Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: February 24, 2017 2. Date of General Procurement Notice: To Be Published 3. Period covered by this procurement plan: August 2017 to February 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (>=US million) Works (including turnkey, supply and 5 installation of plant and equipment, and Public Private Partnership (PPP) Goods, information technology and non- 1.5 consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual Issued by the Ministry of Water, Irrigation and Electricity, August 2017. 5. Any Other Special Procurement Arrangements: Not Applicable. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domestic Review Com No. Cost Preference by Bank ments US$ million (yes/no) (Prior / Post) July 9, 2010 1 Summary of 32 2 To be Prior the ICB Determined (Works) 2 Summary of 10.2 6 To be Prior the ICB Determined (Goods) 3 Summary of 19.4 5 No Post the NCB (Works) 4 Summary of 0.28 1 No Post the NCB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: 2. Type of Procurement Prior Review Threshold (>=US million) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Estimated Packages Review Comments No. Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 3.5 3 Prior number of contracts that will be let under QCBS 2 Summary of 11.8 14 Post number of contracts that will be let under QCBS 3 Summary of 10.1 31 Post CQS/IC number of contracts July 9, 2010 that will be let under other methods July 9, 2010 PROCUREMENT Ethiopia : Second Ethiopia Urban Water Supply and Sanitation Project PLAN General Information Country: Ethiopia Banks Approval Date of the Original Procurement Plan: 2018-01-15 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-07-11 Project ID: P156433 GPN Date: 2018-02-02 Project Name: Second Ethiopia Urban Water Supply and Sanitation Project Loan / Credit No: IDA / 60070, IDA / 60080 Executing Agency(ies): Addis Ababa Water and Sanitation Development and Rehabilitation Project Office, Ministry of Water Irrigation and Electricity, WSS Program Management Unit WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAWSA-43105-CW-DIR / Component 1: Sanitation and Procurement of kality sanitary IDA / 60070 water supply services Prior Direct Selection Direct 24,528,903.54 0.00 Under Review 2018-03-01 2018-03-06 2018-05-01 2019-05-01 sewer trunk mains for remaining improvements in Addis Ababa work ET-AAWSA-42142-CW-RFB / Procurement of specialized Component 1: Sanitation and contractor or operator on Single Stage - One Under IDA / 60070 water supply services Prior Request for Bids Open - International 11,000,000.00 0.00 2018-05-11 2018-05-25 2018-07-09 2018-08-08 2018-09-12 2023-07-07 operation and maintenance of 12 Envelope Implementation improvements in Addis Ababa MBR decentralized wastewater treatment plants # lot 2 ET-AAWSA-42871-CW-RFB / Procurement of specialized contractor or operator on Component 1: Sanitation and Single Stage - One Under operation and maintenance of IDA / 60070 water supply services Prior Request for Bids Open - International 14,000,000.00 0.00 2018-05-18 2018-06-01 2018-07-13 2018-08-12 2018-09-16 2023-07-07 Envelope Implementation koye feche (3 sites) and chefe improvements in Addis Ababa phase one and two wastewater treatment # lot 3 ET-AAWSA-45501-CW-DIR / Procurement of Kality Component 1: Sanitation and Under wastewater treatment plant IDA / 60070 water supply services Prior Direct Selection Direct 10,336,166.03 0.00 2018-02-28 2018-03-14 2018-04-25 2019-04-25 Implementation rehabilitation and expansion for improvements in Addis Ababa remaining works ET-AAWSA-57113-CW-RFB / Procurement of Data center facilities construction ,supply Component 1: Sanitation and Single Stage - One Pending and installation of hardware IDA / 60070 water supply services Post Request for Bids Open - International 279,050.00 0.00 2018-05-30 2018-06-04 2018-07-16 2018-08-15 2018-09-19 2019-08-30 Envelope Implementation equipment and software for improvements in Addis Ababa disaster recovery (DRS) for AAWSA main data center ET-AAWSA-42850-CW-RFB / Procurement of specialized contractor or operator for Component 1: Sanitation and Under operation and maintenance of IDA / 60070 water supply services Prior Direct Selection Direct 6,000,000.00 0.00 2018-04-15 2018-04-29 2018-06-14 2018-05-30 2020-05-30 Implementation kality 100,000 m^3/day improvements in Addis Ababa wastewater treatment plants # lot 1 ET-AAWSA-42875-CW-RFB / NRW management through performance based contract(PBC). (Assessment of Component 1: Sanitation and existing water supply network Single Stage - Two Pending IDA / 60070 water supply services Prior Request for Bids