Rajasthan Agriculture competitiveness Project Government of Rajasthan Procurement Plan 18 months (From May 2016 to December 2017 ) I. General 1. Project information Country : India Borrower : Government of India Project Name : Rajasthan Agriculture competitiveness Project Project Identification No (ID) : P124614 -- Applicable Bank Guideline : a) For Goods ,Works and Non-consulting Services :"Guidelines: Procurement of Goods, Works and Non-Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers" dated January 2011 (Procurement Guidelines) and revised July 2014; and b) For Consultancy Services :"Guidelines: Selection and Employment of Consultants under IBRD Loans and IDA Credits & Grants by World Bank Borrowers" dated January 2011 (Consultant Guidelines) and revised July 2014; II. Goods, Works and Non-Consulting Services Category Method of Threshold (US$ Equivalent)* Prior review Procurement threshold Goods and International Contracts more than the equivalent of US$ 3 million per Non- competitive contract All contracts consulting Bidding equal to or services Limited As per para 3.2 of the Guideline .All Contracts more than greater than International the equivalent of US $ 100,000 per contract US 2 million Bidding equivalent; National Contracts more than the equivalent of US$ 100,000 but less competitive than the equivalent of US$ 3 million per contract (with Bidding NCB conditions) Shopping ** Contracts equivalent of US$ 100,000 or less per contract. Direct Contracting Proprietary software; educational journals and other procurement justified as per para 3.7 of Guidelines and estimated to cost equivalent of US$ 10,000 or less per contract Force Account As per para 3.9 of Guidelines Community As per guideline para 3.19 of the guideline participation# Framework As per para 3.6 of Guidelines Agreements@ Works International Civil works more or equivalent of US$40,000,000 per all contracts Competitive contract equal to or Bidding greater than National Civil works more than $10000 and Up to $40,000,000 US$10 competitive per contract (with NCB conditions) million Bidding equivalent Shopping** Civil works Up to $100,000 per contract Direct contracting As per para 3.7 of Guidelines. All Civil Works estimated to cost equivalent of US$ 10,000 or less Community As per guideline para 3.19 of the guideline participation# Force Account As per para 3.9 of Guidelines Consultant Consultant Contracts Up to $300,000 or less per contract All contracts s’ Services Qualification equal to or /Least cost greater than selection US$1 Million Category Method of Threshold (US$ Equivalent)* Prior review Procurement threshold Single source As per para 3.9-3.11 of Guidelines and less than or equivalent for selection equal to $10000 firms; and Individual As per Section V of Guidelines equal to or Contracts greater than Quality and cost for All other Contracts US$300,000 Based selection equivalent for /Quality Based individuals Selection /Fixed Based Selection (i) International >800,000 shortlist (ii) Shortlist may Up to 800,000 comprise national consultants only * If a transaction comprises several contracts, lots or slices, the aggregate estimated value of all contracts, lots or slices will determine the applicable threshold amount# *State Rate Contracts cannot be used at par with Shopping. If state rate contract exists for an item, the same can be considered as one of the 3 quotations to be sought under shopping procedures. However DGS&D rate contracts are acceptable under any procurement under the Shopping procedure .#Community Procurement would be applicable to activities under learning/training pilots It would be based on World Bank “Guidance Note For Management of Procurement Responsibilities In Community-Driven Development Projects dated December 2009 and as included in the Procurement manual. @Use of DGS&D rate contracts under Framework Agreement (FA) method can be used, provided that: • Use of DGS&D rate contracts as FA must be reflected on the procurement plan agreed by the Bank for particular goods. • Before issuing the purchasing order, the borrower carries-out a price analysis on the specific good that is intended to be purchased. If after this due diligence the borrower concludes (and Bank agrees) that the DGS&D rate contract is not suitable, then the borrower will have to proceed using NCB or shopping depending on the value. • To meet the Bank's requirements for right to audit and F&C, these clauses may be included in the Purchase Orders (in case the purchasers are directly placing the purchase orders to DGS&D rate contract holders). On the other hand, if indent is placed through DGS&D, the Purchaser has the option to sign a separate undertaking with DGS&D rate contract holder, where Bank’s right to audit and F&C clauses could be mentioned. 2. Pre-qualification: Not Applicable 3. Reference to Project Procurement Manual: A Procurement Manual based on World Bank Guidelines “Procurement of Goods, Works, and Non-Consulting Services under IBRD Loans and IDA Credits & Grants by World Bank Borrowers, January 2011,Revised July 2014”and “Selection and Employment of Consultants under IBRD Loans and IDA Credits and Grants by World Bank Borrowers” has been prepared. All procurements in the project will be governed by the procedures described in the Manual. In case of any inconsistency between the Procurement Manual and the World Bank Guidelines 2011, Revised July 2014, the provisions of the Guidelines shall prevail. 4. Any Other Special Procurement Arrangements (Goods & Works) : A. Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided they are procured in accordance with agreed processes and procedures for the project and have been cleared as part of procurement plan. B. National Competitive Bidding (NCB) method for procurement of goods, works and non-consulting services as per the above value thresholds will be conducted in accordance with paragraph 3.3 and 3.4 of the World Bank Procurement Guidelines and the following provisions: (i) Only the model bidding documents for NCB agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding; (ii) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access ) along with an abridged version of the said advertisement published in a widely circulated national daily inter-alia giving the website/electronic portal details from which the details of the invitation to bid can be downloaded), at least 30 days prior to the deadline for the submission of bids; (iii) No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. (iv) Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder; (v) Extension of bid validity shall not be allowed with reference to contracts subject to prior review without the