22 2017-04-20 2016-12-22 2017-10-17 System Envelope Drain IN-UPBSN-3391-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 45,974.00 56,525.14 Signed 2016-11-15 2016-09-25 2016-11-20 2017-01-01 2016-11-18 2017-03-16 2016-12-05 2017-04-20 2016-12-24 2017-10-17 Rehabilitation of Barhad Drain System Envelope IN-UPBSN-3392-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 25,736.00 29,656.69 Signed 2016-11-15 2016-11-06 2016-11-20 2017-01-01 2016-12-20 2017-03-16 2016-12-21 2017-04-20 2016-12-29 2017-10-17 Rehabilitation of Jor Drain System Envelope IN-UPBSN-3396-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 50,622.00 34,872.72 Signed 2016-11-15 2016-10-20 2016-11-20 2017-01-01 2016-12-07 2017-03-16 2016-12-17 2017-04-20 2016-12-29 2017-10-17 Rehabilitation of Kansuwa Drain System Envelope IN-UPBSN-3401-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 73,551.00 55,416.41 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-10 2017-03-16 2016-11-23 2017-04-20 2016-12-24 2017-10-17 Rehabilitation of Kushiya Drain System Envelope IN-UPBSN-3402-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 61,830.00 62,484.80 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-10 2017-03-16 2016-11-23 2017-04-20 2016-12-30 2017-10-17 Rehabilitation of Nandaut Drain System Envelope IN-UPBSN-3404-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 25,660.00 21,099.93 Signed 2016-11-15 2016-09-21 2016-11-20 2017-01-01 2016-11-09 2017-03-16 2016-11-16 2017-04-20 2016-12-14 2017-10-17 Rehabilitation of Ramgarh Drain System Envelope IN-UPBSN-3405-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 64,274.00 51,770.69 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-10 2017-03-16 2016-11-23 2017-04-20 2016-12-24 2017-10-17 Rehabilitation of Purkhipur Drain System Envelope IN-UPBSN-3407-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 81,761.00 76,722.20 Signed 2016-11-15 2016-09-22 2016-11-20 2017-01-01 2016-11-10 2017-03-16 2016-11-23 2017-04-20 2016-12-24 2017-10-17 Rehabilitation of Hasanpur Drain System Envelope IN-UPBSN-3409-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 43,559.00 42,314.01 Signed 2016-11-15 2016-10-10 2016-11-20 2017-01-01 2016-11-29 2017-03-16 2016-12-09 2017-04-20 2016-12-22 2017-10-17 Rehabilitation of Bhagohi Drain System Envelope IN-UPBSN-3414-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 102,091.00 77,889.75 Signed 2016-11-15 2017-05-10 2016-11-20 2017-01-01 2017-06-15 2017-03-16 2017-07-14 2017-04-20 2017-08-24 2017-10-17 Rehabilitation of Jamo Drain System Envelope IN-UPBSN-3412-CW-RFB / 2. Improvement of Drainage Single Stage - Two IDA / 46400 Post Request for Bids Open - National 35,155.00 33,591.50 Signed 2017-01-09 2016-12-10 2017-01-14 2017-02-25 2017-03-25 2017-05-10 2017-03-29 2017-06-14 2017-04-24 2017-12-11 Rehabilitation of Pithanpur Drain System Envelope IN-UPBSN-3413-CW-RFB / 2. Improvement of Drainage Single Stage - Two Rehabilitation of Biraichamau IDA / 46400 Post Request for Bids Open - National 34,316.00 29,732.30 Signed 2017-01-12 2017-05-10 2017-01-17 2017-02-28 2017-06-15 2017-05-13 2017-07-26 2017-06-17 2017-08-26 2017-12-14 System Envelope Drain IN-UPBSN-28802-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Dhakwa drain in IDA / 46400 Post Request for Bids Open - National 47,390.00 0.00 2017-09-15 2017-09-04 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation District Unnao IN-UPBSN-28803-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Kamapur drain IDA / 46400 Post Request for Bids Open - National 26,378.00 0.00 2017-09-15 2017-08-24 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation in District Amethi IN-UPBSN-28807-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Khande Khera IDA / 46400 Post Request for Bids Open - National 29,650.00 0.00 2017-09-15 2017-08-24 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation drain in District Raibareli. IN-UPBSN-28808-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Kapoorpur drain IDA / 46400 Post Request for Bids Open - National 35,777.00 0.00 2017-09-15 2017-07-26 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation in District Raibareli Page 2 IN-UPBSN-28809-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Lachchan Ka IDA / 46400 