Open - International 18,700,979.00 0.00 2018-05-15 2018-05-20 2018-07-01 2018-10-20 2018-11-24 2022-12-30 and verification of NRW base Envelope Implementation improvements in Addis Ababa line, DMA zone establishment, identification ,supply and installation of pipes fittings and water meters (replacement) ET-AAWSA-42884-CW-RFB / Procurement of Construction of Component 1: Sanitation and 20 communal latrines and Single Stage - One Pending IDA / 60070 water supply services Post Request for Bids Open - National 1,000,000.00 0.00 2018-09-20 2018-09-25 2018-11-06 2018-12-06 2019-01-10 2020-01-10 Construction of5 Public latrines Envelope Implementation improvements in Addis Ababa in low income and commercial area of the city Addis Ababa GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-MOWIE-43004-GO-DIR / Supply of pipes and fittings for Component 2: Sanitation and Under the remaining work of Dire Dewa IDA / 60070 water supply services Prior Direct Selection Direct 1,897,466.00 0.00 2018-01-12 2018-01-17 2018-02-24 2018-05-25 Implementation City Water Supply and Sanitation improvement in secondary cities Project ET-MOWIE-43329-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-17 2018-06-16 Quotations Envelope Implementation and lap top computers) for strengthening Gambella City Water Supply and Sewerage Service ET-MOWIE-43286-GO-RFQ / procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-22 2018-05-03 2018-06-02 Quotations Envelope Implementation and lap top computers)for strengthening Deghabur Town Water Supply and Sewerage Service ET-MOWIE-43289-GO-RFQ / procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-22 2018-05-03 2018-06-02 Quotations Envelope Implementation and lap top computers) for strengthening Arbaminch Town Water Supply and Sewerage Service Page 1 ET-MOWIE-43291-GO-RFQ / procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-22 2018-05-03 2018-06-02 Quotations Envelope Implementation and lap top computers) for Harar strengthening Town Water Supply and Sewerage Service ET-MOWIE-43294-GO-RFQ / procurement of office equipment(printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One Pending IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope Implementation strengthening computers) for Bishoftu Town Water Supply and Sewerage Service ET-MOWIE-43297-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-17 2018-06-16 Quotations Envelope Implementation and lap top computers) for strengthening Shashemane City Water Supply and Sewerage Service ET-MOWIE-43299-GO-RFQ / procurement of office equipment(printers, desk top Component 3: Project Request for Single Stage - One Pending computers, scanners, photo IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-17 2018-06-16 Quotations Envelope Implementation copy machines and lap top strengthening computers) for Jigjiga City Water Supply and Sewerage Service ET-MOWIE-43300-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for strengthening Hawassa City Water Supply and Sewerage Service ET-MOWIE-43035-GO-RFQ / Procurement of IT equipment Component 3: Project (printers, desk top computers, Request for Single Stage - One Pending IDA / 60070 management & institutional Post Limited 50,000.00 0.00 2018-04-14 2018-06-09 2018-07-09 scanners, photo copy machines Quotations Envelope Implementation strengthening and lap top computers) for Ministry PIU ET-MOWIE-43317-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-17 2018-06-16 Quotations Envelope Implementation and lap top computers) for strengthening Assosa City Water Supply and Sewerage Service ET-MOWIE-43319-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for Asella strengthening City Water Supply and Sewerage Service ET-MOWIE-43322-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for Sodo strengthening City Water Supply and Sewerage Service ET-MOWIE-43324-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for Debre strengthening Berhan City Water Supply and Sewerage Service ET-MOWIE-43326-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for strengthening Dessie City Water Supply and Sewerage Service ET-MOWIE-43328-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for strengthening Gonder City Water Supply and Sewerage Service ET-MOWIE-43331-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for strengthening Nekmte City Water Supply and Sewerage Service ET-MOWIE-43333-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for Jimma strengthening City Water Supply and Sewerage Service Page 2 ET-MOWIE-43303-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for strengthening Adama City Water Supply and Sewerage Service ET-MOWIE-43304-GO-RFQ / Procurement