The World Bank Kenya Transport Sector Support Project (P124109) REPORT NO.: RES34865 RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING OF KENYA TRANSPORT SECTOR SUPPORT PROJECT APPROVED ON APRIL 21, 2011 TO THE REPUBLIC OF KENYA TRANSPORT GLOBAL PRACTICE AFRICA REGION Regional Vice President: Hafez M. H. Ghanem Country Director: Carlos Felipe Jaramillo Senior Global Practice Director: Guangzhe Chen Practice Manager: Benedictus Eijbergen Task Team Leaders: Josphat O. Sasia, Susan Apudo Owuor The World Bank Kenya Transport Sector Support Project (P124109) ABBREVIATIONS AND ACRONYMS AF Additional Financing DOSH Directorate of Occupational Safety and Health Services EASA East Africa School of Aviation EBK Engineers Board of Kenya FY Fiscal Year GoK Government of Kenya GRS Grievance Redress Service ICAO International Civil Aviation Organization IDA International Development Agency IP Implementation Progress JKIA Jomo Kenyatta International Airport KAA Kenya Airport Authority KAA KCAA Kenya Civil Aviation Authority KeNHA Kenya National Highway Authority KES Kenyan Shilling KTSSP Kenya Transport Sector Support Project MTI Marine Training Institute NCA National Construction Authority NTSA National Transport and Safety Authority PAP Project Affected Persons PDO Project Development Objective SDR Special Drawing Rights US$ United States Dollar The World Bank Kenya Transport Sector Support Project (P124109) BASIC DATA Product Information Project ID Financing Instrument P124109 Investment Project Financing Original EA Category Current EA Category Partial Assessment (B) Partial Assessment (B) Approval Date Current Closing Date 21-Apr-2011 31-Dec-2018 Organizations Borrower Responsible Agency Kenya Civil Aviation Authority,Kenya National Highways Authority (KeNHA),Kenya Airport Authority,Ministry of The National Treasury Transport, Infrastructure, Housing and Urban Development Project Development Objective (PDO) Original PDO The Project Development Objectives are to: (a) increase the efficiency of road transport along the Northern Corridor and the Tanzania-Kenya-Sudan road corridor; (b) enhance aviation safety and security to meet international standards; and (c) improve the institutional arrangements and capacity in the transport sector. Current PDO The revised PDOs are to: (a) increase the efficiency of road transport along the Northern Corridor and the Tanzania- Kenya-South Sudan road corridor; (b) enhance aviation safety and security to meet international standards; (c) improve the institutional arrangements and capacity in the transport sector; (d) restore the capacity of the international passenger terminal destroyed in a fire at JKIA; and (e) strengthen the capacity of KAA in disaster preparedness and responsiveness at Kenyan airports. OPS_TABLE_PDO_CURRENTPDO Summary Status of Financing Net Ln/Cr/Tf Approval Signing Effectiveness Closing Commitment Disbursed Undisbursed IDA-54100 26-Mar-2014 31-Mar-2014 20-Jun-2014 31-Dec-2018 203.50 167.70 17.21 The World Bank Kenya Transport Sector Support Project (P124109) IDA-49260 21-Apr-2011 23-May-2011 22-Aug-2011 31-Dec-2018 300.00 261.63 11.12 Policy Waiver(s) Does this restructuring trigger the need for any policy waiver(s)? No I. PROJECT STATUS AND RATIONALE FOR RESTRUCTURING Summary of the Proposed Restructuring 1. The proposed restructuring of the Kenya, Transport Sector Support Project (KTSSP, P124109) entails extending the closing date of the credit by twelve months from December 31, 2018 to December 31, 2019 to allow for the completion of some incomplete activities including implementation of associated resettlement action plans. The Government of Kenya (GoK) in a letter dated November 19, 2018 requested an 18-months extension of the closing dates of Credit No. 4926-KE and Credit No. 5410-KE to allow the completion of the outstanding activities, primarily civil works, associated resettlement action plans and other safeguards issues. This restructuring proposes a twelve-month extension considering the current completion rate of the outstanding activities. A first extension of the parent project by two years was part of the Additional Financing (AF) for KTSSP (which was provided in 2014 in the amount of US$203.5 million equivalent to respond to an emergency after part of the premier airport of Kenya-Jomo Kenya International Airport (JKIA), Nairobi was partially destroyed by a fire). The proposed extension will be the second extension of the parent project, which if approved will lead to a cumulative extension of thirty six months. This is the first extension (twelve months) of the AF. With this extension, the project will be