Procurement Plan for Punjab RWSS (P150520) I. General 1. Bank’s approval Date of the procurement Plan 2012 2. Date of General Procurement Notice: [October 01, 2014 ] 3. Period covered by this procurement plan: January 2017 onwards II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 2. NCB (Goods) Above US$ 100,000 3. ICB (Works) Above US$ 40 million 4. NCB (Works) Above US$ 10 million 5. (Non-Consultant Services) Below US$ 100,000 2. Prequalification for Bidders _Not applicable_ 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P150520 5. Any Other Special Procurement Arrangements: In addition, the justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. Justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 50,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT India : IN Punjab Rural Water and Sanitation Sector Improvement Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2018-08-29 2019-07-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150520 GPN Date: Project Name: IN Punjab Rural Water and Sanitation Sector Improvement Project Loan / Credit No: IBRD / 84870 Executing Agency(ies): Division Gurdaspur (EE-2nd) WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRWSS-S-DIV81-5426-1 / Renovation of rooms for new JE Sections (S085 to S100) under jurisdiction of Request for Single Stage - One Gurdaspur-EE 2nd IBRD / 84870 Post Open - National 3,596.79 Signed 2018-09-22 2018-11-17 2019-05-16 Quotations Envelope including White washing repair of room fixing electric fans and lights e.t.c under component 4A of PRWSSIP PRWSS-W-DIV81-4219-1 / WSS Chack Alia Block Dinanagar District Gurdaspur : Provision of Request for Single Stage - One IBRD / 84870 Post Open - National 638.73 Completed 2018-11-06 2018-11-06 2018-11-06 additonal Pipe Line and Quotations Envelope New Water Connection in village under component 2B of PRWSSIP DWSS-W-DIV81-5783-1 / WSS Village Ucha Dhakala Block Dorangla District Gurdaspur : Providing Request for Single Stage - One IBRD / 84870 Post Open - National 46,550.21 Signed 2019-01-02 2019-02-27 2019-08-26 tubewell and districbution Quotations Envelope pipe and construction of OHSR uder component 1A(iii) of PRWSSIP. DWSS-W-DIV81-5946-1 / WSS Village Bhaini Mian Khan Block Kahnuwan District Gurdaspur: Providing Request for Single Stage - One IBRD / 84870 Post Open - National 11,312.40 Signed 2019-02-09 2019-04-06 2019-12-02 Remaining Pipe Line and Quotations Envelope water connection under component 2A(i) of PRWSSIP. DWSS-W-DIV81-5878-1 / WSS Scheme Village Rajpur Chib Block Dinanagar District Under Gurdaspur :Providing and Request for Single Stage - One IBRD / 84870 Post Open - National 0.00 Implementati 2019-02-10 2019-04-07 2019-10-04 Installing Tubewell, OHSR, Quotations Envelope on Pump Chamber and Distribution PipeLine under component 1A(iii) of PRWSSIP Page 1 PRWSS-W-DIV81-6034-1 / WSS Village Narangpur Block Dinanagar District Under Gurdaspur : Providing Request for Single Stage - One IBRD / 84870 Post Open - National 0.00 Implementati 2019-02-19 2019-04-16 2019-10-13 Remaining Pipe Line and Quotations Envelope on Water Connection etc.under component 2A(i) of PRWSSIP. DWSS-W-DIV81-6267-1 / WSS Vill Dhaburi ,Block Dorangla District Gurdaspur: Providing and installing Pending Request for Single Stage - One Tube well, OHSR,Civil Work, IBRD / 84870 Post Open - National 0.00 Implementati 2019-08-23 2019-11-22 2020-05-20 Quotations Envelope Pump Chamber, Pumping on Machinery Distributions Pipe Line under component 1A(ii) of PRWSSIP. DWSS-W-DIV81-6625-1 / WSS village Sultani Block Dorangla District Gurdaspur: Pending Request for Single Stage - One Improvement of Water works IBRD / 84870 Post Open - National 0.00 Implementati 2019-08-23 2019-11-22 2020-01-21 Quotations Envelope by providing household on connections and Development of Water Works GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PRWSS-G-DIV81-5424-1 / Procurement of Office Furniture, Electric Fans Tools and plants and other Request for Single Stage - One facilities for new JE sections IBRD / 84870 Post Open - National 3,643.62 Signed 2018-09-22 2018-11-17 2019-05-16 Quotations Envelope (S085 to S100) under jurisdiction of Division no. Gurdaspur EE2nd under component 4A of PRWSSIP PRWSS-G-DIV81-5424-2 / Procurement of Office Tools and plants and other facilities for New JE Request for Single Stage - One IBRD / 84870 Post Open - National 3,681.01 Signed 2019-03-16 2019-05-11 2019-11-07 sections (S085 to S092) Quotations Envelope under jurisdiction of Division Gurdaspur under component 4A of PRWSSIP NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 INDIVIDUAL CONSULTANTS Page 3