PART A: GENERAL PROJECT AND SITE INFORMATION INSTITUTIONAL & ADMINISTRATIVE Project title LOCAL ECONOMY AND INFRASTRUCTURE DEVELOPMENT Sub-project number and Rehabilitation of the road segment leading to Tatev monastery title Municipality, community Tatev enlarged community, Syuniq marz Scope of site-specific The sub-project includes asphalt paving of the earth road on its entire length of activity 6,100 meters, starting from the Devil’s Bridge site up to the Tatev Monastery; widening of the existing road (where the width is less than 7 meters); constructing retaining walls along the risky parts of the road to prevent rock fall; constructing drainage ditch; arranging a metallic barrier, and installing traffic signs. As requested by the community 30-meter drainage pipe will be installed under the asphalted road close to “Satani Kamurj� part, which will enable discharge of rain waters from the incurved part of the road. After installation of the pipeline 17,4m2 asphalt will be recovered. Institutional Task Team Leader: Safeguards Specialists: arrangements (WB) Zaruhi Tokhmakhian Darejan Kapanadze (Environment) Ahmed Eiweida Vera Dugandzic (Social) Implementation Implementing entity: Works supervisor: Works contractor: arrangements (RoA) ATDF Haldi Consult LLC A.A.B. Project LLC SITE DESCRIPTION Name of institution Tatev enlarged community’s administrative unit whose premises are to be rehabilitated Address and site location of Tatev enlarged community’s administrative unit, Shinuhayr village institution whose premises are to be rehabilitated Who owns the land? The road to be rehabilitated belongs to Tatev Enlarged Community. The Sub- Who uses the land project will not impose any activities that will reduce other people’s access to (formal/informal)? their economic resources. There are no shops, kiosk or other small business activities along the road to be reconstructed. The implementation of sub-project does not include acquisition of private land. All the parts where the road will be broadened are communal property. The sub-project will not result in the temporary or permanent loss of crops, fruit trees and/or household infrastructure. No resettlement issues are anticipated. Description of physical and The segment of the road envisaged to rehabilitate starts 150m away from Devil’s natural environment around bridge natural monument and ends at the Tatev monastery’s metallic gate. Tatev the site Monastery is a 9th century cultural heritage site and Develi’s bridge is a designated natural monument of Armenia. The cable way of “Wings of Tatev� is located in the proximity of Tatev monastery. The existing road segment is an earth road with the width of 6-9 meters and total length of 6,100 meters. Currently there are concrete single barriers in some parts of the road which are located 20-30 meters far from each other. Some parts of the road are under a rock fall risk and there the protection walls are envisaged. Alongside the road, there is a partial drainage ditch. Temporary traffic safety enhancement activities will be implemented during civic works. LEGISLATION National & local legislation According to RA national legislation the subproject requires: & permits that apply to ➢ positive environmental expertise conclusion** sub-project activity ➢ construction permit*** ➢ construction waste disposal permit PUBLIC CONSULTATION When / where the public Four public consultation meetings were carried out in Tatev community on consultation process will February 5, March 28, April 27 and June 6, 2018. take /took place The minutes attached to this ESMP reflect public consultation meetings held on April 27 and June 6, 2018 in Tatev Community to discuss draft Environmental and Social Management Plan. ATTACHMENTS Attachment 1: Site map/photo Attachment 2: Permission for construction waste disposal from Tatev’s enlarged community Attachment 3: Minutes of public consultation meeting Attachment 4: Conclusion of the State environmental assessment and expert examination of the design Attachment 5: Construction permit PART B: SAFEGUARDS INFORMATION ENVIRONMENTAL /SOCIAL SCREENING Activity/Issue Status Triggered Actions 1. Building rehabilitation [ ] Yes [x] No See Section A below 2. New construction [ ] Yes [x ] No See Section A below 3. Individual wastewater treatment system [ ] Yes [x] No See Section B below Will the site 4. Historic building(s) and districts [ ] Yes [x] No See Section C below activity include/involve 5. Acquisition of land1 [ ] Yes [x] No See Section D below any of the following? 6. Hazardous or toxic materials2 [ ] Yes [x] No See Section E below 7. Impacts on forests and/or protected areas [ ] Yes [x] No See Section F below 8. Handling / management of medical waste [ ] Yes [x] No See Section G below 9. Traffic and pedestrian safety [x] Yes [ ] No See Section H below 10. Social risk management [x] Yes [ ] No See Section I below 1 Land acquisitions includes displacement of people, change of livelihood encroachment on private property this is to land that is purchased/transferred and affects people who are living and/or squatters and/or operate a business (kiosks) on land that is being acquired. 