PROCUREMENT PLAN Project information: Mozambique - P165453 - Mozambique Energy For All (ProEnergia) Project Implementation agency: EDM (Electricidade de Moçambique); FUNAE (Fundo de Energia Date of the Procurement Plan: March 2019 Period covered by this Procurement Plan: March 2019 – December 2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Regulamento 5/2016 of March 8, 2016, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable. Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable for those contracts identified in the Procurement Plan tables; Works: is not applicable for those contracts identified in the Procurement Plan tables PROCUREMENT Mozambique : Mozambique Energy For All (ProEnergia) PLAN General Information Country: Mozambique Bank’s Approval Date of the Original Procurement Plan: 2020-02-28 2020-03-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P165453 GPN Date: 2019-03-15 Project Name: Mozambique Energy For All (ProEnergia) Loan / Credit No: IDA / D4410 Executing Agency(ies): Energy Fund WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-FUNAE-158159-GO-RFQ Pending Technical Assistance and Request for Single Stage - One / IT equipment to support IDA / D4410 Post Limited 0.00 Implementati 2020-04-07 2020-06-05 2020-09-03 Implementation Support Quotations Envelope the project activities on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MZ-FUNAE-158152-CS- QCBS / Feasibility Studies Technical Assistance and Quality And Cost- Pending for 11 Photovoltaic Mini- IDA / D4410 Post Open - National 0.00 2020-03-31 2020-04-21 2020-06-01 2020-06-02 2020-06-17 2020-07-09 2020-08-15 2021-08-15 Implementation Support Based Selection Implementation grids in Mozambique and Procurement Strategy MZ-FUNAE-158162-NC-RFQ Technical Assistance and Least Cost Pending / Financial Audit of the IDA / D4410 Post Open - National 0.00 2020-03-31 2020-04-21 2020-06-04 2020-07-02 2020-08-01 2020-09-05 2020-10-10 2021-10-10 Implementation Support Selection Implementation Project MZ-FUNAE-162824-CS- QCBS / Preparation of an off-grid electrification roadmap and supporting Technical Assistance and Quality And Cost- Open - Pending analysis for the design of IDA / D4410 Post 0.00 2020-03-31 2020-04-21 2020-05-25 2020-06-15 2020-07-05 2020-07-26 2020-08-24 2020-12-22 Implementation Support Based Selection International Implementation results-based financing instruments to deliver off- grid energy services to underserved areas in Mozambique Page 1 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2