of office equipment (printers, desk top computers, Component 3: Project Request for Single Stage - One Pending scanners, photo copy machines IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation and lap top computers) for strengthening Mekelle City Water Supply and Sewerage Service ET-MOWIE-43307-GO-RFQ / Procurement of office equipment(printers, desk top Component 3: Project computers, scanners, photo Request for Single Stage - One Pending IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 copy machines and lap top Quotations Envelope Implementation strengthening computers) for Bahir Dar City Water Supply and Sewerage Service ET-MOWIE-43310-GO-RFQ / Procurement of office equipment for Dire Dawa City Water Supply Component 3: Project Request for Single Stage - One Pending and Sewerage Service(Printers, IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation desk top computers, scanners, strengthening photo copy machines and lap top computers) ET-MOWIE-43311-GO-RFQ / Procurement of office equipment for Semera City Water Supply Component 3: Project Request for Single Stage - One Pending and Sewerage Service(Printers, IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation desk top computers, scanners, strengthening photo copy machines and lap top computers) ET-MOWIE-43313-GO-RFQ / Procurement of office equipment for Adegrat City Water Supply Component 3: Project Request for Single Stage - One Pending and Sewerage Service (printers, IDA / 60070 management & institutional Post Limited 10,000.00 0.00 2018-03-29 2018-05-10 2018-06-09 Quotations Envelope Implementation desk top computers, scanners, strengthening photo copy machines and lap top computers) ET-MOWIE-50407-GO-DIR / Procurement of Bulk Flow meter Component 2: Sanitation and Under for Mekelle Town Water Supply IDA / 60070 water supply services Prior Direct Selection Direct 433,013.00 0.00 2018-02-28 2018-04-05 2018-03-05 2018-04-06 2018-07-05 Implementation and Sewerage Service by improvement in secondary cities Mekelle town WSSS ET-AAWSA-43126-GO-RFB / Procurement of GPS, surveying Component 3: Project Single Stage - One Pending equipment, laptop , computers, IDA / 60070 management & institutional Post Request for Bids Open - National 200,000.00 0.00 2018-09-03 2018-09-08 2018-10-20 2018-11-19 2018-12-24 2019-12-24 Envelope Implementation printers and copy machines and strengthening office furniture's. ET-AAWSA-42879-GO-RFB / Component 1: Sanitation and Procurement of 90 Vacuum Single Stage - One Under IDA / 60070 water supply services Prior Request for Bids Open - International 10,227,272.73 0.00 2018-06-08 2018-06-22 2018-08-06 2018-09-20 2018-11-01 2019-11-01 Trucks and 22 Double Cabin Envelope Implementation improvements in Addis Ababa Pick Up Vehicles. ET-MOWIE-55837-GO-RFB / Component 2: Sanitation and Single Stage - One Pending Procurement of Automatic Water IDA / 60070 water supply services Post Request for Bids Open - National 250,000.00 0.00 2018-06-20 2018-06-25 2018-07-25 2018-08-24 2018-09-28 2018-12-27 Envelope Implementation Meter Test Bench improvement in secondary cities ET-MOWIE-43018-GO-RFB / Procurement of 44 vehicles(double Cabins) for Component 3: Project secondary city utilities, Regional Pending IDA / 60070 management & institutional Prior Direct Selection Direct 1,800,000.00 0.00 2018-06-20 2018-06-25 2018-07-30 2018-11-27 Water Bureaus and 2 Vehicles( Implementation strengthening double Cabins) for Ministry PIU by the Ministry of Water Irrigation and Electricity through UNOPS NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UWSSP- II/AAWSA/CON/01/2017 / Component 1: Sanitation and feasibilty study ,deatil design and Quality And Cost- Under IDA / 60070 water supply services Prior Open - International 4,656,175.00 0.00 2017-08-18 2017-08-18 2017-08-31 2018-06-29 2017-10-16 2017-11-15 2018-01-15 2018-02-19 2023-02-09 construction supervision for Based Selection Implementation improvements in Addis Ababa eastern addis Ababa waste water treatment plant ET-AAWSA-42833-CS-QCBS / Supervision Consultancy service for operation and maintenance of existing waste water treatment Component 1: Sanitation and Quality And Cost- Under plants (chefe, koye fache, kaliti IDA / 60070 water supply services Prior Open - International 5,000,000.00 0.00 2018-02-28 2018-05-23 2018-03-21 2018-05-04 2018-06-15 2018-07-15 2018-08-19 2018-09-23 2023-09-22 Based Selection Implementation and decenteralized package improvements in Addis Ababa waste water treatment plants) found in different location of addis city. Page 3 ET-AAWSA-42834-CS-QCBS / Consultancy service for ESIA of Component 1: Sanitation and Quality And