Appendix to Annex 3 Procurement Plan I. General 1. Project Information Country : India Borrower : Government of India Project Name : National Hydrology Project Loan Credit No. : 2. Bank’s Approval Date of the Procurement Plan : 3. Date of General Procurement Notice : 4. Period Covered by this procurement plan : 18 months II. Goods, Works, and Non-Consulting Services Thresholds for Method of Procurement for procurement of goods, works and non-consulting services Procurement of Goods, Information technology and non consultancy services: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 3 million Limited Competitive Bidding (LIB) Must meet the requirements as per Para 3.2 of the Procurement Guidelines, and with prior agreement in PP with the Bank National Competitive Bidding (NCB) > USD 100,000 and up to USD 3 million Shopping Up to USD 100,000 (INR 6.5 m) Direct Must meet the requirements as per Para 3.7 of the Procurement Guidelines, and with prior agreement in PP with the Bank Framework Agreement Must meet the requirements as per Para 3.6 of the Procurement Guidelines, and with prior agreement in PP with the Bank Procurement of Works: Method of Procurement Thresholds for Methods International Competitive Bidding (ICB) > US Dollars 40 million National Competitive Bidding (NCB) > USD 100,000 and up to USD 40 million Comparison of three quotations / Shopping Up to USD 100,000 (INR 6.5 m) Force Account Must meet the requirements as per Para 3.9 of the Procurement Guidelines, and with prior agreement in PP with the Bank Prior Review Thresholds: The following would be subject to Prior review of the Bank regardless of the Method of selection: (a) Works: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 10 million (b) Goods: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 2 million; and The Prior Review Thresholds will be reviewed and updated during the implementation of the project, and modified based on the risk assessment. 1. In the case of contracts subject to prior review, Project Implementing Entity shall seek the Bank’s no objection before granting/agreeing to (a) an extension of the stipulated time for performance of a contract that either increases the contract price or has an impact on the planned completion of the project; (b) any substantial modification of the scope of works, goods, non-consulting services or consulting services, other significant changes to the terms and conditions of such that the contract,; (c) any variation order or amendment (except in cases of extreme urgency) which singly or combined with all variation orders or amendments previously issued, increase the original contract amount by more than 15 percent; or (d) the proposed termination of the contract.. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Prequalification Not Applicable Domestic Preference: The provision of domestic preference is applicable in the evaluation of Goods only. 3. Reference to Procurement Manual The procurement manual for the project is presently under preparation. SBDs agreed between the Project and Bank will be used for all works, goods, and non consultancy procurements. 4. Any Other Special Procurement Arrangements The National bidding method for procurement and goods and works according to the above value thresholds will be conducted in accordance with paragraphs 3.3 and 3.4 of the Bank’s Procurement Guidelines and the following provisions: (a) Only the model bidding documents for NCB agreed with the GOI task force (and as amended for time to time) shall be used for bidding. (b) Invitations to bid shall be advertised in at least one widely circulated national daily newspaper (or on a widely used website or electronic portal with free national and international access along with an abridged version of the said advertisement published in a widely circulated national daily, among others, giving the website/electronic portal details from which the details of the invitation to bid can be downloaded) at least 30 days before the deadline for the submission of bids. (c) No special preferences will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises, or enterprises from any given state. (d) Extension of bid validity shall not be allowed with reference to contracts subject to Bank prior review without the prior concurrence of the Bank (i) for the first request for extension if it is longer than four weeks and (ii) for all subsequent requests for extension irrespective of the period (such concurrence will be considered by the Bank only in cases of force majeure and circumstances beyond the control of the purchaser/employer). (e) Rebidding shall not be carried out with reference to contracts subject to Bank prior review without the prior concurrence of the Bank. The system of rejecting bids outside a predetermined margin or ‘bracket’ of prices shall not be used in the project. (f) Rate contracts entered into by the DGS&D will not be acceptable as a substitute for NCB procedures unless incorporation of right to audit and fraud corruption clauses. DGS&D contracts will be acceptable, however, for any procurement under the shopping procedures. (g) Two or three envelope system will not be used (except when using the e-procurement system assessed and agreed by the Bank). (h) No negotiations are conducted even with the lowest evaluated responsive bidders. 