2 Toxic / hazardous material includes but is not limited to asbestos, toxic paints, noxious solvents, removal of lead paint, etc. PART C: MITIGATION MEASURES ACTIVITY PARAMETER MITIGATION MEASURES 0. General Notification and (a) The local construction and environment inspectorates and communities are notified of upcoming activities Conditions Worker Safety (b) The public is notified of the works through appropriate notification in the media and/or at publicly accessible sites (including the site of the works) (c) All legally required permits are acquired for construction and/or rehabilitation (d) The Contractor formally agrees that all work will be carried out in a safe and disciplined manner designed to minimize impacts on neighboring residents and environment. (e) Workers’ personal protection equipment complies with international good practice (always hardhats, as needed masks and safety glasses, harnesses and safety boots) (f) Appropriate signposting of the sites informs workers of key rules and regulations to follow. A. General Air Quality (a) During interior demolition, debris-chutes are used above the first floor. Rehabilitation (b) Demolition debris is kept in controlled area and sprayed with water mist to reduce debris dust. (c) During pneumatic drilling/wall destruction dust is suppressed by ongoing water spraying and/or installing dust screen and /or enclosures at site. construction (d) The surrounding environment (sidewalks, roads) is kept free of debris to minimize dust. activities (e) There is no open burning of construction / waste material at the site. (f) There is no excessive idling of construction vehicles at sites. Noise (a) Construction noise is limited to restricted times agreed to in the permit. (b) During operations, the engine covers of generators, air compressors and other powered mechanical equipment are closed, and equipment placed as far away from residential areas as possible. Water Quality (a) Appropriate erosion and sediment control measures are applied such as e.g. hay bales and / or silt fences to prevent sediment from moving off site and causing excessive turbidity in nearby streams and rivers. Waste (a) Waste collection and disposal pathways and sites are identified for all major waste types expected from demolition and Management construction activities. (b) Mineral construction and demolition wastes are separated from general refuse, organic, liquid and chemical wastes by on- site sorting and stored in appropriate containers. (c) Construction waste is being collected and disposed properly by licensed collectors. (d) Whenever feasible, appropriate and viable materials (except asbestos) are reused or recycled. B. Individual Water Quality (a) The approach to handling sanitary wastes and wastewater from building sites (installation or reconstruction) is approved by wastewater the local authorities. (b) Before being discharged into receiving waters, effluents from individual wastewater systems are treated in order to meet the treatment system minimal quality criteria set out by national guidelines on effluent quality and wastewater treatment. (c) Monitoring of new wastewater systems (before/after) is carried out (d) Construction vehicles and machinery are washed only in designated areas where runoff will not pollute natural surface water bodies. C. Historic Cultural Heritage (a) If the building is a designated historic structure, very close to such a structure, or located in a designated historic district, building(s) notification is made, and approvals/permits be obtained from local authorities and all construction activities planned and carried out in line with local and national legislation. (b) Provisions are put in place so that artifacts or other possible chance finds encountered in excavation or construction are noted and registered, responsible officials contacted, and works activities delayed or modified to account for such finds. D. Acquisition of Land Acquisition (a) If expropriation of land was not expected but is required, or if loss of access to income of legal or illegal users of land was land Plan/Framework not expected but may occur, that the Bank’s Task Team Leader is immediately consulted. (b) The approved Land Acquisition Plan/Framework (if required by the project) is implemented E. Toxic Asbestos (a) If asbestos is located on the project site, it is marked clearly as hazardous material. materials management (b) When possible, the asbestos is appropriately contained and sealed to minimize exposure. (c) Prior to removal (if removal is necessary), the asbestos is treated with a wetting agent to minimize asbestos dust. (d) Asbestos is handled and disposed by skilled & experienced professionals (e) If asbestos material is stored temporarily, the wastes are securely enclosed inside closed containments and marked appropriately. Security measures are taken against unauthorized removal from the site. (f) The removed asbestos is not reused. Toxic / (a) Temporarily storage on site of all hazardous or toxic substances is in safe containers labeled with details of composition, hazardous waste properties and handling information. (b) The containers of hazardous substances are placed in a leak-proof container to prevent spillage and leaching. management (c) The wastes are transported by specially licensed carriers and disposed in a licensed facility. (d) Paints with toxic ingredients or solvents or lead-based paints are not used. F. Affected Protection (a) All recognized natural habitats, wetlands and protected areas in the immediate vicinity of the activity are not damaged or forests, wetlands exploited; all staff is strictly prohibited from hunting, foraging, logging or other damaging activities. (b) A survey and an inventory are made of large trees in the vicinity of the construction activity, large trees are marked and