prior concurrence of the World Bank (i) for the first request for extension if it is longer than four weeks; and (ii) for prior approved packages, all subsequent requests for extension irrespective of the period. (Such concurrence will be considered by the Bank only in cases of Force Majeure and circumstances beyond the control of the Purchaser/Employer); (vi) Re-bidding shall not be carried out with reference to Contracts subject to Bank prior review without the prior concurrence of the Bank. (vii) The system of rejecting bids outside a pre-determined margin or "bracket" of prices shall not be used in the project. (viii) Rate contracts entered into by Directorate General of Supplies and Disposals will not be acceptable as a substitute for NCB procedures unless agreed with the Bank on case to case basis. Such contracts will be acceptable however for any procurement under the Shopping procedures. (ix) Two or three envelop system will not be used (except when using e-Procurement system assessed and agreed by the Bank). (x) As per 1.1(e) of World Bank Procurement Guidelines, the Association’s right to inspect accounts and records of the bidders, suppliers and contractors will be included in the bidding document. III) Selection of Consultants 1. Methods and Value thresholds for Consultancy Services Consulting Methods Value Review Arrangements Services Threshold* Consulting i) Quality and Cost Based All contracts valued above US$ 1 Services Selection (QCBS) Million will be subject to Prior (Firms) ii) Quality Based Selection Review by the World Bank. All (QBS) other contracts will be subject to iii) Selection based on a Fixed post review. Budget (FBS) iv) Selection Based on Least Cost Basis (LCS) v) (Selection based on Contracts Consultant’s Qualification estimated to cost (CQS) equivalent of US$ 300,000 or less per contract. vi) Single Source Selection (SSS)# provided the conditions stipulated in Procurement is in accordance paragraph 3.8 to 3.11 of with para 3.9-3.11 of the Bank Consultant Guidelines are guidelines. met Individual i) Competitive Selection All other contracts subject to post Consultants review provided procurement is in accordance with Section V of the Bank guidelines. ii) Single Source Selection All contracts equal to or above (SSS)# US$ 300,000 shall be subject to prior review. All procurement to be in accordance with Section V of the Bank guidelines. * If a transaction comprises several packages, lots or slices, the aggregate estimated value of contracts will determine the applicable threshold amount. # Irrespective of contract value any hiring of Government or Research Institutes of unique and exceptional nature requires prior no objection of the World Bank on case to case basis. 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than US $800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of Para 2.7 the World Bank Consultant Guidelines. 3. Any Other Special Selection Arrangements (Consulting Services) : (a) Contracts procured in advance will be financed under retroactive financing within the specified limits, as agreed to in the Credit Agreement provided procurement is in accordance with agreed processes and procedures for the project. (b) Requests for Expression of Interest (REOI) for assignments expected to cost more than US$ 300,000 shall be advertised in UNDB online in accordance with Para 2.5 of the Consultant Guidelines. PROCUREMENT India : Rajasthan Agricultural Competitiveness Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-09-15 2019-11-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124614 GPN Date: Project Name: Rajasthan Agricultural Competitiveness Project Loan / Credit No: IDA / 50850 Executing Agency(ies): Watershed Development & Soil Conservation Department WORKS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-WDSCD-4590-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 86,045.00 86,539.08 Signed 2017-01-01 2017-01-31 2017-03-30 watershed no 10 of macro Agriculture Quotations Envelope watershed 10 in Kushalgarh cluster district Banswara IN-WDSCD-4593-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 2 of macro IDA / 50850 Post Limited 52,940.00 44,587.87 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4596-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 4 of macro IDA / 50850 Post Limited 28,358.00 24,182.63 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4597-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 5 of macro IDA / 50850 Post Limited 15,940.00 12,958.55 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4598-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 7 of macro IDA / 50850 Post Limited 77,985.00 64,043.38 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4599-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 10 of macro IDA / 50850 Post Limited 36,642.00 30,860.79 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 9 in Gudha Catchment cluster district Bundi IN-WDSCD-4600-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 3 of macro IDA / 50850 Post Limited 14,284.00 14,419.67 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 36 in Orai Bassi cluster district Chittorgarh IN-WDSCD-4601-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 4 of macro IDA / 50850 Post Limited 71,985.00 68,870.31 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 36 in Orai Bassi Cluster district Chittorgarh IN-WDSCD-4602-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 58,836.00 59,338.05 Signed 2017-01-01 2017-01-31 2017-03-30 watershed no 5 of macro Agriculture Quotations Envelope watershed no 2 in Bari cluster district Dholpur IN-WDSCD-4604-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 93,925.00 94,733.33 Signed 2017-01-01 2017-01-31 2017-03-30 watershed no 6 of macro Agriculture Quotations Envelope watershed no 2 in Bari cluster district Dholpur IN-WDSCD-4607-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 9 of macro IDA / 50850 Post Limited 26,687.00 26,830.04 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 34 in Manohar Thana cluster district Jhalawar IN-WDSCD-4617-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 9 of macro IDA / 50850 Post Limited 64,731.00 65,043.26 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 40 in Manohar Thana cluster district Jhalawar Page 1 IN-WDSCD-4633-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 19 of macro IDA / 50850 Post Limited 61,343.00 50,236.96 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 6 in Jakham Catchment District Pratapgarh IN-WDSCD-4634-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 20 of macro IDA / 50850 Post Limited 37,254.00 29,439.86 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 