Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: March 21, 2017 2. Date of General Procurement Notice: June 11, 2013 3. Period covered by this procurement plan: March 2017 to Feb 2018 II. Goods, Works, Consultant and Non-Consulting Services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Comments Threshold (PRT) US$ (Millions) 1. Works (Including turnkey, supply & 10 Substantial risk installation of plant and equipment and PPP) 2. (Goods; Information Technology & Non- 2 Substantial risk Consulting Services) 3. Consultant Services (Firms) 1 Substantial risk 4. Consultant Services (Individual Consultants) 0.3 Substantial risk 2. Prequalification. NA 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Available in Project files 5. Any Other Special Procurement Arrangements: NA 6. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 7. All TORs for the procurement of consultants services irrespective of the estimated cost of the assignment shall be reviewed and cleared by the TTL 8. Operating expenditures are neither subject to the Procurement and Consultant Guidelines nor prior or post reviews. Operating expenditures are normally verified by TTLs and FM specialists and obtained using the Borrower’s national procurement and administrative procedures. 9. Renewal or extension of individual consultant’s contracts hired for technical assistance and which are intended for a long-term period but signed for an initial period shorter than the duration of the project, and that have been prior reviewed, do not require procurement clearance if there is no substantial change in the terms and conditions of the contract. March 21, 2017 PROCUREMENT Kenya : Kenya Water Security and Climate Resilience Project PLAN General Information Country: Kenya Bank’s Approval Date of the Original Procurement Plan: 2017-03-01 2020-04-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P117635 GPN Date: Project Name: Kenya Water Security and Climate Resilience Project Loan / Credit No: IDA / 52680, IDA / 56740 Executing Agency(ies): Ministry of Water and Irrigation WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOWI-7904-CW-RFB / Program for the C1: Water Resources Single Stage - One Improvement of Water IDA / 52680 Post Request for Bids Open - National 5,266,602.84 Signed 2017-02-21 2017-03-07 2017-04-18 2017-05-18 2016-12-23 2017-06-22 2017-02-02 2019-12-09 Development Envelope Services in Mombasa County Likoni Area - Phase 1 KE-MOWI-11092-CW-RFB / Program for the C1: Water Resources Single Stage - One Improvement of Water IDA / 52680 Post Request for Bids Open - National 4,334,704.60 Signed 2017-04-28 2018-08-23 2017-05-12 2017-06-23 2017-10-05 2017-07-23 2018-10-17 2017-09-05 2017-12-22 2018-11-29 Development Envelope Services in Mombasa County West Mainland Area-Phase I KE-MOWI-13183-CW-RFB / Minor Construction Works C1: Water Resources Single Stage - One IDA / 56740 Post Request for Bids Open - National 0.00 Canceled 2017-05-30 2017-06-13 2017-07-25 2017-08-24 2017-09-28 2018-03-27 and Renovation of Storage Development Envelope Yards at MOWASCO KE-MOWI-16584-CW-RFB / CONSTRUCTION WORKS OF THE LOWER NZOIA PROJECT IN TWO LOTS C1: Water Resources Open - Single Stage - One LOT 1 LOWER NZOIA IDA / 52680 Prior Request for Bids 51,295,364.44 Signed 2017-06-05 2017-06-10 2017-06-10 2017-06-15 2017-07-22 2017-08-15 2017-08-21 2017-10-30 2017-09-25 2017-11-22 2020-09-09 Development International Envelope IRRIGATION PROJECT PHASE 1 AND LOT 2 IMPROVEMENT OF FLOOD MITIGATION STRUCTURES KE-MOWI-10752-CW-RFB / Construction Works