FEDERAL REPUBLIC OF NIGERIA Nigeria Erosion and Watershed Management Project (NEWMAP) PROCUREMENT PLAN I. GENERAL 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Nigeria Erosion and Watershed Management Project-(NEWMAP) Loan / Credit No.: PIA: National NEWMAP Coordinating Unit. 2. Bank’s approval Date of the procurement Plan: March, 2012 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments (US$ equivalent) 1. ICB and LIB (Goods and services other > 750,000.00 ALL than consultancy services) 2. NCB 50,000.00 ≤ 750,000.00 NONE 3. ICB (Works) > 5,000,000.00 ALL 4. NCB (Works) 200,000 ≤ 5,000,000.00 NONE 5 Shopping-Goods < 50,000.00 NONE 6 Shopping-Works < 100,000.00 NONE 7 Training, Workshops, Study Tours All Values Based on Annual Work Plans & Budgets 2. Prequalification. Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply 4. Reference to (if any) Project Operational/Procurement Manual: shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages with Methods and Time Schedule Procurement of Goods : 1 2 3 4 5 6 7 8 9 Re Contract Estimate Procure Prequalificati Domestic Review Expected Comments f. (Description) d ment on (yes/no) Preference by Bank Bid- No Cost Method (yes/no) (Prior / Post) Opening . US$’000 Date 1 Computer Systems, Office, software and Accessories Computers and 684 NCB NO NO POST June 7, Procureme Accessories, software (see 2012 nt by each remark of the 7 packages, Photo- Colum) SPMU & copiers, UPS, Printers FPMU is and Scanners, Fax estimated Machines, Laptops, at ( USD Stationeries, 85.5) Consumables, LAN, Telephony,Lasers Software Licenses and Application,. 2 Office Furniture’s and Equipment Computer workstations 680 NCB NO NO PRIOR June 7, Procureme and Office Furniture (see 2012 nt by each remark of the 7 Water Dispenser, Colum) SPMU & Refrigerators, FPMU is Airconditioners, estimated Tables, Chairs, etc at ( USD 85) 3 Operational Vehicles 4-WD Vehicles (32 1440 NCB NO NO PRIOR June 7, Procureme units) (see 2012 nt by each remark of the 7 Colum) SPMU & FPMU is estimated at (180USD 4 Generator 40KVA Sound-Proof 240 NS NO NO PRIOR June 7, Procureme Electricity Generating (see 2012 nt by each Set-Purchase and remark of the 7 Installation (8 units) Colum) SPMU & FPMU is estimated at (30 USD 5 Training Communication, Presentation, Media Equipment and materials, etc Multimedia 364 NS NO NO PRIOR June 7, Procureme Projectors, (see 2012 nt by each remark of the 7 Flip Chart Stands, Colum) SPMU & Boards, GSM FPMU is TV/Video/Radio/Reco estimated rders and Digital at (45.5 Cameras, Internet USD Facilities, GPS, Raincoats and Enumerators bags, Program information kit, Program posters Community oriented Implementation manual 6 Field Equipment Purchase of Weather 2,400 NCB NO NO PRIOR June 7, Procureme Monitoring Stations, (see 2012 nt by each GPSs, Laser Measures, remark of the 7 Measuring Wheels, 1- Colum) SPMU & 2km Range Radios and FPMU is other survey equipment estimated and tools to gauge and at (300 trace watershed, USD terrestrial carbon and water flow 7 Geographic Information System Purchase of GIS 3520 NCB NO NO PRIOR June 7, Procureme data/Satellite Imagery,, (see 2012 nt by each Overhead photography, remark of the 7 etc Colum) SPMU & FPMU is estimated at (440 USD Sub Total 9,328.00 Procurement of Civil Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procure Prequalificati Domestic Review Expected Comments No. (Description) Cost ment on (yes/no) Preference by Bank Bid- US$’000 Method (yes/no) (Prior / Post) Opening Date 1 Civil works, and 252,000.00 ICB NO YES PRIOR October Procureme maintenance of flood 12, 2012 nt by ICB and gully erosion sites for all 7 SPMU 2 Office accommodation 240,000 NS NO NO PRIOR July, 2012 for 7 SPMU & FPCU SUB TOTAL 252,240.00 