Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) AFRICA | Ethiopia | Transport & Digital Development Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 4 | ARCHIVED on 25-May-2018 | ISR32324 | Implementing Agencies: Ministry of Finance and Economic Cooperation (MOFEC), Addis Ababa Road and Transport Bureau, Federal Transport Authority Key Dates Key Project Dates Bank Approval Date:03-Jun-2016 Effectiveness Date:26-Jul-2016 Planned Mid Term Review Date:15-Oct-2019 Actual Mid-Term Review Date:-- Original Closing Date:31-Dec-2023 Revised Closing Date:31-Dec-2023 Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed Project Development Objective (PDO) is to improve mobility along selected corridors in Addis Ababa and the effectiveness of road safety compliance systems throughout Ethiopia. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Component A: Traffic Management and Road Safety in the City of Addis Ababa:(Cost $190.10 M) Component B: Improvement of Integrated Urban Planning and Transport System:(Cost $2.80 M) Component C: Road Safety Interventions and Institutional Strengthening of Selected Federal Transport Institutions:(Cost $107.10 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Unsatisfactory  Moderately Unsatisfactory Overall Risk Rating  Substantial  High 5/25/2018 Page 1 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) Implementation Status and Key Decisions 1 . Implementation progress is getting better with time as the Client acquires more experience in Bank financed projects. It is expected that the procurement process will be expedited in the coming months with four major assignments to be signed soon, and another three will be at advanced procurement stage. Overall, project implementation is expected to be improved in the coming 3-4 months. 2 . The concept design and preparation of a ToR to hire Architecture design consultant for the Federal Transport Authority (FTA) is at advanced stage and expected to be finalized before May 30, 2018. This is a major milestone as this will allow FTA to move to the next stage of hiring architectural design consultant that will produce the detail design for the vehicle registrations system. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Moderate  Substantial  Substantial Macroeconomic  Moderate  Moderate  Moderate Sector Strategies and Policies  Moderate  Moderate  Moderate Technical Design of Project or Program  High  High  High Institutional Capacity for Implementation and Sustainability  High  High  High Fiduciary  High  Substantial  Substantial Environment and Social  Substantial  Substantial  Substantial Stakeholders  High  High  Moderate Other  High  High  Moderate Overall  High  Substantial  High Results 5/25/2018 Page 2 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) Project Development Objective Indicators PHINDPDOTBL  Roads constructed, non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 21.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments No civil works has started yet. PHINDPDOTBL  Passenger traffic flow per day along five selected project road corridors (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 396.00 396.00 396.00 455.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Corridor 1: British Embassy to Africa Avenue (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 11.00 11.00 11.00 13.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Corridor 2: Arat Kilo to Degol to Abune Petros (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 151.00 151.00 151.00 173.00 Date 27-May-2016 28-Nov-2017 28-Nov-2017 31-Dec-2023 5/25/2018 Page 3 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) PHINDPDOTBL  Corridor 3: St George Cathedral to Dil Ber (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 90.00 90.00 90.00 104.00 Date 27-May-2016 28-Nov-2017 28-Nov-2017 31-Dec-2023 PHINDPDOTBL  Corridor 4: Arat Kilo to Brass Hospital (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 130.00 130.00 130.00 149.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Corridor 5: Ummer Sumeter to Grand Palace (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 14.00 14.00 14.00 16.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Pedestrian fatalities on prescribed corridors per 1,000 vehicles (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 25.00 25.00 25.00 19.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 5/25/2018 Page 4 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) Comments Various civil works that are intended to improve mobility of pedestrians has not yet started; hence the baseline remains unchanged. PHINDPDOTBL  Corridor 1: British Embassy to Africa Avenue (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 3.00 3.00 3.00 2.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Corridor 2: Arat Kilo to Degol to Abune Petros (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 5.00 5.00 4.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Corridor 3: St George Cathedral to Dil Ber (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 10.00 10.00 10.00 8.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Corridor 4: Arat Kilo to Brass Hospital (Number, Custom Breakdown) 5/25/2018 Page 5 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 5.00 5.00 4.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  Corridor 5: Ummer Sumetar to Grand Palace (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 2.00 2.00 2.00 1.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 PHINDPDOTBL  In-service Bus-km per bus per day (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 130.00 130.00 130.00 143.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments The support to Anbessa Public Transport service is still under procurement, and hence there is no change to the baseline value. PHINDPDOTBL  Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3.90 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments Many of the activities are still under procurement, and hence beneficiaries have not yet benefitted project. 5/25/2018 Page 6 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) PHINDPDOTBL  Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 50.00 50.00 50.00 50.00 Overall Comments Many of the activities are still under procurement, and hence beneficiaries have not yet benefitted project. Intermediate Results Indicators PHINDIRITBL  Number of Manpower Trained under the Project (number of people) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 100.00 100.00 1,500.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments No training was organized after the last supervision mission. 5/25/2018 Page 7 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) PHINDIRITBL  Percentage of vehicles registered using the new system (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments The FTA component is still under procurement, and hence there is no progress yet. PHINDIRITBL  Percentage of driver licenses issued using the new system (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments The FTA component is still under procurement, and hence there is no progress yet. PHINDIRITBL  Average processing time for citizen to register a vehicle. (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 20.00 20.00 20.00 4.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments 5/25/2018 Page 8 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) PHINDIRITBL  Average processing time for citizen to obtain a driving license. (Days, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 45.00 45.00 45.00 8.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments The FTA component is still under procurement, and hence there is no progress yet. PHINDIRITBL  Number of intersections with traffic signals installed under the project. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 158.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments Improving traffic signals has not yet started. PHINDIRITBL  Percentage of buses installed with an electronic fare collection system (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 100.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments Improving the public transportation system has not yet started. Major activities are still under procurement. 5/25/2018 Page 9 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) PHINDIRITBL  Deployment of a new Penalty Management System (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments The system is not yet in place. PHINDIRITBL  Number of TODs designed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments This activity is delayed. PHINDIRITBL  Number of pedestrian crossings constructed in Addis Ababa (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments ToR for the design of pedestrian is under preparation. 5/25/2018 Page 10 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) PHINDIRITBL  Proportion of registered grievances related to construction and implementation of the project in Addis Ababa addressed to the satisfaction of the complainant within 30 days (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 95.00 Date 27-May-2016 28-Nov-2017 26-Apr-2018 31-Dec-2023 Comments No construction has yet started. Overall Comments Major interventions that may lead to the improvements of the various systems are still under procurements, and hence it will take sometime to see changes in the indicators. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P151819 IDA-58160 Effective USD 300.00 300.00 0.00 19.22 282.94 6.4% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P151819 IDA-58160 Effective 03-Jun-2016 15-Jun-2016 26-Jul-2016 31-Dec-2023 31-Dec-2023 Cumulative Disbursements 5/25/2018 Page 11 of 12 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Ethiopia: Transport Systems Improvement Project (TRANSIP) (P151819) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/25/2018 Page 12 of 12 Public Disclosure Copy