5. The bid evaluation will be carried out according to the agreed timeline in the Procurement Activity Schedule. III. Selection of Consultants 1. Methods and Prior Review Threshold Procurement methods of procurement of Consultants' Services (Firms) Method of Procurement Thresholds for Methods Quality and Cost Based Selection (QCBS) Quality Based Selection (QBS) Must meet the requirements as per Para 3..2 to 3.4 of the Consultant Guidelines Selection based on a Fixed Budget (FBS) Must meet the requirements as per Para 3.5 of the Consultant Guidelines, Selection Based on Least Cost Basis (LCS) Must meet the requirements as per Para 3.6 of the Consultant Guidelines, Selection based on Consultant’s Qualification Estimated not to exceed USD 300,000, and (CQ) must meet the requirements as per Para 3.7 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements as per Para 3.8 to 3.11 of the Consultant Guidelines, and with prior agreement in PP with the Bank. Procurement methods for Selection of Individual Consultants (IC) Method of Procurement Thresholds for Methods Competitive Selection Must meet the requirements of Section V, Para 5.1 to 5.5 of the Consultant Guidelines. Single Source Selection (SSS) Must meet the requirements of Section V, Para 5.6 of the Consultant Guidelines and with prior agreement in PP with the Bank *Shall meet the requirements as stated in Consultant Guidelines Prior Review Thresholds: (a). Consulting Firm: First procurement under the project irrespective of value and all procurements estimated to cost more than USD 1 million. (b). Individual Consultant: all procurements estimated to cost more than USD 0.3 million Terms of Reference (ToR) for all consultant contracts shall be furnished to the Bank for its prior review and No Objection. Note: The Prior Review Thresholds will be reviewed during the implementation of the project and modified. 1. In the case of contracts subject to prior review, before agreeing to: (a) an extension of the stipulated time for performance of a contract; (b) any substantial modification of the scope of services, substitutions of key experts, or other significant changes to the terms and conditions of the contract; or (c) the proposed termination of the contract, the Borrower shall seek the Bank’s no objection. A copy of all amendments to the contract shall be furnished to the Bank for its record. 2. Short List comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than USD 800,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. The Request for Expression of Interest for consultancy services estimated to cost above USD 300,000 equivalent per contract for firms shall be advertised in UNDB online and World Bank external Website and in accordance with other provisions of Para 2.5 of the Consultant Guidelines 4. Any other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable] I. Implementing Agency Capacity Building Activities with Time Schedule No Expected Outcome/Activity Description Estimated Date Duration ASCI training on Procurement Procedures arranged for 1. Executive, Assistant Engineers who are responsible for 2 weeks Continuous Procurement – multiple trainings 2. Contract management training – multiple trainings 2 weeks Continuous Customized training on Procurement Procedures arranged for 3. Executive, Assistant Engineers who are responsible for 1 week Continuous Procurement – multiple trainings PROCUREMENT India : National Hydrology Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2017-08-16 2020-02-13 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152698 GPN Date: Project Name: National Hydrology Project Loan / Credit No: IBRD / 87250 Executing Agency(ies): Rajasthan - NHP WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2018-2019-RJ-214021- Pending Water Resources Monitoring Request for Single Stage - One CW-SH-QU / District data IBRD / 87250 Post Open - National 41,538.46 0.00 Implementati 2018-07-20 2018-09-14 2019-03-13 System Quotations Envelope center on NHP-2018-2019-RJ-968644 / Pending Construction , Renovation & Institutional Capacity Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 523,076.92 0.00 Implementati 2018-07-09 2018-07-14 2018-08-25 2018-11-07 2018-12-12 2019-06-10 modernisation of knowledge Enhancement Envelope on center NHP-2018-2019-RJ-483550 / Institutional Capacity Request for Single Stage - One Establishment of SPMU ( IBRD / 87250 Post Open - National 76,923.08 74,250.93 Signed 2018-08-06 2018-10-01 2019-03-30 Enhancement Quotations Envelope Renovation/ civil work) NHP-2018-2019-RJ-927345 / Water Resources Monitoring Request for Single Stage - One Regional Data center- IBRD / 87250 Post Open - National 7,692.31 6,577.22 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Bikaner NHP-2018-2019-RJ-782929 / Under Water Resources Monitoring Request for Single Stage - One Regional Data center- IBRD / 87250 Post Open - National 7,692.31 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Jodhpur on Pending NHP-2018-2019-RJ-760627 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 7,692.31 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 Regional Data center-Kota System Quotations Envelope on NHP-2018-2019-RJ-936016 / Water Resources Monitoring Request for Single Stage - One Regional Data