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS-National > 200,000.00 ALL 3 Consultant Services-CQS < 200,000.00 NONE 4 Consultant Services-lC > 50,000.00 ALL 5 Consultant Services-lC < 50,000.00 ToR only but ALL 6 Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review Expected Comments No. Method by Bank Proposals Cost. (Prior / Submission US$’000 Post) Date 1 Consultancy for the detailed 3,395.24 QCBS Prior On-going Consultancy for Engineering designs and data (see remark Priority sites collation for 35 sites Colum by each of the 7 SPMU (see each State Proc. Plan). 2 Consultancy for the supervision 6,824.47 QCBS Prior September Consultancy for of Civil Works for 35sites (see remark 2012 Priority sites Colum by each of the 7 SPMU (see each State Proc. Plan). 3 Consultancy for the RAP study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 4 Consultancy for the ESIA study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 5 Consultancy for the Socio- 875.00 IC Prior On-going Consultancy for Economic study 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at 25 USD per site 6 Consultancy for GIS data 875.00 IC Prior On-going Consultancy for collection and Mapping for 35 (see remark Priority sites sites Colum by each of the 7 SPMU is estimated at 75 USD per site 7 Consultancy for the detailed 3500.00 QCBS Prior August, 2012 Consultancy for Engineering designs and data (see remark 5 additional collation for additional 35sites Colum sites by each of the 7 SPMU is estimated at 100 USD per site 8 Consultancy for the detailed 2625.00 QCBS Prior June, 2013 Consultancy for ESIA, RAP and Socio (see remark 5 additional Economic Studies for Colum sites by each of additional 35 sites the 7 SPMU is estimated at 75 USD per site 9 Environmental engineering and 800 QCBS 9 design consultancy, 10 Procurement consultancy for 800 QCBS 10 June 1012 support of FPMU and SPMUs 11 M&E consultancy 400 QCBS 11 12 Consultancy for the support of 800.00 QCBS 12 Sept., 2012 Consultancy by SPMUs and FPMU (see remark each of the 7 Colum SPMU & FPMU is estimated at (100 USD 13 Consultancy for Legal Services 800.00 IC 13 Sept., 2012 Consultancy by each of the 7 (see remark SPMU & Colum FPMU is estimated at (100 USD 14 Consultancy for valuation and 3500.00 14 Sept., 2012 Consultancy by resettlement implementation (see remark each of the 7 Colum SPMU, to cover all sites is estimated at (500 USD per SPMU 15 Consultancy for Training and 1600.00 QCBS Prior August, 2012 Consultancy by Capacity Building (see remark each of the 7 Colum SPMU & FPMU is estimated at (200 USD 16 Consultancy-External Auditor 400.00 QCBS Prior March, 2013 Consultancy by (see remark FPMU to cover Colum each SPMU 17 Consultancy on Community 800.00 IC Prior Sept., 2012 Consultancy by consultation, Public Education (see remark each of the 7 and Erosion Management and Colum SPMU & awareness Techniques, FPMU is estimated at (100 USD Sub Total 27,744.71 IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities are listed with time schedule below; No. Expected outcome / Estimated Estimated Start Date Com Activity Description Cost US$ Duration m ‘000 e n t s A. TRAINING 1 3. Nos. Training courses for August 2012 Capacity Building PMU staff; Project activities for each Coordinator, Procurement of the 7 SPMU & Specialist, and financial mgt, FPMU is estimated at (90 USD M&E, Environmental specialists, Communication, Livelihood, Engineering 720.00(see 2WKS, specialists remark Colum each 2 Training of project finance August 2012 Capacity Building staff(FMS, APA, FO, IA) on 160.00(see activities for each flexible accounting software remark Colum 1wk of the 7 SPMU & FPMU is estimated at (20 USD B. WORKSHOP 3 September Capacity Building 2012 activities for each of the 7 SPMU & Capacity Building for key 240.00(see FPMU is estimated stakeholders remark Colum 3 days at (30 USD 4 September, Capacity Building 2012 activities for each of the 7 SPMU & 160(see FPMU is estimated ICT Training remark Colum 1 wk at (20 USD 5 Various Capacity Building activities for each Professional of the 7 SPMU & Seminars/Workshops/ 120.00(see FPMU is estimated subscriptions remark Colum Various at (15 USD 6 September Capacity Building 2 Days Sensitization/ activities for each 2012 Workshop for State and Local of the 7 SPMU & Govt. Officials on erosion and 200.00(see FPMU is estimated watershed management remark Colum 2 days at (25 USD 7 October Capacity Building 3 Day workshop for Line activities for each 2012 Ministries and MDAs on of the 7 SPMU & addressing and prevention of 240.00(see FPMU is estimated Land Degradation remark Colum 3- days at (30 USD 8 3 Day workshop for local October Capacity Building Govt. Focal Persons and 2012 activities for each Community Erosion watch of the 7 SPMU & Dogs on prevention of erosion FPMU is estimated 240.00(see at (30 USD and land degradation remark Colum 3-days 9 2013 Capacity Building activities for each Capacity Building on use of of the 7 SPMU & Metrological and GPS 200.00(see FPMU is estimated Equipment remark Colum 5-days at (25 USD C. STUDY/TOURS 10 240.00(see Various October Capacity Building remark Colum times 2012 activities for each Baseline survey/ Community of the 7 SPMU & needs assessment and capacity FPMU is estimated building at (30 USD 11 240.00(see Various August, Capacity Building remark Colum times 2012 activities for each Sensitization/ Awareness of the 7 SPMU & creation of NEWMAP in the FPMU is estimated 18 LGA at (30 USD 12 160.00(see WB and Capacity Building remark Colum FAO to activities for each Participation in watershed of the 7 SPMU & determine studies organized by the world FPMU is estimated bank and FAO at (20 USD 13 240.00(see Various December, Capacity Building remark Colum 2012 activities for each of the 7 SPMU & Launching of ESIA and RAP FPMU is estimated for priority sites at (30 USD 14 160.00(see Various Oct., 2012 Capacity Building remark Colum activities for each of the 7 SPMU & FPMU is estimated livelihood studies at (20 USD 15 160.00(see Various World Bank Capacity Building Participation in remark Colum activities for each determined Biodiversity/forest carbon of the 7 SPMU & study organized by the World FPMU is estimated Bank at (20 USD 16 120.00(see 4-days each July 2012 Capacity Building remark Colum activities for each Recognizance survey of of the 7 SPMU & Project sites (Erosion and FPMU is estimated Watershed) at (15 USD 17 2480.00(see 4-wks February., Capacity Building remark Colum 2013 activities for each of the 7 SPMU & International Training and FPMU is estimated study tours at (310 USD 18 Various World Bank Capacity Building determined activities for each Attendance of World Bank of the 7 SPMU & Organized training, meetings, 800.00(see FPMU is estimated seminar and workshops remark Colum at (100 USD Sub Total 6,880.00 PROCUREMENT Nigeria : Nigeria Erosion and Watershed Management Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-06-12 2019-08-01 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124905 GPN Date: Project Name: Nigeria Erosion and Watershed Management Project Loan / Credit No: IDA / 51050 Executing Agency(ies): ABIA STATE PROJECT MANAGEMENT UNIT WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/NCB/CW/14/02 Component 1: Erosion and Under / Amuda Achara and Single Stage - One IDA / 51050 Watershed Management Post Request for Bids Open - National 3,013,000.00 0.00 Implementati 2013-11-08 2014-01-07 2014-01-28 2014-02-18 2014-03-25 2015-11-15 Amuzukwu Gully Erosion Envelope Infrastructure