Procurement Plan Colombia - Plan PAZcifico: WSS Infrastructure & Service Delivery Project P156239 I. General 1. Bank’s approval Date of the procurement Plan: Original 2016/08/29; Revision 2016/12/15 and 2017/4/19 2. Date of General Procurement Notice: Dec 13, 2016 3. Period covered by this procurement plan: First 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank will be marked in the procurement plan according to the level of risk of the agency 2. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P156239 issued by National Unit For The Management Of Disaster Risk – UNGRD 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 40.00 1 No Prior the ICB (Works) Summary of 54.00 09 No Post the NCB (Works) Summary of 1.00 1 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank will be marked in the procurement plan according to the level of risk of the agency July 9, 2010 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_400,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 11.6 6 Post number of contracts that will be let under QCBS Summary of 1.6 5 Post CQS, LCBS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Colombia : CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project PLAN General Information Country: Colombia Bank’s Approval Date of the Original Procurement Plan: 2016-12-15 2019-09-02 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P156239 GPN Date: 2016-12-13 Project Name: CO Plan PAZcifico:Water Supply and Basic Sanitation Infrastructure and Service Delivery Project Loan / Credit No: IBRD / 86490 Executing Agency(ies): National Unit for the Management of Disaster Risk WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-002 / Acueducto Tumaco, Nariño. Component 2. Water Supply Aduccion: suministro e and Basic Sanitation Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 2,973,324.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 2019-06-04 instalacion de 5.5 km de Improvements in the ofertas Envelope tuberia en HD de 20" (1 de Municipality of Tumaco 4) PTSP-BIRF8649-003 / Acueducto Tumaco, Nariño. Optimización PTAP Buchelly (incluye: construccion empate Component 2. Water Supply con la nueva aduccion de and Basic Sanitation Solicitud de Single Stage - One 20", construccion 4 modulos IBRD / 86490 Posterior Open - National 1,547,966.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 2019-06-04 Improvements in the ofertas Envelope de desarenacion, Municipality of Tumaco mejoramiento sistema dosificacion coagulante, construccion 4 modulos de floculacion. (2 de 4) PTSP-BIRF8649-004 / Acueducto Tumaco, Nariño. Component 2. Water Supply Red matriz continental: and Basic Sanitation Solicitud de Single Stage - One suministro e instalacion de IBRD / 86490 Posterior Open - National 822,003.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 2019-06-04 Improvements in the ofertas Envelope 2229 metros de tuberia HD Municipality of Tumaco y suministro e instalacion de macromedidores. (3 de 4) PTSP-BIRF8649-005 / Acueducto Tumaco, Nariño. Component 2. Water Supply Suministro e instalacion de and Basic Sanitation Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 1,519,053.00 0.00 Cancelado 2017-07-06 2017-08-06 2017-09-24 2017-11-06 2017-12-11 2019-06-04 12331 metros de redes de Improvements in the ofertas Envelope distribucion de PVC RDE 21 Municipality of Tumaco (4 de 4) PTSP-BIRF8649-055 / CONSTRUCCION DE 7.800 M DE ADUCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMPLIACION DE LA PTAP Component 2. Water Supply BUCHELLI EN 50 LPS, and Basic Sanitation Solicitud de Open - Single Stage - One CONSTRUCCION DE 2.231 IBRD / 86490 Posterior 7,779,897.00 0.00 Cancelado 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2019-01-09 Improvements in the ofertas International Envelope M DE RED MATRIZ EN Municipality of Tumaco TUBERIA HD, CONSTRUCCION DE 15.298 M DE REDES DE DISTRIBUCION EN TUBERIA PVC-POI SEGUNDO Q Page 1 PTSP-BIRF8649-045 / CONSTRUCCION DE 5.500 M DE ADUCCION EN TUBERIA EN HD DE 20", OPTIMIZACION Y AMPLIACION DE LA PTAP Component 2. Water