and/or protected cordoned off with fencing; their root system protected, and any damage to the trees avoided. areas (c) Adjacent wetlands and streams are protected from construction site run-off with appropriate erosion and sediment control feature to include by not limited to hay bales and silt fences. (d) There is no unlicensed borrow pits, quarries or waste dumps in adjacent areas, especially not in protected areas. G. Disposal of Infrastructure for (a) In compliance with national regulations, the newly constructed and/or rehabilitated health care facilities include sufficient medical waste medical waste infrastructure for medical waste handling and disposal; this includes and not limited to: ▪ Special facilities for segregated healthcare waste (including soiled instruments “sharps�, and human tissue or fluids) management from other waste disposal; ▪ Appropriate storage facilities for medical waste are in place; and ▪ If the activity includes facility-based treatment, appropriate disposal options are in place and operational H. Traffic and Direct or indirect (a) In compliance with national regulations, the construction site is properly secured and construction related traffic regulated. pedestrian safety hazards to public This includes but is not limited to ▪ Signposting, warning signs, barriers and traffic diversions: site will be clearly visible and the public warned of all traffic and potential hazards. pedestrians by ▪ Traffic management system and staff training, especially for site access and near-site heavy traffic. Provision of safe passages and crossings for pedestrians where construction traffic interferes. construction ▪ Adjustment of working hours to local traffic patterns, e.g. avoiding major transport activities during rush hours or times activities of livestock movement. ▪ Active traffic management by trained and visible staff at the site, if required for safe and convenient passage for the public. ▪ Ensuring safe and continuous access to office facilities, shops and residences during renovation activities, if the buildings stay open for the public. I. Social risk Public (a) The Contractor has a local liaison person assigned who is in charge of communication with and receiving requests / management relationship complaints from local population. (b) Local communities are consulted to identify and pro-proactively manage potential conflicts between an external workforce management and local people. (c) The Contractor raises local community’s awareness about sexually transmitted disease risks associated with the presence of an external workforce and include local communities in awareness activities. (d) The population is informed about construction and work schedules, interruption of services, traffic detour routes and provisional bus routes, blasting and demolition, as appropriate. (e) Construction activities are limited at night. When necessary, night work will be carefully scheduled and the community properly informed, so they can take necessary measures. (f) At least five days in advance of any service interruption (including water, electricity, telephone, bus routes), the community is advised through postings at the project site, at bus stops, and in affected homes/businesses. Labor (g) To the extent possible, work camps are not located in close proximity to local communities. management (h) Siting and operation of worker camps is undertaken in consultation with neighboring communities. (i) The Contractor recruits unskilled or semi-skilled workers from local communities to the extent possible. Where and when feasible, worker skills training, is provided to enhance participation of local people. (j) Adequate lavatory facilities (toilets and washing areas) are provided in the work site with adequate supplies of hot and cold running water, soap, and hand drying devices. A temporary septic tank system is established for any residential labor camp and without causing pollution of nearby watercourses. (k) The Contractor raises awareness of workers on overall relationship management with local population, establish the code of conduct in line with international practice and strictly enforce them, including the dismissal of workers and financial penalties of adequate scale. PART D: MONITORING PLAN When What Where How Why Who Activity (Define the (Is the parameter (Is the parameter to (Is the parameter to (Is the parameter (Is responsible for frequency / or to be monitored?) be monitored?) be monitored?) being monitored?) monitoring?) continuous?) CONSTRUCTION PHASE Supply of construction Purchase of In supplier’s office or Verifications of the In the process of signing To ensure technical ATDF materials construction materials warehouse documents the contracts for material quality of construction, from the licensed supply human health and suppliers environmental quality Transportation of Technical condition of In the entrances and exits Inspection of pre- Unannounced monthly To control emissions ATDF construction materials construction vehicles of construction site defined movement inspection during work release into the Technical Supervisor and waste; and machinery; routes, entrances and hours and beyond environment exits of construction Movement of Coverage of loads when To control nuisance to sites construction vehicles carrying dust, soil, spoil local communities and machinery and construction waste; To minimize traffic Movement of disruption, ensure construction vehicles pedestrian safety and and machinery