6 in Jakham Catchment District Pratapgarh IN-WDSCD-4635-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One watershed no 21 of macro IDA / 50850 Post Limited 84,821.00 72,268.80 Signed 2017-01-01 2017-01-31 2017-03-30 Agriculture Quotations Envelope watershed no 6 in Jakham Catchment District Pratapgarh IN-WDSCD-4636-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 84,119.00 76,054.80 Signed 2017-01-01 2017-01-31 2017-03-30 watershed no 5 of macro Agriculture Quotations Envelope watershed no 15 in Deoli Dooni Cluster District Tonk IN-WDSCD-4637-CW-RFQ / Implementation of NRM activities for Watershed Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 12,284.00 11,546.70 Signed 2017-01-01 2017-01-31 2017-03-30 Development in Village Agriculture Quotations Envelope Bharnawa Ladnu Cluster District Nagour IN-WDSCD-4638-CW-RFQ / Implementation of NRM activities for Watershed Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 14,627.00 13,613.58 Signed 2017-01-01 2017-01-31 2017-03-30 Development in Village Agriculture Quotations Envelope Toki Ladnu Cluster District Nagour IN-WDSCD-4639-CW-RFQ / Implementation of NRM activities for Watershed Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 77,239.00 74,046.68 Signed 2017-01-01 2017-01-31 2017-03-30 Development in Village Agriculture Quotations Envelope Lukhash Ladnu Cluster District Nagour IN-WDSCD-6544-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 58,866.00 0.00 Canceled 2017-03-06 2017-04-20 2018-02-14 Watershed no.6 of Macro Agriculture Quotations Envelope Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-7619-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 151,269.00 0.00 Canceled 2017-03-01 2017-03-06 2017-04-17 2017-04-27 2017-05-09 2018-02-27 Watershed no. 8 of Macro Agriculture Envelope Watershed no. 6 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-6617-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 65,910.00 0.00 Canceled 2017-03-06 2017-04-20 2018-02-14 Watershed no.1 of Macro Agriculture Quotations Envelope Watershed no.8 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-6620-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 46,746.00 0.00 Canceled 2017-03-06 2017-04-20 2018-02-14 Watershed no.2 of Macro Agriculture Quotations Envelope Watershed no.8 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-7611-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 259,731.00 0.00 Canceled 2017-03-01 2017-03-06 2017-04-17 2017-04-27 2017-05-09 2018-02-27 Watershed no. 4 of Macro Agriculture Envelope Watershed no. 8 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-7617-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 114,000.00 0.00 Canceled 2017-07-10 2017-07-15 2017-08-26 2017-09-05 2017-09-17 2018-07-08 Watershed no. 5 of Macro Agriculture Envelope Watershed no. 6 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-7574-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 180,567.00 0.00 Canceled 2017-07-10 2017-07-15 2017-08-26 2017-09-05 2017-09-17 2018-07-08 Watershed no. 2 of Macro Agriculture Envelope Watershed no. 7 in Bansur Cluster District Alwar for F.Y.2017-18 Page 2 IN-WDSCD-6577-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 93,194.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Watershed no.5 of Macro Agriculture Quotations Envelope Watershed no.7 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-6473-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 61,567.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Watershed no.4 of Macro Agriculture Quotations Envelope Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-6548-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 23,388.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Watershed no.7 of Macro Agriculture Quotations Envelope Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-4588-CW-RFQ / Implementation of NRM activities in micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 60,100.00 0.00 Canceled 2017-07-15 2017-08-14 2017-10-11 watershed no 9 of macro Agriculture Quotations Envelope watershed 6 in Bansur cluster district Alwar IN-WDSCD-6576-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 25,597.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Watershed no.10 of Macro Agriculture Quotations Envelope Watershed no.6 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-6579-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 70,373.00 0.00 Canceled 2017-07-15 2017-08-29 2018-06-25 Watershed no.6 of Macro Agriculture Quotations Envelope Watershed no.7 in Bansur Cluster District Alwar for F. Y. 2017-18 IN-WDSCD-7606-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 188,955.00 0.00 Canceled 2017-07-10 2017-07-15 2017-08-26 2017-09-05 2017-09-17 2018-07-08 Watershed no. 3 of Macro Agriculture Envelope Watershed no. 7 in Bansur Cluster District Alwar for F.Y.2017-18 IN-WDSCD-22460-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 90,255.00 59,713.62 Signed 2017-08-23 2017-10-18 2018-12-31 watershed No. 5 of Macro Agriculture Quotations Envelope Watershed no. 7 in Bansur Cluster District Alwar for FY 2017-18 IN-WDSCD-22553-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 68,070.00 47,145.25 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 6 of Macro Agriculture Quotations Envelope watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-WDSCD-22563-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 103,896.00 88,544.65 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 5 of Macro Agriculture Envelope watershed No. 6 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-WDSCD-22599-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 173,959.00 137,029.37 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 1 of Macro Agriculture Envelope watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-WDSCD-22602-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 182,156.00 143,678.15 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 3 of Macro Agriculture Envelope watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2017-18 IN-WDSCD-22609-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 75,110.00 71,141.19 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 12 of Macro Agriculture Quotations Envelope watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 Page 3 IN-WDSCD-22610-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 340,037.00 310,700.44 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 09 of Macro Agriculture Envelope watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 IN-WDSCD-22614-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 110,874.00 89,474.59 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 