Supply BUCHELLI EN 50 LPS, and Basic Sanitation Solicitud de Single Stage - One CONSTRUCCION DE 2.231 IBRD / 86490 Posterior Open - National 6,862,347.00 0.00 Cancelado 2017-08-25 2017-08-30 2017-10-11 2017-11-10 2017-12-15 2018-09-11 Improvements in the ofertas Envelope M DE RED MATRIZ EN Municipality of Tumaco TUBERIA HD, CONSTRUCCION DE 15.298 M DE REDES DE DISTRIBUCION EN TUBERIA PVC - POI SEGUNDO QUINQ PTSP-BIRF8649-018 / “Red Component 2. Water Supply Menor de  distribución de la and Basic Sanitation Solicitud de Single Stage - One zona continental fase 2 en IBRD / 86490 Posterior Open - National 1,724,138.00 0.00 Cancelado 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2020-05-13 Improvements in the ofertas Envelope el Municipio de Tumaco, Municipality of Tumaco Departamento de Nariño” PTSP-BIRF8649-017 / “Construcción segunda fase Component 2. Water Supply de 20” en tubería de hierro and Basic Sanitation Solicitud de Single Stage - One dúctil para aducción, IBRD / 86490 Posterior Open - National 1,436,782.00 0.00 Cancelado 2018-02-01 2018-02-06 2018-03-20 2018-04-19 2018-05-24 2019-05-19 Improvements in the ofertas Envelope Municipio de San Andrés de Municipality of Tumaco Tumaco, Departamento de Nariño” PTSP-BIRF8649-014 / Component 1. Water Supply Construcción del sistema and Basic Sanitation Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 1,353,180.00 0.00 Cancelado 2018-06-01 2018-06-06 2018-07-18 2018-08-17 2018-09-21 2020-09-10 definitivo de disposición final Improvements in the ofertas Envelope de residuos. Municipality of Guapi PTSP-BIRF8649-013 / Component 1. Water Supply Construccion del Sistema de and Basic Sanitation Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 12,865,288.00 0.00 Cancelado 2018-04-02 2018-05-01 2018-06-12 2018-07-12 2018-08-16 2021-07-31 Manejo de las Aguas Improvements in the ofertas Envelope Residuales Casco Urbano Municipality of Guapi PTSP-BIRF8649-019 / Component 2. Water Supply Construcción nuevo relleno and Basic Sanitation Solicitud de Single Stage - One IBRD / 86490 Posterior Open - National 4,281,100.00 0.00 Cancelado 2018-07-01 2018-07-06 2018-08-17 2018-09-16 2018-10-21 2019-04-19 sanitario del municipio de Improvements in the ofertas Envelope Tumaco Municipality of Tumaco PTSP-BIRF8649-074 / "OBRAS DE OPTIMIZACION Y AMPLIACION DEL SISTEMA DE Component 2. Water Supply ACUEDUCTO DEL and Basic Sanitation Solicitud de Single Stage - One DISTRITO ESPECIAL DE IBRD / 86490 Posterior Open - National 13,263,597.00 0.00 En ejecución 2019-03-04 2019-03-06 2019-04-03 2019-05-03 2019-06-07 2020-11-28 Improvements in the ofertas Envelope TUMACO FASE II, Municipality of Tumaco COMPONENTES PARA EL ABASTECIMIENTO A LOS SECTORES DE CONTINENTE E ISLA TUMACO". PTSP-BIRF8649-076 / "OBRAS DE OPTIMIZACION Y Component 2. Water Supply AMPLIACION DEL and Basic Sanitation Solicitud de Single Stage - One SISTEMA DE ACUEDUCTO IBRD / 86490 Posterior Open - National 7,700,000.00 0.00 En ejecución 2019-04-30 2019-05-05 2019-06-04 2019-06-29 2019-08-03 2020-07-28 Improvements in the ofertas Envelope DEL DISTRITO ESPECIAL Municipality of Tumaco DE TUMACO FASE I, DEPARTAMENTO DE NARIÑO, COLOMBIA" Page 2 PTSP-BIRF8649-064 / Construcción de 7.800 m de aducción tubería hd 20", optimización y ampliación Component 2. Water Supply PTAP Buchelli 50 lps, and Basic Sanitation Solicitud de Single Stage - One construcción de 2.231 m red IBRD / 86490 Posterior Open - National 7,733,591.00 0.00 Cancelado 2018-12-28 2019-01-02 2019-02-13 2019-03-15 2019-04-19 2020-04-13 Improvements in the ofertas Envelope matriz tubería hd, Municipality of Tumaco construccion de 15.298 m redes de distribución tubería pvc - poi segundo quinquenio del municipio de Tumaco PTSP-BIRF8649-083 / “OPTIMIZACION Y AMPLIACION DEL Component 1. Water Supply SISTEMA DE ACUEDUCTO and Basic Sanitation Solicitud de Single Stage - One DE LA CABECERA IBRD / 86490 Posterior Open - National 4,500,000.00 0.00 En ejecución 2019-07-10 2019-07-12 2019-08-09 2019-09-08 2019-10-13 2021-04-05 Improvements in the