Water Resources and Irrigation project Summarized Procurement Plan for Additional Financing I. General 1. Bank’s approval Date of the procurement Plan: Original: October 31, 2017 (as part of Final PPSD; Revision 1 of Procurement Plan, March 08, 2018; 2. Date of General Procurement Notice: May 25, 2010 (initial publication); GPN Updated December 20, 2012; 3. Period covered by this procurement plan: Until May 31, 2020; II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Prior Review Threshold: Procurement subject to Prior Review by the Bank in accordance with World Bank document named: "Bank Guidance: “Thresholds for procurement approaches and methods by country”, Effective July 01, 2016. Prior Review Thresholds (US$ Million) Type of Procurement Based Substantial Procurement Risk Ratings* High Substantial* Moderate Low Works, Turnkey, S&I of Plant & 10 5.0 15.0 20.0 Equipment and PPP (Euro 8,600) 2 Goods, IT and Non-Consultant Services 1.5 4.0 6.0 (Euro 1.72) 1 Consultant (Firms) 0.5 2.0 4.0 (Euro 0.86) 0.3 Consultant (Individuals) 0.2 0.4 0.5 (Euro 0.26) * Exchange Rate according to the "Project Paper on a proposed Additional Loan" (December 05, 2017) July 9, 2010 Procurement Method Thresholds** (US$ thousands) GOODS, IT & Non-consulting WORKS Services Country Region Open Open Open Open RfQ RfQ International National International National > < < > < < Albania ECA > 5,000 < 5,000 < 200 > 1,000 < 1,000 < 100 (EURO thousands)* Albania ECA > 4,3 < 4,3 < 172.00 > 860.00 < 860.00 < 86.00 All DS (Direct Selection) are subject to "Prior Review" *) All contracts subject to justification for Direct Selection and confirmation that price of items are consistent with the prevailing market price. 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: N/A 4. Reference to (if any) Project Operational/Procurement Manual: Project Operational Manual for World Bank Loan No. 8817 – AL (PMT/WRIP) 5. Any Other Special Procurement Arrangements: N/A 1 2 3 4 5 6 7 Estimated Domestic Review Ref. No. Description Cost Packages Preference by Bank Comments Euro million (yes/no) (Prior / Post) Summary of the RFB (International) (Works) 19.88 2 No Rehabilitation of irrigation schemes (location in Municipality of Has, Kucove, WRIP/1/W/001 Maliq & Lushnja): Tregtan 2, Tregtan 3, Slanice, Leminot, 14.052 Prior Murriz-Thana: Lushnja branch - Upstream & Murriz-Thana: Cukas branch Rehabilitation of Janjari system (Location in Municipality of Konispol): WRIP/1/W/001a Janjari canal and Janjari & 5.82 Post Mursi dams and irrigation schemes Xarra-Bufi & Konispol July 9, 2010 Summary of the RFB (International) (Goods) - - - - - Summary of the RFB (National) (Works) - - - - - Summary of the RFB (National) (Goods) 0.200 1 No Supply and Installation of WRIP/1/G/001 Dam safety Instrumentation 0.200 Post with associated training Summary of the - - - - - 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) * Procurement methods in the Procurement Plan are defined considering Total Contract amount (VAT included) and Threshold and are based on the World Bank document named: "Bank Guidance: Thresholds for procurement approaches and methods by country”, Effective July 01, 2016. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Procurement Method Thresholds** (US$ thousands) Shortlist of National Consultants Consulting Engineering & Services Construction Supervision < < < 300 N/A (EURO thousands)* < 260.00 N/A Contracts with Firms (QCBS) > € 260,000 Contracts with Firms (CQ) < € 260,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than € 260,000 equivalent per contract, may comprise entirely of national consultants in accordance with the World Bank document named: "Bank July 9, 2010 Guidance: Thresholds for procurement approaches and methods by country”, Effective July 01, 2016. 