11 of Macro Agriculture Envelope watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 IN-WDSCD-22615-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 161,707.00 127,534.13 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 13 of Macro Agriculture Envelope watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2017-18 IN-WDSCD-22618-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 55,355.00 40,977.10 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 1 of Macro Agriculture Quotations Envelope watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22623-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 88,268.00 64,139.68 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 3 of Macro Agriculture Quotations Envelope watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22627-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 75,388.00 53,362.91 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 4 of Macro Agriculture Quotations Envelope watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22628-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 48,206.00 34,471.71 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 5 of Macro Agriculture Quotations Envelope watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22631-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 125,940.00 103,255.42 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 2 of Macro Agriculture Envelope watershed No. 8 in Gudha Cluster District Bundi for F.Y. 2017-18 IN-WDSCD-22633-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 81,009.00 63,466.05 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 1 of Macro Agriculture Quotations Envelope watershed No. 31 in Orai Bassi Cluster District Chittorgarh for F.Y. 2017- 18 IN-WDSCD-22635-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 104,258.00 82,381.89 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 2 of Macro Agriculture Envelope watershed No. 31 in Orai Bassi Cluster District Chittorgarh for F.Y. 2017- 18 IN-WDSCD-22637-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 392,458.00 323,262.55 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 6 of Macro Agriculture Envelope watershed No. 31 in Orai Bassi Cluster District Chittorgarh for F.Y. 2017- 18 IN-WDSCD-22638-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 241,556.00 206,212.79 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 4 of Macro Agriculture Envelope watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2017-18 IN-WDSCD-22639-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 134,829.00 111,639.42 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 8 of Macro Agriculture Envelope watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2017-18 Page 4 IN-WDSCD-22640-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 220,791.00 188,192.38 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 2 of Macro Agriculture Envelope watershed No. 3 in Bari Cluster District Dholpur for F.Y. 2017-18 IN-WDSCD-22642-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No. 3 of Macro IDA / 50850 Post Limited 25,062.00 23,258.17 Signed 2017-08-23 2017-10-18 2018-12-31 Agriculture Quotations Envelope watershed No. 23 in Manoharthana Cluster District Jhalawar for F.Y. 2017-18 IN-WDSCD-22647-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 3 of Macro IDA / 50850 Post Request for Bids Open - National 409,984.00 358,280.95 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Agriculture Envelope watershed No. 32 in Manohar thana Cluster District Jhalawar for F.Y. 2017-18 IN-WDSCD-22651-CW-RFB / Implementation of Natural Resource Management activities Watershed Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 277,800.00 231,245.37 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Development in Village Agriculture Envelope Manu Ladnu Cluster District Nagour for F.Y. 2017-18 IN-WDSCD-22656-CW-RFB / Implementation of Natural Resource Management activities Watershed Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 126,046.00 103,476.48 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Development in Village Agriculture Envelope Jhardiya Ladnu Cluster District Nagour for F.Y. 2017-18 IN-WDSCD-22658-CW-RFB / Implementation of Natural Resource Management activities Watershed Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 122,400.00 99,402.74 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Development in Village Agriculture Envelope Sunari Ladnu Cluster District Nagour for F.Y. 2017-18 IN-WDSCD-22663-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 74,369.00 65,659.49 Signed 2017-08-23 2017-10-18 2018-12-31 Watershed No. 16 of Macro Agriculture Quotations Envelope watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22668-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 126,169.00 107,180.07 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 15 of Macro Agriculture Envelope watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22671-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 186,723.00 148,657.05 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 17 of Macro Agriculture Envelope watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22673-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 167,222.00 133,279.24 Signed 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 18 of Macro Agriculture Envelope watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2017-18 IN-WDSCD-22676-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 903,323.00 0.00 Canceled 2017-08-18 2017-08-23 2017-10-04 2017-11-03 2017-12-08 2018-12-31 Watershed No. 1 of Macro Agriculture Envelope watershed No. 17 in Duni Deoli Cluster District Tonk for F.Y. 2017-18 IN-WDSCD-22643-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No. 4 of Macro IDA / 50850 Post Limited 58,995.00 54,852.59 Signed 2017-08-23 2017-10-18 2018-12-31 Agriculture Quotations Envelope watershed No. 32 in Manohar thana Cluster District Jhalawar for F.Y. 2017-18 IN-WDSCD-45131-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 81,550.00 65,034.06 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 4 of Macro Agriculture Quotations Envelope watershed No. 6 in Bansur Cluster District Alwar for F.Y. 2018-19 Page 5 IN-WDSCD-45149-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 119,079.00 104,830.97 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 7 of Macro Agriculture Envelope Watershed No. 8 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45610-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 97,920.00 78,088.43 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 6 of Macro Agriculture Quotations Envelope Watershed No. 6 