PROCUREMENT PLAN (Textual Part) Project information: Dominican Republic, Integrated Social Protection and Promotion Project , P147213 Project Implementation agency: Gabinete de Coordinación de Política Sociales (GCPS) Date of the Procurement Plan: 11/19/2018 Period covered by this Procurement Plan: 18 MONTHS Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. i This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in Not Applicable such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. Not Applicable When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for each Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; “Not Applicable” Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] “Not Applicable” Other Relevant Procurement Information. We have other procedures that we are using that were established in the Operational Manual, for the selection of training providers, under subcomponent 1.3, following the procedures in point 3.19 of the Bank's procurement rules. Likewise, the Operative Manual establishes the contracting of minor works of subcomponent 1.2, where non-governmental organizations (NGOs) will be convened, using an approach of Community Participation in Contracting (PCC or CDD), following the provisions of the Bank's procurement rules. iRules Acquisitions Of Goods, Works And Services Different From The Consultants With Loans Of The IBRD, Ida Credits And Donations By Bank World Borrowers January 2011 Revised In July 2014 PROCUREMENT Dominican Republic : INTEGRATED SOCIAL PROTECTION AND PROMOTION PROJECT PLAN General Information Country: Dominican Republic Bank’s Approval Date of the Original Procurement Plan: 2018-04-24 2019-09-03 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P147213 GPN Date: Project Name: INTEGRATED SOCIAL PROTECTION AND PROMOTION PROJECT Loan / Credit No: IBRD / 84790 Executing Agency(ies): Social Policy Coordination Cabinet WORKS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DO-GCPS-80213-CW-RFB / (Act. 1.2.2.1.2) Contratación Component 1. Integrated de obras para la Area-Based Social Solicitud de Single Stage - One IBRD / 84790 Previa Open - National 7,169,295.82 0.00 En ejecución 2018-10-01 2018-10-11 2018-11-26 2019-01-07 2019-02-13 2020-05-01 rehabilitación de pisos de Protection and Pro-poor ofertas Envelope tierra por cemento de Service Delivery viviendas PSIP5AESPCDD / (Act. 1.2.1.1) Subproyectos Component 1. Integrated ejecutados por ONG para la Participación de Area-Based Social adecuación (pisos de tierra IBRD / 84790 Previa la comunidad en Open - National 3,250,000.00 0.00 En ejecución 2017-09-25 2017-09-30 2017-11-11 2017-12-11 2018-01-15 2018-07-14 Protection and Pro-poor por cemento) de las las adquisiciones Service Delivery viviendas en las provincias seleccionadas PSIP-10-LPI-OC / (Act. 1.2.2.1) Contratación de Component 1. Integrated contratistas privados para Area-Based Social Solicitud de Open - Single Stage - One IBRD / 84790 Previa 3,430,704.00 0.00 En ejecución 2019-02-01 2019-02-06 2019-03-20 2019-04-19 2019-05-24 2019-11-20 la rehabilitación de pisos de Protection and Pro-poor ofertas International Envelope tierra por cemento de Service Delivery viviendas DO-GCPS-128159-CW-RFQ / (Act. 1.2.2.1) Lote 31- (214 viviendas) - Fase IV "Sustitución de Piso de Component 1. Integrated tierra por pisos de Area-Based Social Solicitud de Single Stage - One Ejecución IBRD / 84790 Posterior Open - National 319,288.00 0.00 2019-09-07 2019-11-02 2020-04-30 cemento", Provincia: Azua, Protection and Pro-poor cotizaciones Envelope pendiente Municipios: (Estebania, Las Service Delivery Charcas, Peralta, Pueblo Viejo, Sabana Yegua, Tabara