3. Any Other Special Selection Arrangements: N/A 4. Consultancy Assignments with Selection Methods and Time Schedule * Procurement methods in the Procurement Plan are defined considering Total Contract amount (VAT included) and Threshold and are based on the World Bank document named: "Bank Guidance: Thresholds for procurement approaches and methods by country”, Effective July 01, 2016. 1 2 3 4 5 6 Estimated Review Ref. No. Description of Assignment Cost Packages by Bank Comments Euro million (Prior / Post) Summary of number of contracts 1.70 4 Post that will be let under QCBS Supervisory Services for rehabilitation works WRIP/1/CS/001 of up to 11 additional I & D schemes, WRIP/1/CS/001a including Design, ESMPs and Supervision for rehabilitation of Janjari' canal and Janjari & Mursi dams Technical Assistance to Monitoring and Evaluation of irrigation performance and benchmarking and for sustainable and performance based management 0.35 Post WRIP/2/CS/001 improvements at IDUs, financing and investment planning at municipal level Limited targeted specialized and just-in-time support to operationalization of the law on I & D at National level and in support of institutional performance strengthening at WRIP/2/CS/003 scheme and municipal level, such as (i) irrigation service fee setting mechanisms, (ii) 0.25 Post private participation in financing of irrigation in pilot irrigation schemes (e.g. Xarra), and (iii) support to WUO strengthening as required Summary of number of contracts that 0.25 11 will be let under other methods Local Consultant(s) to support MoARD on WRIP/1/IC/002 technical oversight for the CWs and WRIP/1/IC/002a Supervision contract(s) for rehabilitation of up to 11 additional I&D schemes, including 0.06 2 Post IC rehabilitation of Janjari' canal and Janjari & Mursi dams and safeguards compliance Panel of Experts (PoEs) (1 International Consultant (IC) & 4 Local Consultants (IC) for review/approval of Technical WRIP/1/IC/003 Specifications for Instrumentation Plan (IP) WRIP/1/IC/003a concerning safety of agricultural dams and WRIP/1/IC/003b review its implementation; Review any issues WRIP/1/IC/003c concerning Janjari & Mursi Dam, until 0.07 5 Prior IC (DS) WRIP/1/IC/003d completion of the Defects Liability Period and issue the Final/Completion Certificate and related plans [(i) Construction Supervision and Quality Assurance (CSQA) Plan; (ii) Emergency Preparedness Plan (EPP); (iii) July 9, 2010 Operation and Maintenance (O & M) Plan and (iv) Instrumentation Plan], drafting by MoARD. WRIP/4/IC/002 Procurement Consultant for WRIP 0.032 1 Prior IC (DS) WRIP/4/IC/003 Financial Management Consultant for WRIP 0.032 1 Prior IC (DS) Environmental & Social Safeguard and WRIP/4/IC/004 Monitoring & Evaluation Consultant 0.032 1 Prior IC Monitoring & Evaluation (M&E) end Project CQS WRIP/4/CS//001 survey for Component 1, 2 & 4 following 0.020 1 Post Interim evaluation (National) July 9, 2010 PROCUREMENT Albania : Water Resources and Irrigation Project PLAN General Information Country: Albania Bank’s Approval Date of the Original Procurement Plan: 2018-07-06 2019-10-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P121186 GPN Date: 2018-09-12 Project Name: Water Resources and Irrigation Project Loan / Credit No: TF / 14255, IBRD / 82110, IBRD / 88170 Executing