The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) China: Tianjin Urban Transport Improvement Project (P148129) EAST ASIA AND PACIFIC | China | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 7 | ARCHIVED on 21-Dec-2018 | ISR35234 | Implementing Agencies: Tianjin PMO, People's Republic of China Key Dates Key Project Dates Bank Approval Date: 21-Dec-2015 Effectiveness Date: 26-May-2016 Planned Mid Term Review Date: 30-Nov-2018 Actual Mid-Term Review Date: 12-Nov-2018 Original Closing Date: 31-Mar-2021 Revised Closing Date: 31-Mar-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to leverage the Tianjin metro system and to promote walking and biking in the urban core (in Heping and Nankai) in order to make transport greener and safer in Tianjin and draw lessons for other large cities. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Green Transport Improvement in Heping and Nankai Districts:(Cost $89.48 M) Metro Access Improvement:(Cost $89.05 M) Public Bike Sharing System (PBS) Pilot:(Cost $23.14 M) Bus Terminal Development:(Cost $15.99 M) Technical Assistance:(Cost $2.90 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The project has made substantial progress in developing high quality conceptual design for initial pilots under the project to improve the quality of the urban space for pedestrians and bicycles in the center of Tianjin. Overall, the main project achievements to date have been through both technical assistance and civil works. Especially, the city has made remarkable progress in implementing the green transport development recommendations and interventions from technical assistance, with active campaign to communicate the positive impacts of green transport. Civil 12/21/2018 Page 1 of 6 The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) works is catching up pace and progressing well. Three contracts have been awarded and construction will be completed by the end of the year 2018 for two of those. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Low Low Low Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Moderate Moderate Moderate Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes To make transport greener and safer in Tianjin IN00614087 ►Increase in metro ridership with the project compared to without the project (trips) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 14,667.00 85,000 12/21/2018 Page 2 of 6 The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 IN00614088 ►Increase in volume of non-motorized trips by project, including Public Bike Sharing trips and increase in walking and biking trips with the project in Heping and Nankai pilot areas (trips). (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 11,052 135,000.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 IN00614089 ►GHG emission reduction (tons) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 648.00 6,500 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 IN00614090 ►Reduction in number of accidents in Heping and Nankai pilot area (accidents) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 100.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 IN00614147 ►System of detailed performance evaluation with citizen engagement (men and women) in place (number of sites) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Pilot selected -- 10.00 20.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 Sites have been identified, initial consultation took place. The detailed measurement will be done as part Comments: of a new technical assistance after completion of construction. Intermediate Results Indicators by Components Green Transport Improvement in Heping and Nankai Districts IN00614149 ►NMT Space Ratio in Nankai and Heping Districts (Percentage) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 25.00 -- 28.00 46.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 IN00614148 ►Changes to project activities as a result of consultation (Yes/No) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/21/2018 Page 3 of 6 The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) Value No -- yes Yes Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 IN00614146 ►Roads rehabilitated, Non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 4.40 50.00 Date 01-Sep-2015 -- 13-Dec-2018 31-Mar-2021 Actual construction to be completed by December 31, 2018. Comments: Metro Access Improvement IN00614151 ►Metro station areas improved (number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 20.00 111.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 Public Bike Sharing System (PBS) Pilot IN00614152 ►PBS stations in operation (Number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- not relevant 446.00 Date 01-Sep-2015 -- 13-Dec-2018 31-Mar-2021 with the arrival of several hundred thousand dockless shared bikes, this indicator has lost its meaning. Comments: Bus Terminal Development IN00614153 ►Bus terminals completed (number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 5.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 Technical Assistance IN00614154 ►Technical Assistance Leading to Changes (number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/21/2018 Page 4 of 6 The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) Value 0.00 -- 2.00 4.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 IN00614150 ►IRAP's road safety assessment scores above 3 for streets in Heping and Nankai that are upgraded under the project (Percentage) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30.00 -- 100% 90.00 Date 01-Sep-2015 -- 15-Nov-2018 31-Mar-2021 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P148129 IBRD-85650 Effective USD 100.00 100.00 0.00 19.85 80.15 20% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P148129 IBRD-85650 Effective 21-Dec-2015 26-Feb-2016 26-May-2016 31-Mar-2021 31-Mar-2021 Cumulative Disbursements 12/21/2018 Page 5 of 6 The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/21/2018 Page 6 of 6