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45618-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 20,954.00 13,262.63 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 7 of Macro Agriculture Quotations Envelope Watershed No.6 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45638-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 51,808.00 41,315.78 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 8 of Macro Agriculture Quotations Envelope Watershed No. 6 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45643-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 23,506.00 18,745.49 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 9 of Macro Agriculture Quotations Envelope Watershed No. 6 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45644-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 18,243.00 11,540.40 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 10 of Macro Agriculture Quotations Envelope Watershed No. 6 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45649-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 98,041.00 78,184.74 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 2 of Macro Agriculture Quotations Envelope Watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45653-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 39,120.00 24,757.34 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 4 of Macro Agriculture Quotations Envelope Watershed No. 7 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45655-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 52,297.00 41,705.32 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 1 of Macro Agriculture Quotations Envelope Watershed No. 8 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45657-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 21,572.00 17,203.30 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 2 of Macro Agriculture Quotations Envelope Watershed No. 8 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45659-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 41,469.00 26,190.20 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 3 of Macro Agriculture Quotations Envelope Watershed No. 8 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45660-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 85,338.00 58,221.42 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 4 of Macro Agriculture Quotations Envelope Watershed No. 8 in Bansur Cluster District Alwar for F.Y. 2018-19 IN-WDSCD-45662-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 19,859.00 12,515.90 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 6 of Macro Agriculture Quotations Envelope Watershed No. 8 in Bansur Cluster District Alwar for F.Y. 2018-19 Page 6 IN-WDSCD-45664-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 103,535.00 86,906.14 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 4 of Macro Agriculture Envelope Watershed No.4 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45665-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 171,943.00 174,874.78 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 7 of Macro Agriculture Envelope Watershed No. 6 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45667-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 296,191.00 235,829.83 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 1 of Macro Agriculture Envelope Watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45671-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 391,151.00 307,077.04 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 2 of Macro Agriculture Envelope Watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45674-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 83,558.00 69,213.62 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 3 of Macro Agriculture Quotations Envelope Watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45675-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 81,594.00 0.00 Canceled 2018-02-06 2018-04-02 2019-03-31 Watershed No. 4 of Macro Agriculture Quotations Envelope Watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45680-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 179,039.00 142,368.39 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 5 of Macro Agriculture Envelope Watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45682-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 98,603.00 78,800.87 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 6 of Macro Agriculture Quotations Envelope Watershed No.10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45684-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 118,381.00 92,816.42 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 7 of Macro Agriculture Envelope Watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45686-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 70,608.00 0.00 Canceled 2018-02-06 2018-04-02 2019-03-31 Watershed No. 8 of Macro Agriculture Quotations Envelope Watershed No. 10 in Kushalgarh Cluster District Banswara for F.Y. 2018-19 IN-WDSCD-45689-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No. 1 of Macro IDA / 50850 Post Limited 48,396.00 29,305.31 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No. 7 in Gudha Catchment District Bundi for F.Y. 2018-19 IN-WDSCD-45690-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 92,440.00 67,223.80 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.2 of Macro Agriculture Quotations Envelope Watershed No.7 in Gudha Catchment District Bundi for F.Y. 2018-19 IN-WDSCD-45691-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 60,212.00 39,559.22 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.4 of Macro Agriculture Quotations Envelope Watershed No.7 in Gudha Catchment District Bundi for F.Y. 2018-19 Page 7 IN-WDSCD-45692-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 152,920.00 126,855.05 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.1 of Macro Agriculture Envelope Watershed No.9 in Gudha Catchment District Bundi for F.Y. 2018-19 IN-WDSCD-45693-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 293,317.00 266,973.92 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.3 of Macro Agriculture Envelope Watershed No.9 in Gudha Catchment District Bundi for F.Y. 2018-19 IN-WDSCD-45695-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.3 of Macro IDA / 50850 Post Limited 42,555.00 34,814.81 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45697-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.4 of Macro IDA / 50850 Post Limited 50,535.00 44,253.28 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45699-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No.5 