Arriba, Guayabal) DO-GCPS-128162-CW-RFQ / (Act. 1.2.2.1) Lote 32 - (212 viviendas) - Fase IV Component 1. Integrated "Sustitución de Piso de Area-Based Social Solicitud de Single Stage - One Ejecución tierra por pisos de IBRD / 84790 Posterior Open - National 316,304.00 0.00 2019-09-07 2019-11-02 2020-04-30 Protection and Pro-poor cotizaciones Envelope pendiente cemento", Provincia: San Service Delivery Juan de la Maguana, Municipios: (El Cercado, Sección, El pinar) GOODS Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 1. Integrated PIPPS - 197- 2016 / Area-Based Social Solicitud de Open - Proceso Adquisicion de IBRD / 84790 Previa 60,000.00 38,500.00 Firmado Protection and Pro-poor cotizaciones International Vehiculos Service Delivery Component 2. DO-GCPS-78735-GO-RFB / Strengthening of the Solicitud de Single Stage - One Ejecución (Act. 2.2.1.1.4.5) Uniformes IBRD / 84790 PROSOLI CCT Program Posterior Limited 372.74 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope pendiente de Encuestadores and Support to Targeted Households DO-GCPS-78829-GO-RFB / (Act. 3.2.2.3.2) Adquisición Component 3. Enhancing Solicitud de Single Stage - One Ejecución de equipos para la IBRD / 84790 Equity and Results- Posterior Open - National 200,000.00 0.00 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-07-17 ofertas Envelope pendiente implementación de la orientation segunda fase del SIME DO-GCPS-79030-GO-RFB / Component 3. Enhancing Solicitud de Single Stage - One Ejecución (Act. 3.4.2.1.2) Software y IBRD / 84790 Equity and Results- Posterior Limited 45,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope pendiente Digitalización orientation DO-GCPS-79035-GO-RFB / (Act. 3.4.2.1.4) Adquisición Component 3. Enhancing de Equipos para adecuación Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 15,000.00 0.00 2018-10-03 2018-11-28 2019-05-27 de Salón de Conferencias cotizaciones Envelope pendiente orientation UTP, equipos de comunicación. DO-GCPS-79038-GO-RFB / Component 3. Enhancing (Act. 3.4.2.1.5) Aumento Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 100,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 Capacidad de cotizaciones Envelope pendiente orientation Almacenamientos Servidores DO-GCPS-80975-GO-RFQ / Component 3. Enhancing (Act. 3.4.2.1.1) Adquisición Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 45,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 de Equipos y Software para cotizaciones Envelope pendiente orientation la UTP Component 2. PSIP-285-LPN-B / (Act. Strengthening of the Solicitud de Single Stage - One Ejecución 2.1.3.5) Motocicletas para IBRD / 84790 PROSOLI CCT Program Posterior Open - National 235,238.00 0.00 2017-01-07 2017-03-04 2017-08-31 cotizaciones Envelope pendiente coordinadores municipales and Support to Targeted Households PSIP-282-CP-B / Component 2. (Act.2.3.5.1.2) Adquirir el Strengthening of the Solicitud de Single Stage - One Ejecución Certificado para apoyar el IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,519.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones Envelope pendiente intercambio de datos de la and Support to Targeted JCE e interoperatividad Households PSIP-87-CP-B / (Act. 3.1.1.1.1) Adquisición de almacenamiento para las Component 3. Enhancing Solicitud de Single Stage - One Ejecución bases de datos 1er, 2do, 3er IBRD / 84790 Equity and Results- Posterior Limited 58,906.00 0.00 2016-07-13 2016-09-07 2017-03-06 cotizaciones Envelope pendiente ESH, Base de datos orientation maestras y adicionales. SIUBEN Page 1 PSIP-250-CP-B / Component 3. Enhancing Solicitud de Single Stage - One Ejecución (Act.3.1.1.1.8) Vestimenta- IBRD / 84790 Equity and