Yunnan Honghe Prefecture Diannan Center Urban Transport Project Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: August2014]: Revision 6 of Updated Procurement Plan, April 2018] 2. Date of General Procurement Notice: July 9, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year April 2018 to June 2020 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 10 million All 2. NCB (Goods) Above US$ 2 million First contract regardless value 3. ICB (Works) Above US$ 40 million All 4. NCB (Works) Above US$ 10 million First contract regardless value 5. (Non-Consultant Services) NA NA 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project 8369CN 06/01/2016 issued by Honghe PMO 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness : The updated procurement plan comprises of three categories, i) Category A including 12 civil works contracts with a total estimated value of US$82.80 million (6 prior-review contracts); ii) Category B including 6 goods contracts with a total estimated value of US$18.40 million (4 prior-review contracts); and iii) Category C including 8 July 9, 2010 consultancy services contracts with a total estimated value of US$2.66 million (4 prior- review contracts). [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 0 0 No Prior the ICB (Works) Summary of 6.25 1 No Prior the ICB (Goods) Summary of 82.80 12 No Post 1st the NCB contract (Works) of each subprojec t for Prior Review Summary of 12.15 3 No Post 1st the NCB contract (Goods) of each subprojec t for Prior Review Summary of 0 0 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$1 million 2. Single Source (Firms) Above US$1 million 3. Individual Above US$0.3 million 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.71 1 Prior number of contracts that will be let under QCBS Summary of 1.95 7 Prior/Pos CQS/SSS number of t contracts that will be let under other methods July 9, 2010 PROCUREMENT China : CN Yunnan Honghe Prefecture Diannan Center Urban Transport PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2018-05-18 2019-07-09 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P101525 GPN Date: Project Name: CN Yunnan Honghe Prefecture Diannan Center Urban Transport Loan / Credit No: IBRD / 83690 Executing Agency(ies): Honghe PMO WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JS-CW-03-A / South Bypass Under Package 1: To build South Single Stage - One IBRD / 83690 Prior Request for Bids Open - National 7,930,326.22 Implementati 2018-08-01 2018-08-06 2018-09-05 2018-09-19 2018-10-24 2020-02-16 Bypass K0+000-K1+320 and Envelope on K1+400-K3+140. JS-CW-03-B / South Bypass Under Single Stage - One Package 2: To build South IBRD / 83690 Prior Request for Bids Open - National 7,991,949.94 Implementati 2018-08-01 2018-08-06 2018-09-05 2018-09-19 2018-10-24 2020-02-16 Envelope Bypass K3+140-K6+465.419. on JS-CW-03-C / South Bypass Under Package 3: To build South Single Stage - One IBRD / 83690 Post Request for Bids Open - National 0.00 Implementati 2018-08-01 2018-08-06 2018-09-05 2018-09-19 2018-10-24 2020-02-16 Bypass's railway intersection Envelope on K1+320-K1+400. MZ-CW-05-01 / Jinhua Pending Road South Section: Single Stage - One IBRD / 83690 Post Request for Bids Open - National 0.00 Implementati 2018-10-27 2018-11-01 2018-12-01 2018-12-15 2019-01-04 2019-10-06 Reconstruction of south Envelope on section of Jinhua Road MZ-CW-13 / Integrated Intermodal Yard at Datiepu Pending Single Stage - One of Wenlan Town: To build IBRD / 83690 Post Request for Bids Open - National 0.00 Implementati 2018-09-26 2018-10-01 2018-10-31 2018-11-03 2018-11-23 2019-11-23 Envelope integrated intermodal yard on at Datiepu of Wenlan Town. MZ-CW-15 / Civil Works of Improving School Safety: Single Stage - One IBRD / 83690 Post Request for Bids Open - National 1,751,632.80 Signed 2018-06-26 2018-07-01 2018-07-31 2018-08-03 2018-08-23 2019-02-19 Civil works of improving Envelope school safety. JS-CW-04 / Ancilliary Request for Single Stage - One IBRD / 83690 Prior Open - National 0.00 Canceled 2019-03-16 2019-04-22 2019-07-21 works of the bus depots Quotations Envelope MZ-CW-09 / Integrated Request for Single Stage - One Station of Beijing South IBRD / 83690 Post Open - National 5,204,652.51 Signed 2019-04-02 2019-04-02 2019-04-02 2019-04-02 2019-04-02 2019-08-31 Proposals Envelope Road MZ-CW-14 / Non-corridor Request for Single Stage - One Road Bus Station Renovation IBRD / 83690 Post Open - National 5,135,158.42 Signed 2019-04-02 2019-04-02 2019-04-02 2019-04-02 2019-04-02 2019-05-31 Proposals Envelope and Construction JS-CW-02 / Public Request for Single Stage - One IBRD / 83690 Prior Open - National 2,356,125.96 Signed 2019-04-02 2019-04-02 2019-04-02 2019-04-02 2019-04-02 2019-08-31 transportation station Proposals Envelope JS-CW-03BA / South Pending Bypass Package 2: To build Single Stage - One IBRD / 83690 Prior Request for Bids Open - National 0.00 Implementati 2019-06-27 2019-06-27 2019-06-27 2019-06-27 2019-06-27 2020-09-27 South Bypass K3+140- Envelope on K6+465.419. Page 1 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual JS-GD-01 / Traffic Control Single Stage - One IBRD / 83690 Prior Request for Bids Open - National 6,061,089.04 Signed 2018-06-22 2018-06-30 2018-07-30 2018-08-19 2018-09-28 2019-03-27 and Monitoring Equipment Envelope JS-GD-02 / Bus Priority Single Stage - One IBRD / 83690 Prior Request for Bids Open - National 0.00 Canceled 2018-07-01 2018-07-15 2018-08-14 2018-08-28 2018-10-02 2019-03-31 Intelligent System Envelope MZ-GD-05 / Bus Priority Single Stage - One IBRD / 83690 Prior Request for Bids Open - National 5,800,270.93 Signed 2018-10-12 2018-11-01 2018-12-01 2018-12-15 2019-01-28 2019-07-27 Intelligent System Envelope Under JS-GD-07 / Fire prevention Request for Single Stage - One IBRD / 83690 Post Open - National 0.00 Implementati 2019-04-05 2019-05-31 2019-11-27 goods of the bus depots Quotations Envelope on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual HH-CS-06 / Public Consultant Open - Transportation Policy IBRD / 83690 Prior Qualification 226,237.59 Signed International Research Selection HH-CS-03 / Project Quality And Cost- Open - Management Consultant IBRD / 83690 Prior 704,735.50 Signed Based Selection International Selection HH-CS-01 / Parking and Traffic Calming Policy Consultant Open - Research, Planning the IBRD / 83690 Prior Qualification 245,002.18 Signed 2018-12-17 2018-12-17 2018-12-17 2018-12-17 2018-12-17 2019-12-17 International Implementation of Pilot Selection Programs INDIVIDUAL CONSULTANTS Page 2