Post Request for Bids Open - National 31,431.00 0.00 2017-09-15 2017-08-24 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation Purwa drain in District Raibareli IN-UPBSN-28810-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Gadkhara drain IDA / 46400 Post Request for Bids Open - National 22,044.00 0.00 2017-09-15 2017-08-24 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation in District Varanashi IN-UPBSN-28811-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Karkhiyon drain IDA / 46400 Post Request for Bids Open - National 34,858.00 0.00 2017-09-15 2017-08-26 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation in District Varanashi IN-UPBSN-28812-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Bharathipur IDA / 46400 Post Request for Bids Open - National 21,836.00 0.00 2017-09-15 2017-08-26 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation drain in District Varanashi IN-UPBSN-28815-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Atthi drain in IDA / 46400 Post Request for Bids Open - National 38,691.00 0.00 2017-09-15 2017-08-26 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation District Varanashi IN-UPBSN-28816-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Dasrathpur drain IDA / 46400 Post Request for Bids Open - National 44,209.00 0.00 2017-09-15 2017-08-26 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation in District Varanashi IN-UPBSN-28818-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Devpur drain in IDA / 46400 Post Request for Bids Open - National 23,432.00 0.00 2017-09-15 2017-08-26 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation District Kannuj IN-UPBSN-28820-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Mehi drain in IDA / 46400 Post Request for Bids Open - National 32,349.00 0.00 2017-09-15 2017-09-04 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation District Sahajahanpur IN-UPBSN-28821-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Nagar drain in IDA / 46400 Post Request for Bids Open - National 52,611.00 0.00 2017-09-15 2017-09-02 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation District Kashganj IN-UPBSN-28822-CW-RFB / 2. Improvement of Drainage Single Stage - Two Under Rehabilitation of Aghar drain in IDA / 46400 Post Request for Bids Open - National 65,276.00 0.00 2017-09-15 2017-09-06 2017-09-20 2017-11-01 2018-01-14 2018-02-18 2018-08-17 System Envelope Implementation District Sahajahanpur IN-UPBSN-68884-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Kalua drain in IDA / 46400 Post Limited 14,628.00 0.00 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope Implementation District Unnao IN-UPBSN-68886-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Dewara drain in IDA / 46400 Post Limited 18,499.00 0.00 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope Implementation District Unnao IN-UPBSN-68887-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Chhichha-II drain IDA / 46400 Post Open - National 18,262.00 0.00 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope Implementation in District Amethi IN-UPBSN-68889-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Fatepur drain in IDA / 46400 Post Open - National 1,627.00 0.00 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope Implementation District Varanashi IN-UPBSN-68890-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Kadihad drain in IDA / 46400 Post Open - National 18,451.00 0.00 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope Implementation District Varanashi IN-UPBSN-68892-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Devpur Link IDA / 46400 Post Limited 10,373.00 0.00 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope Implementation drain in District Kannuj IN-UPBSN-68893-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Kharja drain in IDA / 46400 Post Limited 9,777.00 0.00 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope Implementation District Hardoi IN-UPBSN-68895-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Kamalapur-II IDA / 46400 Post Request for Bids Open - National 58,492.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation drain in District Raibareli IN-UPBSN-68898-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Pothai Cut drain IDA / 46400 Post Request for Bids Open - National 33,102.