Investments on Remediation Works ABS/NEWMAP/NCB/CW/17/01 / Umuda Isingwu/Ibeku Complex Gully Erosion Component 1: Erosion and Under Single Stage - One Remediation Works and IDA / 51050 Watershed Management Prior Request for Bids Open - National 5,200,000.00 0.00 Implementati 2017-02-13 2017-02-27 2017-03-20 2017-04-10 2017-05-08 2018-08-31 Envelope Umuogele Umuakwu Nsulu Infrastructure Investments on Gully Erosion Remediation Works ABS/NEWMAP/NCB/CW/17/03 / Procurement and Component 1: Erosion and Pending implementation of Household Single Stage - One IDA / 51050 Watershed Management Post Request for Bids Open - National 400,000.00 0.00 Implementati 2017-12-06 2017-12-13 2018-01-10 2018-01-24 2018-02-14 2018-06-14 and community water Envelope Infrastructure Investments on harvesting for seven Multiple sites. ABS/NEWMAP/NS/CW/16/03 / Renovation of New Office Complex (Paintings, Under electricals, plumbing, Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 100,000.00 0.00 Implementati 2017-06-12 2017-07-24 2017-08-23 perimeter fencing, Management Quotations Envelope on transformer, roofing, room restructuring, ashphalting, drainage, etc) ABS/NEWMAP/NS/CW/16/01 / Provision for the Routine Component 1: Erosion and Pending Request for Single Stage - One Maintenance of the Civil IDA / 51050 Watershed Management Post Open - National 100,000.00 0.00 Implementati 2017-12-25 2018-03-19 2019-03-19 Quotations Envelope Works at the Completed Infrastructure Investments on Sites ABS/NEWMAP/NCB/CW/16/02 / Emergency and Temporary Component 1: Erosion and Pending Request for Single Stage - One Stabilization of Gullies and IDA / 51050 Watershed Management Post Open - National 100,000.00 0.00 Implementati 2017-07-17 2017-08-19 2019-01-25 Quotations Envelope Slide Management for the Infrastructure Investments on New Wave of Gullies ABS/NEWMAP/NCB/CW/14/01 Component 1: Erosion and Under / Umuezeukwu Gully Single Stage - One IDA / 51050 Watershed Management Prior Request for Bids Open - National 1,980,000.00 0.00 Implementati 2013-11-08 2014-01-29 2014-02-26 2014-03-12 2014-04-23 2017-03-31 Erosion Remediation Works Envelope Infrastructure Investments on and Extra Works ABS/NEWMAP/ICB/CW/17/01 / Emergency flood Component 1: Erosion and Under mitigation measures for Aba Open - Single Stage - One IDA / 51050 Watershed Management Prior Request for Bids 100,998,000.00 0.00 Implementati 2017-09-18 2017-09-25 2017-11-06 2017-12-16 2018-01-22 2019-11-03 municipality Lot 1 - Uratta International Envelope Infrastructure Investments on Pond, Umuagbai/Port Harcourt Road flood plain Page 1 ABS/NEWMAP/NCB/CW/18/01 / Construction / Remediation Component 1: Erosion and Pending Single Stage - One works at Gully erosion site IDA / 51050 Watershed Management Post Request for Bids Open - National 2,000,000.00 0.00 Implementati 2018-03-05 2018-03-10 2018-04-21 2018-05-21 2018-06-25 2020-02-15 Envelope in AMUDA ACHARA Infrastructure Investments on ISUOCHI in Abia state ABS/NEWMAP/NCB/CW/18/02 / Construction / Remediation works at Gully erosion site Component 1: Erosion and Pending in UMUDA Single Stage - One IDA / 51050 Watershed Management Post Request for Bids Open - National 1,563,000.00 0.00 Implementati 2018-03-19 2018-03-24 2018-05-05 2018-06-04 2018-07-09 2020-06-28 ISINGWU/UMUAGU IBEKU Envelope Infrastructure Investments on GULLY EROSION SITE Works in Abia State (Additional works) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/NS/GDS/17/01 / Computers and Accessories, software packages, Photo- Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 130,000.00 0.00 Completed 2017-03-14 2017-05-30 2017-07-29 copiers, UPS, Printers and Management Quotations Envelope Scanners,Fax Machines, Laptops, etc ABS/NEWMAP/NS/GDS/17/02 / Office