prevent accidents according to predefined traffic routes and within working hours: 9AM-6PM. Generation of Temporary storage of Construction site Inspection of site Unannounced monthly To prevent construction ATDF construction waste waste at the pre- inspection during entire related waste Waste disposal site Technical Supervisor defined areas of construction phase accumulation in construction site construction site and its neighborhood Timely disposal of waste in the permitted dumpsite 7 Deploying manpower Provision of uniforms Construction site Inspection Unannounced monthly To minimize probability ATDF for construction; and safety gears to visits during entire of accidents Technical Supervisor workers and construction phase Undertaking works in To protect workers’ enforcement of their construction site health use by the constructor; To exclude nuisance to Provision of work-site neighborhood after safety instruction to working hours contractor’s personnel and instructions proper To exclude vibrations recording; impacts to Tatev monastery Installation of fencing; Provisions of nuisance activities within working hours from 9AM-6PM and in accordance with allowed norms of noise and vibrations Site reinstatement Construction- related Construction site Inspection At the post -construction To ensure cleaned site ATDF waste removal from all Phase for operation Technical Supervisor the areas of the site OPERATION PHASE Household waste Trash bins placement Rehabilitated site Inspection During operation phase To prevent litter in Tatev’s community management and timely rehabilitated site administrative unit transportation of waste to the final disposal site Maintenance and Non-authorized Rehabilitated site Inspection During operation phase Prevent aesthetic view Tatev’s community protection of site constructions and land of site and surrounding administrative unit use in rehabilitated area area; Police of RA Prevent roadside Maintenance of road accidents due to lack of Ministry of Transport signage road signage that may and Communication arise from the loss or damage of the initially installed signs 8 Attachment 1 1.1. Map of the sub-project site 9 1.2. Photos from the subproject site 10 Attachment 2: Permission for construction waste disposal from Tatev’s enlarged community Unofficial translation: Republic of Armenia, Syunik marz, Tatev community № 503 07 May, 2018 Reference The construction waste generated from the rehabilitation of the road segment leading to Tatev monastery to be transferred to “Khigari twist� called site (the average distance of transportation is 3-4 km). Tatev Community Head /signed/ Murad Simonyan 11 Attachment 3: Minutes of public consultation meetings MINUTES OF PUBLIC CONSULTATION MEETING on the draft Environmental and Social Management Plan Tatev, April 27, 2018 A public consultation meeting was held in Tatev Community Administrative office of Syunik Marz on April 27, 2018 at 13:00pm on the draft Environmental and Social Management Plan developed for the rehabilitation of the road segment leading to Tatev Monastery, to be implemented within the framework of “Local Economy and Infrastructure Development� Project. The agenda of public consultation meeting was the following: ▪ Introduction of Local Economy and Infrastructure Development Project to the stakeholders ▪ Introduction of Environmental and Social safeguard policies and Environmental and Social Management Plan ▪ Introduction of Grievance Redress Mechanisms under the Program ▪ Q&A session with stakeholders Information on the meeting day and time was posted on information boards of Tatev Community Administration Offices and other public visible places of enlarged settlements; in addition, the Administration conducted telephone calls to ensure participants’ attendance. The announcement for the meeting in Armenian and English languages, including its date and time, and Environmental and Social Management Plan was disclosed on the ATDF web page on April 17, 2018(http://atdf.am/en/Reports). The public consultation was carried out by ATDF Environmental Specialist Lusine Gevorgyan and ATDF Social Specialist Sonya Msryan. The meeting was attended by representatives of Tatev community including 18 participants were present at the meeting, among which 7 women (about 29%). Head of Community Mr. Simonyan welcomed the participants, introduced ATDF Specialists and introduced the purpose of the meeting and encouraged them to provide feedbacks on the topics discussed further. ATDF Environmental Specialist Lusine Gevorgyan introduced Local Economy and Infrastructure Development Project among which Rehabilitation of the Road Segment Leading to Tatev Monastery sub-project was presented to the participants. L. Gevorgyan outlined that 12 development of Environmental and Social Management Plan document is required according to the WB Operational Policy while local legislation requires development and approval of Environmental Impact Assessment which is at the current moment ongoing. The categories of the sub-project according to the WB categorization and local laws were also introduced to the participants. L. Gevorgyan introduced the procedure of environmental and social expertise, description of the sub-project, including the length of the road to be rehabilitated, construction of water removal system, traffic safety measures and etc. L. Gevorgyan introduced Environmental and Social Management Plan Document of the sub- project including the purpose of the document, structure, and