Restructuring Status: Archived Restructuring Type: Level two Last modified on date : 02/20/2013 1. Basic Information Project ID & Name P087912: IQ-TF EMERG. BAGHDAD WATER SUPPLY Country Iraq Task Team Leader Caroline van den Berg Sector Manager/Director Lia Carol Sieghart Country Director Ferid Belhaj Original Board Approval Date 12/03/2004 Original Closing Date: 08/31/2007 Current Closing Date 06/30/2013 Proposed Closing Date [if applicable] EA Category C-Not Required Revised EA Category C-Not Required-Not Required EA Completion Date Revised EA Completion Date 2. Revised Financing Plan (US$m) Source Original Revised BORR 0.00 0.00 SPF 65.00 65.00 Total 65.00 65.00 3. Borrower Organization Department Location Republic of Iraq Iraq Republic of Iraq Iraq Mayoralty of Baghdad Mayoralty of Baghdad 4. Implementing Agency Organization Department Location i 5. Disbursement Estimates (US$m) Actual amount disbursed as of 03/04/2013 51.45 Fiscal Year Annual Cumulative 2013 0.00 51.45 Total 51.45 6. Policy Exceptions and Safeguard Policies Does the restructured project require any exceptions to Bank policies? N Does the restructured projects trigger any new safeguard policies? If yes, please select N from the checklist below and update ISDS accordingly before submitting the package. 7a. Project Development Objectives/Outcomes Original/Current Project Development Objectives/Outcomes The principal objective of the project is to assist in restoring basic water supply and sanitation services for the capital city of Baghdad through (a) the reconstruction and rehabilitation of existing priority networks and treatment facilities and (b) providing capacity building support through training and technical assistance. 7b. Revised Project Development Objectives/Outcomes [if applicable] ii