Agency(ies): Ministry of Agriculture and Rural Development WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MAFCP/W/ICB/003 / Rehabilitation of 11 dams Dams and Irrigation and Open - Single Stage - One (located in Kuk s, Berat, IBRD / 82110 Drainage Systems Prior Request for Bids 8,600,000.00 8,491,971.11 Signed International Envelope Fier, Korca and Murriz Rehabilitation Thana) MEFWA/MW/001a / Dams and Irrigation and Request for Open - Rehabilitation of Drin-Buna TF / 14255 Drainage Systems Prior 0.00 78,875.33 Signed Quotations International and Seman RBM offices Rehabilitation MAFCP/W/ICB/004 / Rehabilitation of 5 irrigation Dams and Irrigation and Open - Single Stage - One schemes (location in IBRD / 82110 Drainage Systems Prior Request for Bids 0.00 17,515,338.58 Signed International Envelope Municipality of Lushnje, Rehabilitation Divjaka, Roskovec, Devoll) WRIP/1/W/001 / Rehabilitation of irrigation schemes (location in Municipality of Has, Kucove, Dams and Irrigation and Maliq & Lushnja): Tregtan Open - Single Stage - One IBRD / 88170 Drainage Systems Prior Request for Bids 16,440,461.00 13,466,557.21 Signed 2018-08-17 2018-08-22 2018-10-03 2018-11-02 2018-12-07 2019-12-02 2, Tregtan 3, Slanice, International Envelope Rehabilitation Leminot, Murriz-Thana: Lushnja branch - Upstream & Murriz-Thana: Cukas branch MAFCP/W/ICB/005 / Dams and Irrigation and Rehabilitation of Murriz - Open - Single Stage - One IBRD / 82110 Drainage Systems Prior Request for Bids 4,235,400.00 2,854,126.81 Signed 2018-08-15 2018-08-15 2018-08-15 2018-08-15 2018-09-13 2019-04-30 Thana Irrigation scheme - International Envelope Rehabilitation Krutja (V1 & V2) WRIP/1/W/001-A / Rehabilitation of Janjari system (Location in Dams and Irrigation and Pending Municipality of Konispol): Open - Single Stage - Two IBRD / 88170 Drainage Systems Prior Request for Bids 9,946,890.00 0.00 Implementati 2019-10-18 2019-10-23 2019-12-04 2020-02-16 2020-03-22 2020-09-18 Janjari canal and Janjari & International Envelope Rehabilitation on Mursi dams and irrigation schemes Xarra-Bufi & Konispol GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MEFWA/G/001a / Procurement of office Dams and Irrigation and Request for Open - equipment for RBM offices TF / 14255 Drainage Systems Prior 107,888.00 126,145.74 Signed Quotations International Drin Buna and Seman and Rehabilitation MoE MEFWA/G/003 / Dams and Irrigation and Procurement of Cars for Single Stage - One IBRD / 82110 Drainage Systems Prior Request for Bids Open - National 216,112.00 211,922.96 Signed River Basin Management Envelope Rehabilitation Offices MAFCP/G/001 / Computer Dams and Irrigation and Request for Open - Equipment and Software for IBRD / 82110 Drainage Systems Prior 57,272.00 107,290.68 Signed Quotations International DBs and MARDWA Rehabilitation WRIP/G/S/002 / Dams and Irrigation and Request for Open - Procurement of Financial IBRD / 82110 Drainage Systems Prior 13,500.00 7,433.10 Signed Quotations International Software Rehabilitation WRIP/1/G/001 / Supply and Dams and Irrigation and Pending Installation of Dam safety Single Stage - One IBRD / 88170 Drainage Systems Post Request for Bids Open - National 234,000.00 0.00 Implementati 2019-01-10 2019-01-15 2019-02-26 2019-03-28 2019-05-02 2019-08-30 Instrumentation with Envelope Rehabilitation on associated training WRIP/4/G/001 / Financial IBRD / 88170 Implementation Support Prior Direct Selection Direct 2,340.00 0.00 Canceled 2018-10-25 2018-10-30 2018-12-04 2019-06-02 software WRIP/WMA/3/G/001 / Institutional Support for Under