of the C1: Water Resources Open - Single Stage - One IDA / 52680 Prior Request for Bids 0.00 Canceled 2017-04-20 2017-07-29 2017-07-29 2017-05-04 2017-10-07 2017-11-06 2017-12-27 2022-02-04 Lower Nzoia Irrigation Development International Envelope Project - Phase I KE-MOWI-10755-CW-RFB / Construction Works for C1: Water Resources Open - Single Stage - One Improvement of Flood IDA / 52680 Prior Request for Bids 0.00 Canceled 2017-04-20 2017-07-29 2017-07-29 2017-05-04 2017-10-07 2017-11-06 2017-12-20 2020-01-09 Development International Envelope Mitigation Structures on the Lower Nzoia River KE-MOWI-19433-CW-RFB / Program for the Improvement of Water C1: Water Resources Single Stage - One IDA / 52680 Post Request for Bids Open - National 3,897,597.92 Signed 2017-09-14 2017-08-23 2017-09-28 2017-11-09 2017-10-05 2017-12-09 2017-10-17 2018-01-13 2017-12-22 2020-07-01 Services in Mombasa County Development Envelope Mombasa West Mainland - Phase 1 Page 1 KE-MOWI-30787-CW-RFB / Refurbishishment offices at a) the National Flood Forecasting and Early Warning Center (N-FFEWC), C1: Water Resources Single Stage - One IDA / 52680 Post Request for Bids Open - National 66,764.53 Signed 2017-11-15 2018-02-21 2017-11-29 2018-01-10 2018-04-04 2018-02-09 2018-04-12 2018-03-16 2018-06-28 2018-09-12 b) Flood Mapping and Development Envelope Impact Assessment Center (FMIAC) and c) the Regional Management Center (R- FMC). KE-MOWI-47509-CW-RFB / PROGRAM FOR THE IMPROVEMENT OF WATER Under C1: Water Resources Single Stage - One SERVICES IN MOMBASA IDA / 52680 Post Request for Bids Open - National 0.00 Implementati 2018-02-09 2019-10-01 2018-02-14 2019-10-01 2018-03-28 2018-04-27 2018-06-01 2019-11-23 Development Envelope COUNTY MOMBASA on NORTH MAINLAND - PHASE 1 KE-MOWI-47916-CW-RFB / Drilling, Construction, Pending Installation (Data Loggers) C2: Effective Water Sector Single Stage - One IDA / 52680 Post Request for Bids Open - National 0.00 Implementati 2018-02-22 2018-02-27 2018-04-10 2018-05-10 2018-06-14 2018-12-11 and Commissioning of Institutions Envelope on Ground Water Monitoring Wells - 25 No. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KE-MOWI-13142-GO-RFQ / Supply, Installation, Training C1: Water Resources Request for Single Stage - One IDA / 56740 Post Limited 0.00 Canceled 2017-05-30 2017-08-08 2017-10-07 and Commission of SCADA Development Quotations Envelope for MOWASCO KE-MOWI-13145-GO-RFB / Supply and Delivery of Under C1: Water Resources Single Stage - One Motor Vehicles, Motor Cycles IDA / 56740 Post Request for Bids Open - National 0.00 Implementati 2017-05-19 2019-01-21 2017-06-02 2017-07-14 2017-08-13 2017-09-17 2018-03-16 Development Envelope and Service Vans for on MOWASCO KE-MOWI-13168-GO-RFQ / Supply and Delivery of Leak Pending Detection Equipment, C1: Water Resources Request for Single Stage - One IDA / 56740 Post Limited 0.00 Implementati 2017-05-26 2017-08-04 2018-01-31 Associated Accessories, Development Quotations Envelope on Pressure Pumps and Safety Gears KE-MOWI-13868-GO-RFB / Design, Supply, Installation, Under C1: Water Resources Single Stage - One Training and Commissioning IDA / 56740 Post Request for Bids Open - National 0.00 Implementati 2017-06-21 2018-02-16 2017-07-05 2017-08-16 2018-03-15 2017-09-15 2018-06-14 2017-10-20 2018-10-20 Development Envelope of an ERP system for on MOWASCO KE-MOWI-19437-GO-RFB / SUPPLY, DELIVERY, INSTALLATION& COMMISSIONING OF AN INTEGRATED REAL-TIME HYDRO-METEOROLOGICAL C2: Effective Water Sector Single Stage - One MONITORING SYSTEM IDA / 52680 