Results- Posterior Limited 1,761.00 0.00 2017-01-25 2017-03-22 2017-09-18 cotizaciones Envelope pendiente Piloto Estudio orientation PSIP-286-CP-B / (Act. 3.1.1.2.2.2.1) Adquisicion de equipo para la Preparación Component 3. Enhancing Solicitud de Single Stage - One Ejecución y distribución de la IBRD / 84790 Equity and Results- Posterior Limited 9,561.00 0.00 2017-06-17 2017-08-12 2018-02-08 cotizaciones Envelope pendiente cartografía (420.000 mapas orientation para distribución del trabajo) PSIP-287-CP-B / (Act. Component 3. Enhancing 3.1.1.2.2.2.2) Adquisición de Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 1,678.00 0.00 2016-11-26 2017-01-21 2017-07-20 Equipo Drone para la cotizaciones Envelope pendiente orientation ejecución del ESH DO-GCPS-97727-GO-RFQ / Component 3. Enhancing (Act. 3.3.9.8) Readecuación Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 5,884.06 0.00 2019-02-05 2019-04-02 2019-09-29 de oficinas del proyecto cotizaciones Envelope pendiente orientation Cultura Ciudadana. DO-GCPS-78783-GO-RFB / (Act. 2.2.2.3.1) Component 2. Automatización del Strengthening of the mecanismo mediante la Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 38,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 adquisión de tabletas para cotizaciones Envelope pendiente and Support to Targeted el Feedback de los Reportes Households Comunitarios en los puntos solidarios o colmados DO-GCPS-78788-GO-RFB / Component 2. (Act. 2.2.3.9) Adquisición de Strengthening of the Solicitud de Single Stage - One Ejecución Mobiliario y Equipos IBRD / 84790 PROSOLI CCT Program Posterior Limited 2,592.97 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope pendiente Informáticos para los and Support to Targeted Reportes Comunitarios. Households PSIP-187-CP-B / (Act. Component 2. 2.1.3.2.3.2.1) Material Strengthening of the Solicitud de Single Stage - One Ejecución Gastable para la imrpesion IBRD / 84790 PROSOLI CCT Program Posterior Limited 15,991.66 0.00 2016-03-21 2016-05-16 2016-11-12 cotizaciones Envelope pendiente de la Ficha del and Support to Targeted levantamiento Households PSIP-313-CP-B / (Act. 2.1.4.3) Adquisición de equipos informáticos para capacitación y operación de Component 2. los Comites Provinciales y Strengthening of the Solicitud de Single Stage - One Ejecución Regionales en la IBRD / 84790 PROSOLI CCT Program Posterior Limited 54,965.49 0.00 2017-05-07 2017-07-02 2017-12-29 cotizaciones Envelope pendiente implementacion sobre la and Support to Targeted estrategia Progresando Households Unidos (Laptop, impresoras, Camaras Digitales, Scanner, Proyectores, etc.) PSIP-296-CP-B / (Act. 2.2.1.1.3) Adquisición de Component 2. Equipos Informáticos para Strengthening of the la expansión de puntos Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 61,294.97 0.00 2016-11-06 2017-01-01 2017-06-30 solidarios (PC, Printers, cotizaciones Envelope pendiente and Support to Targeted Scanners, UPS y Routers Households para servicios telefónicos y conectividad) Component 2. PSIP-288-CP-B / (Act. Strengthening of the 2.2.1.1.5) Adquisición de Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 12,473.17 0.00 2017-06-12 2017-08-07 2018-02-03 Uniformes para oficiales de cotizaciones Envelope pendiente and Support to Targeted servicios de PS Households Component 2. PSIP-289-CP-B / (Act. Strengthening of the 2.2.1.1.7) Adquisicion de Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 11,500.12 0.00 2016-11-06 2017-01-01 2017-06-30 mobiliario para los puntos cotizaciones Envelope pendiente and Support to Targeted solidarios Households PSIP-57-CP-SGO / (Act. Component 2. 