Furniture Water Dispenser, Refrigerators, Air conditioners, Tables, Chairs for the project office. Procure Component 4: Project Request for Single Stage - One office internet for IDA / 51050 Post Open - National 100,000.00 12,446.53 Completed 2017-03-21 2017-05-23 2017-06-22 Management Quotations Envelope Engineering design and supervision firm and basic office furniture and equipment for PMU and EDSF ABS/NEWMAP/NS/GDS/17/05 / Personal Protective Equipment for site works ( Under Component 4: Project Request for Single Stage - One Cover alls, helmets, safety IDA / 51050 Post Open - National 10,000.00 0.00 Implementati 2017-06-19 2017-07-22 2017-08-19 Management Quotations Envelope boots, nose, eye and ear on masks, rain coats, rain boots, etc ABS/NEWMAP/NS/GDS/17/07 / Provide for ABIA Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 13,000.00 9,974.57 Completed 2017-06-10 2017-07-10 2017-08-07 NEWMAP branding products Management Quotations Envelope and activities. ABS/NEWMAP/NS/GDS/17/10 / Provision of 33KVA Component 4: Project Request for Single Stage - One transformer for NEWMAP IDA / 51050 Post Open - National 40,000.00 54,011.04 Completed 2017-03-27 2017-05-22 2017-06-21 Management Quotations Envelope OFFICE and Provision of 16KVA Generating set. ABS/NEWMAP/NS/GDS/17/03 / 1Nos. 16- seater Bus for Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 210,000.00 239,206.45 Completed 2017-02-24 2017-04-14 2017-05-24 PMUand 2NOS 4 x4 2016 Management Quotations Envelope Pickup Van with bootcover. ABS/NEWMAP/NS/CW/18/01 Component 1: Erosion and Pending / Perimeter fencing of Request for Single Stage - One IDA / 51050 Watershed Management Post Limited 100,000.00 0.00 Implementati 2018-05-19 2018-07-14 2018-09-12 completed Erosion sites to Quotations Envelope Infrastructure Investments on avoid encroachment Page 2 ABS/NEWMAP/CP/GDS/17/04 / Community disaster risk Component 1: Erosion and management activities for Request for Single Stage - One IDA / 51050 Watershed Management Post Open - National 100,000.00 0.00 Canceled 2017-08-21 2017-09-04 2017-09-18 2017-09-25 2017-10-16 2018-01-24 flood and landslide/gully Quotations Envelope Infrastructure Investments expansion for prioritized sites. ABS/NEWMAP/CP/GDS/17/01 / Community sub grants for management of Soil & Water conservation zones and Support to Component 1: Erosion and communities & Line MDAs Request for Single Stage - One IDA / 51050 Watershed Management Post Open - National 50,000.00 0.00 Canceled 2017-03-28 2017-07-11 2017-08-20 to establish nurseries, plant Quotations Envelope Infrastructure Investments trees, grasses of assorted indigenous species; construction of renno mattreasses and gabion boxes. ABS/NEWMAP/CP/GDS/16/02 / Sub-grants to community Component 1: Erosion and Request for Single Stage - One associations on livelihood IDA / 51050 Watershed Management Post Open - National 338,000.00 0.00 Canceled 2017-03-26 2017-08-08 2018-09-12 Quotations Envelope enhancements,employment Infrastructure Investments and skill acquisition NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/QCBS/CON/16 /01 / Consultancy for the Component 1: Erosion and generation of LRID for Quality And Cost- Open - IDA / 51050 Watershed Management Post 160,000.00 152,447.55 Completed 2016-08-15 2016-09-26 2016-11-21 2016-12-05 2016-12-26 2017-01-09 2017-02-06 2017-05-17 erosion and watersheds, Based Selection International Infrastructure Investments drainage basins of storm water multiple sites ABS/NEWMAP/QCBS/CON/15 Component 2: Erosion and /01 / Consultancy for the Watershed Management Quality And Cost- Open - Pending IDA / 51050 Prior 900,000.00 0.00 2015-05-27 2015-06-10 2015-09-02 2015-09-16 2015-10-07 2015-11-18 2015-12-23 2016-12-22 Aba Urban Storm Water