Post Request for Bids Open - National 1,148,745.52 Signed 2017-09-14 2017-01-24 2017-09-19 2017-10-31 2017-11-14 2017-11-30 2017-11-22 2018-01-04 2017-12-20 2018-12-30 Institutions Envelope FOR UPGRADING THE NZOIA RIVER BASIN FLOOD EARLY WARNING SYSTEM IN LAKE VICTORIA NORTH CATCHMENT AREA Page 2 KE-MOWI-7607-GO-RFB / Supply, Delivery, Installation & Commissioning of an Integrated Real-Time Hydro- Meteorological Monitoring C2: Effective Water Sector Single Stage - One IDA / 52680 Post Request for Bids Open - National 0.00 Canceled 2017-02-17 2017-01-25 2017-03-03 2017-04-14 2017-03-23 2017-05-14 2017-05-05 2017-06-28 2018-06-23 System for Upgrading The Institutions Envelope Nzoia River Basin Flood Early Warning System in Lake Victoria North Catchment Area KE-MOWI-30789-GO-RFB / Procurement of Flood Pending Analysis and Mapping C2: Effective Water Sector Single Stage - One IDA / 52680 Post Request for Bids Open - National 0.00 Implementati 2018-04-20 2018-05-04 2018-06-15 2018-07-15 2018-08-19 2019-02-15 Workstations at WRA Institutions Envelope on (FMIAC) and KMD (N- FFEWC) KE-MOWI-47909-GO-RFB / SUPPLY AND DELIVERY C2: Effective Water Sector Single Stage - One OF GROUND WATER & IDA / 52680 Post Request for Bids Open - National 0.00 Canceled 2018-02-28 2018-03-05 2018-04-16 2018-05-16 2018-06-20 2018-12-17 Institutions Envelope WATER QUALITY EQUIPMENT KE-MOWI-47910-GO-RFB / Supply and Delivery of C2: Effective Water Sector Single Stage - One IDA / 52680 Post Request for Bids Open - National 0.00 Canceled 2018-02-27 2018-03-04 2018-04-15 2018-05-15 2018-06-19 2018-12-16 Information, Communication Institutions Envelope and Technology for WRA KE-MOWI-47915-GO-RFB / Supply, Delivery, Installation C2: Effective Water Sector Single Stage - One and Training of Hydromet IDA / 52680 Post Request for Bids Open - National 2,151,205.69 Signed 2018-03-13 2018-03-02 2018-03-18 2018-04-29 2018-04-27 2018-05-29 2018-06-29 2018-07-03 2018-08-20 2018-12-30 Institutions Envelope Monitoring Equipment and Instruments KE-MOWI-85760-GO-RFB / Supply, Delivery and Installation of Surface C2: Effective Water Sector Single Stage - One IDA / 52680 Prior Request for Bids Open - National 0.00 Canceled 2018-11-15 2018-11-20 2019-01-01 2019-01-31 2019-03-07 2020-03-06 Water, Water Quality and Institutions Envelope Weather Stations Equipment In 6 Lots KE-MOWI-125348-GO-RFB / Installation & Commissioning of Automatic Water Level (AWL) Equipment in Five (5) Basins, Automatic Under Weather Station (AWS) C2: Effective Water Sector Single Stage - One IDA / 52680 Post Request for Bids Open - National 0.00 Implementati 2019-08-09 2019-09-12 2019-08-14 2019-10-09 2019-09-25 2019-10-24 2019-10-25 2019-11-29 2020-11-23 Equipment in Five (5) Institutions Envelope on Basins and Atomic Absorption Spectrophotometer (AAS) Equipment in Central Water Testing Laboratory Nairobi NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 KE-MOWI-7909-CS-CQS / Consulting services to Consultant Conduct Baseline Survey for C1: Water Resources Under IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-15 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-12-28 Impact Evaluation for Lower Development Implementation Selection Nzoia Irrigation Project - Phase 1 KE-MOWI-7941-CS-CQS / Consulting services for the preparation and updating of Consultant C1: Water Resources Under Resettlement Action Plan IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-24 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-11-28 Development Implementation (RAP) for Lower Nzoia