Request for Single Stage - One Groundwater monitoring TF / 14255 Integrated Water Resources Post Open - National 100,000.00 0.00 Implementati 2018-10-15 2018-12-06 2019-01-20 Quotations Envelope equipment Management on MAFCP/G/006 / Motorcycles Institutional Support for Request for Single Stage - One for DIUs at municipality IBRD / 82110 Post Open - National 100,000.00 96,825.85 Completed 2019-01-27 2019-03-27 2019-06-25 Irrigation and Drainage Quotations Envelope level MAFCP/G/002A / Hardware & Software for a Management Information Institutional Support for Request for Single Stage - One System for rehabilitated IBRD / 82110 Post Open - National 77,000.00 76,663.28 Completed 2019-01-30 2019-04-10 2019-05-10 Irrigation and Drainage Quotations Envelope Irrigation schemes for DIU at municipality level and Hardware for PMT WRIP/4/G/001-A / Financial IBRD / 88170 Implementation Support Post Direct Selection Direct 2,340.00 1,896.09 Signed 2019-04-15 2019-04-20 2019-05-25 2019-11-21 software NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MEFWA/CS/002 / Dams and Irrigation and Quality And Cost- Open - Preparation of Water TF / 14255 Drainage Systems Prior 0.00 942,588.61 Signed Based Selection International Cadastre Rehabilitation Page 2 MAFCP/CS/005- Dams and Irrigation and CANCELLED / Supervisory Quality And Cost- Open - IBRD / 82110 Drainage Systems Prior 0.00 308,570.43 Canceled Services for Irrigation and Based Selection International Rehabilitation Drainage Works MAFCP/CS/ 005 / Dams and Irrigation and Supervisory Services for Quality And Cost- Open - IBRD / 82110 Drainage Systems Prior 0.00 668,439.01 Signed Irrigation and Drainage Based Selection International Rehabilitation Works MAFCP/CS/002b / Dams and Irrigation and Quality And Cost- Open - Supervisory Services for the IBRD / 82110 Drainage Systems Prior 0.00 409,339.15 Signed Based Selection International Rehabilitation of Dams Rehabilitation MAFCP/CS/003 / Feasibility Study and Detailed Design Dams and Irrigation and Quality And Cost- Open - for Irrigation and Drainage, IBRD / 82110 Drainage Systems Prior 1,700,000.00 1,320,743.87 Signed Based Selection International Consultative Scheme, Rehabilitation Training and Mobilization MEFWA/CS/003 / Dams and Irrigation and Preparation and Quality And Cost- Open - TF / 14255 Drainage Systems Prior 576,500.00 867,955.17 Signed Implementation of an IWRM Based Selection International Rehabilitation Strategy MAFCP/CS/007 / Dams and Irrigation and Preparation of the Quality And Cost- Open - IBRD / 82110 Drainage Systems Prior 0.00 261,173.19 Signed Environment and Social Based Selection International Rehabilitation Management Plan (ESMP) MEFWA/CS/001 / Dams and Irrigation and Preparation of River Basin Quality And Cost- Open - IBRD / 82110 Drainage Systems Prior 0.00 1,724,966.28 Signed Management Plan for Drin- Based Selection International Rehabilitation Buna and Semani MAFCP/CS/009 / Training Dams and Irrigation and Least Cost Open - Services for Drainage Boards IBRD / 82110 Drainage Systems Prior 0.00 599,100.79 Signed Selection International (DBs) Rehabilitation WRIP/1/CS/001 / Feasibility Study, Detailed Design & ESMPs for Janjari system, including Janjari' canal, irrigation scheme of Dams and Irrigation and Quality And Cost- Open - Konispol, and Janjari & IBRD / 88170 Drainage Systems Post 596,700.00 483,215.38 Signed 2018-07-24 2018-08-21 2018-09-18 2018-10-02 2018-10-16 2018-11-13 2018-12-04 2020-04-27 Based Selection International Mursi dams and Rehabilitation Supervisory Services for