ofertas Envelope MUNICIPAL DE GUAPI, Municipality of Guapi DEPARTAMENTO DEL CAUCA, COLOMBIA – ETAPA I” GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-053 / and Basic Sanitation Solicitud de Single Stage - One Programa de monitoreo de IBRD / 86490 Posterior Limited 17,242.00 0.00 Cancelado 2017-12-27 2018-02-21 2018-05-22 Improvements in the cotizaciones Envelope aguas sub-superficiales Municipality of Guapi PTSP-BIRF8649-078 / ADQUISICIÓN EN MODALIDAD DE ARRENDAMIENTO DE UN Component 3. Capacity SOFTWARE INTEGRAL Building and Institutional QUE PERMITA A AGUAS Strengthening of Service Solicitud de Single Stage - One Ejecución DE TUMACO SA ESP, IBRD / 86490 Posterior Open - National 86,210.00 0.00 2019-04-30 2019-06-28 2020-04-11 Providers in the cotizaciones Envelope pendiente EJECUTAR EN FORMA Municipalities of Guapi and EFICIENTE EL CONTROL Tum aco DE LOS PROCESOS COMERCIALES, CONTABLES Y FINANCIEROS" CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Water Supply PTSP-BIRF8649-015 / and Basic Sanitation Selección basada Consultoría Restauración IBRD / 86490 Posterior Open - National 112,024.00 101,622.79 Firmado 2017-07-01 2017-07-22 2017-09-04 2017-10-02 2017-11-01 2017-12-06 2018-01-10 2018-08-08 Improvements in the en calidad y costo Urbana Municipality of Guapi Page 3 Component 3. Capacity PTSP-BIRF8649-021 / Building and Institutional Selección basada Asistencia fortalecimiento Strengthening of Service IBRD / 86490 Posterior en calificaciones Open - National 235,000.00 78,605.00 Firmado 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2020-09-28 institucional Aguas de Providers in the de consultores Tumaco en el area urbana Municipalities of Guapi and Tum aco Component 4. Project PTSP-BIRF8649-043 / Management and Selección basada IBRD / 86490 Posterior Open - National 450,000.00 0.00 Cancelado 2017-08-01 2017-09-01 2017-10-15 2017-11-12 2017-12-12 2018-01-16 2018-02-20 2019-02-15 Auditoria Externa Environmental and Social en calidad y costo Management Component 3. Capacity PTSP-BIRF8649-020 / Building and Institutional Aseguramiento en la Strengthening of Service Selección basada IBRD / 86490 Posterior Open - National 1,800,000.00 0.00 En ejecución 2018-06-01 2018-06-22 2018-08-05 2018-09-02 2018-10-02 2018-11-06 2018-12-11 2019-12-11 prestación de los servicios Providers in the en calidad y costo públicos Guapi. Municipalities of Guapi and Tum aco PTSP-BIRF8649-001 / Interventoría integral para Component 2. Water Supply obras de acueducto, and Basic Sanitation Selección basada Open - IBRD / 86490 Previa 6,266,775.00 0.00 Cancelado 2016-12-14 2017-01-28 2017-03-14 2017-04-13 2017-05-13 2017-06-12 2017-07-07 2023-07-06 alcantarillado y residuos Improvements in the en calidad y costo International sólidos en el Municipio de Municipality of Tumaco Tumaco. PTSP-BIRF8649-049 / Interventoria integral para Component 2. Water Supply obras de acueducto y and Basic Sanitation Selección basada Open - IBRD / 86490 Previa 5,762,334.24 0.00 En ejecución 2017-12-20 2018-01-12 2018-02-25 2018-03-25 2018-04-24 2018-05-29 2018-07-03 2022-07-02 alcantarillado y residuos Improvements in the en calidad y costo International sòlidos en el Municipio de Municipality of Tumaco Tumaco PTSP-BIRF8649-062 / REALIZAR LOS ESTUDIOS Y DISEÑOS PARA LA PLANTA DE TRATAMIENTO AGUAS Component 1. Water Supply RESIDUALES DEL and Basic Sanitation Selección basada IBRD / 86490 Posterior Open - National 259,310.00 0.00 Cancelado 2018-06-15 2018-07-06 2018-08-19 2018-09-16 2018-10-01 2018-10-19 2018-11-13 2019-06-11 MUNICIPIO DE GUAPI, Improvements in the en calidad y costo DEPARTAMENTO DEL Municipality of Guapi CAUCA, EN EL MARCO DEL FONDO PARA EL DESARROLLO DEL PLAN TODOS SOMOS PAZCÍFICO Component 3. Capacity PTSP-BIRF8649-041 / Building and Institutional Asistencia fortalecimiento Selección basada Strengthening of Service institucional Aguas de IBRD / 86490 Posterior en calificaciones Open - National 235,000.00 0.00 Cancelado 2018-06-01 2018-06-22 2018-08-05 2018-09-04 2018-10-09 2020-09-28 Providers in the Tumaco (para el piloto de la de consultores Municipalities of Guapi and politica en el area rural) Tum aco PTSP-BIRF8649-022 / Component 4. Project Implementacion del Plan de Management and Selección basada IBRD / 86490 Posterior Open - National 400,000.00 0.00 Cancelado 2017-11-01 2017-11-22 2018-01-05 2018-02-02 2018-03-04 2018-04-08 2018-05-13 2018-11-09 Informacion, Comunicacion y Environmental and Social en el menor costo Participacion Management PTSP-BIRF8649-016 / Component 1. Water Supply Interventoria Obras and Basic Sanitation Selección basada Alcantarillado, Acueducto y IBRD / 86490 Previa Open - National 2,333,451.00 0.00 Cancelado 2018-05-21 2018-06-11 2018-07-25 2018-08-22 2018-09-21 2018-10-26 2018-11-30 2019-11-30 Improvements in the en calidad y costo Residuos Solidos en Municipality of Guapi Municipio de Guapi Page 4 PTSP-BIRF8649-077 / INTERVENTORÍA TÉCNICA, ADMINISTRATIVA, FINANCIERA, CONTABLE, Component 3. Capacity AMBIENTAL, SOCIAL Y Building and Institutional JURÍDICA PARA LA Strengthening of Service Selección basada Ejecución "CONSULTORÍA DE IBRD / 86490 Posterior Open - National 211,800.00 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Providers in the en calidad y costo pendiente ACOMPAÑAMIENTO EN LA Municipalities of Guapi and OPERACIÓN DE LOS Tum aco SERVICIOS PÚBLICOS DE ACUEDUCTO, ALCANTARILLADO Y ASEO PARA EMGUAPI SAS ESP PTSP-BIRF8649-079 / FORTALECIMIENTO Y Component 3. Capacity ACOMPAÑAMIENTO EN LA Building and Institutional OPERACIÓN DE LOS Strengthening of Service Selección basada Ejecución SERVICIOS PÚBLICOS DE IBRD / 86490 Posterior Open - National 1,380,000.00 0.00 2019-04-30 2019-05-21 2019-07-04 2019-08-01 2019-08-31 2019-10-05 2019-11-09 2020-11-08 Providers in the en calidad y costo pendiente ACUEDUCTO, Municipalities of Guapi and ALCANTARILLADO Y ASEO Tum aco DEL OPERADOR DE GUAPI - FASE I, II Y III PTSP-BIRF8649-082 / Interventoría técnica, administrativa, financiera, Component 1. Water Supply legal, ambiental y social and Basic Sanitation Selección basada Open - para los estudios, diseños y IBRD / 86490 Previa 2,900,000.00 0.00 En ejecución 2019-07-10 2019-08-02 2019-09-15 2019-10-13 2019-11-12 2019-12-17 2020-01-21 2024-01-20 Improvements in the en calidad y costo International obras de los sistemas de Municipality of Guapi acueducto y alcantarillado y proyectos de residuos sólidos del municipio de Guapi. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PTSP-BIRF8649-010 / Apoyar el componente social, en el Departamento del Component 4. Project Cauca en la implementaciòn Management and y ejecuciòn del FDPTSP que IBRD / 86490 Posterior Individual Open 21,450.78 16,386.55 Finalizado 2017-05-11 2017-06-05 2017-06-15 2017-07-05 2018-07-05 Environmental and Social adelanta como entidad Management ejecutora la Unidad Nacional para la Gestiòn del Riesgo de Desastres. PTSP-BIRF8649-009 / Liderar el componente social, en la implementación y ejecución del Fondo para el Component 4. Project Desarrollo del Plan Todos Management and IBRD / 86490 Posterior Individual Open 82,299.37 62,869.64 Finalizado 2017-05-11 2017-06-11 2017-06-21 2018-07-01 2018-12-28 Somos Pazcífico que adelanta Environmental and Social como entidad ejecutora la Management Unidad Nacional para la Gestión del Riesgo de Desastres. Page 5 PTSP-BIRF8649-007 / Brindar apoyo al FTSP que adelanta como entidad ejecutora la Unidad Component 4. Project Nacional para la Gestión del Management and Riesgo de Desastres, en la IBRD / 86490 Posterior Individual Open 48,873.76 36,452.16 Firmado 2017-06-01 2017-06-16 2017-07-01 2017-07-21 2018-07-21 Environmental and Social viabilización de proyectos del Management componente de Agua y Saneamiento Básico, ante el Ministerio de Vivienda, Ciudad y Territorio - MVCT PTSP-BIRF8649-006 / Brindar apoyo al FTSP en la coordinación de las acciones y actividades al Component 4. Project interior del MVCT Management and IBRD / 86490 Posterior Individual Open 56,033.61 40,456.30 Firmado 2017-06-01 2017-06-16 2017-06-21 2017-07-02 2018-07-02 relacionadas con el crédito