of Macro IDA / 50850 Post Request for Bids Open - National 165,180.00 157,780.98 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45701-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.7 of Macro IDA / 50850 Post Limited 24,992.00 20,667.42 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45703-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.8 of Macro IDA / 50850 Post Limited 36,262.00 29,144.05 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45705-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.9 of Macro IDA / 50850 Post Limited 46,706.00 37,081.29 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45708-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.10 of Macro IDA / 50850 Post Limited 55,908.00 45,264.42 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45709-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.11 of Macro IDA / 50850 Post Limited 32,972.00 26,026.38 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45712-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.12 of Macro IDA / 50850 Post Limited 17,246.00 15,211.86 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.31 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45714-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.1 of Macro IDA / 50850 Post Limited 97,903.00 76,404.83 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.35 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 Page 8 IN-WDSCD-45716-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.2 of Macro IDA / 50850 Post Limited 19,015.00 16,462.73 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.35 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45718-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.3 of Macro IDA / 50850 Post Limited 38,558.00 33,890.66 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.35 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45721-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.4 of Macro IDA / 50850 Post Limited 18,352.00 16,130.62 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.35 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45722-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.1 of Macro IDA / 50850 Post Limited 19,909.00 17,499.07 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.36 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45723-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.2 of Macro IDA / 50850 Post Limited 19,858.00 17,192.63 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.36 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45724-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.5 of Macro IDA / 50850 Post Limited 32,923.00 28,955.29 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.36 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45727-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No.6 of Macro IDA / 50850 Post Limited 18,784.00 16,603.09 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No.36 in Orai Bassi Catchment District Chittorgarh for F.Y. 2018- 19 IN-WDSCD-45819-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 6,906.00 0.00 Canceled 2018-02-06 2018-04-02 2019-03-31 Watershed No. 1 of Macro Agriculture Quotations Envelope Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45820-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 266,729.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 2 of Macro Agriculture Envelope Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45821-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 33,129.00 0.00 Canceled 2018-02-06 2018-04-02 2019-03-31 Watershed No. 3 of Macro Agriculture Quotations Envelope Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45824-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 260,678.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 7 of Macro Agriculture Envelope Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45825-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 180,444.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 9 of Macro Agriculture Envelope Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2018-19 Page 9 IN-WDSCD-45826-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 92,784.00 86,702.06 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 10 of Macro Agriculture Quotations Envelope Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45827-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 7,523.00 4,530.40 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 11 of Macro Agriculture Quotations Envelope Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45828-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 152,126.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 12 of Macro Agriculture Envelope Watershed No.2 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45829-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 261,267.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 1 of Macro Agriculture Envelope Watershed No. 3 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45831-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 161,271.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No. 1 of Macro Agriculture Envelope Watershed No. 4 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45832-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 244,069.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.2 of Macro Agriculture Envelope Watershed No. 4 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45833-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 27,934.00 0.00 Canceled 2018-02-06 2018-04-02 2019-03-31 Watershed No. 3 of Macro Agriculture Quotations Envelope Watershed No. 4 in Bari Cluster District Dholpur for F.Y. 2018-19 IN-WDSCD-45834-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 4 of Macro IDA / 50850 Post Request for Bids Open - National 178,714.00 157,930.90 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No. 22 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45835-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 2 of Macro IDA / 50850 Post Request for Bids Open - National 249,185.00 238,706.05 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No. 29 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45836-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 6 of Macro IDA / 50850 Post Request for Bids Open - National 197,385.00 189,987.82 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No. 29 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45837-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No. 2 of Macro IDA / 50850 Post Limited 85,230.00 79,401.28 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No. 31 