rehabilitation works of Janjari System (Location in Municipality of Konispol): WRIP/1/CS/001A / Supervisory Services for rehabilitation works of irrigation schemes (location in Municipality of Has, Dams and Irrigation and Quality And Cost- Open - Kucove, Maliq & Lushnja): IBRD / 88170 Drainage Systems Post 690,300.00 461,926.28 Signed 2018-07-25 2018-08-17 2018-09-21 2018-10-19 2018-11-02 2018-11-30 2018-12-28 2019-12-28 Based Selection International Tregtan 2, Tregtan 3, Rehabilitation Slanice, Leminot, Murriz- Thana: Lushnja branch - Upstream & Murriz-Thana: Cukas branch WRIP/4/CS//001 / Monitoring & Evaluation Consultant (M&E) end Project survey IBRD / 88170 Implementation Support Post Qualification Open - National 23,400.00 0.00 Canceled 2018-09-19 2018-10-10 2018-11-23 2018-12-23 2019-01-27 2019-05-15 for Component 1, 2 & 4 Selection following Interim evaluation Page 3 WRIP/CS/CQ/006 / M&E Consultancy End Project Consultant Survey Final for Component IBRD / 82110 Implementation Support Post Qualification Open - National 50,660.00 45,329.10 Signed 2018-08-15 2018-08-15 2018-08-15 2018-08-15 2018-08-15 2018-12-31 3 and Interim for Selection Component 1, 2 & 4 MAFCP/CS/005A / Supervisory Services for Dams and Irrigation and Consultant Open - rehabilitation works of IBRD / 82110 Drainage Systems Post Qualification 175,500.00 166,245.93 Signed 2018-08-15 2018-08-15 2018-08-15 2018-08-15 2018-08-15 2019-04-30 International Murriz -Thana Irrigation Rehabilitation Selection scheme - Krutja (V1 & V2) WRIP/2/CS/001 / Technical Assistance to Monitoring and Evaluation of irrigation performance and benchmarking and for Institutional Support for Quality And Cost- Open - IBRD / 88170 Post 702,000.00 0.00 Canceled 2018-08-10 2018-08-31 2018-10-14 2018-11-11 2018-12-11 2019-01-15 2019-02-19 2020-05-14 sustainable and performance Irrigation and Drainage Based Selection International based management improvements at IDUs, financing and investment planning at municipal level WRIP/2/CS/001A / Technical Assistance to Monitoring and Evaluation of irrigation performance and benchmarking and Institutional Support for Quality And Cost- Open - installation of software for IBRD / 88170 Prior 702,000.00 0.00 Canceled 2018-09-07 2018-09-28 2018-11-02 2018-11-23 2018-12-14 2019-01-11 2019-02-08 2020-05-18 Irrigation and Drainage Based Selection International sustainable and performance based management improvements at IDUs, financing and investment planning at municipal level WRIP/1/CS/002 / Design of pressurized irrigation in pilot Dams and Irrigation and Quality Based area Divjaka and IBRD / 88170 Drainage Systems Post Open - National 115,000.00 0.00 Canceled 2018-10-03 2018-10-17 2018-11-21 2018-12-12 2019-01-02 2019-01-16 2019-02-13 2019-04-14 Selection improvements in Lushnja Rehabilitation irrigation schemes. WRIP/2/CS/001A-1 / Technical Assistance to improving irrigation Institutional Support for Quality And Cost- Open - IBRD / 88170 Prior 702,000.00 626,300.00 Signed 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2020-09-03 performance and Monitoring Irrigation and Drainage Based Selection International and Evaluation at municipal level WRIP/WMA/3/CS/006 / TA Institutional Support for Consultant for establish a Regulatory Open - TF / 14255 Integrated Water Resources Post Qualification 300,000.00 299,505.26 Signed 2018-12-12 2019-01-02 2019-02-06 2019-02-27 2019-03-27 2019-08-24 and Institutional Platform International Management Selection for National Water Cadastre WRIP/1/CS/001B / Feasibility Study, Detailed Design & ESMPs