Environmental and Social para dar respuesta a los Management requerimientos de la Banca Multilateral y las entidades del gobierno nacional PTSP-BIRF8649-008 / Apoyar el componente social, en el Departamento de Nariño en la implementación Component 4. Project y ejecución del Fondo para Management and el Desarrollo del Plan Todos IBRD / 86490 Posterior Individual Open 21,450.78 1,660.60 Firmado 2017-05-18 2017-06-11 2017-06-26 2017-07-16 2018-07-16 Environmental and Social Somos Pazcífico que adelanta Management como entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. Component 4. Project PTSP-BIRF8649-024 / Apoyo Management and IBRD / 86490 Posterior Individual Open 17,908.97 12,960.77 Finalizado 2017-05-16 2017-07-04 2017-07-25 2017-08-29 2018-02-25 Administrativo (nivel técnico) Environmental and Social Management Component 4. Project PTSP-BIRF8649-028 / Lider Management and IBRD / 86490 Posterior Individual Direct 99,507.79 63,711.53 Finalizado 2017-03-01 2017-03-11 2017-04-01 2017-05-06 2017-11-02 de Adquisiciones Environmental and Social Management Component 4. Project PTSP-BIRF8649-029 / Management and IBRD / 86490 Posterior Individual Open 70,938.36 48,197.86 Finalizado 2017-04-01 2017-05-20 2017-06-10 2017-07-15 2018-01-11 Especialista Adquisiciones Environmental and Social Management Component 4. Project PTSP-BIRF8649-033 / Lider Management and IBRD / 86490 Posterior Individual Direct 93,771.65 61,167.00 Firmado 2017-04-01 2017-04-11 2017-05-02 2017-06-06 2017-12-03 Ambiental Environmental and Social Management Component 4. Project PTSP-BIRF8649-034 / Management and IBRD / 86490 Posterior Individual Open 56,458.32 36,452.16 Finalizado 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 Especialista ambiental Environmental and Social Management Component 4. Project PTSP-BIRF8649-035 / Lider Management and IBRD / 86490 Posterior Individual Direct 99,507.79 61,167.00 Firmado 2017-03-01 2017-03-11 2017-04-01 2017-05-06 2017-11-02 Componente Agua Environmental and Social Management Component 4. Project PTSP-BIRF8649-036 / Management and IBRD / 86490 Posterior Individual Direct 63,844.53 41,645.62 Firmado 2017-04-01 2017-04-11 2017-05-02 2017-06-06 2017-12-03 Especialista Proyectos Agua Environmental and Social Management Page 6 Component 4. Project PTSP-BIRF8649-037 / Management and IBRD / 86490 Posterior Individual Open 56,033.61 36,452.16 Firmado 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 Especialista Proyectos RSU Environmental and Social Management Component 4. Project PTSP-BIRF8649-038 / Management and Ingeniero de apoyo (Agua IBRD / 86490 Posterior Individual Open 35,053.71 16,386.55 Finalizado 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 Environmental and Social Tumaco) Management Component 4. Project PTSP-BIRF8649-039 / Management and Ingeniero de apoyo ( Agua IBRD / 86490 Posterior Individual Open 35,053.71 19,500.00 Finalizado 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 Environmental and Social Guapi) Management Component 4. Project PTSP-BIRF8649-040 / Apoyo Management and IBRD / 86490 Posterior Individual Open 16,742.07 12,960.77 Finalizado 2017-06-01 2017-07-20 2017-08-10 2017-09-14 2018-03-13 Administrativo (lideres) Environmental and Social Management Component 4. Project PTSP-BIRF8649-023 / Management and Coordinación General - LUZ IBRD / 86490 Posterior Individual Direct 116,664.30 71,591.30 Firmado 2017-03-01 2017-03-11 2017-04-01 2017-05-06 2017-11-02 Environmental and Social AMANDA PULIDO Management PTSP-BIRF8649-026 / Lider Component 4. Project Financiero - CLAUDIA Management and IBRD / 86490 Posterior Individual Direct 99,507.79 63,711.53 Finalizado 2017-03-01 2017-03-11 2017-04-01 2017-05-06 2017-11-02 AGUDELO SEDANO - Por Environmental and Social continuidad de Servicios Management PTSP-BIRF8649-031 / Lider Component 4. Project de Planeación y Seguimiento Management and - JUAN DE DIOS IBRD / 86490 Posterior Individual Direct 99,507.79 61,063.18 Firmado 2017-03-01 2017-03-11 2017-04-01 2017-05-06 2017-11-02 Environmental and Social