PROCUREMENT PLAN (Textual Part) Project information: Central African Backbone SOP5 (P132821) Project Implementation agency: SOCOF Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January 2018 – December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Africa : AFCC2/RI-Central African Backbone SOP5 PLAN General Information Country: Africa Banks Approval Date of the Original Procurement Plan: 2018-02-10 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-07-24 Project ID: P132821 GPN Date: Project Name: AFCC2/RI-Central African Backbone SOP5 Loan / Credit No: IDA / H9810 Executing Agency(ies): Centrale Central African Backbone WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component B - Construction, CAB5-REF-13 / Réhabilitation Management and du Siège de la SOCOF SA Request for Single Stage - One IDA / H9810 Commercialization of the CAB5 Post Limited 500,000.00 0.00 Canceled 2018-09-27 2018-11-22 2019-02-20 (bâtiment affecté par le Quotations Envelope Infrastructure through a PPP Gouvernement) Scheme CAB5-REF-14 / Travaux et Component B - Construction, Fournitures relatifs à la Management and construction de la FO-Axe Single Stage - One IDA / H9810 Commercialization of the CAB5 Prior Request for Bids Open - International 50,000,000.00 0.00 Under Review 2018-03-15 2018-03-20 2018-06-18 2018-07-18 2018-08-22 2019-08-22 LUBUMBASHI-TENKE-DILOLO Envelope Infrastructure through a PPP et TENKE-KABALO-KALEMIE- Scheme GOMA (Cluster Sud et Est) Component B - Construction, CAB5-REF-15 / Travaux de Management and Single Stage - One construction-Carrier Hôtel Cluster IDA / H9810 Commercialization of the CAB5 Post Request for Bids Open - International 1,200,000.00 0.00 Canceled 2018-05-22 2018-05-27 2018-07-26 2018-08-25 2018-09-29 2019-03-28 Envelope 1 à Kinshasa Infrastructure through a PPP Scheme Component B - Construction, CAB5-REF-16 / Aménagement Management and Request for Single Stage - One des bureaux de la SOCOF SA IDA / H9810 Commercialization of the CAB5 Post Limited 20,000.00 0.00 Canceled 2018-01-27 2018-03-24 2018-04-23 Quotations Envelope (cloisonnement) Infrastructure through a PPP Scheme CAB5-REF-12 / Travaux et fournitures relatifs à la Component A - Emergence of an Pending réahabilitation de la FO de la IDA / H9810 Post Direct Selection Direct 600,000.00 0.00 2018-08-15 2018-08-20 2018-10-24 2019-05-22 Inclusive Digital Economy Implementation SCPT-Axe Muanda-Kinshasa (avec HUAWEI) CAB5-REF-11 / Travaux de Component A - Emergence of an Single Stage - One Pending construction du Centre de IDA / H9810 Post Request for Bids Open - National 3,000,000.00 0.00 2018-07-30 2018-08-04 2018-09-15 2018-10-15 2018-11-19 2019-05-18 Inclusive Digital Economy Envelope Implementation traitement D3E GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAB5-REF-1 / Fournitures des é uipements et installations de q Component A - Emergence of an Single Stage - One Pending l'intranet du IDA / H9810 Prior Request for Bids Open - International 3,250,000.00 0.00 2018-08-05 2018-08-10 2018-10-09 2018-11-08 2018-12-13 2019-04-12 Inclusive Digital Economy Envelope Implementation Gouvernement+Formation des utlisateurs Component B - Construction, Management and CAB5-REF-2 / Mobilier de Request for Single Stage - One Pending IDA / H9810 Commercialization of the CAB5 Post Limited 2,000.00 0.00 2018-02-27 2018-04-24 2018-05-24 bureau pour nouveau personnel Quotations Envelope Implementation Infrastructure through a PPP Scheme Component B - Construction, CAB5-REF-3 / Acquisitions des Management and Request for Single Stage - One tablettes et logiciels IDA / H9810 Commercialization of the CAB5 Post Limited 53,000.00 0.00 Canceled 2018-04-20 2018-06-15 2018-07-30 Quotations Envelope informatiques Infrastructure through a PPP Scheme Component B - Construction, Management and CAB5-REF-4 / Fournitures de Request for Single Stage - One IDA / H9810 Commercialization of the CAB5 Post Limited 10,000.00 4,527.55 Completed 2018-01-27 2018-03-28 2018-03-24 2018-05-03 2018-04-23 2018-05-08 bureau SOCOF 2018 Quotations Envelope Infrastructure through a PPP Scheme Component B - Construction, CAB5-REF-7 / Acquisition d'un Management and Request for Single Stage - One véhicule tout terrain pour le suivi IDA / H9810 Commercialization of the CAB5 Post Limited 42,000.00 0.00 Canceled 2018-02-17 2018-04-14 2018-05-29 Quotations Envelope des travaux Infrastructure through a PPP Scheme Component B - Construction, CAB5-REF-8 / Acquisition du Management and Request for Single Stage - One Under matériel audio visuel pour la IDA / H9810 Commercialization of the CAB5 Post Limited 12,000.00 0.00 2018-01-27 2018-02-16 2018-03-24 2018-04-23 Quotations Envelope Implementation SOCOF SA Infrastructure through a PPP Scheme CAB5-REF-9 / Acquisition et Component C - Enabling é uipements de installation des q Single Stage - One Pending IDA / H9810 Environment and Regulatory Prior Request for Bids Open - International 1,500,000.00 0.00 2018-06-06 2018-06-11 2018-07-23 2018-08-22 2018-09-26 2019-03-25 cybersécurité et intégrité des Envelope Implementation Effectiveness réseaux CAB5-REF-10 / Acquisition du matériel informatique, du matériel Component C - Enabling Single Stage - One Under audio visuel et des logiciels pour IDA / H9810 Environment and Regulatory Post Request for Bids Open - National 500,000.00 0.00 2018-01-22 2018-04-05 2018-01-27 2018-04-10 2018-03-13 2018-04-12 2018-05-17 2018-07-16 Envelope Implementation le nouveau système d'information Effectiveness de l'ARPTC Page 1 Component B - Construction, CAB5-REF-42 / Acquisition du Management and matériel audiovisuel ( 2 Appareils Request for Single Stage - One Pending IDA / H9810 Commercialization of the CAB5 Post Limited 2,960.00 0.00 2018-02-27 2018-04-24 2018-10-21 photo et 1 vidéo retrojecteur) en Quotations Envelope Implementation Infrastructure through a PPP faveur de la SOCOF SA Scheme NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component B - Construction, CAB5-REF-5 / Sélection d'une Management and société de maintenance des Request for Single Stage - One IDA / H9810 Commercialization of the CAB5 Post Limited 10,000.00 0.00 Canceled 2018-03-27 2018-05-22 2019-05-22 é uipements informatiques et q Quotations Envelope Infrastructure through a PPP bureautiques Scheme Component B - Construction, CAB5-REF-41 / Connexion Management and Request for Single Stage - One internet des bureaux de la IDA / H9810 Commercialization of the CAB5 Post Limited 54,000.00 18,685.66 Signed 2018-02-03 2018-02-15 2018-03-27 2018-03-06 2019-03-27 Quotations Envelope SOCOF Infrastructure through a PPP Scheme CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Estimated Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion Amount (US$) (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAB5-REF-17 / Assistance technique-conception de l'intranet Component A - Emergence of an Quality And Cost- IDA / H9810 Prior Open - International 500,000.00 268,805.67 Signed 2017-01-15 2018-02-19 2017-02-05 2017-03-21 2018-04-24 2017-04-18 2018-02-23 2017-05-18 2018-04-25 2017-06-22 2018-05-11 2017-07-27 2018-06-09 2018-07-27 du Gouvernement y compris Inclusive Digital Economy Based Selection supervision Consultant CAB5-REF-18 / Etudes EIES du Component A - Emergence of an Pending IDA / H9810 Post Qualification Open - International 100,000.00 0.00 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-07-24 Centre D3E Inclusive Digital Economy Implementation Selection CAB5-REF-19 / Formation des Consultant cadres du MINIPTNTIC en Component A - Emergence of an Under IDA / H9810 Post Qualification Open - International 50,000.00 0.00 2018-03-15 2017-10-23 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2018-09-21 recyclage des déchets Inclusive Digital Economy Implementation Selection é ectriques et l l é ectroniques CAB5-REF-24 / Recrutement Component B - Construction, d'une firme chargée de la Management and Quality And Cost- supervision des travaux de IDA / H9810 Commercialization of the CAB5 Prior Open - International 1,500,000.00 809,444.81 Signed 2016-12-15 2018-02-19 2017-01-05 2017-02-18 2018-04-05 2017-03-18 2018-02-22 2017-04-17 2018-04-05 2017-05-22 2018-06-04 2017-06-26 2018-06-19 2018-06-26 Based Selection construction