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Raibareli IN-UPBSN-68901-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Marui drain in IDA / 46400 Post Request for Bids Open - National 35,777.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Varanashi IN-UPBSN-68902-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Majhwa drain in IDA / 46400 Post Request for Bids Open - National 31,192.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Varanashi IN-UPBSN-68904-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Gajokhar drain IDA / 46400 Post Request for Bids Open - National 38,510.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Varanashi IN-UPBSN-68905-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Debethua drain IDA / 46400 Post Request for Bids Open - National 102,749.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Varanashi IN-UPBSN-68906-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Malhathdrain in IDA / 46400 Post Request for Bids Open - National 97,888.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Varanashi IN-UPBSN-68908-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Kuwar drain in IDA / 46400 Post Request for Bids Open - National 128,040.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Varanashi IN-UPBSN-68909-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Panser drain in IDA / 46400 Post Request for Bids Open - National 52,682.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Sahajahanpur Page 3 IN-UPBSN-68911-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Kharaua drain in IDA / 46400 Post Request for Bids Open - National 52,221.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Sahajahanpur IN-UPBSN-68912-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Sota drain in IDA / 46400 Post Request for Bids Open - National 53,844.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Sahajahanpur IN-UPBSN-68917-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Sendha drain in IDA / 46400 Post Request for Bids Open - National 99,306.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Sahajahanpur IN-UPBSN-68918-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Shripalpur drain IDA / 46400 Post Request for Bids Open - National 36,723.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Sitapur IN-UPBSN-68919-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Shivsinghpur IDA / 46400 Post Request for Bids Open - National 32,141.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation drain in District Sitapur IN-UPBSN-68921-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Tedwadundhiya IDA / 46400 Post Request for Bids Open - National 89,718.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation drain in District Sitapur IN-UPBSN-68922-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Chopariya drain IDA / 46400 Post Request for Bids Open - National 26,869.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Sitapur IN-UPBSN-68923-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Gujreheta drain IDA / 46400 Post Request for Bids Open - National 73,149.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Sitapur IN-UPBSN-68925-CW-RFB / Rehabilitation of 2. Improvement of Drainage Single Stage - Two Pending IDA / 46400 Post Request for Bids Open - National 45,881.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 Nawagaondundpur drain in System Envelope Implementation District Sitapur IN-UPBSN-68926-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Ranipurgrant IDA / 46400 Post Request for Bids Open - National 131,983.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation Ext. drain in District Unnao IN-UPBSN-68928-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Methitikur drain IDA / 46400 Post Request for Bids Open - National 78,516.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Unnao IN-UPBSN-68930-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Garha drain in IDA / 46400 Post Request for Bids Open - National 49,984.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Unnao IN-UPBSN-68931-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Gauriya drain in IDA / 46400 Post Request for Bids Open - National 34,901.