RAMP -2: Procurement Plan – Jan. 2017. (RURAL ROADS AND MOBILTY PROJECT-2 PP:2017) I. General 1. Project Information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Rural Road and Mobility Project 2 (RAMP2). Loan/Credit No.: P095003 PIA: Federal Project Management Unit (FPMU) 2. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision of Updated Procurement Plan, June 2010]. Updated January 2017 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by initial procurement plans: The procurement period of project covered from year June 2010 to December 2012; (Period covered by this current procurement plan: and January 2017 to December 2017 and or to June 2018). II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comment (US$ equivalent) 1. ICB and LIB (Goods and services other > 1,000,000.00 ALL than consultancy services) 2. NCB (Goods) 100,000.00 ≤ 1,000,000.00 NONE 3 IT System, and Non-Consulting Services > 1,000,000.00 (ICB). NCB: 100,000.00 ≤ 1,000,000.00 4. ICB (Works) > 10,000,000.00 ALL 5. NCB (Works) 300,000 ≤ 10,000,000.00 NONE 6 Shopping-Goods < 100,000.00 NONE 7 Shopping-Works < 300,000.00 NONE 8. Community Participation in All Values SSS of Community Procurement acceptable to the Maintenance Association and described in the PIM groups, etc. 9 Training, Workshops, Study Tours All Values Based on Annual Work Plans & Budgets July 9, 2010 2. Pre-qualification. Bidders for major works could be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply. 4. Reference to (if any) Project Operational/Procurement Manual: Shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Summary of the Procurement Packages planned during the next 12 to18 (from January 2017). [ Packages which require Bank’s Prior review and Post Review packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 Yes Prior the ICB (Works) Summary of 43.77 15 Yes Prior the ICB (Goods) Summary of 64.53 18 No Post the NCB (Works) Summary of 1.86 4 No Post the NCB (Goods) Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) July 9, 2010 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Selection Method Prior Review Threshold Comment 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS-National > 300,000.00 ALL 3 Consultant Services-CQS < 300,000.00 NONE 4 Consultant Services-lC > 200,000.00 ALL 5 Consultant Services-lC < 100,000.00 ToR only but ALL 6 Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior reviewed QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description Estimated Packages Review Comments of Cost by Bank Assignment US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods (***This is the consolidated Procurement Plan for all the RAMP2 PIUs (Federal and States.). The individual PP submitted for review/ or already cleared for each SPIU is uploaded in the system). July 9, 2010 July 9, 2010 PROCUREMENT Nigeria : NG-RURAL ACCESS & MOBILITY PROJECT-Phase 2 PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-07-19 2020-01-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P095003 GPN Date: Project Name: NG-RURAL ACCESS & MOBILITY PROJECT-Phase 2 Loan / Credit No: IDA / 51540 Executing Agency(ies): Niger RAMP 2 WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-1 / Cluster 1: Upgrading and Pending Rehabilitation of 94.8km Single Stage - One IDA / 51540 Rehabilitation of Rural Prior Request for Bids Open - National 8,478,261.12 0.00 Implementati 2014-01-20 2014-02-07 2014-03-24 2014-05-05 2014-06-13 2015-12-31 rural roads (Wuya,Enagi, Envelope Transport Infrastructure on Mokwa) MOF-REF-2 / Cluster 2: Upgrading and Pending Rehabilitation of 52.5km Single Stage - One IDA / 51540 