2.2.3.2) Material gastable Strengthening of the para para la Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,052.98 0.00 2017-06-12 2017-08-07 2018-02-03 Implementacion de los 5 cotizaciones Envelope pendiente and Support to Targeted ciclos de Reportes Households Comunitarios en las 14 provincias seleccionadas PSIP-194-CP-B / (Act. 2.3.2.2.1) Adquisición de Component 2. equipos de tecnologia Strengthening of the Solicitud de Single Stage - One Ejecución (desktop, laptop, IBRD / 84790 PROSOLI CCT Program Posterior Limited 22,784.06 0.00 2017-02-06 2017-04-03 2017-09-30 cotizaciones Envelope pendiente multimedia, software y and Support to Targeted equipos de backup y Households almacenamiento, Swich) PSIP-193-CD-S / (Act. Component 2. 2.3.2.2.2) Actualizacion de Strengthening of the licencias del sistema de Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 54,841.70 0.00 2017-06-12 2017-08-07 2018-02-03 mensajeria y correo cotizaciones Envelope pendiente and Support to Targeted electronico para apoyar la Households plataforma Punto Solidario. Component 2. PSIP-74-CP-B / (Act. Strengthening of the 2.3.2.3) Adquisción de Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 16,080.01 0.00 2017-06-12 2017-08-07 2018-02-03 herramientas de seguridad cotizaciones Envelope pendiente and Support to Targeted (Licencias de Antivirus) Households PSIP-77-CD-B / Component 2. (Act.2.3.5.1) Adquisicion de Strengthening of the Adquisición Ejecución la Base de Datos de IBRD / 84790 PROSOLI CCT Program Previa Direct 15,132.85 0.00 2016-05-13 2016-05-18 2016-06-22 2016-12-19 directa pendiente Ciudadanos de la JCE y and Support to Targeted sus actualizaciones por un Households perido de 4 años PSIP-274-CP-B / (Act. 3.2.3.2) Adquisición equipo Component 3. Enhancing informatico para Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 10,122.57 0.00 2017-06-12 2017-08-07 2018-02-03 implementación del cotizaciones Envelope pendiente orientation Observatorio de Políticas Sociales PSIP-006-CP-B / (Act. Component 3. Enhancing 3.3.8.5) Equipos de Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 6,823.70 0.00 2017-06-12 2017-08-07 2018-02-03 Cómputos (Computadores de cotizaciones Envelope pendiente orientation escritorio, Impresoras, UPS) PSIP-005-CP-B / (Act. 3.3.8.6) Materiales y Component 3. Enhancing Suministros (material Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 3,944.81 0.00 2017-06-12 2017-08-07 2018-02-03 gastable de oficina y bultos cotizaciones Envelope pendiente orientation para cargar material de trabajo) Page 2 PSIP-004-CP-B / (Act. 3.3.8.8) Adquisición de Component 3. Enhancing Solicitud de Single Stage - One Ejecución prendas de vestir IBRD / 84790 Equity and Results- Posterior Limited 1,531.56 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones Envelope pendiente (Camisetas para personal de orientation documentación) PSIP-015-CP-B / (Act. Component 3. Enhancing Solicitud de Single Stage - One Ejecución 3.4.2.1.6) Equipos de IBRD / 84790 Equity and Results- Posterior Limited 60,981.91 0.00 2018-06-20 2018-08-15 2019-02-11 cotizaciones Envelope pendiente informatíca para la UTP orientation PSIP-016-CP-B / (Act.3.4.2.2) Adquisicion Component 3. Enhancing Solicitud de Single Stage - One Ejecución Equipos y mobiliarios de IBRD / 84790 Equity and Results- Posterior Limited 28,526.55 0.00 2018-01-13 2018-03-10 2018-09-06 cotizaciones Envelope pendiente oficina UTP (varios procesos orientation de adq.) PSPI-017-CP-B / (Act.3.4.2.4) Material Component 3. Enhancing Gastable (suministro Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 37,827.03 0.00 2016-06-08 2016-08-03 2017-01-30 operativos oficina, papeleria, cotizaciones Envelope pendiente orientation