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Lucknow IN-UPBSN-68940-CW-RFB / 2. Improvement of Drainage Single Stage - Two Rehabilitation of Nagram Ext. IDA / 46400 Post Request for Bids Open - National 35,877.00 0.00 Canceled 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope drain in District Lucknow IN-UPBSN-68941-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Maharajganj IDA / 46400 Post Request for Bids Open - National 59,274.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation Ext. drain in District Lucknow IN-UPBSN-68942-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Abbasnagar Ext. IDA / 46400 Post Request for Bids Open - National 65,840.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation drain in District Lucknow IN-UPBSN-68943-CW-RFB / 2. Improvement of Drainage Single Stage - Two Rehabilitation of Mitauli Ext. IDA / 46400 Post Request for Bids Open - National 23,613.00 0.00 Canceled 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope drain in District Lucknow IN-UPBSN-68944-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Saital drain in IDA / 46400 Post Request for Bids Open - National 60,828.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Hardoi IN-UPBSN-68946-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Chhoha drain in IDA / 46400 Post Request for Bids Open - National 113,718.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Hardoi IN-UPBSN-68948-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Jamuniya drain IDA / 46400 Post Request for Bids Open - National 116,270.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Barabanki IN-UPBSN-68949-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Mainapar drain IDA / 46400 Post Request for Bids Open - National 52,547.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation in District Barabanki IN-UPBSN-68951-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Saifpur drain in IDA / 46400 Post Request for Bids Open - National 100,102.00 0.00 2018-07-10 2018-07-15 2018-08-26 2018-11-08 2018-12-13 2019-06-11 System Envelope Implementation District Barabanki IN-UPBSN-72845-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Nadar drain in IDA / 46400 Post Request for Bids Open - National 56,211.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-11-05 2018-11-12 2018-12-15 System Envelope Implementation District Jaunpur IN-UPBSN-72847-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Mahandru drain IDA / 46400 Post Request for Bids Open - National 57,071.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-26 2018-10-03 2018-12-15 System Envelope Implementation in District Jaunpur IN-UPBSN-72849-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Fattupur Kala IDA / 46400 Post Request for Bids Open - National 84,258.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-26 2018-10-03 2018-12-15 System Envelope Implementation drain in District Jaunpur IN-UPBSN-72850-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Semsi drain in IDA / 46400 Post Request for Bids Open - National 50,708.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-10-01 2018-10-06 2018-12-15 System Envelope Implementation District Faizabad Page 4 IN-UPBSN-72856-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Sihipur drain in IDA / 46400 Post Request for Bids Open - National 154,785.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-10-01 2018-10-06 2018-12-15 System Envelope Implementation District Faizabad IN-UPBSN-72859-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Baitu (betwa) IDA / 46400 Post Request for Bids Open - National 23,827.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-10-01 2018-10-06 2018-12-15 System Envelope Implementation drain in District Faizabad IN-UPBSN-72860-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Maraha drain in IDA / 46400 Post Request for Bids Open - National 138,933.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation District Faizabad IN-UPBSN-72865-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Madhanpatti IDA / 46400 Post Request for Bids Open - National 57,965.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation drain in District Azamgargh IN-UPBSN-72866-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Akbarpur Drain IDA / 46400 Post Request for Bids Open - National 52,956.