center- IBRD / 87250 Post Open - National 7,692.31 3,804.97 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Hanumangarh NHP-2018-2019-RJ-716078 / Pending Water Resources Monitoring Request for Single Stage - One Regional Data center- IBRD / 87250 Post Open - National 7,692.31 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Udaipur on NHP-2018-2019-RJ-181873 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,421.22 Completed 2018-09-25 2018-11-20 2019-05-19 District data center-Ajmer System Quotations Envelope NHP-2018-2019-RJ-259944 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,404.12 Completed 2018-09-25 2018-11-20 2019-05-19 District data center- Alwar System Quotations Envelope NHP-2018-2019-RJ-200489 / Water Resources Monitoring Request for Single Stage - One District Data center- IBRD / 87250 Post Open - National 1,538.46 1,448.94 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Banswara NHP-2018-2019-RJ-602177 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,407.03 Completed 2018-09-25 2018-11-20 2019-05-19 District Data center- Baran System Quotations Envelope Page 1 Pending NHP-2018-2019-RJ-991061 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 District Data Center-Barmer System Quotations Envelope on NHP-2018-2019-RJ-771042 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,061.40 Signed 2018-09-25 2018-11-20 2019-05-19 District Data Center-tonk System Quotations Envelope NHP-2018-2019-RJ-752350 / Water Resources Monitoring Request for Single Stage - One District Data center- IBRD / 87250 Post Open - National 1,538.46 1,425.05 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Bharatpur NHP-2018-2019-RJ-548301 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,456.75 Completed 2018-09-25 2018-11-20 2019-05-19 District Data Center-sirohi System Quotations Envelope NHP-2018-2019-RJ-410294 / Water Resources Monitoring Request for Single Stage - One District Data Center- IBRD / 87250 Post Open - National 1,538.46 910.70 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Bhilwara NHP-2018-2019-RJ-509917 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,274.66 Completed 2018-09-25 2018-11-20 2019-05-19 District Data Center-sikar System Quotations Envelope NHP-2018-2019-RJ-983453 / Water Resources Monitoring Request for Single Stage - One District Data Center -sawai IBRD / 87250 Post Open - National 1,538.46 1,404.28 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope madhopur NHP-2018-2019-RJ-310532 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,423.31 Completed 2018-09-25 2018-11-20 2019-05-19 District Data Center- Bundi System Quotations Envelope NHP-2018-2019-RJ-571742 / Water Resources Monitoring Request for Single Stage - One District Data Center- IBRD / 87250 Post Open - National 1,538.46 1,335.26 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Chittorgarh Pending NHP-2018-2019-RJ-969516 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 District Data Center-Nagaur System Quotations Envelope on Pending NHP-2018-2019-RJ-178723 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 District Data Center-Churu System Quotations Envelope on Pending NHP-2018-2019-RJ-833176 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 District Data Center-pali System Quotations Envelope on NHP-2018-2019-RJ-390411 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,415.63 Completed 2018-09-25 2018-11-20 2019-05-19 District Data Center-Dausa System Quotations Envelope NHP-2018-2019-RJ-168639 / Water Resources Monitoring Request for Single Stage - One District Data Center - IBRD / 87250 Post Open - National 1,538.46 1,380.20 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Pratapgarh NHP-2018-2019-RJ-709863 / Water Resources Monitoring Request for Single Stage - One District Data Center - IBRD / 87250 Post Open - National 1,538.46 1,333.61 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Rajsamand NHP-2018-2019-RJ-876975 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,446.97 Completed 2018-09-25 2018-11-20 2019-05-19 District Data Center-Dholpur System Quotations Envelope NHP-2018-2019-RJ-740080 / Pending Water Resources Monitoring Request for Single Stage - One District Data Center- IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Dungarpur on NHP-2018-2019-RJ-787628 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,575.14 Completed 2018-09-25 2018-11-20 2019-05-19 District Data Center-Jalore System Quotations Envelope Page 2 NHP-2018-2019-RJ-991487 / Water Resources Monitoring Request for Single Stage - One District Data Center- IBRD / 87250 Post Open - National 1,538.46 1,438.74 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope jhalawar NHP-2018-2019-RJ-944494 / Water Resources Monitoring Request for Single Stage - One District Data Center- IBRD / 87250 Post Open - National 1,538.46 1,378.26 Completed 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Ganganagar NHP-2018-2019-RJ-526947 / Pending Water Resources Monitoring Request for Single Stage - One District Data Center - IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope jhunjhunu on NHP-2018-2019-RJ-212055 / Pending Water Resources Monitoring Request for Single Stage - One District Data Center- IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-09-25 2018-11-20 2019-05-19 