carpetas, papel bond, material de oficina) DO-GCPS-77676-GO-RFB / Component 2. (Act. 2.2.1.1.1) Adquisición Strengthening of the Solicitud de Single Stage - One Ejecución de 2 Unidades Móviles para IBRD / 84790 PROSOLI CCT Program Posterior Open - National 490,000.00 0.00 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-07-17 ofertas Envelope pendiente Brindar los Servicios de and Support to Targeted Puntos Solidarios Households DO-GCPS-78807-GO-RFB / (Act. 2.3.7.1) Adquisición de Component 2. equipo y servidores para Strengthening of the Solicitud de Single Stage - One Ejecución apoyo de bases de datos IBRD / 84790 PROSOLI CCT Program Posterior Open - National 211,627.93 0.00 2018-09-28 2018-10-03 2018-11-14 2018-12-14 2019-01-18 2019-07-17 ofertas Envelope pendiente intermediarios y servicios de and Support to Targeted web para intercambio de Households data entre aplicaciones DO-GCPS-104154-GO-RFQ Component 2. / (Act. 2.3.8) Adquisición de Strengthening of the Solicitud de Single Stage - One Ejecución Licencias para Equipos IBRD / 84790 PROSOLI CCT Program Posterior Open - National 8,300.00 0.00 2019-04-03 2019-05-05 2019-06-04 cotizaciones Envelope pendiente Informáticos para el and Support to Targeted monitoreo del Data Center. Households Component 2. DO-GCPS-104192-GO-RFQ Strengthening of the / (Act. 2.1.3.3.2) Camisetas Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 11,118.12 0.00 2019-04-03 2019-05-29 2019-11-25 para Supervisores Enlaces cotizaciones Envelope pendiente and Support to Targeted Progreando Unidos Households DO-GCPS-104885-GO-RFQ Component 3. Enhancing Solicitud de Single Stage - One Ejecución / (Act. 3.2.5.4) Adquisición IBRD / 84790 Equity and Results- Posterior Limited 50,000.00 0.00 2019-04-05 2019-05-31 2019-11-27 cotizaciones Envelope pendiente de Hardware y Software orientation DO-GCPS-104887-GO-RFQ Component 3. Enhancing Solicitud de Single Stage - One Ejecución / (Act. 3.2.5.5) Adquisición IBRD / 84790 Equity and Results- Posterior Limited 2,000.00 0.00 2019-04-05 2019-05-31 2019-11-27 cotizaciones Envelope pendiente de mobiliario de oficina orientation Component 2. DO-GCPS-105069-GO-RFQ Strengthening of the / (Act. 2.2.1.1.7) Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 18,542.18 0.00 2019-05-05 2019-06-30 2019-12-27 Adquisición de mobiliario cotizaciones Envelope pendiente and Support to Targeted para los puntos solidarios Households Component 2. DO-GCPS-105070-GO-RFQ Strengthening of the Solicitud de Single Stage - One Ejecución / (Act. 2.3.2.2.1) Adquisición IBRD / 84790 PROSOLI CCT Program Posterior Limited 22,000.00 0.00 2019-05-05 2019-06-30 2019-12-27 cotizaciones Envelope pendiente de equipos de tecnología and Support to Targeted Households DO-GCPS-77484-GO-RFB / (Act. 1.3.2.6.5) Equipos y Component 1. Integrated Materiales para las Area-Based Social Solicitud de Single Stage - One Ejecución actividades del IBRD / 84790 Posterior Limited 8,494.00 0.00 2018-11-04 2018-12-30 2019-06-28 Protection and Pro-poor cotizaciones Envelope pendiente Subcomponentes (Adquisición Service Delivery de Tabletas para Supervisión de cursos) DO-GCPS-119186-GO-RFQ Component 1. Integrated / (Act. 1.2.1.9) Adquisición Area-Based Social Solicitud de Single Stage - One Ejecución IBRD / 84790 Posterior Open - National 18,000.00 0.00 2019-06-19 2019-08-14 2020-02-10 de Equipos Informáticos Protection and Pro-poor cotizaciones Envelope pendiente para el Depto. de Service Delivery Infraestructura DO-GCPS-119188-GO-RFQ Component 1. Integrated / (Act. 1.2.1.9 Adquisición Area-Based Social Solicitud de Single Stage - One Ejecución IBRD / 84790 Posterior Open - National 1,800.00 0.00 