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation drain in District Unnao IN-UPBSN-72877-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Saraiyan IDA / 46400 Post Request for Bids Open - National 53,185.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation Escape drain in District Unnao IN-UPBSN-72878-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Hardoia drain in IDA / 46400 Post Request for Bids Open - National 32,031.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation District Lucknow IN-UPBSN-72879-CW-RFB / Rehabilitation of 2. Improvement of Drainage Single Stage - Two Pending IDA / 46400 Post Request for Bids Open - National 44,952.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 Bhatehata(Bheraha) drain in System Envelope Implementation District Barabanki IN-UPBSN-72881-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Siswai drain in IDA / 46400 Post Request for Bids Open - National 29,230.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation District Barabanki IN-UPBSN-72882-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Godein Gaon IDA / 46400 Post Request for Bids Open - National 34,185.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation drain in District Amethi IN-UPBSN-72883-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of KahiravExt. IDA / 46400 Post Request for Bids Open - National 23,698.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation drain in District Varanashi IN-UPBSN-72884-CW-RFB / 2. Improvement of Drainage Single Stage - Two Pending Rehabilitation of Fattupur drain IDA / 46400 Post Request for Bids Open - National 70,985.00 0.00 2018-08-06 2018-08-11 2018-09-22 2018-09-28 2018-10-08 2018-12-15 System Envelope Implementation in District Varanashi IN-UPBSN-72885-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Bahabrmau IDA / 46400 Post Limited 7,254.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation drain in District Faizabad IN-UPBSN-72886-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Nadgara drain in IDA / 46400 Post Limited 1,767.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation District Kannuj IN-UPBSN-72887-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Changauli Cut IDA / 46400 Post Limited 6,722.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation drain in District Bulandshar IN-UPBSN-72888-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Bailana drain in IDA / 46400 Post Limited 10,621.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation District Bulandshar IN-UPBSN-72890-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Sakahan drain in IDA / 46400 Post Limited 17,392.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation District Unnao IN-UPBSN-72891-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Kulaha Bagaha IDA / 46400 Post Limited 5,442.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation drain in District Unnao IN-UPBSN-72893-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Pahi Hardo drain IDA / 46400 Post Limited 4,238.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation in District Unnao IN-UPBSN-72894-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Navinagar drain IDA / 46400 Post Limited 3,855.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation in District Lucknow IN-UPBSN-72895-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Mamaimau drain IDA / 46400 Post Limited 4,401.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation in District Lucknow IN-UPBSN-72896-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Khagapur drain IDA / 46400 Post Limited 1,604.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation in District Lucknow IN-UPBSN-72897-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Bajgiha drain in IDA / 46400 Post Limited 5,008.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation District Lucknow IN-UPBSN-72898-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Haidarganj drain IDA / 46400 Post Limited 17,616.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation in District Barabanki IN-UPBSN-72899-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Newada drain in IDA / 46400 Post Limited 2,712.