and Dams and Irrigation and Consultant Supervision services for IBRD / 82110 Drainage Systems Post Qualification Open - National 118,000.00 114,346.16 Signed 2019-01-22 2019-02-12 2019-03-28 2019-04-27 2019-06-01 2019-11-28 Implementation a Rehabilitation Selection Pressurized system for a pilot area of Divjaka INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 MAFCP/CS/010a (International Consultant) / Dams and Irrigation and Individual PREPARATION OF IBRD / 82110 Drainage Systems Prior Consultant Open 0.00 65,754.12 Signed 2014-12-29 NATIONAL IRRIGATION Rehabilitation Selection AND DRAINAGE STRATEGY MAFCP/CS/008a / Dam Dams and Irrigation and Individual Portfolio Risk Management IBRD / 82110 Drainage Systems Prior Consultant Open 0.00 27,996.68 Signed Expert Rehabilitation Selection MAFCP/CS/008b / Dam Dams and Irrigation and Individual Engineering/Hydro Technique IBRD / 82110 Drainage Systems Prior Consultant Open 0.00 7,491.18 Signed Expert (Local Consultant) Rehabilitation Selection Dams and Irrigation and Individual WRIP/CS/IC/001 / Local IBRD / 82110 Drainage Systems Prior Consultant Open 23,730.00 24,923.33 Signed 2016-09-13 2016-09-20 2016-09-21 2017-09-16 Procurement Consultant Rehabilitation Selection WRIP/1/IC/002 / Local Consultant to support MoARD on technical oversight for the CWs and Dams and Irrigation and Individual Supervision contract for IBRD / 88170 Drainage Systems Post Consultant Open 42,120.00 0.00 Canceled 2018-07-25 2018-09-10 2018-10-01 2018-11-05 2019-12-30 rehabilitation works of Rehabilitation Selection irrigation schemes (location in Municipality of Has, Kucove, Maliq & Lushnja) and safeguards compliance WRIP/1/IC/002A / Local Consultant to support MoARD on technical oversight for the CWs and Supervision contracts for Dams and Irrigation and Individual Pending rehabilitation works of IBRD / 88170 Drainage Systems Post Consultant Open 28,080.00 0.00 2018-09-28 2019-02-10 2019-03-03 2019-04-07 2020-05-31 Implementation Janjari system (Location in Rehabilitation Selection Municipality of Konispol): Janjari' canal and Janjari & Mursi dams and irrigation schemes Xarra-Bufi & WRIP/1/IC/003 / PoEs - Dams and Irrigation and Dam Portfolio Risk IBRD / 88170 Drainage Systems Prior Direct Selection Direct 42,120.00 0.00 Canceled 2018-08-03 2018-08-13 2018-09-24 2020-04-16 Management Expert Rehabilitation (International Consultant) WRIP/1/IC/003A / PoEs - Dams and Irrigation and Dam Engineering/Hydro IBRD / 88170 Drainage Systems Prior Direct Selection Direct 11,700.00 0.00 Canceled 2018-08-03 2018-08-13 2018-09-24 2020-04-16 Technique Expert (Local Rehabilitation Consultant) WRIP/1/IC/003B / PoEs - Dams and Irrigation and Mechanical Engineering IBRD / 88170 Drainage Systems Prior Direct Selection Direct 9,360.00 0.00 Canceled 2018-08-03 2018-08-13 2018-09-24 2020-04-16 Expert (Local Consultant) Rehabilitation WRIP/1/IC/003C / PoEs - Dams and Irrigation and Engineering Geology Expert IBRD / 88170 Drainage Systems Prior Direct Selection Direct 10,530.00 0.00 Canceled 2018-08-03 2018-08-13 2018-09-24 2020-04-16 (Local Consultant) Rehabilitation WRIP/1/IC/003D / PoEs - Dams and Irrigation and Dam Hydrologist Expert IBRD / 88170 Drainage Systems Prior Direct Selection Direct 8,190.00 0.00 Canceled 2018-08-03 2018-08-13 2018-09-24 2020-04-16 (Local Consultant) Rehabilitation WRIP/4/IC/002 / Individual Procurement Consultant for IBRD / 88170 Implementation Support Prior Consultant Open 37,440.00 1,230.48 Signed 2018-07-26 2018-08-01 2018-08-15 2018-08-29 2020-05-20 WRIP Selection Page 