2019-06-19 2019-08-14 2020-02-10 de Laptop para el Depto. Protection and Pro-poor cotizaciones Envelope pendiente de Infraestructura) Service Delivery Component 2. DO-GCPS-119190-GO-RFQ Strengthening of the / (Ac.t. 2.3.8 Adquisición de Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Open - National 17,500.00 0.00 2019-06-19 2019-08-14 2020-02-10 Switches y Disco Duros cotizaciones Envelope pendiente and Support to Targeted para el Data Center) Households Component 2. DO-GCPS-80781-GO-RFQ / Strengthening of the Solicitud de Single Stage - One (Act. 2.2.1.4) Habilitación IBRD / 84790 PROSOLI CCT Program Posterior Limited 45,000.00 0.00 Cancelado 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope de Punto Solidario and Support to Targeted Households Component 2. DO-GCPS-98430-GO-RFQ / Strengthening of the (Act.2.3.7.1.2.3) Adquisición Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Open - National 73,374.00 0.00 2019-03-05 2019-04-30 2019-10-27 de Licencias y Servidores cotizaciones Envelope pendiente and Support to Targeted para el Data Center Households DO-GCPS-121823-GO-RFB / (Act. 3.3.17) Adquisición de Component 3. Enhancing Solicitud de Single Stage - One Ejecución Vehículos para Monitoreo y IBRD / 84790 Equity and Results- Posterior Open - National 250,000.00 0.00 2019-07-31 2019-08-10 2019-09-09 2019-10-09 2019-11-13 2020-05-11 ofertas Envelope pendiente Evaluación de los Trabajos orientation de campo NON CONSULTING SERVICES Bid Evaluation Activity Reference No. Estimated Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalificatio Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and / Description Component Review Type Method Amount qualification Document / Signed Contract Contract Completion No. Approach Process n (Y/N) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for (US$) Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2. DO-GCPS-78740-NC-RFB / Strengthening of the Solicitud de Single Stage - One Ejecución (Act. 2.2.1.1.4.6) IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,627.24 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope pendiente Reproducción de Materiales and Support to Targeted Households Page 3 Component 2. DO-GCPS-78750-NC-RFB / Strengthening of the Solicitud de Single Stage - One Ejecución (Act. 2.2.1.1.4.10) Mesa de IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,587.08 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope pendiente Ayuda and Support to Targeted Households DO-GCPS-78982-NC-RFB / (Act. 3.3.4.4) Reproducción Component 3. Enhancing de documento de Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 37,500.00 0.00 2018-11-04 2018-12-30 2019-06-28 sistematizacion de buenas cotizaciones Envelope pendiente orientation practicas en la protección social del país DO-GCPS-79020-NC-RFB / (Act. 3.3.9.11) Contratación Component 3. Enhancing de firma para la realización Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 12,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 de un audiovisual cotizaciones Envelope pendiente orientation educativo para las charlas universitarias DO-GCPS-79029-NC-RFB / (Act. 3.3.9.12) Impresión de Component 3. Enhancing Solicitud de Single Stage - One Ejecución volantes, carpetas y creación IBRD / 84790 Equity and Results- Posterior Limited 10,000.00 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope pendiente del contenido para los orientation mismos PSIP-28-CP-SGO / (Act. 2.1.2.3) Logística para la Component 2. Creación de los Comites Strengthening of the Solicitud de Single Stage - One Ejecución Provinciales y capacitación IBRD / 84790 PROSOLI CCT Program Posterior Limited 29,701.