System Quotations Envelope Jaisalmer on NHP-2018-2019-RJ-834818 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 1,301.47 Completed 2018-09-25 2018-11-20 2019-05-19 District Data Center-Karauli System Quotations Envelope NHP-2018-2019-RJ-354417- Pending Water Resources Monitoring Request for Single Stage - One CW-SH-QU / Regional data IBRD / 87250 Post Open - National 38,461.54 0.00 Implementati 2018-07-20 2018-09-14 2019-03-13 System Quotations Envelope center on NHP-2018-2019-RJ-229316 / Remaining work (for Institutional Capacity Request for Single Stage - One IBRD / 87250 Post Open - National 7,692.31 7,148.03 Completed 2019-02-12 2019-04-09 2019-10-06 establishment of SPMU) and Enhancement Quotations Envelope vehicle parking work NHP-2019-2020-RJ-498339 / Under Water Resources Monitoring Request for Single Stage - One Civil works for Material IBRD / 87250 Post Open - National 18,461.54 0.00 Implementati 2019-08-06 2019-10-01 2020-03-29 System Quotations Envelope testing lab on NHP-2019-2020-RJ-402773 / Pending Water Resources Monitoring Single Stage - Two Solar system for State data IBRD / 87250 Post Request for Bids Open - National 115,384.62 0.00 Implementati 2019-08-10 2019-08-15 2019-09-26 2019-12-09 2020-01-13 2020-07-11 System Envelope center on NHP-2019-2020-RJ-597470 / Pending Water Resources Monitoring Request for Single Stage - One Rain water harvesting for IBRD / 87250 Post Open - National 38,461.54 0.00 Implementati 2019-08-15 2019-10-10 2020-04-07 System Quotations Envelope state data center on NHP-2019-2020-RJ-682345 / Supply, Installation and Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 467,692.31 0.00 Canceled 2019-07-31 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 maintenance of SCADA System Envelope system at Mahi NHP-2019-2020-RJ-321347 / Under Supply, Installation and Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 461,538.46 0.00 Implementati 2019-07-31 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 maintenance of SCADA System Envelope on system at Jawai dam NHP-2019-2020-RJ-329125 / Supply, Installation and Under Water Resources Monitoring Single Stage - Two maintenance of SCADA IBRD / 87250 Post Request for Bids Open - National 784,615.38 0.00 Implementati 2019-07-31 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 System Envelope system at Narmada canal on project Sanchore NHP-2019-2020-RJ-769416 / Supply, Installation and Pending Water Resources Monitoring Single Stage - Two maintenance of SCADA IBRD / 87250 Post Request for Bids Open - National 1,423,076.92 0.00 Implementati 2019-07-31 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 System Envelope system at Gang and Bhakra on canal system Hanumangarh NHP-2019-2020-RJ-991028 / Pending Civil works for water quality Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 153,846.15 0.00 Implementati 2019-09-15 2019-09-20 2019-11-01 2020-01-14 2020-02-18 2020-08-16 lab building at GWD and System Envelope on WRD Page 3 NHP-2019-2020-RJ-519757 / Establishment of SCADA Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 43,076.92 38,118.79 Signed 2019-09-25 2019-11-20 2020-05-18 Control room at Bisalpur System Quotations Envelope dam NHP-2019-2020-RJ-801777 / Repair & Renovation Work Under Water Resources Monitoring Single Stage - Two for Establishment of State IBRD / 87250 Post Request for Bids Open - National 630,769.23 0.00 Implementati 2019-08-10 2019-08-15 2019-09-26 2019-12-09 2020-01-13 2020-07-11 System Envelope Water Resources Informatic on Center at Jaipur NHP-2018-2019-RJ-106903- Water Resources Monitoring Single Stage - Two CW-NCB-DE / State data IBRD / 87250 Post Request for Bids Open - National 1,384,615.38 0.00 Canceled 2018-08-16 2018-08-21 2018-10-02 2018-12-15 2019-01-19 2019-07-18 System Envelope center NHP-2019-2020-RJ-535810 / Preparation of estimation for Water Resources Monitoring Request for Single Stage - One motorization and IBRD / 87250 Post Open - National 1,538.46 0.00 Canceled 2019-12-12 2020-02-06 2020-08-04 System Quotations Envelope electrification of gates of Bhakra & Gang Canal NHP-2019-2020-RJ-661206 / Pending Supply, Installation and Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 507,692.31 0.00 Implementati 2020-02-12 2020-02-17 2020-03-30 2020-06-12 2020-07-17 2021-01-13 maintenance of SCADA System Envelope on system at Gudha dam NHP-2019-2020-RJ-445779 / Pending Supply, Installation and Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 507,692.31 0.00 Implementati 2020-02-12 2020-02-17 2020-03-30 2020-06-12 2020-07-17 2021-01-13 maintenance of SCADA System Envelope on system at Mahi GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-RAJASTHAN -21107-GO- RFQ / Manual Rain Gauge Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Limited 3,077.00 67.11 Completed 2017-07-20 2017-08-10 2017-09-09 equipment with measuring System Quotations Envelope glass. 