Cost- Pending Eastern Catchment Waster IDA / 60070 water supply services Prior Open - International 1,000,000.00 0.00 2019-01-05 2019-01-26 2019-03-11 2019-04-08 2019-05-08 2019-06-12 2019-07-17 2020-07-16 Based Selection Implementation Water Treatment plant and improvements in Addis Ababa Swere line ET-AAWSA-42881-CS-CQS / Consultancy service for updating of AAWSA Business Plan and Component 1: Sanitation and Consultant Pending Hiring of individual consultant for IDA / 60070 water supply services Post Qualification Open - National 100,000.00 0.00 2019-02-28 2019-03-21 2019-05-04 2019-06-03 2019-07-08 2020-07-07 Implementation support in the preparation of improvements in Addis Ababa Selection branch level AAWSA Business Plan ET-MOWIE-43218-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and Quality And Cost- Pending Town Sanitation plan for Dire IDA / 60070 water supply services Post Open - National 200,000.00 0.00 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-08 2018-11-19 2019-08-16 Based Selection Implementation Dewa town by Dire Dawa Town improvement in secondary cities water supply and sewerage service ET-MOWIE-43227-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated Quality And Cost- Pending IDA / 60070 water supply services Post Open - National 200,000.00 0.00 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-08 2018-11-19 2019-08-16 Town Sanitation plan for Mekelle Based Selection Implementation improvement in secondary cities town by Mekelle Town water supply and sewerage service ET-MOWIE-43231-CS-QCBS / Consultancy service for Component 2: Sanitation and Development of an integrated Quality And Cost- Pending IDA / 60070 water supply services Post Open - National 200,000.00 0.00 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-01 2018-11-12 2019-08-09 Town Sanitation plan for Adama Based Selection Implementation improvement in secondary cities town by Adama Town water supply and sewerage service ET-MOWIE-43234-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and Quality And Cost- Pending Town Sanitation plan for IDA / 60070 water supply services Post Open - National 200,000.00 0.00 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-01 2018-11-12 2019-08-09 Based Selection Implementation Hawassa town by Hawassa Town improvement in secondary cities water supply and sewerage service ET-AAWSA-43920-CS-QBS / procurement of Consultancy Service on the Assessment on Component 1: Sanitation and the Quality Based Pending IDA / 60070 water supply services Post Open - National 200,000.00 0.00 2018-09-17 2018-10-08 2018-11-21 2018-12-19 2019-01-18 2019-02-17 2019-03-24 2020-03-23 Impacts of Industrial Waste Selection Implementation improvements in Addis Ababa Water discharge on municipal wastewater treatment plants and associated structures ET-MOWIE-43222-CS-QCBS / Consultancy service for Development of an integrated Component 2: Sanitation and Quality And Cost- Pending City Wide Sanitation plan for IDA / 60070 water supply services Post Open - National 200,000.00 0.00 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-08-28 2018-10-09 2018-11-20 2019-08-17 Based Selection Implementation Bahir Dar town by Bahir Dar improvement in secondary cities Town water supply and sewerage service ET-MOWIE-43244-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Pending Feasibility Study and Detail IDA / 60070 water supply services Post Open - National 250,000.00 0.00 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Implementation Design of Waste Water improvement in secondary cities Management System for Harari town by Harari Town water supply and sewerage service ET-AAWSA-42137-CS-QCBS / A Comprehensive Groundwater Component 2: Sanitation and Sustainable Management Quality And Cost- Under IDA / 60070 water supply services Prior Open - International 6,456,740.00 0.00 2018-02-28 2018-05-28 2018-03-21 2018-05-19 2018-07-03 2018-08-17 2018-10-06 2018-11-10 2020-11-09 System establishment , water Based Selection Implementation improvement in secondary cities extraction management and ground water modeling ET-AAWSA-42832-CS-QCBS / Consultancy service for Component 1: Sanitation and Development of an integrated Quality And Cost- Under IDA / 60070 water supply services Prior Open - International 6,000,000.00 0.00 2018-02-28 2018-06-27 2018-03-21 2018-06-19 2018-08-03 2018-09-17 2018-11-22 2019-01-05 2020-06-28 Town Sanitation plan and city Based Selection Implementation improvements in Addis Ababa sewerage master plan and feasibility study ET-MOWIE-50559-CS-QCBS / Consultancy Service for Establishment of Urban Water Component 2: Sanitation and Quality And Cost- Pending Supply