5 WRIP/4/IC/003 / Financial Management Consultant for IBRD / 88170 Implementation Support Prior Direct Selection Direct 37,440.00 32,853.99 Signed 2018-07-26 2018-07-26 2018-07-26 2020-05-31 WRIP WRIP/4/IC/004 / Individual Environmental & Social IBRD / 88170 Implementation Support Prior Consultant Open 37,440.00 28,747.27 Signed 2018-07-26 2018-09-04 2018-09-18 2018-10-16 2020-05-28 Safeguard and Monitoring & Selection Evaluation Consultant MAFCP/CS/006C / Local Consultant to support MoARD on technical Dams and Irrigation and Individual oversight for the CWs and IBRD / 82110 Drainage Systems Post Consultant Open 12,870.00 12,682.49 Signed 2018-08-15 2018-08-30 2018-09-06 2018-09-20 2019-05-31 Supervision contract for Rehabilitation Selection Rehabilitation of Murriz - Thana Irrigation scheme - Krutja (V1 & V2) WRIP/1/IC/002C / Local Consultant to support MoARD on technical oversight for the CWs and Dams and Irrigation and Individual Supervision contract for IBRD / 88170 Drainage Systems Post Consultant Open 20,516.00 20,400.11 Signed 2018-11-27 2019-01-15 2019-02-05 2019-03-12 2019-09-08 rehabilitation works of Rehabilitation Selection irrigation schemes (location in Municipality of Lushnja) and safeguards compliance WRIP/1/IC/002B / Local Consultant to support MoARD on technical oversight for the CWs and Dams and Irrigation and Individual Supervision contract for IBRD / 88170 Drainage Systems Post Consultant Open 21,604.00 21,539.52 Signed 2018-11-20 2019-01-08 2019-01-29 2019-03-05 2019-09-01 rehabilitation works of Rehabilitation Selection irrigation schemes (location in Municipality of Has, Kuçove, Maliq WRIP/1/IC/003-1 / PoEs Dams and Irrigation and Dam Portfolio Risk IBRD / 82110 Drainage Systems Post Direct Selection Direct 42,120.00 30,596.22 Signed 2019-02-04 2019-02-14 2019-04-20 2019-10-17 Management Expert Rehabilitation (International Consultant) WRIP/1/IC/003C-1 / PoEs Dams and Irrigation and Engineering Geology Expert IBRD / 82110 Drainage Systems Post Direct Selection Direct 10,530.00 10,160.00 Signed 2019-02-04 2019-02-14 2019-04-20 2019-10-17 (Local Consultant) Rehabilitation WRIP/1/IC/003A-1 / PoEs Dams and Irrigation and Engineering Hydro Technique IBRD / 82110 Drainage Systems Post Direct Selection Direct 11,700.00 11,147.38 Signed 2019-02-04 2019-02-14 2019-04-20 2019-10-17 Expert (Local Consultant) Rehabilitation WRIP/1/IC/003D-1 / PoEs Dams and Irrigation and Dam Engineering Hydroligist IBRD / 82110 Drainage Systems Post Direct Selection Direct 8,190.00 8,206.35 Signed 2019-02-04 2019-02-14 2019-04-20 2019-10-17 Expert (Local Consultant) Rehabilitation WRIP/1/IC/003B-1 / PoEs Dams and Irrigation and Engineering Mechanical IBRD / 82110 Drainage Systems Post Direct Selection Direct 9,360.00 9,308.52 Signed 2019-02-04 2019-02-14 2019-04-20 2019-10-17 Expert (Local Consultant) Rehabilitation WRIP/4/CS//001-A / Baseline Survey and Monitoring & Evaluation (M&E) end IBRD / 88170 Implementation Support Post Direct Selection Direct 70,000.00 0.00 Canceled 2019-04-15 2019-04-25 2019-06-29 2019-12-26 Project survey for Component 1, 2 & 4 following Interim evaluation Page 6 WRIP/4/CS/001-B / Baseline Survey for the new I&D IBRD / 88170 Implementation Support Post Direct Selection Direct 54,000.00 50,054.72 Signed 2019-08-22 2019-09-01 2019-11-05 2020-05-03 schemes and lessons learned from project implementation WRIP/4/IC/005 / Project Pending IBRD / 88170 Implementation Support Post Direct Selection Direct 14,025.00 0.00 2019-10-07 2019-10-17 2019-12-21 2020-06-18 Manager Implementation Page 7