45 Nos IN-RAJASTHAN -40425-GO- Water Resources Monitoring Single Stage - Two RFB / RTDAS for State of IBRD / 87250 Prior Request for Bids Open - National 2,353,846.15 2,327,020.07 Signed 2018-05-16 2018-05-21 2018-07-12 2018-09-09 2018-10-14 2019-07-11 System Envelope Rajasthan NHP-2018-2019-RJ-398027- Water Resources Monitoring Single Stage - Two GO-NCB-DE / Discharge IBRD / 87250 Post Request for Bids Open - National 319,230.77 0.00 Canceled 2018-07-01 2018-07-06 2018-08-17 2018-10-30 2018-12-04 2019-06-02 System Envelope measurement equipment NHP-2018-2019-RJ-302457- Water Resources Monitoring Request for Single Stage - One GO-SH-QU / Manual SRG IBRD / 87250 Post Open - National 3,076.92 2,647.31 Completed 2018-07-15 2018-09-09 2019-03-08 System Quotations Envelope (2018-19) NHP-2018-2019-RJ-573302- Water Resources Monitoring Single Stage - Two GO-NCB-DE / SCADA and IBRD / 87250 Post Request for Bids Open - National 461,538.46 450,166.94 Signed 2018-07-01 2018-07-06 2018-08-17 2018-10-30 2018-12-04 2019-06-02 System Envelope gate sensors for other dams NHP-2018-2019-RJ-270099- GO-SH-QU / LCD screen for Water Resources Monitoring Request for Single Stage - One conference /meetin room and IBRD / 87250 Post Open - National 46,153.85 0.00 Canceled 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope procurement of video conference facility(2018-19) Page 4 NHP-2018-2019-RJ-436351- Pending Water Resources Monitoring Request for Single Stage - One GO-SH-QU / Software for IBRD / 87250 Post Open - National 56,923.08 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope data center(2018-19) on Pending NHP-2018-2019-RJ-759763- Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 38,461.54 0.00 Implementati 2018-07-15 2018-09-09 2019-03-08 GO-SH-QU / Software/models System Quotations Envelope on NHP-2018-2019-RJ-596058 / Water Resources Monitoring Request for Single Stage - One Communication equipment IBRD / 87250 Post Open - National 1,538.46 1,430.01 Completed 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope for data center(2018-19) NHP-2018-2019-RJ-551788 / Water Resources Monitoring Request for Single Stage - One Plotter/ printers for data IBRD / 87250 Post Open - National 13,846.15 6,058.06 Completed 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope center (2018-19) NHP-2018-2019-RJ-416392 / Water Resources Monitoring Request for Single Stage - One Scanner for data center IBRD / 87250 Post Open - National 1,615.38 1,448.58 Completed 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope (2018-19) NHP-2018-2019-RJ-293051 / Water Resources Monitoring Request for Single Stage - One Servers for data center IBRD / 87250 Post Open - National 1,538.46 0.00 Canceled 2018-12-06 2019-01-31 2019-07-30 System Quotations Envelope (2018-19) NHP-2018-2019-RJ-235140 / Pending Water Resources Monitoring Request for Single Stage - One Storage and back up devices IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope for data center (2018-19) on Pending NHP-2018-2019-RJ-651934 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 3,846.15 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 Handheld GPS ( 2018-19) System Quotations Envelope on Under NHP-2018-2019-RJ-632856 / Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 346,153.85 208,027.05 Implementati 2018-09-15 2018-09-20 2018-11-01 2019-01-14 2019-02-18 2019-08-17 DWLR with telemetry GSM System Envelope on NHP-2018-2019-RJ-581558 / Pending Water Resources Monitoring Request for Single Stage - One Software for data IBRD / 87250 Post Open - National 3,230.77 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope center(2018-19) on NHP-2018-2019-RJ-801730 / Water Resources Information Request for Single Stage - One Development of Information IBRD / 87250 Post Open - National 3,600.00 0.00 Canceled 2018-08-21 2018-10-16 2019-04-14 Systems Quotations Envelope brochures(2018-19) NHP-2018-2019-RJ-330361 / Water Resources Information Request for Single Stage - One Servers for hosting website IBRD / 87250 Post Open - National 20,461.54 0.00 Canceled 2018-09-06 2018-11-01 2019-04-30 Systems Quotations Envelope and data services(2018-19) NHP-2018-2019-RJ-294757 / Pending Water Resources Information Request for Single Stage - One Internet charges for IBRD / 87250 Post Open - National 5,384.62 0.00 Implementati 2018-09-06 2018-11-01 2019-04-30 Systems Quotations Envelope hosting(2018-19) on NHP-2018-2019-RJ-334890 / Pending Communication system for Water Resources Information Request for Single Stage - One IBRD / 87250 Post Open - National 7,692.31 0.00 Implementati 2018-09-06 2018-11-01 2019-04-30 data exchange among Systems Quotations Envelope on agencies NHP-2018-2019-RJ-997858 / Pending Institutional Capacity Single Stage - Two Furnishing of center IMTI IBRD / 87250 Post Request for Bids Open - National 153,846.15 0.00 Implementati 2018-07-09 2018-07-14 2018-08-25 2018-11-07 2018-12-12 2019-06-10 Enhancement Envelope kota on NHP-2018-2019-RJ-537251 / Installation of network, Water Resources Monitoring Request for Single Stage - One cabling etc & Training IBRD / 87250 Post Open - National 5,384.62 0.00 Canceled 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope equipment/ LCD projector and screen Page 5 IN-RAJASTHAN -72381-GO- Pending Water Resources Monitoring Single Stage - Two RFB / Medium and deep IBRD / 87250 Post Request for Bids Open - National 419,230.77 0.00 Implementati 2018-09-15 2018-09-20 2018-11-01 2019-01-14 2019-02-18 2019-08-17 System Envelope piezometer on NHP-2018-2019-RJ-796471 / Water Resources Monitoring Request for Single Stage - One Laptops for data center(2018- IBRD / 87250 Post Open - National 11,076.92 10,540.62 Completed 