FO-KINSHASA- Infrastructure through a PPP MUANDA (Cluster Ouest) Scheme CAB5-REF-25 / Recrutement d'une firme chargée de la Component B - Construction, supervision des travaux de Management and Quality And Cost- Under construction FO-LUBUMUBASHI- IDA / H9810 Commercialization of the CAB5 Prior Open - International 1,500,000.00 0.00 2018-01-15 2018-03-19 2018-02-05 2018-03-22 2018-03-21 2018-07-11 2018-04-18 2018-05-18 2018-06-22 2018-07-27 2019-07-27 Based Selection Implementation TENKE-DILOLO et TENKE- Infrastructure through a PPP KABALO-KALEMIE-GOMA Scheme (Cluster Sud et Est) Component B - Construction, CAB5-REF-26 / Elaboration du Management and Consultant Plan en faveur des Populations IDA / H9810 Commercialization of the CAB5 Post Qualification Open - National 150,000.00 160,018.20 Signed 2017-06-20 2017-03-08 2017-07-11 2017-08-24 2018-02-09 2017-09-23 2018-03-28 2017-10-28 2018-04-04 2017-12-27 Autocthones Infrastructure through a PPP Selection Scheme CAB5-REF-28 / Proposition de Component B - Construction, la structure organisationnelle et Management and Consultant é aboration du manuel de l IDA / H9810 Commercialization of the CAB5 Post Qualification Open - National 70,000.00 0.00 Canceled 2018-02-15 2018-03-06 2018-03-08 2018-04-21 2018-05-21 2018-06-25 2018-09-23 procédures de gestion Infrastructure through a PPP Selection administrative, fiancière et Scheme comptable Component B - Construction, CAB5-REF-33 / Recrutement Management and Consultant d'un Cabinet d'Avocats pour IDA / H9810 Commercialization of the CAB5 Post Qualification Open - National 30,000.00 0.00 Canceled 2018-03-15 2018-04-05 2018-05-19 2018-06-18 2018-07-23 2019-07-23 assistance juridique Infrastructure through a PPP Selection Scheme CAB5-REF-37 / Recrutement Component B - Construction, d'un cabinet pour la mesure de Management and Consultant l'impact du déploiement de la IDA / H9810 Commercialization of the CAB5 Post Qualification Open - International 100,000.00 0.00 Canceled 2019-02-15 2019-03-08 2019-04-21 2019-05-21 2019-06-25 2019-08-24 Fibre sur l'axe MUANDA- Infrastructure through a PPP Selection KINSHASA Scheme CAB5-REF-39 / Etudes de Component C - Enabling faisabiloité et assistance à Quality And Cost- Under IDA / H9810 Environment and Regulatory Prior Open - International 500,000.00 0.00 2017-11-15 2018-02-19 2017-12-06 2018-01-19 2018-04-26 2018-02-16 2018-06-01 2018-03-18 2018-07-09 2018-04-22 2018-05-27 2019-05-27 l'acquisition du matériel pour Based Selection Implementation Effectiveness l'intégrité et la sécurité du réseau Component B - Construction, CAB5-REF-30 / Recrutement Management and Quality And Cost- Under Auditeur CAB5, Exercices 2018 - IDA / H9810 Commercialization of the CAB5 Post Open - National 30,000.00 0.00 2018-06-15 2018-04-12 2018-07-06 2018-08-19 2018-09-16 2018-10-16 2018-11-20 2018-12-25 2020-05-13 Based Selection Implementation 2019 et clôture Infrastructure through a PPP Scheme INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Contract Type Estimated Actual Amount Draft Negotiated Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion Amount (US$) (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CAB5-REF-23 / Protocole Component B - Construction, d'Accord avec l'Agence Management and Congolaise de l'Environnement IDA / H9810 Commercialization of the CAB5 Prior Direct Selection Direct 100,000.00 0.00 Under Review 2018-05-15 2018-07-10 2018-06-12 2018-08-31 2019-08-31 pour le Suivi Environnemental Infrastructure through a PPP des activités du Projet CAB5- Scheme Cluster Est et Sud (Phase 1) Page 2 Component B - Construction, CAB5-REF-29 / Recurutement Management and d'un Consultant individuel chargé Individual Consultant IDA / H9810 Commercialization of the CAB5 Post Open 48,000.00 0.00 Canceled 2017-01-15 2018-03-06 2017-03-05 2017-03-26 2017-04-30 2018-04-30 de communication du Projet Selection Infrastructure through a PPP CAB5 Scheme Component B - Construction, Management and CAB5-REF-31 / Recrutement Individual Consultant IDA / H9810 Commercialization of the CAB5 Post Limited 14,000.00 0.00 Canceled 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2019-05-15 