Selection Irrigation Project and Nzoia Flood Protection Structures KE-MOWI-7948-CS-CQS / Consultancy services for environmental and social impact assessment (ESIA) Consultant and Resettlement Action C1: Water Resources Under IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-27 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-11-28 Plan (RAP) for proposed Development Implementation Selection rehabilitation, extension and construction of North Mainland pipelines, Mombasa county. KE-MOWI-7950-CS-CQS / Consultancy services for environmental and social impact assessment (ESIA) and Resettlement Action Consultant C1: Water Resources Under Plan (RAP) for proposed IDA / 52680 Post Qualification Open - National 0.00 2017-02-21 2016-09-24 2017-03-14 2017-04-27 2017-05-27 2017-07-01 2017-11-28 Development Implementation rehabilitation, extension and Selection construction of west mainland pipelines West Mainland pipelines, Mombasa county KE-MOWI-7951-CS-QCBS / Consultancy services for developing a National Water Infrastructure Investment Pipeline, Feasibility Study C1: Water Resources Quality And Cost- Open - IDA / 52680 Prior 3,824,379.10 Signed 2017-02-21 2017-03-14 2017-05-13 2017-04-12 2017-07-12 2017-06-21 2017-08-11 2017-08-06 2017-10-10 2017-11-10 2017-11-30 2017-12-04 2019-06-03 for Malewa Dam and Water Development Based Selection International Supply to Ol Kalou, Naivasha and Gilgil Towns in Nyandarua and Nakuru Counties KE-MOWI-8302-CS-QCBS / Consultancy Services for Implementation Support C2: Effective Water Sector Quality And Cost- Open - IDA / 52680 Prior 5,611,318.79 Signed 2017-02-24 2017-03-17 2017-04-30 2017-06-25 2017-07-25 2017-08-29 2017-04-25 2017-10-03 2017-05-11 2020-09-17 Consultants (ISC) for Water Institutions Based Selection International Resources Planning and Management KE-MOWI-8332-CS-CQS / Consultancy Services for Social Impact Assessment Consultant C1: Water Resources Under Study combining downstream IDA / 52680 Post Qualification Open - National 0.00 2017-02-28 2017-03-14 2017-03-21 2017-05-04 2017-07-03 2017-08-07 2017-11-05 Development Implementation of Lower Nzoia Irrigation Selection Project and Mwache Dam projects KE-MOWI-8291-CS-QCBS / Consultancy Services for Design and Construction Supervision of Lunga Lunga, C1: Water Resources Quality And Cost- Open - IDA / 52680 Prior 1,294,075.28 Signed 2017-02-24 2017-03-26 2017-05-09 2017-06-20 2017-07-20 2017-08-24 2017-05-10 2017-09-28 2017-05-26 2020-05-15 Msambweni, Kwale and Development Based Selection International Ukunda Water Supplies Rehabilitation and Expansion Work - R35/ Page 4 KE-MOWI-10756-CS-QCBS / Consultancy Services for Upgrading of Flood C1: Water Resources Quality And Cost- Open - IDA / 52680 Prior 1,232,336.59 Signed 2017-04-20 2017-05-11 2017-07-10 2017-04-25 2017-09-08 2017-11-07 2017-10-08 2017-12-07 2017-12-03 2018-03-12 2018-01-07 2018-04-04 2021-01-11 Forecasting and Early Development Based Selection International Warning Systems for Nzoia River Basin KE-MOWI-11087-CS-QCBS / Consultancy Services for Implementation Support Consultant (ISC) For C1: Water Resources Quality And Cost- Open - Pending Improvement of Flood IDA / 52680 Prior 0.00 2017-03-31 2017-04-21 2017-06-04 2017-08-13 2017-09-12 2017-10-26 2017-11-30 2023-12-09 Development Based Selection International Implementation Mitigation Structures (IFMS) on Lower Nzoia River and Lower Nzoia Irrigation Project (LNIP) Phase 1 KE-MOWI-27582-CS-QCBS / consulting services to Support to Water Sector Reforms -Development of a Costed Water Sector Transition