key aspects covered by the document. She described baseline environmental conditions, biophysical and social environment of the site. She duly introduced likely negative environmental impacts related to the sub-project implementation including construction and operation phases. L. Gevorgyan outlined anticipated negative impacts including the generation of construction related waste, dust emissions and localized atmospheric air pollution, wastewater discharge which could cause minor contamination of soil and water bodies, increase of noise and vibration level during the construction machinery movement, temporary disruption of some parts of public access roads during construction activities and temporary distortion of natural landscape due to construction activities. L. Grigoryan introduced key measures to be undertaken to mitigate adverse environmental impacts and outlined that technical supervisions on monthly basis will keep under control the fulfillment of all the environmental mitigation measures included in ESMP. She highlighted that all sub-project related documents, including ESMP is available on ATDF Web-page and explained where participants can find the documents. She emphasized that long-terms impacts of the Project are positive as rehabilitation of the road will promote flow of tourists and will be beneficial for the community. S. Msryan presented the main provisions of the ESMP concerning to the social aspects of the Project. She emphasized that the project does not involve any resettlement as all activities will be implemented in public lands. S. Msryan specified that the construction activities will not disrupt any private business. The roads will be accessible for pedestrians and cars during construction activities and total closure of the road during construction activities is not anticipated. Ms. Msryan explained mechanisms of public engagement and Grievance Redress Mechanism (GRM) to be applied during project implementation. S. Msryan introduced that Grievance Redress Mechanism includes selection of local focal point and explained key activities and responsibilities of FP. She welcomed participants to nominate and select FP. Mr. Gevorg Baghshyan was selected as grievance focal point at the community level. S. Msryan introduced 13 that in case of questions/feedback or grievances concerning to the project implementation community member can apply to Mr. Baghshyan. S. Msryan informed the beneficiaries that they also have the option to contact ATDF directly to communicate their grievance if they are unable to, or do not wish to, go through local focal point. S. Msryan explained all the cannels of grievance submission involving the e-mail address, hot line telephone number, postal address and web-site link and outlined that ATDF contact information is reflected on the booklets delivered to the participants, as well as on the information desk posted in public visible places in the Community, including Community Administrative Office building. S. Msryan introduced that information on sub-project details permanently will be available on the information desks, as well as on-going announcements and references. She outlined that these will support to raising public awareness and early identification, assessment and resolution of complaints on Project activities. The participants were welcomed to raise questions regarding to the presented information. The following questions were raised by the participants: One of the participants raised question whether the Sub-project envisages construction of protective wall where rock-fall risks are high. The ATDF Specialists explained the Sub-project design includes construction of protective walls against rock-fall in the 5 parts of the road of 2-meter height. The Head of Community introduced that he offers to ATDF to include rehabilitation of drainage system of “Statni Kamurj� in the Sub-project. ATDF specialists explained that this question in under discussion now and will be clarified during the next consultation meeting. The list of participants and photos are attached. 14 List of Participants 15 Photos of Public Consultation meeting 16 MINUTES OF PUBLIC CONSULTATION MEETING on the draft Environmental and Social Management Plan Tatev, June 6, 2018 A public consultation meeting was held in Tatev Community Administrative office of Syunik Marz on June 6, 2018 at 13:00pm on Environmental and Social Management Plan developed for rehabilitation of the road segment leading to Tatev Monastery to be implemented within the framework of “Local Economy and Infrastructure Development� Project. The agenda of public consultation meeting was the following: ▪ Introduction of Local Economy and Infrastructure Development Project to the stakeholders ▪ Introduction of Environmental and Social safeguard policies and Environmental and Social Management Plan Document ▪ Introduction of Grievance Redress Mechanisms under the Program ▪ Q&A session with stakeholders Information on the meeting day and time was posted on information boards of Tatev Community Administration Offices and other public visible places of enlarged settlements; in addition, the Administration conducted telephone calls to ensure participants’ attendance. The announcement for the meeting in Armenian and English languages, including its date and time, and Environmental and Social Management Plan was disclosed on the ATDF web page on May 26, 2018 (http://atdf.am/en/Reports). The public consultation was carried out by LEID Project