Rehabilitation of Rural Prior Request for Bids Open - National 5,384,354.35 0.00 Implementati 2014-01-20 2014-02-12 2014-03-24 2014-05-05 2014-06-13 2015-12-31 rural roads (Dikko, Kabo, Envelope Transport Infrastructure on Tafa - Abuci Izom) MOF-REF-3 / Cluster 3: Upgrading and Pending Rehabilitation of 58.0km Single Stage - One IDA / 51540 Rehabilitation of Rural Prior Request for Bids Open - National 5,599,643.44 0.00 Implementati 2014-01-20 2014-02-07 2014-03-24 2014-05-05 2014-06-13 2015-12-31 rural roads (Auna, Tungan Envelope Transport Infrastructure on Jika, Wawa, Malali) MOF-REF-4 / Cluster 1: Construction of 3Nr box Upgrading and Pending culverts at Mashegu and Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Open - National 592,236.18 0.00 Implementati 2016-03-24 2016-03-24 2016-05-05 2016-05-18 2016-06-16 2017-04-28 Magama LGAs and Envelope Transport Infrastructure on Rehabilitation of 3Nr Box Culvert at Kontagora LGA MOF-REF-5 / Cluster 2: Construction of 1No. Bridge Upgrading and Pending Single Stage - One and 1No. Box culvert at IDA / 51540 Rehabilitation of Rural Post Request for Bids Open - National 592,236.18 0.00 Implementati 2016-03-24 2016-03-29 2016-05-05 2016-05-18 2016-06-16 2017-04-28 Envelope Agaie LGA and 1No. Pipe Transport Infrastructure on culvert at Lapai LGA MOF-REF-6 / Cluster 3: Construction of 2Nr bridges Upgrading and Pending Single Stage - One at Edati and Gbako LGAs IDA / 51540 Rehabilitation of Rural Post Request for Bids Open - National 789,648.24 0.00 Implementati 2016-03-24 2016-03-24 2016-05-05 2016-05-18 2016-06-16 2017-04-28 Envelope and 1Nr culvert at Lavun Transport Infrastructure on LGA MOF-REF-7 / Cluster 4: Constrution of 1Nr bridge Upgrading and Pending and 1Nr box culvert at Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Open - National 630,499.07 0.00 Implementati 2016-03-24 2016-03-24 2016-05-05 2016-05-18 2016-06-16 2017-04-28 Bosso LGA and 2Nr box Envelope Transport Infrastructure on culvert at Wushishi and Rafi LGAs MOF-REF-8 / Cluster 5: Upgrading and Pending Construction of 1Nr Bridge Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Open - National 748,877.64 0.00 Implementati 2016-03-24 2016-03-24 2016-05-05 2016-05-18 2016-06-16 2017-04-28 at Gurara LGA and 3Nr box Envelope Transport Infrastructure on culverts at Shiroro, Paiko, MOF-REF-19 / 4th Annual Community-based Road Pending Request for Single Stage - One Mechanized maintenance of IDA / 51540 Maintenance and Annual Post Limited 80,645.16 0.00 Implementati 2017-09-23 2017-10-27 2017-12-28 Quotations Envelope 8.1km pilot road project Mechanized Maintenance on Page 1 MOF-REF-20 / Upgrading and Rehabilitation/Construction of Single Stage - One IDA / 51540 Rehabilitation of Rural Prior Request for Bids Open - National 28,771,808.90 23,575,808.95 Signed 2018-02-13 2018-02-23 2018-04-06 2018-04-27 2018-05-26 2019-07-12 403.54km rural roads in Envelope Transport Infrastructure Niger State in 7 Clusters NG-NIGER RAMP 2-48362- CW-RFB / On the Spot Upgrading and Pending Improvement of 104km rural Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Open - National 1,670,997.00 0.00 Implementati 2018-02-16 2018-02-21 2018-04-04 2018-04-18 2018-05-10 2018-11-29 roads to 20 No. River Envelope Transport Infrastructure on crossing locations in Niger State NG-NIGER RAMP 2-48366- Community-based Road Pending CW-RFB / Annual Single Stage - One IDA / 51540 Maintenance and Annual Post Request for Bids Limited 487,871.00 0.00 Implementati 2018-02-28 2018-03-05 2018-04-02 2018-04-17 2018-05-09 2018-11-30 mechanized maintenance of Envelope Mechanized Maintenance on 50km pilot roads