Plan - including a C2: Effective Water Sector Quality And Cost- Open - IDA / 52680 Prior 1,898,250.00 Signed 2017-09-08 2017-10-08 2017-09-20 2017-11-28 2018-01-09 2018-02-08 2018-03-19 2018-03-22 2018-05-16 2018-05-03 2018-07-02 2019-05-03 Transfer Plan Conduct Institutions Based Selection International Organizational Reviews, Study on Water Works Development Agencies and Development of Subsidiary Legislation KE-MOWI-27585-CS-QCBS / Consulting services to C2: Effective Water Sector Quality And Cost- Open - Support Water Sector IDA / 52680 Prior 1,397,034.00 Signed 2017-09-08 2017-10-08 2017-09-20 2017-11-28 2018-01-09 2018-02-08 2018-03-19 2018-03-22 2018-05-29 2018-04-26 2018-07-24 2018-12-22 Institutions Based Selection International Reform Communication and Staff Inductions KE-MOWI-13141-CS-QCBS / consulting services to Support to Water Sector Reforms Development of a Costed Water Sector Transition Plan including a C2: Effective Water Sector Quality And Cost- Open - IDA / 52680 Prior 0.00 Canceled 2017-05-26 2017-06-16 2017-06-09 2017-08-15 2017-10-10 2017-11-09 2018-01-08 2018-02-12 2019-02-12 Transfer Plan Conduct Institutions Based Selection International Organizational Reviews Study on Water Works Development Agencies and Development of Subsidiary Legislation KE-MOWI-9275-CS-QCBS / Consultancy to Support C2: Effective Water Sector Quality And Cost- Open - Water Sector Reform IDA / 52680 Prior 0.00 Canceled 2017-04-27 2017-04-03 2017-05-18 2017-06-09 2017-07-17 2017-08-28 2017-09-27 2017-12-08 2018-01-12 2018-09-09 Institutions Based Selection International Communication and Staff Induction KE-MOWI-30792-CS-QCBS / Construction Supervision for Program for the C1: Water Resources Quality And Cost- Open - IDA / 52680 Prior 624,628.14 Signed 2017-10-19 2017-11-18 2017-11-24 2018-01-01 2018-01-05 2018-02-12 2018-03-14 2018-03-12 2018-05-25 2018-04-29 2018-06-29 2018-05-25 2020-06-18 Improvement of Water Development Based Selection International Services in Mombasa West and North (Nyali) Mainland KE-MOWI-40043-CS-CQS / CONSULTANCY SERVICES FOR PROVISION OF LEGAL SERVICES Consultant TOWARDS PROJECT C1: Water Resources IDA / 52680 Post Qualification Open - National 284,200.35 Signed 2017-12-22 2017-12-20 2018-01-12 2018-02-25 2018-02-06 2018-03-27 2018-03-09 2018-05-01 2019-03-27 2019-04-26 AFFECTED PERSONS Development Selection (PAPS) SUCCESSION GRANTS AND CONFIRMATION BY COURTS Page 5 KE-MOWI-42455-CS-CQS / CONSULTANCY SERVICES FOR THE PREPARATION OF ENVIRONMENTAL AND SOCIAL IMPACT Consultant C1: Water Resources ASSESSMENT (ESIA) AND IDA / 52680 Post Qualification Open - National 274,822.05 Signed 2018-01-30 2018-02-05 2018-02-20 2018-04-05 2018-04-06 2018-05-05 2018-05-28 2018-06-09 2018-06-28 2018-11-06 Development RESETTLEMENT ACTION Selection PLAN (RAP) FOR KWALE WATER SUPPLIES REHABILITATION AND EXPANSION PROJECT KE-MOWI-44326-CS-CQS / CONSULTANCY SERVICES FOR THE PREPARATION OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) AND RESETTLEMENT ACTION Consultant C1: Water Resources PLAN (RAP) FOR LUNGA IDA / 52680 Post Qualification Open - National 284,685.66 Signed 2018-01-30 2018-02-05 2018-02-20 2018-04-21 2018-04-06 2018-05-21 2017-02-23 2018-06-25 2018-06-28 2018-10-23 Development LUNGA, MSAMBWENI AND Selection UKUNDA WATER SUPPLIES REHABILITATION AND EXPANSION PROJECT KE-MOWI-47880-CS-QCBS / Consultancy services for Consultant design and construction C2: Effective Water Sector Under IDA / 52680 Post Qualification Open - National 0.00 2018-03-08 2018-03-29 2018-05-12 2018-10-12 2018-06-11 