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation District Varanashi IN-UPBSN-72900-CW-RFQ / 2. Improvement of Drainage Request for Single Stage - One Pending Rehabilitation of Kahirav-1 drain IDA / 46400 Post Limited 15,213.00 0.00 2018-08-11 2018-10-06 2018-12-15 System Quotations Envelope Implementation in District Varanashi Page 5 GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4. Institutional Strengthening and Capacity Building for Market Access WBR 31 / Supply, Installation, 1. On-Farm Development and Commissioning, Maintenance Single Stage - One IDA / 46400 Land Treatment Prior Request for Bids Open - International N 2,000,000.00 1,619,921.14 Signed 2014-10-08 2014-11-11 and Operations of the Information Envelope 2. Improvement of Drainage Systems System 3. Agriculture Support Service 5. Project Management 4. Institutional Strengthening and Capacity Building for Market Access 1. On-Farm Development and Single Stage - One WBR 37 / Gypsum (PY5) IDA / 46400 Land Treatment Prior Request for Bids Open - International N 0.00 6,943,317.46 Signed 2015-01-06 2015-01-10 Envelope 2. Improvement of Drainage System 3. Agriculture Support Service 5. Project Management 4. Institutional Strengthening and Capacity Building for Market Access 1. On-Farm Development and Single Stage - One WBR 38 / Gypsum (PY-6) IDA / 46400 Land Treatment Prior Request for Bids Open - International N 0.00 5,118,880.36 Signed 2016-01-11 2016-01-15 Envelope 2. Improvement of Drainage System 3. Agriculture Support Service 5. Project Management IN-UPBSN-1689-GO-RFQ / Procurement of fertilizers (Urea, 1. On-Farm Development and Request for Single Stage - One IDA / 46400 Post Open - National 721,161.00 641,318.90 Signed 2016-09-25 2016-11-20 2016-11-18 2017-05-19 DAP, MOP ) for Rabi PY-6 for Land Treatment Quotations Envelope UPSLRIII P IN-UPBSN-1692-GO-RFQ / Procurement of wheat seed for 1. On-Farm Development and Request for Single Stage - One Under sodic area and Barley, Rape IDA / 46400 Post Open - National 933,093.00 599,672.51 2016-09-26 2016-11-21 2017-05-20 Land Treatment Quotations Envelope Implementation seed, Chik pea, wheat seed and pea seed for ravine area IN-UPBSN-1687-GO-RFB / Procurement of 100 mm Flanged 1. On-Farm Development and Single Stage - One IDA / 46400 Post Request for Bids Open - National 46,549.00 49,347.04 Signed 2016-09-21 2016-09-27 2016-09-26 2016-11-07 2016-10-27 2016-12-07 2017-01-17 2017-01-11 2017-01-31 2017-07-10 No-Return valve for UPSLRIIIP for Land Treatment Envelope boring purposes IN-UPBSN-1688-GO-RFB / 1. On-Farm Development and Single Stage - One Procurement of zinc sulphate for IDA / 46400 Post Request for Bids Open - National 112,499.00 99,215.16 Signed 2016-09-21 2016-10-17 2016-09-26 2016-11-07 2016-10-17 2016-12-07 2016-10-24 2017-01-11 2016-11-08 2017-07-10 Land Treatment Envelope Rabi PY-6 of UPSLRIII P IN-UPBSN-1736-GO-RFB / Procurement of dhaincha seed 1. On-Farm Development and Single Stage - One IDA / 46400 Post Request for Bids Open - National 707,020.00 350,298.07 Signed 2016-11-30 2016-11-11 2016-12-05 2017-01-16 2016-12-12 2017-02-15 2016-12-22 2017-03-22 2017-01-17 2017-09-18 for green manuring for zaid -6 of Land Treatment Envelope UPSLRIIIP IN-UPBSN-1738-GO-RFB / 1. On-Farm Development and Single Stage - One Pending Procurement of NP-3 hume pipe IDA / 46400 Post Request for Bids Open - National 73,507.00 0.00 2016-11-30 2016-12-05 2017-01-16 2017-02-15 2017-03-22 2017-09-18 Land Treatment Envelope Implementation for PY-7 of UPSLRIII P IN-UPBSN-1673-GO-RFB / Procurement of agriculture grade 1. On-Farm Development and Single Stage - One gypsum powder for UPSLRIII P of IDA / 46400 Prior Request for Bids Open - International 10,200,978.00 5,751,104.38 Signed 2016-10-03 2016-11-07 2016-10-08 2016-11-10 2016-11-19 2016-12-26 2016-12-19 2017-01-21 2017-01-23 2017-01-31 2017-07-22 Land Treatment Envelope PY-7 under ICB procedure of the World Bank IN-UPBSN-1680-GO-RFB / Procurement of 110 MM 1. On-Farm Development and Single Stage - One IDA / 46400 Post Request for Bids Open - National 57,775.00 0.00 Canceled 2016-09-21 2016-09-26 2016-11-07 2016-12-07 2017-01-11 2017-07-10 unplasticised PVC pipe for boring Land Treatment Envelope in UPSLRIII