project NG-NIGER RAMP 2-48378- Community-based Road Pending CW-RFB / Annual Single Stage - One IDA / 51540 Maintenance and Annual Post Request for Bids Open - National 851,613.00 0.00 Implementati 2018-07-10 2018-07-15 2018-08-26 2018-09-10 2018-10-01 2019-03-30 mechanized maintenance of Envelope Mechanized Maintenance on 176km rural roads (Phase 1) NG-NIGER RAMP 2-62275- Upgrading and Pending CW-DIR / Construction of IDA / 51540 Rehabilitation of Rural Prior Direct Selection Direct 234,967.61 0.00 Implementati 2018-05-14 2018-05-18 2018-05-31 2018-07-02 Additional Works on Auna Transport Infrastructure on Bridge NG-NIGER RAMP 2-88714- CW-RFB / Annual Community-based Road Single Stage - One mechanized Maintenance and IDA / 51540 Maintenance and Annual Post Request for Bids Limited 541,054.08 366,070.76 Signed 2018-12-03 2018-12-07 2019-01-04 2019-01-18 2019-02-15 2019-05-31 Envelope emergency repairs of 72.6km Mechanized Maintenance Rural Roads under Phase 1 NG-NIGER RAMP 2-97300- CW-RFB / Annual Community-based Road Pending mechanized maintenance of Single Stage - One IDA / 51540 Maintenance and Annual Post Request for Bids Limited 424,219.00 0.00 Implementati 2019-02-01 2019-02-06 2019-03-06 2019-03-15 2019-04-19 2019-10-16 45.25km Mokwa - Ja'agi - Envelope Mechanized Maintenance on Kudu Rural Road under Phase 1 NG-NIGER RAMP 2-97310- CW-RFB / Annual mechanized maintenance of Community-based Road Pending Single Stage - One 56.6km Rural Roads under IDA / 51540 Maintenance and Annual Post Request for Bids Limited 543,281.25 0.00 Implementati 2019-08-05 2019-08-09 2019-09-06 2019-09-13 2019-10-11 2020-04-08 Envelope Phase 1 (Auna - Tungan Mechanized Maintenance on Jika - Shafini, Abuchi - Izom - Suleja) NG-NIGER RAMP 2-97283- CW-RFB / Annual Community-based Road Pending mechanized maintenance of Single Stage - One IDA / 51540 Maintenance and Annual Post Request for Bids Limited 109,375.00 0.00 Implementati 2019-02-25 2019-03-02 2019-03-30 2019-04-09 2019-05-07 2019-11-03 10km Sharubutu - Emi Envelope Mechanized Maintenance on Ndayisa - Emi - Ndajiya Additional Pilot Roads NG-NIGER RAMP 2-101462- Community-based Road Pending CW-RFB / Annual Single Stage - One IDA / 51540 Maintenance and Annual Post Request for Bids Limited 247,656.25 0.00 Implementati 2019-08-06 2019-08-11 2019-09-10 2019-09-24 2019-10-29 2020-04-26 mechanized maintenance of Envelope Mechanized Maintenance on 37.2km additional pilot Road NG-NIGER RAMP 2-48364- CW-RFB / Annual Community-based Road Pending Single Stage - One mechanized maintenance of IDA / 51540 Maintenance and Annual Post Request for Bids Limited 80,645.00 0.00 Implementati 2018-09-13 2018-09-18 2018-10-02 2018-10-16 2018-10-29 2018-12-31 Envelope RafinYashi - Shata pilot Mechanized Maintenance on road (8.1km). NG-NIGER RAMP 2-141415- Upgrading and Pending CW-RFB / Emergency repair Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Limited 210,273.28 0.00 Implementati 2019-10-23 2019-10-28 2019-11-25 2019-12-02 2019-12-26 2020-03-26 works at Sabon Daga and Envelope Transport Infrastructure on Nyela Bridge Page 2 NG-NIGER RAMP 2-141417- CW-RFB / Construction of 3x2.5m 6 cell Box Culvert, Upgrading and Pending 1No. 3x2.5m 3 cell Culvert Single Stage - One IDA / 51540 Rehabilitation of Rural Post Request for Bids Limited 228,855.31 0.00 Implementati 2019-10-23 2019-10-25 2019-11-22 2019-12-03 2019-12-27 2020-03-27 and Repair works along Envelope Transport Infrastructure on Wuya Suman - Lemu Road and Emigimanzhi Bridge in Niger State NG-NIGER RAMP 2-141413- CW-DIR / Construction of 60 Upgrading and Pending Single Stage - One meters 4 Span Bridge at IDA / 