2018-07-16 2020-07-05 supervision of flood control Institutions Implementation Selection operational centres in sub basins KE-MOWI-47898-CS-QCBS / Consultancy services for C2: Effective Water Sector Quality And Cost- Open - design and construction IDA / 52680 Prior 676,619.06 Signed 2018-03-15 2018-04-05 2018-05-19 2018-05-19 2018-10-05 2018-06-30 2018-07-30 2019-01-24 2018-09-03 2019-10-02 2018-10-08 2019-12-17 2020-09-27 Institutions Based Selection International supervision of National Data and Information Centre KE-MOWI-57276-CS-QCBS / Consulting Services for Transaction Advisor for the development of an C2: Effective Water Sector Quality And Cost- Open - IDA / 52680 Prior 501,218.39 Signed 2018-04-12 2018-05-12 2018-05-23 2018-07-02 2018-08-08 2018-08-13 2018-09-12 2018-11-08 2018-10-24 2019-04-27 2018-12-05 2019-06-26 2019-12-05 institutional framework and Institutions Based Selection International delivery structure for the bulk water services in the Coastal counties KE-MOWI-84310-CS-QCBS / Consultancy for Resettlement C1: Water Resources Quality And Cost- Open - IDA / 52680 Post 858,789.14 Signed 2018-11-02 2019-01-29 2018-11-23 2019-03-13 2019-01-06 2019-05-10 2019-02-17 2019-06-18 2019-03-19 2019-07-25 2019-04-23 2019-11-18 2019-05-28 2019-11-18 2022-05-22 Action Plan Implementation Development Based Selection International for Lower Nzoia Project KE-MOWI-166152-CS-CQS / Consultancy Services for The Preparation of Resettlement Consultant C1: Water Resources Under Action Plan No. 4 (RAP 4) IDA / 52680 Post Qualification Open - National 0.00 2020-04-10 2020-04-02 2020-05-01 2020-06-30 2020-07-30 2020-09-03 2021-01-01 Development Implementation for Tertiary Canals in Lower Selection Nzoia Irrigation Project (LNIP) – Phase I INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6 KE-MOWI-8061-CS-INDV / Individual C3: Support for Project PMU Chief Operations IDA / 52680 Prior Consultant Open 540,000.00 Signed 2017-02-22 2017-04-28 2017-04-20 2017-05-19 2018-07-31 2017-06-23 2018-08-24 2020-06-07 Implementation Officer Selection KE-MOWI-8062-CS-INDV / Individual C1: Water Resources Under Social Development Specialist IDA / 52680 Post Consultant Open 0.00 2017-02-22 2016-11-28 2017-04-28 2017-05-19 2017-06-23 2020-06-07 Development Implementation - Western Kenya Selection KE-MOWI-8143-CS-INDV / Individual C1: Water Resources Under Project Engineer, Western IDA / 52680 Post Consultant Open 0.00 2017-02-24 2017-01-31 2017-04-23 2017-05-14 2017-06-18 2018-06-13 Development Implementation Kenya Selection KE-MOWI-8144-CS-INDV / Individual C1: Water Resources Under Inspector of Works, Western IDA / 52680 Post Consultant Open 0.00 2017-02-24 2017-01-31 2017-04-23 2017-05-14 2017-06-18 2018-06-13 Development Implementation Kenya Selection KE-MOWI-8329-CS-INDV / Individual C1: Water Resources Under Assistant Resident Engineer IDA / 52680 Post Consultant Open 0.00 2017-02-28 2017-02-21 2017-04-27 2017-05-18 2017-06-22 2018-12-14 Development Implementation - Likoni Area-Phase 1 Selection KE-MOWI-8331-CS-INDV / Individual C1: Water Resources Under Resident Engineer - Likoni IDA / 52680 Post Consultant Open 0.00 2017-02-28 2017-02-21 2017-04-27 2017-05-18 2017-06-22 2018-12-14 Development Implementation Area-Phase 1 Selection Individual KE-MOWI-8942-CS-INDV / C1: Water Resources IDA / 52680 Prior Consultant Open 139,467.31 Signed 2017-03-16 2017-05-13 2017-01-18 2017-06-03 2017-04-25 2017-07-08 2017-04-26 2020-06-22 Procurement Specialist 1 Development Selection Individual KE-MOWI-8943-CS-INDV / C1: Water Resources