The World Bank Report No: ISR13999 Implementation Status & Results Public Disclosure Copy Brazil PLANTAR GREEN PIG IRON PROJECT (P120637) Operation Name: PLANTAR GREEN PIG IRON PROJECT Seq.No: 3 Status: ARCHIVED Archive Date: 21-Jul-2014 (P120637) Project Stage: Implementation Country: Brazil Approval FY: 2012 Product Line: Carbon Offset Region: LATIN AMERICA AND Lending Instrument: CARIBBEAN Implementing Agency: Key Dates Board Approval 03-Aug-2011 Original Closing 31-Dec-2018 Planned Mid Term Review Last Archived ISR 07-Jun-2013 Date Date Date Date Effectiveness 03-Aug-2011 Revised Closing 31-Dec-2018 Actual Mid Term Review Date Date Date Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Low Low Implementation Status Overview Public Disclosure Copy A supervision mission to verify environmental and social aspects of the operation took place in December 2013. The company continues to hold the relevant licenses and certificates including the FSC one for good forest management. Three areas are already certified (MG02, MG03and MG04), pending only one other area, MG15, which preparative process (contacts with audits and internal preparation, through the formation of special committee manager) is ongoing. A FSC field audit is planned for next July. Locations Page 1 of 2 The World Bank Report No: ISR13999 Country First Administrative Division Location Planned Actual Public Disclosure Copy Brazil Minas Gerais Estado de Minas Gerais ✔ ✔ Key Decisions Regarding Implementation A supervision mission to verify environmental and social aspects of the operation took place in learly December 2013. The company continues to hold the relevant licenses and certificates including the FSC certification for good forest management, and it is in compliance with the Bank safeguards. Related Projects There are no related projects. Public Disclosure Copy Page 2 of 2