d'un deuxième chauffeur Selection Infrastructure through a PPP Scheme Component B - Construction, CAB5-REF-34 / Recrutement Management and d'un consultant individuel pour Individual Consultant IDA / H9810 Commercialization of the CAB5 Post Limited 15,000.00 22,034.00 Completed 2018-01-15 2018-02-20 2018-01-20 2018-01-24 2018-02-10 2018-02-08 2018-03-17 2018-02-16 2018-05-16 2018-03-30 appuyer la revue à mi-parcours Selection Infrastructure through a PPP du Projet CAB5 Scheme Component B - Construction, CAB5-REF-35 / Recrutement de Management and deux consultants individuels Individual Consultant IDA / H9810 Commercialization of the CAB5 Post Open 96,000.00 0.00 Canceled 2018-03-15 2018-05-03 2018-05-24 2018-06-28 2019-06-28 ingénieurs des Selection Infrastructure through a PPP é ommunications télc Scheme Component B - Construction, Management and CAB5-REF-36 / Recurutement Individual Consultant IDA / H9810 Commercialization of the CAB5 Post Limited 15,000.00 0.00 Canceled 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2019-05-15 d'un Archiviste Selection Infrastructure through a PPP Scheme Component B - Construction, CAB5-REF-38 / Recrutemet d'un Management and consultant individuel architecte Individual Consultant IDA / H9810 Commercialization of the CAB5 Post Limited 15,000.00 0.00 Canceled 2018-03-15 2018-03-20 2018-04-10 2018-05-15 2018-08-13 é udes de réhabilitation pour les t Selection Infrastructure through a PPP du bâtiment de la SOCOF SA Scheme CAB5 -REF-40 / Renforcement des capacités sur l'utilisation et Component C - Enabling la maintenance des q é uipements IDA / H9810 Environment and Regulatory Prior Direct Selection Direct 500,000.00 0.00 Canceled 2018-07-15 2018-07-25 2018-09-28 2019-09-28 de gestion des spectres de Effectiveness fréquences radioélectriques ( avec LS TELECOM) CAB5-REF-20 / Formation des cadres du MINIPTNTIC en gestion de projets de mise en Component A - Emergence of an IDA / H9810 Post Direct Selection Direct 100,000.00 94,700.00 Completed 2017-11-15 2017-12-06 2017-11-25 2018-01-19 2018-01-29 2018-02-01 2018-03-30 2018-04-30 place des infrastructures à fibres Inclusive Digital Economy optiques+ intranet (avec ST2i CONSULTING) CAB5-REF-22 / Protocole Component B - Construction, d'Accord avec l'Agence Management and Congolaise de l'Environnement Under IDA / H9810 Commercialization of the CAB5 Post Direct Selection Direct 50,000.00 0.00 2018-01-15 2018-04-20 2018-02-12 2018-06-25 2018-04-18 2019-04-18 pour le Suivi Environnemental Implementation Infrastructure through a PPP des activités du Projet CAB5-Axe Scheme Kinshasa-Muanda CAB5-REF-27 / Protocole Component B - Construction, d'accord avec COPIREP pour la Management and mise en Suvre de la feuille de IDA / H9810 Commercialization of the CAB5 Post Direct Selection Direct 250,000.00 0.00 Canceled 2018-03-15 2018-03-25 2018-05-29 2019-05-29 route de restructuration de la Infrastructure through a PPP SCPT et la mise en Suvre des Scheme PPP Component B - Construction, Management and CAB5-REF-32 / Recrutement Individual Consultant IDA / H9810 Commercialization of the CAB5 Post Open 36,000.00 0.00 Canceled 2017-10-13 2018-03-06 2017-12-01 2017-12-22 2018-01-26 2019-01-26 d'un auditeur interne Selection Infrastructure through a PPP Scheme CAB5-REF-21 / Contractualisation avec la firme Component B - Construction, IDEA CONSULT Management and INTERNATIONAL pour les IDA / H9810 Commercialization of the CAB5 Post Direct Selection Direct 400,000.00 395,550.00 Signed 2017-12-15 2017-11-22 2017-12-25 2018-02-05 2018-02-28 2018-02-02 2018-05-29 Etudes complémentaires Infrastructure through a PPP d'impact environnemental et Scheme social et plan de réinstalation des popolations du Projet CAB5 CAB5-REF-43 / Protocole Component B - Construction, d'accord avec COPIREP pour la Management and mise en Suvre de la feuille de Pending IDA / H9810 Commercialization of the CAB5 Post Direct Selection Direct 50,000.00 0.00 2018-08-20 2018-08-30 2018-11-03 2019-05-02 route de restructuration de la Implementation Infrastructure through a PPP SCPT et la mise en Suvre des Scheme PPP Page 3