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope 19) NHP-2018-2019-RJ-960823 / Water Resources Information Remote sensing based IBRD / 87250 Post Direct Selection Direct 12,815.38 0.00 Canceled 2018-08-01 2018-08-06 2018-09-10 2019-03-09 Systems products (2018-19) NHP-2018-2019-RJ-512724 / Procurement of high Water Resources Information IBRD / 87250 Post Direct Selection Direct 23,076.92 0.00 Canceled 2018-08-01 2018-08-06 2018-09-10 2019-03-09 resolution topographical data Systems products(2018-19) NHP-2018-2019-RJ-652591 / Water Resources Information IBRD / 87250 Post Direct Selection Direct 6,415.38 0.00 Canceled 2018-08-01 2018-08-06 2018-09-10 2019-03-09 Earth observation products Systems NHP-2018-2019-RJ-2700992- GO-SH-QU / LCD screen for Water Resources Monitoring Request for Single Stage - One conference /meeting room IBRD / 87250 Post Open - National 17,692.31 15,167.58 Completed 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope and training equipment/LCD projector and screen NHP-2018-2019-RJ-5372512 / Installation of network, Water Resources Monitoring Request for Single Stage - One cabling etc & communication IBRD / 87250 Post Open - National 6,923.08 6,906.34 Completed 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope services( Broadband, Leaseline, MPLS etc) NHP-2018-2019-RJ-551906 / Pending Water Resources Monitoring Request for Single Stage - One Procurement of video IBRD / 87250 Post Open - National 30,769.23 0.00 Implementati 2019-02-06 2019-04-03 2019-09-30 System Quotations Envelope conference facility on Pending NHP-2018-2019-RJ-362632 / Institutional Capacity Request for Single Stage - One IBRD / 87250 Post Open - National 23,076.92 0.00 Implementati 2019-02-12 2019-04-09 2019-10-06 SITC of Solar power(20KW) Enhancement Quotations Envelope on Under NHP-2018-2019-RJ-310415 / Institutional Capacity Request for Single Stage - One IBRD / 87250 Post Open - National 3,076.92 0.00 Implementati 2019-02-12 2019-04-09 2019-10-06 Fire fighting system Enhancement Quotations Envelope on NHP-2018-2019-RJ-909517 / Pending Institutional Capacity Request for Single Stage - One Establishment cost of SPMU IBRD / 87250 Post Open - National 45,307.69 0.00 Implementati 2018-08-04 2018-09-29 2019-03-28 Enhancement Quotations Envelope ( Furnishing/ Furniture) on NHP-2018-2019-RJ-638136 / Supply, installation, testing, Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 346,153.85 305,465.25 Signed 2019-03-02 2019-03-02 2019-04-08 2019-06-21 2019-07-26 2020-01-22 commissioning and System Envelope maintenance of ADCP NHP-2019-2020-RJ-507974 / Pending Water Resources Monitoring Single Stage - Two Water Quality Lab IBRD / 87250 Post Request for Bids Open - National 274,615.38 0.00 Implementati 2019-08-19 2019-08-24 2019-10-05 2019-12-18 2020-01-22 2020-07-20 System Envelope equipment on NHP-2019-2020-RJ-511282 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 4,615.38 4,100.55 Completed 2019-07-06 2019-08-31 2020-02-27 Manual SRG (2019-20) System Quotations Envelope NHP-2019-2020-RJ-862894 / Pending Water Resources Monitoring Request for Single Stage - One IT equipments including IBRD / 87250 Post Open - National 61,538.46 0.00 Implementati 2019-11-23 2020-01-18 2020-07-16 System Quotations Envelope software (2019-20) on NHP-2019-2020-RJ-641458 / Pending Water Resources Information Request for Single Stage - One Production of info materials IBRD / 87250 Post Open - National 21,538.46 0.00 Implementati 2019-12-14 2020-02-08 2020-08-06 Systems Quotations Envelope and brochures on Page 6 Pending NHP-2019-2020-RJ-756810 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 49,230.77 0.00 Implementati 2019-08-15 2019-10-10 2020-04-07 Differential GPS System Quotations Envelope on NHP-2019-2020-RJ-656410 / Pending Water Resources Monitoring Request for Single Stage - One Furniture/Furnishing of IBRD / 87250 Post Open - National 15,384.62 0.00 Implementati 2019-08-06 2019-10-01 2020-03-29 System Quotations Envelope Material testing lab on Pending NHP-2019-2020-RJ-580063 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,538.46 0.00 Implementati 2019-07-15 2019-09-09 2020-03-07 Antivirus System Quotations Envelope on NHP-2019-2020-RJ-522117 / Pending Water Resources Monitoring Request for Single Stage - One Procurement of DG set for IBRD / 87250 Post Open - National 15,384.62 0.00 Implementati 2019-08-15 2019-10-10 2020-04-07 System Quotations Envelope state data center on NHP-2019-2020-RJ-862234 / Pending Water Resources Monitoring Request for Single Stage - One Fire fighting system for IBRD / 87250 Post Open - National 15,384.62 0.00 Implementati 2019-08-15 2019-10-10 2020-04-07 System Quotations Envelope state data center on NHP-2019-2020-RJ-455351 / Pending Water Resources Monitoring Request for Single Stage - One Video conferencing facility IBRD / 87250 Post Open - National 92,307.69 0.00 Implementati 2019-08-15 2019-10-10 2020-04-07 System Quotations Envelope for State data center on NHP-2019-2020-RJ-308097 / Pending Surveillance and Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 30,769.23 0.00 Implementati 2019-08-15 2019-10-10 2020-04-07 communication system for System Quotations Envelope on State data center NHP-2019-2020-RJ-864659 / Pending Automatic water quality Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 233,846.15 