CISNEROS - - Por Management continuidad de Servicios PTSP-BIRF8649-032 / Component 4. Project Especialista Planeación y Management and Seguimiento - JULIAN IBRD / 86490 Posterior Individual Direct 67,749.98 41,574.93 Firmado 2017-03-01 2017-03-11 2017-04-01 2017-05-06 2017-11-02 Environmental and Social ANDRES VALBUENA - Por Management continuidad de Servicios PTSP-BIRF8649-025 / Component 4. Project Asistente Financiero y Management and Administrativo - BEATRIZ IBRD / 86490 Posterior Individual Direct 37,173.93 0.00 Cancelado 2017-07-03 2017-07-13 2017-08-03 2017-09-07 2018-09-02 Environmental and Social PARRA - Continuidad de Management Servicios Component 4. Project PTSP-BIRF8649-048 / Tulio Management and fuentes Especialista en IBRD / 86490 Posterior Individual Direct 49,242.00 46,194.37 Firmado 2017-11-02 2017-11-07 2017-11-08 2017-11-10 2018-11-09 Environmental and Social Adquisiciones 2 Management Component 4. Project PTSP-BIRF8649-046 / Management and IBRD / 86490 Posterior Individual Open 49,242.00 0.00 Cancelado 2017-10-31 2017-11-06 2017-11-09 2017-11-13 2018-11-13 Especialista Adquisiciones 2 Environmental and Social Management Component 3. Capacity Building and Institutional PTSP-BIRF8649-044 / Strengthening of Service Especialista Fortalecimiento IBRD / 86490 Posterior Individual Open 49,242.00 47,560.97 Firmado 2017-08-18 2017-09-01 2017-09-03 2017-09-17 2018-09-12 Providers in the Institucional Municipalities of Guapi and Tum aco Page 7 PTSP-BIRF8649-51 / IEH GRUCON-Realizar los estudios y diseños de los proyectos priorizados para la Component 2. Water Supply optimización y ampliación and Basic Sanitation Selección directa del sistema de acueducto del IBRD / 86490 Posterior Direct 792,345.00 708,875.23 Firmado 2017-12-18 2017-12-31 2018-01-15 2019-01-10 Improvements in the de consultores municipio de Tumaco, Municipality of Tumaco departamento de Nariño, en el marco del Fondo para el Desarrollo del Plan Todos Somos PAZcífico Component 4. Project PTSP-BIRF8649-054 / Management and Selección directa KPMG-AUDITORIA IBRD / 86490 Posterior Direct 35,000.00 69,291.56 Firmado 2017-12-29 2018-01-08 2018-03-14 2018-09-10 Environmental and Social de consultores EXTERNA Management Component 1. Water Supply PTSP-BIRF8649-057 / and Basic Sanitation Antonio Nieto - Director de IBRD / 86490 Posterior Individual Direct 26,897.00 25,232.22 Firmado 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 Improvements in the Interventorìa Municipality of Guapi PTSP-BIRF8649-058 / Component 1. Water Supply Ramiro Gutierrez. and Basic Sanitation IBRD / 86490 Posterior Individual Direct 6,771.00 6,351.73 Firmado 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 Especialista Electro-mecànico Improvements in the de Interventorìa Municipality of Guapi Component 1. Water Supply PTSP-BIRF8649-060 / and Basic Sanitation Alvaro Bravo - Especialista IBRD / 86490 Posterior Individual Direct 9,233.00 8,661.44 Firmado 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 Improvements in the Geotecnista de Interventorìa Municipality of Guapi PTSP-BIRF8649-059 / Component 1. Water Supply Eduardo Gòmez - and Basic Sanitation IBRD / 86490 Posterior Individual Direct 9,233.00 0.00 Cancelado 2018-04-26 2018-04-27 2018-05-02 2018-05-07 2018-11-03 Especialista Estructural de Improvements in the Interventorìa Municipality of Guapi PTSP-BIRF8649-061 / Component 1. Water Supply FERNANDO VARGAS and Basic Sanitation IBRD / 86490 Posterior Individual Direct 9,233.00 8,661.44 Firmado 2018-05-07 2018-05-08 2018-05-13 2018-06-12 2018-12-09 RODRÍGUEZ. Especialista Improvements in the Estructural de Interventoria. Municipality of Guapi PTSP-BIRF8649-011 / Apoyar el componente social, en el Departamento del Component 4. Project Chocò, en la implementaciòn Management and y ejecuciòn del FDPTSP que IBRD / 86490 Posterior Individual Open 27,082.76 0.00 Cancelado 2017-04-07 2017-05-02 2017-05-12 2017-06-01 2018-06-01 Environmental and Social adelanta como entidad Management ejecutora la Unidad Nacional para la Gestiòn del Riesgo de