eight years and eight months old at the time of the proposed December 31, 2019 closing date. 2. The remaining activities were expected to be completed by the current closing date. However, delays and inadequate releases of funds slowed down implementation progress. A significant part of the counterpart funding under the project is for compensating project affected persons (PAPs) either for land acquisition or structures as well as relocation of services. About KES3.4 billion (about US$34 million equivalent) in counterpart funding is outstanding for land compensation and relocation of services. Other counterpart funding for the remaining activities is estimated at KES7.2 billion or (US$72 million equivalent), a significant portion of it arising from an IDA financing shortfall due to the appreciation of the US$ against Special Drawing Rights (SDR) (refer paragraph 13 (b)). 3. The GoK has committed to budget and release adequate funds on a timely basis in 2019 (for amounts financed by both IDA and counterpart funds). 1 To fully fund the outstanding activities, the GoK will provide part of the funding in the supplementary budget for FY18/19 (ending June 30, 2019) to be released by end of February 2019. The funds will go toward the contracts whose implementation is advanced, but where full access to the site is impeded due to non-payment of compensation to PAPs, such as Kisumu Boys-Mamboleo and Kakamega-Webuye. This will ensure execution and completion of these contracts as scheduled. The balance of the funds will be provided in the FY2019/20 budget and 1 Budget allocations need to be made and released for both counterpart funds and amounts financed by IDA. The World Bank Kenya Transport Sector Support Project (P124109) released beginning July 1, 2019, to fund contracts where land acquisition is not an immediate constraint, and which require a relatively longer implementation period. A. Background 4. The KTSSP was approved on April 21, 2011 in an amount of SDR 190.80 million, (US$300 million equivalent, Credit No. 4926-KE), and became effective on August 22, 2011. The AF was approved on March 26, 2014 in an amount of SDR 132.60 million, (US$203.50 million equivalent, Credit No. 5410-KE), and became effective on June 20, 2014. 5. The AF was to: (a) respond to an emergency at the Jomo Kenyatta International Airport (JKIA) due to an accidental fire on August 7, 2013 that destroyed the entire international passenger arrival terminal facilities; (b) finance increased scope and costs of the original activities to scale-up the development effectiveness of the project; and (c) cover an unanticipated financing gap in the provision of co-financing. The original and AF consists of the following four components: (a) Support to Kenya National Highway Authority (KeNHA) to rehabilitate and improve roads, roadside facilities and road safety interventions and for institutional strengthening; (b) Support to the Ministry of Transport and Infrastructure; (c) Support to the Kenya Airport Authority (KAA); and (d) Support to the Kenya Civil Aviation Authority (KCAA). B. Overall Progress 6. Overall implementation of the project and achievement of the project development objectives (PDOs) are currently on track with the PDO likely to be achieved by the proposed revised closing date. Progress towards achievement of the PDO and Implementation Progress (IP) are rated moderately satisfactory. As of December 27, 2018, the cumulative disbursements for the original IDA and AF are SDR 182.78 million (US$261.63 million equivalent) and SDR 120.19 million (US$167.70 million equivalent), or 96 percent and 91 percent, respectively. 7. Major results/outcomes have been recorded under the project so far and include: (PDO outcome 1) Increase the efficiency of road transport along the Northern Corridor and the Tanzania-Kenya- South Sudan road corridor: About 200 km of roads (out of the targeted 231 km) have been either constructed or reconstructed thereby reducing travel time along the target road sections significantly. Travel time between Kisumu and Kitale, as well as Bachuma Gate and Maji ya Chumvi has been reduced by 2 and 1 hour/s or 40 and 50 percent (surpassing end project targets for the completed road sections). Travel time along Kisumu-Kakamega has been reduced by 55 percent. Five interchanges have been constructed at major junctions with a history of road fatalities, thus improving road safety. Also, social infrastructure and services (e.g. schools, markets and health facilities) have been provided to the project host communities and over 200 graduate engineers have been offered internship opportunities on the road contracts. The targets for the outstanding road sections are expected to be achieved upon their completion. (PDO outcome 2) Enhance aviation safety and security to meet international standards: This objective has been achieved. Kenya and JKIA now meet aviation security and service level standards set by International Civil Aviation Organization (ICAO), Federal Transportation Administration, and Transportation Security Administration of the USA, allowing flights originating from JKIA to and from the USA. Kenya Airways commenced direct flights to New York, USA on October 28, 2018. JKIA was selected as the fifth best airport in Africa in 2017, and Most Improved Airport in Africa in 2016 (Airports Council International). The East Africa School of Aviation (EASA) has been accredited as one of the few centers of excellence in the world by ICAO. Purchase and installation of air navigation equipment have contributed to enhancing safety in Kenya’s airspace. The World Bank Kenya Transport Sector Support Project (P124109) (PDO ouctome 3) Improve the institutional arrangements and capacity in the transport sector: This objective has been achieved. Significant achievements have been realized and with the Government successfully implementing all the agreed institutional and policy reforms and dated covenants. The reforms focused on improving the regulatory framework and performance of the transport sector. These reforms are showing positive results with governance and accountability in the transport sector improving. For example: (a) Reduction in road accidents on the Kenyan roads with the establishment of a national regulatory body and lead agency for road safety, National Transport and Safety Authority (NTSA). (b) Commencement of sanctioning of poor workmanship in the construction industry (cases taken to court where for instance buildings and bridges under construction collapse) with the establishment of a regulatory body for the construction industry, National Construction Authority (NCA) that has created a monitoring and sanction framework in Kenya. (c) Oversight and professional development of the engineering profession and practice has been strengthened with the establishment and enhancing the capacity of a new regulatory body, Engineers Board of Kenya (EBK). (d) Resolution of conflict of interest scenario in the aviation sub-sector where the regulator, KCAA was housed by the operator, KAA. A new office block for KCAA was financed under the project as part of financing reforms in the aviation sub-sector. The reforms executed include: (a) a lead agency for road safety, NTSA established; (b) a regulatory framework for the construction industry, NCA established; (c) a regulatory framework for engineering profession and practice, EBK established; (d) a regulatory framework for railways developed; (e) KCAA restructured through internal separation of the regulatory responsibilities from service provision functions; (f) performance monitoring framework for the maritime sub-sector developed; and (g) a Marine Training Institute (MTI) established at Kisumu. (PDO outcome 4) Restore the capacity of the international passenger terminal destroyed in a fire at JKIA. This objective has been achieved and the destroyed capacity restored. Interim and permanent international passenger arrivals facilities were constructed at JKIA leading to rapid and full restoration of operations at the airport. (PDO outcome 5) Strengthen the capacity of KAA in disaster preparedness and responsiveness at Kenyan airports: Emergency response has been strengthened at major airports with the development of disaster response systems and purchase of firefighting equipment. Table 1: Major Activities Completed No. Activity COMPONENT A 1 Reconstruction of Webuye-Kitale road section (60 km) 2 Three feasibility and design studies for critical road sections – Mombasa Northern Bypass; Lake Victoria ring road; and Nakuru-Nyeri-Marua 3 Reconstruction Bachuma Gate Maji ya Chumvi road section (53 km) 4 Construction of five interchanges at major junctions to improve on safety – Mau Summit-Kericho; Nakuru-Njoro turnoff; Nakuru-Nyahururu turnoff; Kitale turnoff at Webuye; and Webuye turnoff at Kitale 5 Reconstruction of Kisumu-Kakamega road (47 km which includes 12 km dual carriageway) The World Bank Kenya Transport Sector Support Project (P124109) No. Activity COMPONENT A 6 Community social infrastructure: construction of two primary schools (at Mwoki and Musenwa); Mwoki water supply; Lubao market; Misikhu market; Kiminini market; Matete Maternity Ward; and Kamkuywa bus park COMPONENT B 7 A lead agency for road safety, NTSA established 8 A regulatory framework for the construction industry, NCA established 9 A regulatory framework for engineering profession and practice, EBK established 10 KCAA restructured through internal separation of the regulatory responsibilities from service provision functions 11 A regulatory framework for railways developed 12 Performance monitoring framework for the maritime sub-sector developed 13 A Marine Training Institute (MTI) established at Kisumu COMPONENT C 14 An interim international passenger arrival facility (Terminal T1-E) at JKIA 15 Permanent arrival facility for Terminal 1-A and associated supply and installation contracts 15 Supply of fire-fighting engines for KAA 17 Installation of an integrated security system for T1-A at JKIA 18 Installation of an information technology system for JKIA 19 Supply and installation of a baggage handling system at T1-A and T1-E international arrivals 20 Installation of air navigation equipment COMPONENT D 21 Construction of headquarter office complex for KCAA including an access road 22 Establishment of a Marine Training School at Kisumu 23 Equipping the East Africa School of Aviation training workshops 24 Acquisition of air navigation equipment 8. Two other activities are expected to be completed by December 31, 2018 (Table 2). Table 2: Major Activities Expected to be Completed by December 31, 2018 No Activity 1 Construction of access road to EASA 2 Feasibility and detailed engineering design studies for two road sections, namely (i) Malindi-Madogo; and (ii) Nakuru-Marich Pass 9. There are some activities that will not be completed by December 31, 2018, although their implementation is advanced (Table 3). Factors contributing to the delay include: (a) delays and inadequate releases of counterpart and IDA funding likewise which slowed down implementation progress. Some contractors have suspended works while others slowed down for failure of payment for work done. (b) the unprecedented heavy rains recorded during the period March-May 2018 halted execution of civil works during this period; (c) the long electioneering during the 2017 calendar year, which slowed down progress of works, and for sites such as Kisumu, it led to suspension of works; and (d) protracted and slow pace of land acquisition and relocation of utilities/services. Table 3: Major Activities to be Completed by December 31, 2019 No Activity (completion rate as at November 25, 2018 specified) 1 Construction of an office block (Barabara Plaza building) to accommodate KeNHA and other the road agencies, currently at 90 percent completion rate and expected to be completed by May 2019. 2 Kisumu Boys-Mamboleo (4.5 km), currently at 80 percent completion rate and expected to be completed by July 2019. The World Bank Kenya Transport Sector Support Project (P124109) 3 Kakamega-Webuye road section (40 km), currently at 70 percent completion rate expected to be completed by December 2019 (also involves construction of an interchange at Kaburengu currently at 40 percent completion). 4 Athi River-Machakos road section (22 km), currently at 47 percent completion rate and expected to be completed by December 2019. 5 Interchange at Kericho/Kisumu junction, currently at 50 percent completion rate expected to be completed by August 2019. 6 Interchange at Ahero/Kisii junction, currently at 30 percent completion rate expected to be completed by December 2019. 7 Training facilities (e.g. training swimming pool, fire-fighting training facility) at the new MTI, Kisumu, currently at 5 percent completion rate (not major works) expected to be completed by June 2019. 10. About US$28 million would remain unutilized though committed if the credit closes as planned on December 31, 2018 with the contract funding being transferred to GoK thereby increasing the Government’s financial burden. 11. Safeguards. Overall, implementation of social and environmental safeguards is rated moderately satisfactory. (a) Outstanding compensation payments: compensating PAPs either for land acquisition or structures as well as relocation of services. About KES3.4 billion (about US$34 million) is outstanding in payments to PAPs towards compensation for land acquisition or structures of relocation of services. These are expected to be paid when GoK releases budget (as discussed in paragraph 3). (b) There are two pending occupational health and safety (OHS) cases that are yet to be closed. An action plan has been agreed upon between the Borrower and the World Bank and its implementation is being monitored by the World Bank task team. One previous fatality in November 2017 has been closed after full compensation to the deceased family. Similarly, compensation for a serious injury of a worker in April 2018 has been substantially completed after 95 percent of the payment was released to the worker in addition to payment of full monthly wages. The pending cases are: (i) an accident involving the Contractor’s roller that veered off the road near Malava Forest along the Kakamega-Webuye road section and resulted in one fatality (security person) and serious injuries to another contractor employee. The Police, insurance company, and the Directorate of Occupational Safety and Health Services (DOSH) of the State Department of Labour were notified, and the process for compensation of the bereaved family has commenced; and (ii) an accident involving a Contractor’s worker who was part of a group of workers preparing for slope protection works on an existing embarkment at the outlet of a bridge (minor works during defect liability period). The embarkment wall collapsed and killed him. The deceased family, Police, the insurance company, and the DOSH of the State Department of Labour were notified, and the compensation process has commenced. (c) A complaint regarding the Webuye-Kitale road section constructed under the project was received by the World Bank’s Grievance Redress Service (GRS). The complaint was submitted by a representative on behalf of local communities saying that the ongoing construction of the Webuye flyover has compromised the community health and safety by exposing vulnerable people to the risk of hazardous pollutants in the air, soil, water etc.; that no effort had been done at project site to evaluate and mitigate negative environmental impacts of the construction; and that there is poor stakeholder engagement and lack of information disclosure. The Borrower has responded to the complaint, and the report has been shared with the GRS. (d) On December 17, 2018, the Inspection Panel received a Request for Inspection of the project. The Inspection Panel’s website notes that the Request was submitted by three members of the project-affected community who asked the Panel to keep their identities confidential; and that the complaint raises concerns about the impact from works on the Webuye–Kitale road section, including environmental impact, health and safety issues, impact on livelihoods as well as a lack of consultation and information disclosure. The World Bank will follow-up on this, following standard practice. The World Bank Kenya Transport Sector Support Project (P124109) 12. Audits: There are no outstanding audits. Also, the Interim Financial Reports are current. C. Rationale for Restructuring 13. The objective of the restructuring is to extend the closing date by twelve months to allow for the completion of some incomplete activities including implementation of associated resettlement action plans. The following factors were taken into consideration in proposing an extension of the closing date: (a) some of the outstanding activities particularly structures, for instance the interchanges, will require more time to complete due to: (i) the expected rainy season during March-June 2019 that is likely to mean less progress during that period; and (ii) the minimum period between different stages of construction for structures, such as interchanges and bridges, that must be allowed for, to enable different construction materials such as concrete to attain maximum strength; (b) the strengthening of US$ against SDR has reduced the dollar equivalent amount of the credits (Credit No.4926- KE and Credit No. 5410-KE) by US$45.8 million (9 percent) thereby increasing the Government’s financial burden. As of December 27, 2018, the total IDA amount for the two credits had been reduced to US$457.7 million equivalent compared to US$503.5 million at the time of approval. This reduction in US$ amount is impacting adversely on the performance of the project, creating a large financing gap, particularly in the civil works and shifting the burden to the Government; (c) risk of non-completion due to lack of funds, since in addition to counterpart funding, the Government would have to fund the amount undisbursed under the IDA Credits (about US$28 million equivalent) if the IDA Credits are not extended; and (d) need to complete resettlement and compensation payments and other safeguard-related issues, which could pose safeguards and reputational risks if not completed or delayed. 14. The World Bank Task Team confirms that the requirements of World Bank Investment Project Financing (IPF) Policy regarding closing dates specifically: (i) the project objectives continue to be achievable; (ii) the performance of the Borrower remains satisfactory; (iii) the World Bank and the Recipient have agreed on actions that will be undertaken by the Borrower to complete the remaining project activities; and (iv) there are no outstanding audits or interim financial reports. II. DESCRIPTION OF PROPOSED CHANGES 15. The proposed changes are (a) an extension of the closing date of the IDA Credits to December 31, 2019; and (b) updating of the results framework to align it with the proposed extended period of twelve months. The indicators and end of project target results remain unchanged. III. SUMMARY OF CHANGES Changed Not Changed Results Framework ✔ The World Bank Kenya Transport Sector Support Project (P124109) Loan Closing Date(s) ✔ Disbursement Estimates ✔ Implementation Schedule ✔ Implementing Agency ✔ DDO Status ✔ Project's Development Objectives ✔ Components and Cost ✔ Cancellations Proposed ✔ Reallocation between Disbursement Categories ✔ Disbursements Arrangements ✔ Overall Risk Rating ✔ Safeguard Policies Triggered ✔ EA category ✔ Legal Covenants ✔ Institutional Arrangements ✔ Financial Management ✔ Procurement ✔ Other Change(s) ✔ Economic and Financial Analysis ✔ Technical Analysis ✔ Social Analysis ✔ Environmental Analysis ✔ IV. DETAILED CHANGE(S) OPS_DETAILEDCHANGES_LOANCLOSING_TABLE LOAN CLOSING DATE(S) Original Revised Proposed Proposed Deadline Ln/Cr/Tf Status Closing Closing(s) Closing for Withdrawal Applications IDA-49260 Effective 31-Dec-2016 31-Dec-2018 31-Dec-2019 30-Apr-2020 The World Bank Kenya Transport Sector Support Project (P124109) IDA-54100 Effective 31-Dec-2018 31-Dec-2019 30-Apr-2020 OPS_DETAILEDCHANGES_DISBURSEMENT_TABLE DISBURSEMENT ESTIMATES Change in Disbursement Estimates Yes Year Current Proposed 2011 0.00 0.00 2012 5,700,000.00 5,700,000.00 2013 12,124,099.57 12,124,099.57 2014 25,858,897.03 23,052,125.19 2015 130,000,000.00 62,146,924.37 2016 117,000,000.00 56,821,586.89 2017 107,000,000.00 102,077,786.35 2018 105,817,003.40 124,356,689.77 2019 0.00 55,968,326.97 2020 0.00 15,352,460.89 2021 0.00 0.00 . The World Bank Kenya Transport Sector Support Project (P124109) The World Bank Kenya Transport Sector Support Project (P124109) . Results framework COUNTRY: Kenya Kenya Transport Sector Support Project Project Development Objectives(s) The revised PDOs are to: (a) increase the efficiency of road transport along the Northern Corridor and the Tanzania-Kenya-South Sudan road corridor; (b) enhance aviation safety and security to meet international standards; (c) improve the institutional arrangements and capacity in the transport sector; (d) restore the capacity of the international passenger terminal destroyed in a fire at JKIA; and (e) strengthen the capacity of KAA in disaster preparedness and responsiveness at Kenyan airports. Project Development Objective Indicators by Objectives/ Outcomes RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 increase the efficiency of road transport along the Northern Corridor and the Tanzania- Kenya-Sudan Average travel time 5.00 5.00 5.00 5.00 5.00 4.50 4.00 3.00 3.00 3.00 (Hours) Action: This indicator has been Revised Between Kisumu 5.00 5.00 5.00 5.00 5.00 4.50 4.00 3.00 3.00 3.00 and Kitale (Hours) Action: This indicator has been Revised Between Athi River and 1.50 1.50 1.50 1.50 1.50 1.30 1.20 0.90 0.90 0.90 Machakos turn off (Hours) The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 Action: This indicator has been Revised Between Bachuma gate and Maji ya 2.00 2.00 2.00 2.00 2.00 1.60 1.40 1.20 1.20 1.20 Chumvi (Hours) Action: This indicator has been Revised Vehicle operating 2.00 2.00 2.00 2.00 2.00 2.00 1.75 1.50 1.50 1.50 costs (Amount(USD)) Action: This indicator has been Revised on Kisumu-Kitale road 2.00 2.00 2.00 2.00 2.00 2.00 1.75 1.50 1.50 1.50 (Amount(USD)) Action: This indicator has been Revised on Athi RIver - Machakos turnoff 1.80 1.80 1.80 1.80 1.80 1.80 1.50 1.40 1.35 1.35 (Amount(USD)) The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 Action: This indicator has been Revised on Bachuma Gate- Maji ya Chumvi 2.00 2.00 2.00 2.00 2.00 2.00 1.75 1.50 1.50 1.50 (Amount(USD)) Action: This indicator has been Revised Enhance aviation Safety and Security to meet international standards JKIA meets ICAO and TSA aviation security and service level No No No No No No No Yes Yes Yes standards.(Yes/No, Custom) (Yes/No) Action: This indicator has been Revised Kenya meets ICAO standards and None No No No No No No Yes Yes Yes recommended practices (Text) Action: This indicator has been Revised KCAA cleared for IASA Category 1 No None None None None None Yes Yes Yes safety status (Text, Custom The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 Supplement) (Text) Action: This indicator has been Revised Improve the institutional arrangements and capacity in the transport sector Improved Institutional Arrangements and Capacity in the No No No No Yes Yes Yes Yes Yes Yes Transport Sector: NCA established and functional (Yes/No, Custom) (Yes/No) Action: This indicator has been Revised Engineer’s Act passed and effective (Yes/No, No No No Yes Yes Yes Yes Yes Yes Yes Custom Supplement) (Yes/No) Maritime rules and regulations No No No No Yes Yes Yes Yes Yes Yes developed and in use (Yes/No) National Transport No No No No No No No Yes Yes Yes Safety Authority The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 established and functional (Yes/No) KCAA restructured (Yes/No, Custom No No No No No No Yes Yes Yes Yes Supplement) (Yes/No) Coordination on Maritime Search and Rescue Unit strengthened No No No No No No No Yes Yes Yes (Yes/No, Custom Supplement) (Yes/No) Regulatory framework for land transport established No No No No No No No No Yes Yes (Yes/No, Custom Supplement) (Yes/No) Search and rescue capability on L. Victoria enhanced No No No No No No No Yes Yes Yes (Yes/No, Custom Supplement) (Yes/No) Restore the capacity of the international terminal destroyed in fire at JKIA The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_PDO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 Passenger terminal capacity restored by installation of No Yes prefabricated facilities (Yes/No) Strengthen the capacity of KAA in disaster preparedness and responsiveness at Kenyan airports Number of Kenyan Airport Personnel trained in disaster preparedness and 0.00 100.00 responsiveness strengthened (Percentage) Action: This indicator has been Revised PDO Table SPACE Intermediate Results Indicators by Components RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 A. Rehabilitation and improvement of roads, roadside facilities and road safety interventions Roads rehabilitated, Non-rural 0.00 200.00 (Kilometers) Action: This indicator has been Revised The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 Roads constructed, non-rural 0.00 31.00 (Kilometers) Action: This indicator has been Revised B. Institutional Strengthening and Capacity Building in the Transport Sector Navigational charts for Kenyan Coast developed to acceptable No No No No No No Yes Yes Yes Yes international standards and in use (Yes/No) Action: This indicator has been Revised Feasibility and engineering design studies completed to 0.00 7.00 acceptable standards and covering 1,150km (Number) Action: This indicator has been Revised Marking the boundaries for Right of Way and secure No No No No No Yes Yes Yes Yes KeNHA’s road assets (Class A roads) -3,500 The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 km completed (Yes/No) Action: This indicator has been Revised Draft Bill for NCA and NCA functional, ERB presented to ERB Parliament, and rules strengthened None and regulations for and KMA rules KMA developed and regulations (Text) in use. Action: This indicator has been Revised Studies on impact and roles of new 0.00 3.00 institutions completed (Text) Action: This indicator has been Revised C. Support to Kenya Airports Authority Construction of arrivals facility constructed and No No No No No No Yes Yes Yes Yes service in the Terminal 4(Yes/No, Custom) (Yes/No) Passenger terminal capacity restored by No No No No Yes Yes Yes Yes Yes Yes installation of The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 prefabricated facilities (Yes/No, Custom) (Yes/No) Disaster preparedness and response system No No No No Yes Yes Yes Yes Yes Yes developed and in use (Yes/No, Custom) (Yes/No) Action: This indicator has been Revised D. Support to Kenya Civil Aviation Authority Aviation Safety Inspectors in compliance with ICAO standards and IASA 0.00 0.00 6.00 4.00 4.00 4.00 4.00 4.00 4.00 5.00 category 1 safety status (Number, Custom) (Number) Action: This indicator has been Revised Number (KCAA recruited staff): Aviation Safety Inspectors in 0.00 0.00 10.00 20.00 38.00 38.00 38.00 0.00 0.00 38.00 compliance with ICAO standards and IASA category 1 safety status The World Bank Kenya Transport Sector Support Project (P124109) RESULT_FRAME_TBL_IO Indicator Name DLI Baseline Intermediate Targets End Target 1 2 3 4 5 6 7 8 (Number, Custom Breakdown) (Number) Action: This indicator has been Revised Construction of KCAA Office block 0.00 0.00 0.00 0.00 55.00 80.00 100.00 100.00 100.00 100.00 (Percentage) Dummy (Action: This Component has been Marked for Deletion) IO Table SPACE The World Bank Kenya Transport Sector Support Project (P124109)