and Waste Water IDA / 60070 water supply services Post Open - National 200,000.00 0.00 2018-06-20 2018-07-20 2018-09-02 2018-09-30 2018-10-30 2018-12-04 2019-01-08 2020-01-08 Based Selection Implementation Management Service Regulation improvement in secondary cities in Ethiopia by Ministry of Water Irrigation and Electricity ET-MOWIE-43193-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- Pending IDA / 60070 water supply services Prior Open - International 600,000.00 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-09-26 Design of Waste Water Based Selection Implementation improvement in secondary cities Management System for Jimma and Nekemte Towns by Oromia Water Mineral and Energy Bureau ET-MOWIE-43212-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and Quality And Cost- IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Feasibility Study and Detail Based Selection improvement in secondary cities Design for Asella Town WSSS by Asella Town water supply and sewerage service Page 4 ET-MOWIE-43209-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and Quality And Cost- Pending City Wide Sanitation plan and IDA / 60070 water supply services Post Open - National 500,000.00 0.00 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-08 2018-11-19 2019-08-16 Based Selection Implementation Feasibility Study and Detail improvement in secondary cities Design for Sodo and Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-43208-CS-QCBS / Consultancy Service for Development of an Integrated Component 2: Sanitation and City Wide Sanitation plan and Quality And Cost- IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-03-20 2018-04-10 2018-05-31 2018-06-28 2018-08-27 2018-10-01 2018-11-12 2019-08-09 Feasibility Study and Detail Based Selection improvement in secondary cities Design for Sodo Town WSSS by Sodo Town water supply and sewerage service ET-MOWIE-43214-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Pending Feasibility Study and Detail IDA / 60070 water supply services Post Open - National 250,000.00 0.00 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Implementation Design of Waste Water improvement in secondary cities Management System for Adegrat town by Tigray Region Water Bureau ET-MOWIE-43206-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Feasibility Study and Detail IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Design of Waste Water improvement in secondary cities Management System for Dessie town by Dessie Town water supply and sewerage service ET-MOWIE-43200-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Design of Waste Water Based Selection improvement in secondary cities Management System for Gambella town by Gambella Town water supply and sewerage service ET-MOWIE-43198-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-06-24 2018-07-22 2018-09-20 2018-11-01 2018-12-13 2019-09-09 Design of Waste Water Based Selection improvement in secondary cities Management System for Nekemet town by Nekemet Town water supply and sewerage service ET-MOWIE-43237-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Feasibility Study and Detail IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Design of Waste Water improvement in secondary cities Management System for Jigjiga town by Jigijiga Town water supply and sewerage service ET-MOWIE-43239-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Design of Waste Water Based Selection improvement in secondary cities Management System for Shashemene town by Shashemene Town water supply and sewerage service ET-MOWIE-43216-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Feasibility Study and Detail IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Design of Waste Water improvement in secondary cities Management System for Semera town by Semera Town water supply and sewerage service ET-MOWIE-43241-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Feasibility Study and Detail IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Design of Waste Water improvement in secondary cities Management System for Bishoftu town by Bishoftu Town water supply and sewerage service ET-MOWIE-43059-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Design of Waste Water Based Selection improvement in secondary cities Management System for Deghabur town by Deghabur Town water supply and sewerage service Page 5 ET-MOWIE-43248-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Design of Waste Water Based Selection improvement in secondary cities Management System for Arbaminch town by Arbaminch Town water supply and sewerage service ET-MOWIE-43203-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Feasibility