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45838-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 3 of Macro IDA / 50850 Post Request for Bids Open - National 128,370.00 110,530.22 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No. 31 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 Page 10 IN-WDSCD-45840-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No. 1 of Macro IDA / 50850 Post Limited 93,818.00 87,418.06 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No. 32 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45841-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No. 2 of Macro IDA / 50850 Post Limited 98,343.00 92,492.06 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No. 32 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45842-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 5 of Macro IDA / 50850 Post Request for Bids Open - National 182,706.00 174,236.73 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No. 32 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45846-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 1 of Macro IDA / 50850 Post Request for Bids Open - National 121,259.00 104,420.06 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No. 33 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45856-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One Watershed No. 2 of Macro IDA / 50850 Post Limited 81,593.00 78,205.87 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Watershed No. 35 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-45860-CW-RFB / Implementation of Natural Resource Management Climate Resilient Single Stage - One activities in Village-Nimbhi IDA / 50850 Post Request for Bids Open - National 643,354.00 522,025.42 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Jodha in Ladnu Cluster District Nagour for F.Y. 2018-19 IN-WDSCD-45866-CW-RFB / Implementation of Natural Resource Management Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 254,554.00 188,241.60 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 activities in Village- Odeent Agriculture Envelope in Ladnu Cluster District Nagour for F.Y. 2018-19 IN-WDSCD-45868-CW-RFQ / Implementation of Natural Resource Management Climate Resilient Request for Single Stage - One activities in Village- IDA / 50850 Post Limited 87,692.00 70,777.80 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Heerawati in Ladnu Cluster District Nagour for F.Y. 2018-19 IN-WDSCD-45870-CW-RFQ / Implementation of Natural Resource Management Climate Resilient Request for Single Stage - One activities in Village- IDA / 50850 Post Limited 92,308.00 71,333.88 Signed 2018-02-06 2018-04-02 2019-03-31 Agriculture Quotations Envelope Chandrai in Ladnu Cluster District Nagour for F.Y. 2018-19 IN-WDSCD-45875-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 17,841.00 15,817.31 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No. 5 of Macro Agriculture Quotations Envelope Watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2018-19 IN-WDSCD-45915-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 76,755.00 68,645.97 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.6 of Macro Agriculture Quotations Envelope Watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2018-19 IN-WDSCD-45917-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 102,465.00 91,928.19 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.7 of Macro Agriculture Envelope Watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2018-19 IN-WDSCD-45918-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 21,053.00 18,619.64 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.8 of Macro Agriculture Quotations Envelope Watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2018-19 Page 11 IN-WDSCD-45921-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 62,031.00 55,631.69 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.10 of Macro Agriculture Quotations Envelope Watershed No.6 in Jakham Catchment District Pratapgarh for F.Y. 2018-19 IN-WDSCD-45923-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 25,400.00 22,809.42 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.12 of Macro Agriculture Quotations Envelope Watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2018-19 IN-WDSCD-45925-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 114,989.00 103,434.17 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.14 of Macro Agriculture Envelope Watershed No. 6 in Jakham Catchment District Pratapgarh for F.Y. 2018-19 IN-WDSCD-45928-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 230,746.00 194,776.97 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.1 of Macro Agriculture Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45930-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 131,374.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.2 of Macro Agriculture Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45932-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 446,074.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.3 of Macro Agriculture Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45934-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 254,563.00 235,157.77 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.4 of Macro Agriculture Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45938-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 48,734.00 87,167.74 Completed 2018-02-06 2018-04-02 2019-03-31 Watershed No.13 of Macro Agriculture Quotations Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45943-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 50,890.00 45,146.71 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.14 of Macro Agriculture Quotations Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45945-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 29,318.00 26,009.31 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.15 of Macro Agriculture Quotations Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45949-CW-RFQ / Implementation of Natural Resource Management activities in Micro Climate Resilient Request for Single Stage - One IDA / 50850 Post Limited 56,988.00 50,557.10 Signed 2018-02-06 2018-04-02 2019-03-31 Watershed No.1 of Macro Agriculture Quotations Envelope Watershed No. 22 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45957-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 274,673.00 255,045.94 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.2 of Macro Agriculture Envelope Watershed No. 22 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45964-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 493,415.00 459,817.15 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.1 of Macro Agriculture Envelope Watershed No. 23 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 Page 12 IN-WDSCD-45970-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 407,239.