51540 Rehabilitation of Rural Post Request for Bids Limited 1,316,330.61 0.00 Implementati 2019-10-23 2019-10-28 2019-11-25 2019-12-03 2019-12-31 2020-04-30 Envelope Suleja- Izom at KM 16+500 Transport Infrastructure on (Phase 1 Road) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-17 / Procurement Upgrading and Pending Request for Single Stage - One of 6nos 4x4 4WD Double IDA / 51540 Rehabilitation of Rural Post Limited 358,064.52 0.00 Implementati 2017-05-15 2017-07-10 2017-08-01 Quotations Envelope Cabin Pick-up vehicle Transport Infrastructure on Project Management and Strengthening of State and MOF-REF-18 / Procurement Request for Single Stage - One IDA / 51540 Federal Road Sector Post Limited 21,450.00 10,359.62 Completed 2017-08-10 2017-09-08 2017-10-06 of GIS Equipment Quotations Envelope Institutional, Policy and Regulatory Framework NG-NIGER RAMP 2-48347- Project Management and GO-RFQ / Procurement of Strengthening of State and Under Request for Single Stage - One office equipment, Printers, IDA / 51540 Federal Road Sector Post Limited 26,839.00 0.00 Implementati 2018-02-18 2018-03-29 2018-04-26 Quotations Envelope Digital Cameras and sundry Institutional, Policy and on communication devices. Regulatory Framework Project Management and NG-NIGER RAMP 2-48351- Strengthening of State and Under Request for Single Stage - One GO-RFQ / Procurement of IDA / 51540 Federal Road Sector Post Limited 25,033.00 0.00 Implementati 2018-02-18 2018-03-20 2018-04-17 Quotations Envelope Laptops and UPS Institutional, Policy and on Regulatory Framework NG-NIGER RAMP 2-48353- Upgrading and GO-RFQ / Procurement of 2 Request for Single Stage - One IDA / 51540 Rehabilitation of Rural Post Limited 154,839.00 131,652.00 Completed 2018-02-21 2018-03-26 2018-04-23 No 4x4 pickup Vehicles for Quotations Envelope Transport Infrastructure Supervisory Consultancy NG-NIGER RAMP 2-48355- GO-RFQ / Procurement of Community-based Road Pending Request for Single Stage - One Equipment for the IDA / 51540 Maintenance and Annual Post Limited 48,387.10 0.00 Implementati 2018-02-19 2018-03-22 2018-04-19 Quotations Envelope maintenance group of the Mechanized Maintenance on additional 74km pilot road NG-NIGER RAMP 2-48361- Upgrading and Under Request for Single Stage - One GO-RFQ / Procurement of IDA / 51540 Rehabilitation of Rural Post Limited 16,936.00 0.00 Implementati 2018-02-19 2018-03-23 2018-04-20 Quotations Envelope 15nos motorcycle Transport Infrastructure on NG-NIGER RAMP 2-97275- GO-RFQ / Procurement of Community-based Road Pending Request for Single Stage - One Equipment for maintenance IDA / 51540 Maintenance and Annual Post Limited 219,389.35 0.00 Implementati 2019-03-01 2019-03-30 2019-05-05 Quotations Envelope group of the 403km Rural Mechanized Maintenance on Roads Page 3 Project Management and NG-NIGER RAMP 2-97263- Strengthening of State and Pending Request for Single Stage - One GO-RFQ / Procurement of IDA / 51540 Federal Road Sector Post Limited 4,698.44 0.00 Implementati 2019-02-25 2019-03-29 2019-04-25 Quotations Envelope Laptops Institutional, Policy and on Regulatory Framework NG-NIGER RAMP 2-97255- Project Management and GO-RFQ / Procurement of Strengthening of State and Request for Single Stage - One office equipment, Printers, IDA / 51540 Federal Road Sector Post Limited 12,500.00 10,214.16 Completed 2019-02-25 2019-03-30 2019-04-27 Quotations Envelope Digital Cameras and sundry Institutional, Policy and communication devices. Regulatory Framework NG-NIGER RAMP 2-101477- Community-based Road Pending GO-RFQ / Procurement of Request for Single Stage - One IDA / 51540 Maintenance and Annual Post Limited 46,875.00 0.00 Implementati 2019-03-20 2019-04-27 2019-05-30 Feedback Boxes for 403km Quotations Envelope Mechanized Maintenance on Rural Road NG-NIGER RAMP 2-141419- GO-RFQ / Procurement of Upgrading and Pending Request for Single Stage - One 1no. 1.8L 4 cylinder engine IDA / 51540 Rehabilitation of Rural Post Limited 41,562.50 0.00 Implementati 2019-10-24 2019-11-15 2019-12-13 Quotations Envelope Saloon Car 2019 model full Transport Infrastructure on option NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-9 / Supervision of 174.75km designed rural Upgrading and roads (Wuya, Enagi, Mokwa, Quality And Cost- Open - Under IDA / 51540 Rehabilitation of Rural Prior 856,705.00 0.00 2014-01-20 2014-02-03 2014-02-24 2014-04-18 2014-05-02 2014-05-30 2014-07-11 2019-05-30 Diko, Kabo, Tafa - Abuci Based Selection International Implementation Transport Infrastructure Izom, Auna, Tungan Jika, Wawa, Malali) MOF-REF-10 / Consultancy services for the detailed engineering design, environmental and social Upgrading and Quality And Cost- Open - Pending impact assessment, IDA / 51540 Rehabilitation of Rural Prior 2,261,306.53 0.00 2014-09-21 2014-10-03 2014-12-18 2016-04-12 2016-04-26 2016-05-16 2016-06-27 2020-08-31 Based Selection International Implementation Procurement support, and Transport Infrastructure construction supervision of rehabilitation of the 330km rural roads in Niger State MOF-REF-11 / Procurement Project Management and of Consultants for rural Strengthening of State and Consultant Pending roads inventories and GIS IDA / 51540 Federal Road Sector Prior Qualification Open - National 326,633.17 0.00 2016-12-19 2016-12-19 2017-02-01 2017-02-28 2017-03-13 2017-09-29 Implementation based mapping, Road Asset Institutional, Policy and Selection Management Regulatory Framework MOF-REF-12 / Formation and training of Community Community-based Road Consultant Pending based maintenance group for IDA / 51540 Maintenance and Annual Post Qualification Open - National 21,285.81 0.00 2015-12-11 2017-02-01 2017-03-01 2017-03-08 2017-03-22 2017-07-28 Implementation 175.74km rural roads in Mechanized Maintenance Selection Niger State Page 4 Project Management and NG-NIGER RAMP 2-151157- Strengthening of State and Consultant Pending CS-CQS / Video IDA / 51540 Federal Road Sector Post Qualification Open - National 62,500.00 0.00 2019-12-20 2019-12-23 2020-01-29 2020-02-03 2020-02-12 2020-04-07 Implementation Documentary Institutional, Policy and Selection Regulatory Framework INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MOF-REF-14 / Community Community-based Road Pending based routine maintenance of IDA / 51540 Maintenance and Annual Post Direct Selection Direct 7,741.94 0.00 2014-05-01 2014-05-12 2014-06-20 2018-12-31 Implementation Pilot road Project Mechanized Maintenance Upgrading and MOF-REF-15 / Payment of Pending IDA / 51540 Rehabilitation of Rural Post Direct Selection Direct 25,929.65 0.00 2014-01-22 2014-02-11 2014-04-11 2018-12-31 Individual consultant (SPC) Implementation Transport Infrastructure MOF-REF-16 / Engagement Upgrading and Individual of Technical Assistant on Pending IDA / 51540 Rehabilitation of Rural Post Consultant Limited 4,548.39 0.00 2017-05-09 2017-05-22 2017-06-19 2017-06-21 2017-09-13 Road Transport Implementation Transport Infrastructure Selection Infrastructure/Engineering NG-NIGER RAMP 2-48381- Community-based Road CS-CDS / Community Based Pending IDA / 51540 Maintenance and Annual Post Direct Selection Direct 46,452.00 0.00 2018-02-13 2018-02-23 2018-03-05 2019-03-05 Routine Maintenance of Pilot Implementation Mechanized Maintenance road project NG-NIGER RAMP 2-48383- Community-based Road CS-CDS / Community Based Pending IDA / 51540 Maintenance and Annual Post Direct Selection Direct 137,806.00 0.00 2018-02-13 2018-02-23 2018-03-20 2019-03-20 Routine Maintenance of Implementation Mechanized Maintenance 176km rural roads NG-NIGER RAMP 2-48385- CS-CDS / Formation and Community-based Road Pending Training of Maintenance IDA / 51540 Maintenance and Annual Post Direct Selection Direct 8,065.00 0.00 2018-02-26 2018-03-10 2018-04-30 2018-06-29 Implementation group for additional 50km Mechanized Maintenance roads NG-NIGER RAMP 2-84434- CS-INDV / Sensitization on Upgrading and Individual Pending Environment and Safeguard IDA / 51540 Rehabilitation of Rural Post Consultant Limited 10,938.00 0.00 2018-11-05 2018-11-10 2018-11-26 2018-12-03 2018-12-31 Implementation for the completed Phase one Transport Infrastructure Selection roads NG-NIGER RAMP 2-84603- CS-INDV / Engagement of Upgrading and Individual Pending Individual Consultant for IDA / 51540 Rehabilitation of Rural Post Consultant Limited 12,903.23 0.00 2018-11-07 2018-11-12 2018-11-26 2018-12-07 2018-12-31 Implementation ESMP for the 104km Spot Transport Infrastructure Selection Imrovement Roads NG-NIGER RAMP 2-97314- Community-based Road CS-CDS / Community Based Pending IDA / 51540 Maintenance and Annual Post Direct Selection Direct 27,900.00 0.00 2019-01-31 2019-02-04 2019-02-11 2019-12-31 Routine Maintenance of Pilot Implementation Mechanized Maintenance road project (37.2km) NG-NIGER RAMP 2-97338- Community-based Road CS-CDS / Community Based Pending IDA / 51540 Maintenance and Annual Post Direct Selection Direct 132,000.00 0.00 2019-02-01 2019-02-05 2019-03-11 2019-12-31 Routine Maintenance of Implementation Mechanized Maintenance 176km rural roads NG-NIGER RAMP 2-97501- Community-based Road CS-CDS / Community Based Pending IDA / 51540 Maintenance and Annual Post Direct Selection Direct 302,250.00 0.00 2019-03-29 2019-04-08 2019-04-19 2019-12-31 Routine Maintenance of Implementation Mechanized Maintenance 403km rural roads Page 5 NG-NIGER RAMP 2-97502- CS-CDS / Formation and Community-based Road Pending training of maintenance IDA / 51540 Maintenance and Annual Post Direct Selection Direct 78,125.00 0.00 2019-02-05 2019-02-13 2019-03-29 2019-05-31 Implementation groups for 403km rural Mechanized Maintenance roads NG-NIGER RAMP 2-97503- CS-CQS / Engagement of Consultant for the review Upgrading and Under and hydrological analysis of IDA / 51540 Rehabilitation of Rural Post Direct Selection Direct 42,160.51 0.00 2019-02-22 2019-02-27 2019-03-20 2019-05-03 Implementation the damaged vented drift Transport Infrastructure along Izom - Abuchi Suleja Road NG-NIGER RAMP 2-97506- CS-INDV / Engagement of Upgrading and Individual Pending Technical Assistant on IDA / 51540 Rehabilitation of Rural Post Consultant Limited 13,125.00 0.00 2019-02-19 2019-02-22 2019-03-15 2019-03-29 2019-12-31 Implementation Environmental and Transport Infrastructure Selection Safeguard NG-NIGER RAMP 2-101457- Upgrading and Individual CS-INDV / Engagement of Pending IDA / 51540 Rehabilitation of Rural Post Consultant Limited 13,125.00 0.00 2019-02-20 2019-02-22 2019-03-15 2019-03-27 2019-12-31 Technical Assistant on Social Implementation Transport Infrastructure Selection Safeguard NG-NIGER RAMP 2-147038- CS-CDS / SUPERVISION OF THE CONSTRUCTION Upgrading and Pending OF 60M 4X15M SPAN IDA / 51540 Rehabilitation of Rural Prior Direct Selection Direct 62,500.00 0.00 2019-12-23 2019-12-26 2020-01-23 2020-05-22 Implementation BRIDGE KM 16+500 Transport Infrastructure ALONG SULEJA-IZOM ROAD Page 6