IDA / 52680 Prior Consultant Open 139,467.31 Signed 2017-03-16 2017-05-13 2017-01-18 2017-06-03 2017-04-25 2017-07-08 2017-04-26 2020-06-22 Procurement Specialist 2 Development Selection KE-MOWI-9280-CS-INDV / Consultant to provide legal Individual C2: Effective Water Sector Under and policy support for IDA / 52680 Post Consultant Open 0.00 2017-04-12 2017-03-09 2017-06-09 2017-06-30 2017-08-04 2018-08-04 Institutions Implementation development of National Selection Water Policy KE-MOWI-13139-CS-INDV / Consultancy services of Individual C3: Support for Project Under Environmental and Social IDA / 52680 Prior Consultant Open 0.00 2017-05-11 2017-07-15 2017-08-05 2017-09-09 2019-09-29 Implementation Implementation Panel of Experts - Selection Environmental Specialist KE-MOWI-13140-CS-INDV / Consultancy services for Individual C3: Support for Project Under Environmental and Social IDA / 52680 Prior Consultant Open 0.00 2017-05-18 2017-07-22 2017-08-12 2017-09-16 2019-10-06 Implementation Implementation Panel of Experts - Social Selection Specialist Individual KE-MOWI-57281-CS-INDV / C3: Support for Project IDA / 52680 Prior Consultant Open 304,023.85 Signed 2018-04-05 2018-06-09 2018-06-30 2018-05-29 2018-08-04 2018-06-20 2021-07-19 Social Safeguards Officer Implementation Selection KE-MOWI-57278-CS-INDV / Individual C3: Support for Project Planning and M&E IDA / 52680 Prior Consultant Open 0.00 Canceled 2018-05-29 2018-08-02 2018-08-23 2018-09-27 2021-09-11 Implementation Specialist Selection KE-MOWI-71899-CS-INDV / Individual C3: Support for Project Under Planning and Monitoring & IDA / 52680 Prior Consultant Open 0.00 2018-08-03 2018-10-07 2019-02-12 2018-10-28 2019-03-05 2018-12-02 2021-11-16 Implementation Implementation Evaluation Specialist Selection Page 7 KE-MOWI-83366-CS-CDS / CONSULTANCY SERVICES FOR PROVISION OF LEGAL SERVICES C1: Water Resources TOWARDS PROJECT IDA / 56740 Prior Direct Selection Direct 329,774.30 Signed 2018-10-23 2018-11-02 2019-01-06 2019-04-09 2020-01-06 Development AFFECTED PERSONS (PAPS) SUCCESSION GRANTS BY COURTS -RAP III KE-MOWI-84304-CS-INDV / Individual Consultancy services for C3: Support for Project IDA / 52680 Prior Consultant Open 134,221.42 Signed 2018-11-08 2018-12-10 2019-01-12 2019-02-02 2019-03-05 2019-03-09 2019-06-14 2022-02-21 Communication Expert - Implementation Selection Lower Nzoia Project KE-MOWI-112692-CS-INDV Individual / Consultancy Services for C3: Support for Project IDA / 52680 Prior Consultant Open 101,556.46 Signed 2019-04-30 2019-10-10 2019-07-04 2019-10-01 2019-07-25 2019-10-31 2019-08-29 2019-11-26 2021-08-18 Social Safeguards Expert - Implementation Selection LNIP and IFMS KE-MOWI-126348-CS-INDV / Consultancy Services of Two (2) Members to Sit in Individual the Dispute Board of C1: Water Resources Under IDA / 52680 Prior Consultant Open 0.00 2019-08-07 2019-09-01 2019-10-11 2019-12-19 2019-11-01 2020-03-10 2019-12-06 2022-12-05 Construction Works of Lower Development Implementation Selection Nzoia Irrigation Project Phase 1 and Improvement of Flood Mitigation Structures KE-MOWI-167474-CS-INDV Individual / Business Process C1: Water Resources Pending IDA / 52680 Post Consultant Open 0.00 2020-04-09 2020-05-28 2020-06-18 2020-07-23 2021-01-19 Management/Re-Engineering Development Implementation Selection Specialist KE-MOWI-167476-CS-INDV Individual C1: Water Resources Pending / IT Specialist (ERP IDA / 52680 Post Consultant Open 0.00 2020-04-09 2020-05-28 2020-06-18 2020-07-23 2021-01-27 Development Implementation systems) Selection Page 8