Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: September 24, 2013] 2. Date of General Procurement Notice: July 12, 2013 3. Period covered by this procurement plan: The procurement period of project covered from year September 2013 to May 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) Above US$ 1,500,000 All 3. ICB (Works) Above US$ 5 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 500,000 All [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Summary of the Procurement Packages planned during the first 18 months after project effectiveness [See Procurement Plan] III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Consultancy Assignments with Selection Methods and Time Schedule [See Procurement Plan] PROCUREMENT Iraq : Transport Corridors Project PLAN General Information Country: Iraq Bank’s Approval Date of the Original Procurement Plan: 2017-09-11 2019-07-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P131550 GPN Date: Project Name: Transport Corridors Project Loan / Credit No: IBRD / 83220 Executing Agency(ies): Ministry of Municipalities and Public Works - Roads & Bridges Directorate WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP.W.A1.EW.1.R8 / Open - Single Stage - One Rehabilitation of Expressway IBRD / 83220 Prior Request for Bids 95,800,237.07 Signed International Envelope No 1 R8 TCP.W.A1.EW.1.R7 / Open - Single Stage - One Rehabilitation of Expressway IBRD / 83220 Prior Request for Bids 95,685,541.69 Signed International Envelope No.1 R7 TCP.W.A1.EW.1.R8B / Rehabilitation of Expressway Pending No.1Section R8B Open - Single Stage - One IBRD / 83220 Prior Request for Bids 0.00 Implementati 2019-07-18 2019-07-23 2019-09-03 2019-10-03 2019-11-07 2020-05-05 from Basra Junction – International Envelope on Safwan (Remaining works) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP/G/SH/01 / Supply of Pending Request for Single Stage - One Air Conditioner for - New IBRD / 83220 Post Limited 0.00 Implementati 2016-04-04 2016-05-30 2016-11-26 Quotations Envelope PMT offices on TCP/G/SH/02 / Supply of Pending Request for Single Stage - One Lap top and printer for IBRD / 83220 Post Limited 0.00 Implementati 2016-09-30 2016-11-25 2017-05-24 Quotations Envelope PMT TCP on Pending TCP/G/SH/03 / Supply of Request for Single Stage - One IBRD / 83220 Post Limited 0.00 Implementati 2018-09-29 2018-11-24 2019-05-23 Lap top and printer for pmt Quotations Envelope on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Page 1 Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TCP.CON.QCBS.C1(a) / Quality And Cost- Open - IBRD / 83220 Prior 465,046.00 Signed 2015-06-15 2015-08-24 2015-10-19 2015-11-30 2016-01-11 2016-02-22 2017-03-02 Tech Audit Based Selection International TCP.CON.LCS.C1 (b) / Quality And Cost- Open - IBRD / 83220 Prior 153,500.00 Signed External Audit Based Selection International TCP.CON.QCBS.R7&R8 / Technical Assistance for construction supervision of Quality And Cost- Open - Expressway NO.1 section R7: IBRD / 83220 Prior 5,458,686.32 Signed 2013-09-18 2015-05-11 2015-07-05 2015-08-16 2015-09-27 2015-10-21 2016-03-08 Based Selection International Nasiria-Rumaila & R8 A: section Rumaila-Basra , R8 B:Rumaila-Safwan TCP/CON/QCBS/B1/I/01/B / Preparation of ESIA for Safwan- Umm Qasr and Quality And Cost- Open - Under IBRD / 83220 Post 0.00 2017-07-04 2017-12-24 2018-05-10 2018-06-07 2018-07-07 2018-08-11 2018-09-15 2019-09-15 Safwan and Safwan - Based Selection International Implementation Border Crossing Road Rehabilitation Project TCP/CON/QCBS/B1/I/01/A / Preparation of Economic Analysis , Detailed Engineering Design & Quality And Cost- Open - Under IBRD / 83220 Prior 0.00 2017-06-01 2017-06-22 2017-08-05 2017-09-02 2017-10-02 2017-11-06 2017-12-11 2018-12-11 Bidding Document for Based Selection International Implementation Safwan- Umm Qasr and Safwan – Border Crossing Road Rehabilitation Project TCP/CON/QCBS/B1/G / Technical Assistance in Analysis and inmprovement /Develoment of Technical Quality And Cost- Open - Under IBRD / 83220 Prior 0.00 2017-05-08 2018-01-15 2018-05-28 2018-06-25 2018-07-25 2018-08-29 2018-10-03 2019-10-03 Manual /Specification for Based Selection International Implementation road Miantaenance and Superpave implemantation study TCP/CON/QCBS/B1/D / Technical Assistance in development of ICT including citizens'roadway Quality And Cost- Open - Under reporting IBRD / 83220 Prior 0.00 2018-05-20 2018-06-10 2018-07-24 2018-08-21 2018-09-20 2018-10-25 2018-11-29 2019-11-29 Based Selection International Implementation system,estiblishment of call center(s),surveilance system , and axel -load limit enforcement for RBD TCP/CON/QCBS/B1/C / Awareness raising on routine Quality And Cost- Open - IBRD / 83220 Prior 0.00 Canceled 2018-04-11 2018-05-02 2018-06-15 2018-07-13 2018-08-12 2018-09-16 2018-10-21 2019-10-21 maintenance and improving Based Selection International capacity for RBD TCP/CON/QCBS/B1/B / Technical assistance in Quality And Cost- Open - IBRD / 83220 Prior 0.00 Canceled 2018-04-11 2018-05-02 2018-06-15 2018-07-13 2018-08-12 2018-09-16 2018-10-21 2019-10-21 enhancement of the road Based Selection International sector governance for RBD TCP/CON/QCBS/B1/I/ 02 / Technical Assistance for the Quality And Cost- Open - Under upgrade of the existing GIS IBRD / 83220 Prior 0.00 2018-11-21 2018-12-12 2019-01-25 2019-02-22 2019-03-24 2019-04-28 2019-06-02 2020-06-01 Based Selection International Implementation & the road asset management HDM-IV system Page 2 TCP/CON/QCBS/B1/I/02 / Quality And Cost- Open - upgrade of the existing IBRD / 83220 Prior 0.00 Canceled 2018-01-02 2018-01-23 2018-03-08 2018-04-05 2018-05-05 2018-06-09 2018-07-14 2019-07-14 Based Selection International database and GIS at RBD TCP/CON/QCBS/B1/B/C / Technical assistance in Enhancement of the road Quality And Cost- Open - Under IBRD / 83220 Prior 0.00 2018-11-26 2018-12-17 2019-01-30 2019-02-27 2019-03-29 2019-05-03 2019-06-07 2020-06-06 sector governance And Based Selection International Implementation Raising awareness on routine maintenance TCP/CON/QCBS/B4/A / Quality And Cost- Open - Under Training of local contractors IBRD / 83220 Prior 0.00 2018-11-19 2018-12-10 2019-01-23 2019-02-20 2019-03-22 2019-04-26 2019-05-31 2020-05-30 Based Selection International Implementation and consultants for RBD TCP/CON/QCBS/R8B / Technical Assistance of Quality And Cost- Open - Under Construction Supervision for IBRD / 83220 Prior 0.00 2019-01-28 2019-02-18 2019-04-03 2019-05-01 2019-05-31 2019-07-05 2019-08-09 2020-08-08 Based Selection International Implementation Expressway No.1 R8B Project (Remaining Works) INDIVIDUAL CONSULTANTS Page 3