Study and Detail IDA / 60070 water supply services Post Open - National 250,000.00 0.00 Canceled 2018-04-20 2018-05-11 2018-07-01 2018-07-29 2018-09-27 2018-11-08 2018-12-20 2019-09-16 Based Selection Design of Waste Water improvement in secondary cities Management System for Gonder town by Gonder Town water supply and sewerage service ET-MOWIE-65731-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- Pending IDA / 60080 water supply services Prior Open - International 900,000.00 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-09-26 Design of Waste Water Based Selection Implementation improvement in secondary cities Management System for Gambella, Semera and Asosa Towns by Ministry of Water Irrigation and Electricity ET-MOWIE-65735-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- Pending IDA / 60080 water supply services Prior Open - International 900,000.00 0.00 2018-06-28 2018-07-19 2018-09-01 2018-09-29 2018-10-29 2018-12-03 2019-01-07 2019-10-04 Design of Waste Water Based Selection Implementation improvement in secondary cities Management System for Asella, Shashemene and Bishoftu towns by Oromia Water, Mineral and Energy Bureau ET-MOWIE-65737-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Pending Feasibility Study and Detail IDA / 60080 water supply services Prior Open - International 900,000.00 0.00 2018-06-28 2018-07-19 2018-09-01 2018-09-29 2018-10-29 2018-12-03 2019-01-07 2019-10-04 Based Selection Implementation Design of Waste Water improvement in secondary cities Management System for Gonder, Dessie and Debreberhan towns by Amehara Water Bureau ET-MOWIE-65751-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Quality And Cost- Pending Feasibility Study and Detail IDA / 60080 water supply services Prior Open - International 600,000.00 0.00 2018-06-20 2018-07-11 2018-08-24 2018-09-21 2018-10-21 2018-11-25 2018-12-30 2019-09-26 Based Selection Implementation Design of Waste Water improvement in secondary cities Management System for Sodo and Arbaminch Towns by SNNPR Water Bureau ET-MOWIE-65753-CS-QCBS / Consultancy service for Development of an integrated City Wide Sanitation plan and Component 2: Sanitation and Feasibility Study and Detail Quality And Cost- Pending IDA / 60080 water supply services Prior Open - International 600,000.00 0.00 2018-06-26 2018-07-17 2018-08-30 2018-09-27 2018-10-27 2018-12-01 2019-01-05 2019-10-02 Design of Waste Water Based Selection Implementation improvement in secondary cities Management System for Jijiga and Deghabur Towns by Somali Region Water Resource Development Bureau INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-AAWSA-45503-CS-CDS / Procurement of supervision Component 1: Sanitation and consultancy service Kaliti Under IDA / 60070 water supply services Prior Direct Selection Direct 1,180,528.92 0.00 2018-03-01 2018-03-29 2018-05-10 2019-05-08 sanitary sewer trunk mains & Implementation improvements in Addis Ababa treatment plant rehabilitation and expansion for remaining work ET-AAWSA-46275-CS-CDS / Individual consultancy service for Component 2: Sanitation and groundwater flow and solute Pending IDA / 60070 water supply services Post Direct Selection Direct 18,000.00 0.00 2018-02-28 2018-03-10 2018-05-14 2018-11-10 transport modeling of addis Implementation improvement in secondary cities ababa area and its suburbs for the remaining works ET-AAWSA-47575-CS-INDV / Component 3: Project Procurement of individual Individual Consultant Under IDA / 60070 management & institutional Prior Open 200,000.00 0.00 2018-03-30 2018-05-18 2018-06-08 2018-07-13 2023-07-07 procurement specialist Selection Implementation strengthening consultant ET-AAWSA-47564-CS-INDV / Component 3: Project Individual Consultant Pending Procurement of individual law IDA / 60070 management & institutional Prior Open 200,000.00 0.00 2018-04-11 2018-05-30 2018-06-20 2018-07-25 2023-07-07 Selection Implementation specialist consultant strengthening ET-MOWIE-55842-CS-INDV / Selection and Employment of Component 3: Project Individual Consultant Pending Procurement Specialist for IDA / 60070 management & institutional Post Open 54,000.00 0.00 2018-06-18 2018-07-22 2018-08-12 2018-09-16 2024-08-15 Selection Implementation Mekelle Town Water Utility by strengthening Mekelle Town Utility ET-MOWIE-63893-CS-INDV / Selection and Employment of Component 3: Project Financial specialist for Adama Individual Consultant Pending IDA / 60080 management & institutional Post Open 5,185.00 0.00 2018-06-14 2018-07-13 2018-07-27 2018-08-31 2019-08-26 Town Waste Water Selection Implementation strengthening Management project by Adama Town Utility office. Page 6