Institutions and Information Based Selection International Implementation Management MasterPlan Services ABS/NEWMAP/CQS/CON/16/0 2 / Consultancy for Component 1: Erosion and Consultant sensitization, design and IDA / 51050 Watershed Management Post Qualification Open - National 160,000.00 156,606.72 Signed 2017-02-07 2017-03-21 2017-05-31 2017-06-14 2017-07-11 2018-01-27 supervision of Household and Infrastructure Investments Selection community water harvesting ABS/NEWMAP/QCBS/CON/14 /01 / Procurement of consultants for Study, Component 1: Erosion and Designs,and Supervision of Quality And Cost- Open - Under IDA / 51050 Watershed Management Prior 1,900,000.00 0.00 2017-07-24 2017-09-04 2017-11-13 2017-11-27 2017-12-11 2018-01-08 2018-01-29 2020-02-18 erosion/flood sites and re- Based Selection International Implementation Infrastructure Investments adcertisement of a new one at the expiration of existing one Page 3 ABS/NEWMAP/CQS/CON/15/0 Component 1: Erosion and Consultant Open - 1 / Procurement of Focal IDA / 51050 Watershed Management Prior Qualification 183,000.00 0.00 Canceled 2014-02-03 2014-04-28 2014-04-28 2014-08-18 2014-09-29 2017-06-09 International NGO Infrastructure Investments Selection ABS/NEWMAP/CQS/CON/17/0 1 / Support to communities & Line MDAs to establish nurseries, plant trees, grasses of assorted Component 1: Erosion and Consultant indigenous species; IDA / 51050 Watershed Management Post Qualification Open - National 210,000.00 0.00 Canceled 2017-06-26 2017-07-17 2017-08-28 2017-09-11 2017-10-09 2018-01-07 construction of renno Infrastructure Investments Selection mattreasses and gabion boxes.(Multiple contracts) to enhance capacities of Line ministries and ICT tools INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ABS/NEWMAP/IC/CON/16/01 / Consultancy for the Component 1: Erosion and Individual production of Sub-Catchment IDA / 51050 Watershed Management Post Consultant Open 35,000.00 20,749.77 Completed 2017-02-03 2017-04-07 2017-04-28 2017-06-02 2017-08-31 Management Planning maps Infrastructure Investments Selection and 3D models ABS/NEWMAP/IC/CON/17/04 Individual / Delineation of the newly Component 4: Project IDA / 51050 Post Consultant Open 60,000.00 8,482.86 Completed 2017-02-13 2017-03-20 2017-03-27 2017-04-24 2017-06-13 prioritized sites(multiple Management Selection contract) ABS/NEWMAP/IC/CON/17/01 / Safeguards (ESMP Individual Component 4: Project Studies for 6 newly IDA / 51050 Post Consultant Open 175,000.00 57,896.31 Completed 2017-02-01 2017-03-15 2017-05-03 2017-05-24 2017-08-22 Management prioritized sites ) (Multiple Selection contracts) ABS/NEWMAP/IC/CON/17/02 Individual / Safeguards (RAP Studies Component 4: Project IDA / 51050 Post Consultant Open 168,000.00 98,728.03 Completed 2017-01-02 2017-03-15 2017-04-12 2017-05-24 2017-08-22 for 6 newly prioritized sites Management Selection ) (Multiple contracts) ABS/NEWMAP/IC/CON/17/03 / Livelihood need assesment Component 1: Erosion and Individual Studies for 6 newly IDA / 51050 Watershed Management Post Consultant Open 75,000.00 17,938.69 Completed 2017-02-02 2017-03-15 2017-05-03 2017-05-24 2017-08-22 prioritized sites) (Multiple Infrastructure Investments Selection contracts) ABS/NEWMAP/IC/CON/17/05 / Baseline Studies for Individual Component 4: Project Studies for 6 newly IDA / 51050 Post Consultant Open 125,000.00 60,627.39 Completed 2017-02-01 2017-03-08 2017-05-03 2017-05-24 2017-08-22 Management prioritized sites ) (Multiple Selection contracts) ABS/NEWMAP/IC/CON/15/01 Individual / Procurement of Individual Component 4: Project IDA / 51050 Post Consultant Open 50,000.00 0.00 Canceled 2015-02-02 2015-03-02 2016-02-29 2016-03-28 2017-04-10 Procurement Consultant to Management Selection support the PMU Page 4