Coordinator Tadevos Shahbazyan, ATDF Environmental Specialist Lusine Gevorgyan and ATDF Social Specialist Sonya Msryan. The meeting was attended by representatives of Tatev community including 10 participants were present at the meeting, among which 4 women. Head of Community Mr. Simonyan welcomed the participants, introduced ATDF Specialists and introduced the purpose of the meeting and encouraged them to provide feedbacks on the topics discussed further. LEID Project Coordinator Tadevos Shahbazyan introduced Local Economy and Infrastructure Development Project among which Rehabilitation of the Road Segment Leading to Tatev Monastery sub-project was presented to the participants. T. Shahbazyan presented, that all the questions raised during the previous consultation meetings that were not answered should be addressed during the final consultation meeting, accordingly he introduced that to the request of the community to construct drainage system close to “Statni Kamurj� part, it was agreed 17 that 30 meter drainage pipe will be installed under the asphalted road close to “Satani Kamurj� part, which will enable discharge of rain waters from the incurved part of the road. After installation of the pipeline the asphalt will be recovered. L. Gevorgyan outlined that development of Environmental and Social Management Plan document is required according to the WB Operational Policy while local legislation requires development and approval of Environmental Impact Assessment which is at the current moment ongoing. The categories of the sub-project according to the WB categorization and local laws were also introduced to the participants. L. Gevorgyan introduced the procedure of environmental and social expertise, description of the sub-project, including the length of the road to be rehabilitated, construction of water removal system, traffic safety measures and etc. L. Gevorgyan introduced Environmental and Social Management Plan Document of the sub- project including the purpose of the document, structure, and key aspects covered by the document. She described baseline environmental conditions, biophysical and social environment of the site. She duly introduced likely negative environmental impacts related to the sub-project implementation including construction and operation phases. L. Gevorgyan outlined anticipated negative impacts including the generation of construction related waste, dust emissions and localized atmospheric air pollution, wastewater discharge which could cause minor contamination of soil and water bodies, increase of noise and vibration level during the construction machinery movement, temporary disruption of some parts of public access roads during construction activities and temporary distortion of natural landscape due to construction activities. L. Grigoryan introduced key measures to be undertaken to mitigate adverse environmental impacts and outlined that technical supervisions on monthly basis will keep under control the fulfillment of all the environmental mitigation measures included in ESMP. She highlighted that all sub-project related documents, including ESMP is available on ATDF Web-page and explained where participants can find the documents. She emphasized that long-terms impacts of the Project are positive as rehabilitation of the road will promote flow of tourists and will be beneficial for the community. S. Msryan presented the main provisions of the ESMP concerning to the social aspects of the Project. She emphasized that the project does not involve any resettlement as all activities will be implemented in public lands. S. Msryan specified that the construction activities will not disrupt any private business. The roads will be accessible for pedestrians and cars during construction activities and total closure of the road during construction activities is not anticipated. Ms. Msryan explained mechanisms of public engagement and Grievance Redress Mechanism (GRM) to be applied during project implementation. She introduced that Mr. Gevorg 18 Baghshyan was selected as grievance focal point at the community level. S. Msryan introduced that in case of questions/feedback or grievances concerning to the project implementation community member can apply to Mr. Baghshyan. S. Msryan informed the beneficiaries that they also have the option to contact ATDF directly to communicate their grievance if they are unable to, or do not wish to, go through local focal point. S. Msryan explained all the cannels of grievance submission involving the e-mail address, hot line telephone number, postal address and web-site link and outlined that ATDF contact information is reflected on the booklets delivered to the participants, as well as on the information desk posted in public visible places in the Community, including Community Administrative Office building. S. Msryan introduced that information on sub-project details permanently will be available on the information desks, as well as on-going announcements and references. She outlined that these will support to raising public awareness and early identification, assessment and resolution of complaints on Project activities. The participants were welcomed to raise questions regarding to the presented information. No questions were raised by the participants. The list of participants and photos are attached. 19 List of Participants 20 Photos of Public Consultation meeting 21 Attachment 4. POSITIVE ENVIRONMENTAL CONCLUSION 22 Attachment 5. CONSTRUCTION PERMIT 23