P IN-UPBSN-4790-GO-RFQ / 110 1. On-Farm Development and Request for Single Stage - One Pending MM unplasticised PVC pipe for IDA / 46400 Post Open - National 49,000.00 0.00 2017-01-08 2017-03-05 2017-09-01 Land Treatment Quotations Envelope Implementation Boring work IN-UPBSN-15366-GO-RFQ / 1. On-Farm Development and Request for Single Stage - One Pending IDA / 46400 Post Limited 278,318.00 0.00 2017-05-22 2017-07-17 2018-01-13 Procurement of Paddy seed Land Treatment Quotations Envelope Implementation IN-UPBSN-15373-GO-RFQ / 1. On-Farm Development and Request for Single Stage - One Pending IDA / 46400 Post Limited 355,117.00 0.00 2017-05-23 2017-07-18 2018-01-14 Urea ,DAP and MOP Land Treatment Quotations Envelope Implementation IN-UPBSN-15392-GO-RFQ / procurement of Blackgram, 1. On-Farm Development and Request for Single Stage - One Pending Sesame, Moong , Sorghum, IDA / 46400 Post Limited 127,948.00 0.00 2017-06-03 2017-07-29 2018-01-25 Land Treatment Quotations Envelope Implementation Pearl Millet, Pigeon for Ravine area Kharif PY-6 IN-UPBSN-37536-GO-RFB / Procurement of Agriculture Grade 1. On-Farm Development and Single Stage - Two Gypsum Powder for UPSLR IIIP IDA / 46400 Prior Request for Bids Open - International 5,569,955.00 6,628,353.39 Signed 2017-11-20 2017-11-21 2017-11-25 2017-11-29 2018-01-06 2018-01-05 2018-03-21 2018-01-30 2018-04-25 2018-02-09 2018-10-22 Land Treatment Envelope of PY-8 under ICB procedure of World Bank. IN-UPBSN-33480-GO-RFB / 1. On-Farm Development and Single Stage - Two Procurement of Zinc Sulphate for IDA / 46400 Post Request for Bids Open - National 98,387.00 0.00 Canceled 2017-10-24 2017-10-29 2017-12-10 2018-02-22 2018-03-29 2018-09-25 Land Treatment Envelope Rabi PY-7 IN-UPBSN-38785-GO-RFB / Procurement of 100mm 1. On-Farm Development and Single Stage - Two unplastised PVC Pipe for UPSLR IDA / 46400 Post Request for Bids Open - National 52,801.00 32,688.09 Signed 2017-11-30 2017-11-28 2017-12-05 2018-01-16 2018-01-16 2018-03-31 2018-02-15 2018-05-05 2018-02-20 2018-11-01 Land Treatment Envelope IIIP of PY-8 for boring purposes.under NCB procedure. Page 6 IN-UPBSN-38787-GO-RFB / For Procurement of 100 MM FLANGED NON RETURN 1. On-Farm Development and Single Stage - Two IDA / 46400 Post Request for Bids Open - National 37,496.00 29,953.16 Signed 2017-11-30 2017-11-28 2017-12-05 2018-01-16 2018-01-16 2018-03-31 2018-02-12 2018-05-05 2018-02-20 2018-11-01 VALVE (REFLUX VALVE) for Land Treatment Envelope UPSLR IIIP of PY-8 for boring purposes. IN-UPBSN-38790-GO-RFB / FOR THE PROCUREMENT OF 1. On-Farm Development and Single Stage - Two IDA / 46400 Post Request for Bids Open - National 293,082.00 477,654.65 Signed 2017-11-30 2017-11-28 2017-12-05 2018-01-16 2018-01-08 2018-03-31 2018-02-28 2018-05-05 2018-04-10 2018-11-01 DHAINCHA SEED ZAID -7 for Land Treatment Envelope green manuring of UPSLRIIIP. IN-UPBSN-15378-GO-RFQ / 1. On-Farm Development and Single Stage - One Procurement of Zinc sulphate for IDA / 46400 Post Request for Bids Open - National 148,063.00 0.00 Canceled 2017-05-22 2017-05-27 2017-07-08 2017-08-07 2017-09-11 2018-03-10 Land Treatment Envelope Khariff PY-7 IN-UPBSN-39840-GO-RFQ / Procurement of wheat seed for sodic area(PY-7) and Barley, 1. On-Farm Development and Request for Single Stage - One Pending IDA / 46400 Post Open - National 923,077.00 0.00 2017-12-13 2018-02-07 2018-08-06 Rape seed, Chik pea, wheat Land Treatment Quotations Envelope Implementation seed and pea seed for ravine area(PY-6) IN-UPBSN-39856-GO-RFQ / Procurement of fertilizers (Urea, 1. On-Farm Development and Request for Single Stage - One Pending DAP, MOP ) for sodic Rabi PY-7 IDA / 46400 Post Open - National 538,462.00 0.00 2017-12-13 2018-02-07 2018-08-06 Land Treatment Quotations Envelope Implementation and ravine rabi PY-6 for UPSLRIII P IN-UPBSN-61451-GO-RFQ / 1. On-Farm Development and Request for Single Stage - One Pending IDA / 46400 Post Limited 313,285.00 0.00 2018-05-07 2018-07-02 2018-12-29 Paddy seed for Kharif crop PY-8 Land Treatment Quotations Envelope Implementation IN-UPBSN-63971-GO-RFQ / 1. On-Farm Development and Request for Single Stage - One Pending Procurement Of Urea, DAP IDA / 46400 Post Open - National 261,538.00 0.00 2018-05-29 2018-07-24 2019-01-20 