Desastres. PTSP-BIRF8649-012 / Apoyar el componente social, en el Departamento del Component 4. Project Valle en la implementaciòn Management and y ejecuciòn del FDPTSP que IBRD / 86490 Posterior Individual Open 27,082.76 0.00 Cancelado 2017-04-07 2017-05-02 2017-05-12 2017-06-01 2018-06-01 Environmental and Social adelanta como entidad Management ejecutora la Unidad Nacional para la Gestiòn del Riesgo de Desastres. Component 4. Project PTSP-BIRF8649-030 / Apoyo Management and IBRD / 86490 Posterior Individual Open 26,159.48 0.00 Cancelado 2017-06-30 2017-07-21 2017-07-23 2017-07-27 2018-07-22 en adquisiciones Environmental and Social Management Component 4. Project PTSP-BIRF8649-042 / Management and Asistente Financiero y IBRD / 86490 Posterior Individual Open 37,173.93 0.00 Cancelado 2017-08-25 2017-10-13 2017-11-03 2017-12-08 2018-06-06 Environmental and Social Administrativo Management Page 8 CO-UNGRD-87418-CS-INDV / Brindar apoyo jurídico en la gestión predial y catastral de los bienes inmuebles que Component 1. Water Supply sean necesarios para la and Basic Sanitation viabilización de los proyectos IBRD / 86490 Posterior Individual Open 7,763.00 7,763.00 Firmado 2018-11-30 2019-01-18 2019-02-08 2019-03-15 2019-09-11 Improvements in the que se ejecutan en el marco Municipality of Guapi del Fondo para el Desarrollo del Plan Todos Somos Pazcífico, que adelanta como entidad Component 4. Project PTSP-BIRF8649-027 / Management and IBRD / 86490 Posterior Individual Open 63,844.53 0.00 En ejecución 2017-04-01 2017-05-20 2017-06-10 2017-07-15 2018-01-11 Especialista Financiero Environmental and Social Management PTSP-BIRF8649-063 / Liderar el componente de Agua y Saneamiento Básico, en la implementación y Component 4. Project ejecución del Fondo para el Management and Desarrollo del Plan Todos IBRD / 86490 Posterior Individual Open 34,200.00 34,200.00 Firmado 2018-12-26 2019-02-13 2019-03-06 2019-04-10 2019-10-07 Environmental and Social Somos Pazcífico que adelanta Management como entidad ejecutora la Unidad Nacional para la Gestión del Riesgo de Desastres. Component 4. Project PTSP-BIRF8649-072 / Management and Especialista de Adquisiciones IBRD / 86490 Posterior Individual Direct 53,560.00 26,780.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2020-03-12 Environmental and Social - Recontratación Pilar Valero Management PTSP-BIRF8649-073 / Component 4. Project Especialista de Adquisiciones Management and IBRD / 86490 Posterior Individual Direct 53,560.00 53,560.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-15 2020-03-09 - Recontratación Tulio Environmental and Social Fuentes Management PTSP-BIRF8649-075 / Component 4. Project Especialista Financiera - Management and IBRD / 86490 Posterior Individual Direct 53,560.00 26,780.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2020-03-12 Recontratación Sandra Environmental and Social Lorena Peña Management PTSP-BIRF8649-069 / Líder Component 4. Project de Adquisiciones - Management and IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2020-03-12 Recontratación Elkin Adolfo Environmental and Social Pinilla Cañón Management PTSP-BIRF8649-065 / Component 4. Project Directora Ejecutiva / Management and Coordinadora del Proyecto IBRD / 86490 Posterior Individual Direct 83,000.00 41,500.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2020-03-12 Environmental and Social FTSP - Recontratación Luz Management Amanda Pulido Component 4. Project PTSP-BIRF8649-067 / Líder Management and Ambiental - Recontratación IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2020-03-12 Environmental and Social Alejandra Catacoli Management Component 4. Project PTSP-BIRF8649-068 / Líder Management and Financiera - Recontratación IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2020-03-12 Environmental and Social Claudia Agudelo Management Component 4. Project PTSP-BIRF8649-066 / Líder Management and de Planeación y Seguimiento IBRD / 86490 Posterior Individual Direct 70,800.00 35,400.