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones Envelope pendiente de la estrategia Progresando and Support to Targeted Unidos y del funcionamiento Households de los comites PSIP-195-CP-S / (Act. Component 2. 2.1.3.2.2) Diagramacion y Strengthening of the Solicitud de Single Stage - One Ejecución Reproduccion de los IBRD / 84790 PROSOLI CCT Program Posterior Limited 55,832.00 0.00 2017-12-09 2018-02-03 2018-08-02 cotizaciones Envelope pendiente Manuales (material de and Support to Targeted apoyo) Households PSIP-SNC-001 / (Act. 2.1.3.2.3.4.1) Seminario introductorio a equipo Component 2. SENASA (gerentes Strengthening of the Solicitud de Single Stage - One Ejecución regionales y encargados de IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,000.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones Envelope pendiente afiliaciones) y de INFOTEP and Support to Targeted (asesores y coordinadores de Households oficina) a realizarse en 4 regionales Component 2. PSIP-SNC-002 / (Act. Strengthening of the Solicitud de Single Stage - One Ejecución 2.1.3.2.3.4.1) Seminario IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,000.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones Envelope pendiente introductorio para COS and Support to Targeted Households PSIP-37-CP-S / (Act.2.1.5.1) Component 2. Reproduccion de Materiales Strengthening of the Solicitud de Single Stage - One Ejecución para cambio de IBRD / 84790 PROSOLI CCT Program Posterior Limited 6,400.00 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones Envelope pendiente comportamiento y Escuela and Support to Targeted de Familia Households PSIP-248-CP-SNC / Component 3. Enhancing Solicitud de Single Stage - One Ejecución (Act.3.1.1.1.6) Alquiler de IBRD / 84790 Equity and Results- Posterior Limited 4,760.00 0.00 2017-01-25 2017-03-22 2017-09-18 cotizaciones Envelope pendiente Vehiculos- Piloto Estudio orientation DO-GCPS-97705-NC-RFQ / Component 2. (Act. 2.1.3.1.3) Apoyo al Strengthening of the monitoreo y seguimiento del Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 8,099.61 0.00 2019-02-05 2019-03-28 2019-09-24 cumplimiento de las cotizaciones Envelope pendiente and Support to Targeted corresponsabilidades de Households salud y educación Component 2. DO-GCPS-80502-NC-RFQ / Strengthening of the (Act. 2.2.1.1.2) Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 40,000.00 0.00 2019-07-31 2019-08-05 2019-09-09 2020-03-07 Mantenimiento de las directa pendiente and Support to Targeted Unidades Móviles Households Component 2. DO-GCPS-78747-NC-RFB / Strengthening of the Solicitud de Single Stage - One Ejecución (Act. 2.2.1.1.4.8) Alquiler IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,725.41 0.00 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope pendiente de Vehiculos and Support to Targeted Households PSIP-254-CP-S / (Act. Component 1. Integrated (1.3.1.1.3) Seguro Contra Area-Based Social Solicitud de Single Stage - One Ejecución IBRD / 84790 Posterior Limited 20,000.00 0.00 2016-06-06 2016-08-01 2017-01-28 Accidentes a Jovenes Protection and Pro-poor cotizaciones Envelope pendiente durante la Fase de Service Delivery Pasantia PSIP-CP-SC / (Act. 2.1.3.2.3.3.2) Reproducción de rotafolios de educación Component 2. financiera a ser utilizados Strengthening of the en la capacitación de las Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 8,646.92 0.00 2016-08-27 2016-10-22 2017-04-20 familias beneficiarias de la cotizaciones Envelope pendiente and Support to Targeted 14 provincias priorizadas Households del proyecto Progresando Unidos. Y notarizacion de documento Component 2. PSIP-45-CP-S / (Act. Strengthening of the 2.2.1.1.8) