The World Bank Implementation Status & Results Report Africa - Technical Capacity for Nutrition (P144629) Africa - Technical Capacity for Nutrition (P144629) AFRICA | Africa | Health, Nutrition and Population Global Practice | Institutional Development Fund| FY 2014 |Seq No: 1 | ARCHIVED on 13-Apr-2015 | ISR16740 | Implementing Agencies: ECSA-HC Key Dates Key Project Dates Board Approval date:05-Feb-2014 Effectiveness Date:25-Nov-2014 Planned Mid Term Review Date:16-Mar-2016 Actual Mid-Term Review Date:-- Original Closing Date:25-Nov-2017 Revised Closing Date:25-Nov-2017 Project Development Objectives Project Development Objective (from IDF Proposal) To strengthen the ability of the Governments of Kenya, Uganda and Tanzania to build the technical capacity of their front line workers for the delivery of essential nutrition interventions at health facilities and community level. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Building capacity for in-service training on nutrition for community and health workers:(Cost $360820.00 M) Building capacity for pre-service training on nutrition for community and health workers:(Cost $89230.00 M) Knowledge exchanges and advocacy for curricula development and adoption:(Cost $350280.00 M) Audit:(Cost $20000.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Moderately Satisfactory Overall Implementation Progress (IP) -- Moderately Satisfactory Overall Risk Rating -- Moderate Implementation Status and Key Decisions 4/13/2015 Page 1 of 4 The World Bank Implementation Status & Results Report Africa - Technical Capacity for Nutrition (P144629) This is the first ISR of the Technical capacity for Nutrition Project (P144629) which became effective in November 25, 2014. The Bank Team and the ECSA Team have been preparing the next steps in implementation, starting with an April 23-24, 2015 planning meeting held in Arusha, with the objective of discussing, reviewing and identifying, jointly with the three beneficiary countries Tanzania, Uganda and Kenya, the specific activities that need implementing to move forward. With regards to the achievement of the Project Development Objective, given that the project became effective in the latter part of the reporting period, it is still too early a stage to report meaninful progress towards it. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- -- Low 4/13/2015 Page 2 of 4 The World Bank Implementation Status & Results Report Africa - Technical Capacity for Nutrition (P144629) Macroeconomic -- -- Low Sector Strategies and Policies -- -- Moderate Technical Design of Project or Program -- -- Low Institutional Capacity for Implementation and Sustainability -- -- Moderate Fiduciary -- -- Moderate Environment and Social -- -- Low Stakeholders -- -- Low Other -- -- -- Overall -- -- Moderate Results Indicators PHINDPDOTBL Availability of a final pre-service nutrition trainig program and curricula for frontline health workers(Amount(USD),Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 25-Nov-2014 -- -- 25-Nov-2017 PHINDPDOTBL Availability of a final in-service training curricula for frontline health workers(Amount(USD),Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1.00 Date 25-Nov-2014 -- -- 25-Nov-2017 PHINDPDOTBL Availability of country plans of action on pre-service and in-service training on nutrition for frontline health workers(Amount(USD),Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 3.00 Date 25-Nov-2014 -- 25-Nov-2017 -- 4/13/2015 Page 3 of 4 The World Bank Implementation Status & Results Report Africa - Technical Capacity for Nutrition (P144629) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P144629 TF-16658 Effective USD 0.82 0.82 0.00 0.00 0.82 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P144629 TF-16658 Effective 21-Nov-2014 21-Nov-2014 25-Nov-2014 25-Nov-2017 25-Nov-2017 Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 4/13/2015 Page 4 of 4