Land Treatment Quotations Envelope Implementation Fertilizer For Sodic Kharif PY-8 IN-UPBSN-65935-GO-RFQ / Procurement of Fertilizer 1. On-Farm Development and Request for Single Stage - One Under IDA / 46400 Post Open - National 227,272.00 0.00 2018-06-13 2018-08-08 2019-02-04 (Urea,DAP& MOP) for Ravine Land Treatment Quotations Envelope Implementation Kharif PY-6&7. IN-UPBSN-65936-GO-RFQ / 1. On-Farm Development and Request for Single Stage - One Pending Procurement of Various Kharif IDA / 46400 Post Limited 122,470.00 0.00 2018-06-13 2018-08-08 2019-02-04 Land Treatment Quotations Envelope Implementation Seeds for Ravine PY-6&7 . IN-UPBSN-66727-GO-RFB / 1. On-Farm Development and Single Stage - Two Under Procurement of Zinc Sulphate IDA / 46400 Post Request for Bids Open - National 180,000.00 0.00 2018-06-15 2018-05-07 2018-06-20 2018-08-01 2018-06-07 2018-10-14 2018-11-18 2019-05-17 Land Treatment Envelope Implementation For PY-8 Kharif IN-UPBSN-73554-GO-RFQ / PROCUREMENT OF SEED 1. On-Farm Development and Request for Single Stage - One Pending IDA / 46400 Post Open - National 830,474.00 0.00 2018-08-15 2018-10-10 2018-11-09 FOR RABI CROP (SODIC PY-8 Land Treatment Quotations Envelope Implementation & RAVINE PY-7) 2018 IN-UPBSN-73556-GO-RFQ / Procurement of Fertilizer 1. On-Farm Development and Request for Single Stage - One Pending IDA / 46400 Post Open - National 803,692.00 0.00 2018-08-15 2018-10-10 2018-11-09 (Urea,DAP& MOP) for Sodic rabi Land Treatment Quotations Envelope Implementation PY-8 and Ravine rabi PY-7 NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4. Institutional Strengthening and Capacity Building for Market WBR 39 / Non-Consulting Access Services for rake handling, 1. On-Farm Development and Single Stage - One storage and transportation of IDA / 46400 Land Treatment Prior Request for Bids Open - National N 0.00 3,232,301.28 Signed 2016-01-22 2016-01-29 Envelope Gypsum and other agriculture 2. Improvement of Drainage inputs (2015) System 3. Agriculture Support Service 5. Project Management IN-UPBSN-1460-NC-RFB / NATIONAL COMPETITIVE BIDDING FOR SELECTION OF Single Stage - One IDA / 46400 5. Project Management Post Request for Bids Open - National 270,513.00 0.00 Canceled 2016-09-20 2016-09-25 2016-11-06 2016-12-06 2017-01-10 2017-07-09 SERVICE PROVIDER TO Envelope PROVIDE PERSONNEL FOR UPSLRIIIP IN-UPBSN-60301-NC-DIR / Hi ring Services of Man power, Pending IDA / 46400 3. Agriculture Support Service Post Direct Selection Direct 20,397.00 0.00 2018-04-23 2018-04-28 2018-06-02 2018-11-29 Motivator (Livestock) for Live Implementation stock activities. CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 4. Institutional Strengthening and Capacity Building for Market Access 1. On-Farm Development and Quality And Cost- WBR 36 / Internal Auditor IDA / 46400 Land Treatment Prior Open - International N 30,000.00 18,534.93 Signed 2014-03-04 2014-03-04 Based Selection 2. Improvement of Drainage System 3. Agriculture Support Service 5. Project Management INDIVIDUAL CONSULTANTS Page 7 Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-UPBSN-53519-CS-QCBS / Supervision of Construction, 2. Improvement of Drainage IDA / 46400 Post Direct Selection Direct 282,417.00 259,886.51 Signed 2018-03-19 2017-12-08 2018-03-29 2017-12-19 2018-06-02 2018-05-03 2018-11-29 Quality and Quantity Control Of System Drainage Works (2018-19) IN-UPBSN-61449-CS-CDS / Extension of Contract no. IDA / 46400 5. Project Management Post Direct Selection Direct 130,769.00 125,740.46 Signed 2018-05-02 2018-05-12 2018-07-16 2018-05-17 2019-01-12 09/2011-12 with External M&E Agency IN-UPBSN-63970-CS-CDS / Extension agreement of Consultant BAIF Development Pending IDA / 46400 3. Agriculture Support Service Post Direct Selection Direct 465,789.00 0.00 2018-05-24 2018-06-03 2018-08-07 2019-02-03 Research Foundation for Cattle Implementation Breeding Centre (Artificial Insemination Centre). IN-UPBSN-71772-CS-CDS / Amendment to the original 4. Institutional Strengthening Pending contract of Consultant M/s. IDA / 46400 and Capacity Building for Market Post Direct Selection Direct 76,662.00 0.00 2018-07-27 2018-08-06 2018-10-10 2018-12-15 Implementation BASICS Ltd. (Specialized Access Business Support Organization) Page 8