0.00 Implementati 2019-09-01 2019-09-06 2019-10-18 2019-12-31 2020-02-04 2020-08-02 sensors-11 parameters System Envelope on (online) Pending NHP-2019-2020-RJ-232929 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 64,615.38 0.00 Implementati 2019-09-20 2019-11-15 2020-05-13 Furnishing of labs System Quotations Envelope on NHP-2019-2020-RJ-318896 / Pending Water Resources Monitoring Single Stage - One Furniture/Furnishing of State IBRD / 87250 Post Request for Bids Open - National 307,692.31 0.00 Implementati 2019-10-15 2019-10-20 2019-12-01 2019-12-31 2020-02-04 2020-08-02 System Envelope data center on NHP-2019-2020-RJ-398966 / Water Resources Monitoring Single Stage - Two Lab equipments for Material IBRD / 87250 Post Request for Bids Open - National 104,615.38 0.00 Canceled 2019-08-01 2019-08-06 2019-09-17 2019-11-30 2020-01-04 2020-07-02 System Envelope testing lab NHP-2018-2019-RJ-274571- Water Resources Monitoring Single Stage - Two IBRD / 87250 Prior Request for Bids Open - National 2,207,692.31 0.00 Canceled 2018-07-15 2018-07-20 2018-08-31 2018-11-13 2018-12-18 2019-06-16 GO-NCB-DE / Canal SCADA System Envelope NHP-2019-2020-RJ-815596 / Pending Water Resources Monitoring Request for Single Stage - One Atomic Absorption Spectro IBRD / 87250 Post Open - National 95,384.62 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 System Quotations Envelope photo meter on NHP-2019-2020-RJ-500506 / Pending Water Resources Monitoring Request for Single Stage - One UV Visible Spectro Photo IBRD / 87250 Post Open - National 41,538.46 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 System Quotations Envelope Meter on Pending NHP-2019-2020-RJ-766105 / Water Resources Information Request for Single Stage - One IBRD / 87250 Post Open - National 6,153.85 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Flame Photometer Systems Quotations Envelope on Pending NHP-2019-2020-RJ-701949 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 6,153.85 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Digital EC Meter System Quotations Envelope on Page 7 Pending NHP-2019-2020-RJ-833486 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 5,538.46 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Digital ph meter System Quotations Envelope on Pending NHP-2019-2020-RJ-497813 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 15,384.62 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Scientific Balance System Quotations Envelope on Pending NHP-2019-2020-RJ-292235 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 6,923.08 0.00 Implementati 2019-11-24 2020-01-19 2020-07-17 Distilled water plant System Quotations Envelope on Pending NHP-2019-2020-RJ-251634 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 1,846.15 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Vacum Cleaner System Quotations Envelope on Pending NHP-2019-2020-RJ-588887 / Water Resources Monitoring Request for Single Stage - One IBRD / 87250 Post Open - National 3,692.31 0.00 Implementati 2019-11-25 2020-01-20 2020-07-18 Refrigerator System Quotations Envelope on NHP-2019-2020-RJ- Water Resources Monitoring Request for Single Stage - One 268665__1 / Lab equipments IBRD / 87250 Post Open - National 84,615.38 0.00 Canceled 2019-12-15 2020-02-09 2020-08-07 System Quotations Envelope for material testing lab NHP-2018-2019-RJ-854780- Water Resources Monitoring Request for Single Stage - One GO-SH-QU / Computer for IBRD / 87250 Post Open - National 46,030.77 0.00 Canceled 2018-08-06 2018-10-01 2019-03-30 System Quotations Envelope data center( 2018-19) IN-RAJASTHAN -152742- Under Water Resources Monitoring Single Stage - Two GO-RFB / Lab equipments IBRD / 87250 Post Request for Bids Open - National 84,615.38 0.00 Implementati 2020-01-06 2020-01-11 2020-02-22 2020-05-06 2020-06-10 2020-12-07 System Envelope for material testing lab on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Pending NHP-2018-2019-RJ-566978 / Water Resources Monitoring Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 307,692.31 0.00 Implementati 2018-07-30 2018-08-04 2018-09-15 2018-11-28 2019-01-02 2019-07-01 River cross section surveys System Envelope on IN-RAJASTHAN -93225-NC- Water Resources Information Single Stage - Two RFQ / Development of basin/ IBRD / 87250 Post Request for Bids Open - National 15,384.62 0.00 Canceled 2019-02-07 2019-02-12 2019-03-26 2019-06-08 2019-07-13 2020-01-09 Systems Envelope sub basin/ state atlas NHP-2018-2019-RJ-793638-1 / Hiring of expert(Procurement cum Under Institutional Capacity Single Stage - Two contract management, GIS & IBRD / 87250 Post Request for Bids Open - National 769,230.77 0.00 Implementati 2019-02-28 2019-03-05 2019-04-16 2019-06-29 2019-08-03 2020-01-30 Enhancement Envelope Remote sensing, MIS &IT, on Hydromet Instrumentation) and Field staff(35 Nos.) NHP-2018-2019-RJ-474314 / Hiring of services for scanning and digitization of Water Resources Information Single Stage - Two IBRD / 87250 Post Request for Bids Open - National 438,461.54 270,712.58 Signed 2019-07-31 2019-08-05 2019-09-16 2019-11-29 2020-01-03 2020-07-01 historical data , maps and Systems Envelope Reports under National Hydrology Project NHP-2019-2020-RJ-389792 / Water Resources Information Single Stage - Two Digitization of command IBRD / 87250 Post