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2020-03-12 Environmental and Social - Luis Ignacio Alfonso Management Page 9 Component 4. Project PTSP-BIRF8649-070 / Líder Management and Social - Recontratación Kelly IBRD / 86490 Posterior Individual Direct 23,600.00 11,800.00 Firmado 2019-03-04 2019-03-11 2019-03-11 2019-03-18 2019-07-17 Environmental and Social Ruiz Management PTSP-BIRF8649-080 / Component 4. Project Especialista Social para la Management and Evaluación Social de los IBRD / 86490 Posterior Individual Open 13,140.00 0.00 Cancelado 2019-04-12 2019-04-29 2019-05-10 2019-05-20 2019-07-30 Environmental and Social municipios de Tumaco Management (Nariño) y Guapi (Cauca) PTSP-BIRF8649-084 / Electro Mecanico - Realizar apoyo a la Interventoría Integral de los contratos de Component 1. Water Supply Estudios y Diseños como and Basic Sanitation interventor en los aspectos IBRD / 86490 Posterior Individual Open 16,000.00 0.00 En ejecución 2019-07-10 2019-08-28 2019-09-18 2019-10-23 2020-04-20 Improvements in the eléctricos y mecánicos de los Municipality of Guapi proyectos de preinversión priorizados en el componente de Agua y Saneamiento Básico. PTSP-BIRF8649-081 / Dirección de Interventoría Integral de Estudios y Component 1. Water Supply Diseños de los proyectos de and Basic Sanitation IBRD / 86490 Posterior Individual Open 27,000.00 0.00 En ejecución 2019-06-25 2019-08-13 2019-09-03 2019-10-08 2020-04-05 preinversión priorizados en Improvements in the el componente de Agua y Municipality of Guapi Saneamiento Básico en el marco del préstamo BIRF. Component 4. Project PTSP-BIRF8649-085 / Líder Management and IBRD / 86490 Posterior Individual Open 20,000.00 0.00 En ejecución 2019-06-21 2019-08-09 2019-08-30 2019-10-04 2020-04-01 de Seguridad FTSP Environmental and Social Management Component 4. Project PTSP-BIRF8649-086 / Líder Management and Social - Recontratación Kelly IBRD / 86490 Posterior Individual Direct 47,200.00 0.00 En ejecución 2019-07-11 2019-07-12 2019-07-12 2019-07-18 2020-03-17 Environmental and Social Ruiz Management PTSP-BIRF8649-087 / Component 4. Project Especialista Social para la Management and Evaluación Social de los IBRD / 86490 Posterior Individual Open 13,140.00 0.00 Bajo Revision 2019-08-23 2019-09-09 2019-09-20 2019-09-30 2019-12-29 Environmental and Social municipios de Tumaco Management (Nariño) y Guapi (Cauca) PTSP-BIRF8649-089 / Topografo - Prestación de servicios profesionales para la realización de Component 1. Water Supply levantamientos topográficos and Basic Sanitation requeridos para el IBRD / 86490 Posterior Individual Open 13,800.00 0.00 En ejecución 2019-08-26 2019-10-14 2019-11-04 2019-12-09 2020-03-08 Improvements in the saneamiento de los predios Municipality of Guapi requeridos para la ejecución de los proyectos del Fondo para el Desarrollo del Plan Todos Somos PAZcífico. PTSP-BIRF8649-090 / Catastral - Brindar apoyo técnico catastral y de avalúos en la gestión predial Component 1. Water Supply de los bienes inmuebles que and Basic Sanitation sean necesarios para la IBRD / 86490 Posterior Individual Open 27,600.00 0.00 En ejecución 2019-08-26 2019-10-14 2019-11-04 2019-12-09 2020-06-08 Improvements in the viabilización de los proyectos Municipality of Guapi que se ejecutan en el marco del Fondo para el Desarrollo del Plan Todos Somos PAZcífico. Page 10 PTSP-BIRF8649-091 / Apoyo jurídico en las gestiones jurídicas y administrativas Component 1. Water Supply que se requiera adelantar and Basic Sanitation dentro del proceso de IBRD / 86490 Posterior Individual Open 16,000.00 0.00 Bajo Revision 2019-08-26 2019-10-14 2019-11-04 2019-12-09 2020-06-08 Improvements in the saneamiento, adquisición Municipality of Guapi predial y reasentamiento de población, a través de las modalidades de enajenación PTSP-BIRF8649-088 / Component 1. Water Supply Gestora Predial - and Basic Sanitation Ejecución Recontratación NINFA IBRD / 86490 Posterior Individual Direct 27,600.00 0.00 2019-08-30 2019-09-06 2019-09-06 2019-09-13 2020-03-12 Improvements in the pendiente LUCIA SANTANA Municipality of Guapi ESCOBAR. Page 11