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.2 of Macro Agriculture Envelope Watershed No. 23 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45972-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 100,388.00 78,405.21 Signed 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Watershed No.1 of Macro Agriculture Envelope Watershed No. 24 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-45859-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One Watershed No. 6 of Macro IDA / 50850 Post Request for Bids Open - National 334,320.00 0.00 Canceled 2018-02-01 2018-02-06 2018-03-13 2018-03-21 2018-04-12 2019-03-31 Agriculture Envelope Watershed No. 40 in Manoharthana Cluster District Jhalawar for F.Y. 2018-19 IN-WDSCD-68781-CW-RFB / implementation of Natural Resource management activities in micro Climate Resilient Single Stage - One watershed No. 6 of macro IDA / 50850 Post Request for Bids Open - National 334,320.00 0.00 Canceled 2018-07-10 2018-07-16 2018-08-20 2018-09-04 2018-09-28 2019-04-30 Agriculture Envelope watershed no. 40 in manoharthana cluster district Jhalawar for FY 2018-19 IN-WDSCD-71081-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 903,323.00 672,489.94 Signed 2018-07-25 2018-07-30 2018-08-29 2018-09-07 2018-09-27 2019-04-30 Watershed No. 1 of Macro Agriculture Envelope watershed No. 17 in Duni Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-71376-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 131,374.00 100,839.22 Signed 2018-07-25 2018-07-30 2018-08-29 2018-09-07 2018-09-27 2019-04-30 Watershed No.2 of Macro Agriculture Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-71381-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 446,074.00 376,100.99 Signed 2018-07-25 2018-07-30 2018-08-29 2018-09-07 2018-09-27 2019-04-30 Watershed No. 3 of Macro Agriculture Envelope Watershed No. 15 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-71386-CW-RFB / Implementation of Natural Resource Management activities in Micro Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 407,239.00 331,197.21 Signed 2018-07-25 2018-07-30 2018-08-29 2018-09-07 2018-09-27 2019-04-30 Watershed No. 2 of Macro Agriculture Envelope Watershed No. 23 in Dooni- Deoli Cluster District Tonk for F.Y. 2018-19 IN-WDSCD-146312-CW- RFB / Implementation of Natural Resource Pending Management activities in Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 247,676.93 0.00 Implementat 2019-11-25 2019-12-02 2020-01-01 2020-01-09 2020-01-31 2020-06-30 Micro Watershed No. 2 of Agriculture Envelope ion Macro Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2019-20 IN-WDSCD-146321-CW- RFB / Implementation of Natural Resource Pending Management activities in Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 242,057.90 0.00 Implementat 2019-11-25 2019-12-02 2020-01-01 2020-01-09 2020-01-31 2020-06-30 Micro Watershed No. 7 of Agriculture Envelope ion Macro Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2019-20 IN-WDSCD-146324-CW- RFB / Implementation of Natural Resource Pending Management activities in Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 167,555.09 0.00 Implementat 2019-11-25 2019-12-02 2020-01-01 2020-01-09 2020-01-31 2020-06-30 Micro Watershed No.9 of Agriculture Envelope ion Macro Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2019-20 IN-WDSCD-146325-CW- RFB / Implementation of Natural Resource Pending Management activities in Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 141,259.51 0.00 Implementat 2019-11-25 2019-12-02 2020-01-01 2020-01-09 2020-01-31 2020-06-30 Micro Watershed No. 12 of Agriculture Envelope ion Macro Watershed No. 2 in Bari Cluster District Dholpur for F.Y. 2019-20 IN-WDSCD-146326-CW- RFB / Implementation of Natural Resource Pending Management activities in Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 242,605.23 0.00 Implementat 2019-11-25 2019-12-02 2020-01-01 2020-01-09 2020-01-31 2020-06-30 Micro Watershed No. 1 of Agriculture Envelope ion Macro Watershed No. 3 in Bari Cluster District Dholpur for F.Y. 2019-20 Page 13 IN-WDSCD-146327-CW- RFB / Implementation of Natural Resource Pending Management activities in Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 149,751.57 0.00 Implementat 2019-11-25 2019-12-02 2020-01-01 2020-01-09 2020-01-31 2020-06-30 Micro Watershed No. 1 of Agriculture Envelope ion Macro Watershed No. 4 in Bari Cluster District Dholpur for F.Y. 2019-20 IN-WDSCD-146328-CW- RFB / Implementation of Natural Resource Pending Management activities in Climate Resilient Single Stage - One IDA / 50850 Post Request for Bids Open - National 226,635.20 0.00 Implementat 2019-11-25 2019-12-02 2020-01-01 2020-01-09 2020-01-31 2020-06-30 Micro Watershed No. 2 of Agriculture Envelope ion Macro Watershed No. 4 in Bari Cluster District Dholpur for F.Y. 2019-20 GOODS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-WDSCD-63577-GO-RFB / Establishment of 9 Automatic Weather Stations Climate Resilient Single Stage - Two IDA / 50850 Post Request for Bids Open - National 129,462.00 0.00 Canceled 2018-06-01 2018-06-04 2018-07-04 2018-07-31 2018-08-17 2023-08-30 (AWS) in Hydrological Agriculture Envelope Monitoring Network (HMN) under 9 RACP clusters. IN-WDSCD-37568-GO-RFQ / Shopping of Office Table Big Size-1, Office Table Medium Size-2, Almirah-2, Project Management and Request for Single Stage - One IDA / 50850 Post Limited 1,531.00 53,701.43 Signed 2017-11-27 2017-12-18 2018-01-17 Revolving Officer Chairs-1, M&E Quotations Envelope Visitors Chairs-8, Steel Office Rack-1 for F.Y. 2017- 18 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Amount Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal (US$) Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-WDSCD-63682-CS- QCBS / Consultancy services for dissemination of Weather based weekly advisory to the farmers of Climate Resilient Quality And Cost- IDA / 50850 Post Open - National 554,738.00 0.00 Canceled 2018-06-04 2018-07-09 2018-07-26 2018-08-02 2018-08-09 2018-08-23 2018-08-30 2023-08-30 9 RACP clusters through Agriculture Based Selection data received by 9 Automatic Weather Stations(A.W.S.)and processed data received from IMD, Pune INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Draft Negotiated / Description Component Review Type Method Amount Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TL/SSS / Preparation of Climate Resilient various Thematic Layers of IDA / 50850 Prior Direct Selection Direct 0.00 83,462.48 Signed Agriculture Watershed Projects Page 14