Request for Bids Open - National 353,846.15 0.00 Canceled 2019-08-06 2019-08-11 2019-09-22 2019-12-05 2020-01-09 2020-07-07 Systems Envelope area maps Page 8 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2018-2019-RJ-601794- Consultant CS-QCBS-NAT / Water Resources Information Pending IBRD / 87250 Post Qualification Open - National 46,153.85 0.00 2018-07-30 2018-08-20 2018-10-03 2018-11-02 2018-12-07 2019-06-05 Development of mobile Systems Implementation Selection application NHP-2018-2019-RJ-796152- Consultant Water Resources Information CS-QCBS-NAT / Create on IBRD / 87250 Post Qualification Open - National 23,076.92 0.00 Canceled 2018-08-01 2018-08-22 2018-10-05 2018-11-04 2018-12-09 2019-06-07 Systems line e-library Selection NHP-2018-2019-RJ-444765- Water Resources Operations Quality And Cost- Pending CS-QCBS-NAT / River basin IBRD / 87250 Prior Open - National 1,230,769.23 0.00 2018-07-30 2018-08-20 2018-10-03 2018-10-31 2018-11-30 2019-01-04 2019-02-08 2020-02-08 and Planning System Based Selection Implementation management NHP-2018-2019-RJ-316692 / Consultant Water Resources Information Pending Consultancy services for IBRD / 87250 Post Qualification Open - National 8,538.46 0.00 2018-09-01 2018-09-22 2018-11-05 2018-12-05 2019-01-09 2019-07-08 Systems Implementation developing website Selection NHP-2018-2019-RJ-320952- CS-SSS-SSS / Establishment Water Resources Information Quality And Cost- Pending of state chapter WRIS IBRD / 87250 Post Open - National 192,307.69 0.00 2018-07-05 2018-07-26 2018-09-08 2018-10-06 2018-11-05 2018-12-10 2019-01-14 2020-01-14 Systems Based Selection Implementation including integration with India WRIS NHP-2018-2019-RJ-977784 / Water Resources Operations Quality And Cost- Pending Benchmarking of Irrigation IBRD / 87250 Post Open - National 1,038,461.54 0.00 2019-07-31 2019-08-21 2019-10-04 2019-11-01 2019-12-01 2020-01-05 2020-02-09 2021-02-08 and Planning System Based Selection Implementation projects NHP-2018-2019-RJ-760744 / Consultant Water Resources Monitoring Consultancy for design, IBRD / 87250 Post Qualification Open - National 15,384.62 0.00 Canceled 2018-08-16 2018-09-06 2018-10-20 2018-11-19 2018-12-24 2019-06-22 System architecture etc. Selection NHP-2018-2019-RJ-289949 / Study of water availability, Water Resources Operations Quality And Cost- Dynamic land use land cover IBRD / 87250 Post Open - National 76,923.08 0.00 Canceled 2018-07-30 2018-08-20 2018-10-03 2018-10-31 2018-11-30 2019-01-04 2019-02-08 2020-02-08 and Planning System Based Selection pattern and water quality for Bisalpur project INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NHP-2018-2019-RJ-374579 / Individual Institutional Capacity Pending Architecture Consultancy for IBRD / 87250 Post Consultant Open 15,384.62 0.00 2018-07-09 2018-08-27 2018-09-17 2018-10-22 2019-04-20 Enhancement Implementation IMTI Selection NHP-2018-2019-RJ-793638 / Individual Institutional Capacity Hiring of technical expert( IBRD / 87250 Post Consultant Open 61,538.46 0.00 Canceled 2018-08-07 2018-09-25 2018-10-16 2018-11-20 2019-05-19 Enhancement RS&GIS) Selection NHP-2018-2019-RJ-961781 / Individual Institutional Capacity Hiring of technical expert( IBRD / 87250 Post Consultant Open 61,538.46 0.00 Canceled 2018-08-07 2018-09-25 2018-10-16 2018-11-20 2019-05-19 Enhancement IT) Selection NHP-2018-2019-RJ-778831 / Individual Institutional Capacity Hiring of technical expert( IBRD / 87250 Post Consultant Open 30,769.23 0.00 Canceled 2018-08-07 2018-09-25 2018-10-16 2018-11-20 2019-05-19 Enhancement Procurement) Selection Page 9 NHP-2018-2019-RJ-326985 / Individual Institutional Capacity Hiring of technical expert( IBRD / 87250 Post Consultant Open 61,538.46 0.00 Canceled 2018-08-07 2018-09-25 2018-10-16 2018-11-20 2019-05-19 Enhancement water quality) Selection NHP-2019-2020-RJ-644876 / Development of decision tool for efficient utilization of Water Resources Operations Pending water resources in parwati IBRD / 87250 Post Direct Selection Direct 76,923.08 0.00 2019-04-22 2019-05-02 2019-07-06 2020-01-02 and Planning System Implementation canal & Dholpur piped irrigation project of Rajasthan NHP-2019-2020-RJ-241122 / Development of Mobile Individual Water Resources Information Pending application for collection and IBRD / 87250 Post Consultant Open 15,384.62 0.00 2019-08-12 2019-09-30 2019-10-21 2019-11-25 2020-05-23 Systems Implementation dissemination of Selection HydroMeteorological data NHP-2019-2020-RJ-394583 / Individual Development of Mobile Water Resources Information Pending IBRD / 87250 Post Consultant Open 15,384.62 0.00 2019-09-10 2019-10-29 2019-11-19 2019-12-24 2020-06-21 application for Project Systems Implementation Selection monitoring NHP-2019-2020-RJ-565859 / Individual Consultancy for design, Water Resources Monitoring Pending IBRD / 87250 Post Consultant Open 3,076.92 0.00 2019-09-20 2019-11-08 2019-11-29 2020-01-03 2020-07-01 architecture for Ground System Implementation Selection Water Department IN-RAJASTHAN -152745-CS- INDV / Preparation of Individual Water Resources Monitoring Pending estimation for motorization IBRD / 87250 Post Consultant Open 1,538.46 0.00 2020-01-10 2020-02-28 2020-03-20 2020-04-24 2020-10-21 System Implementation and electrification of gates of Selection Bhakra & Gang Canal Page 10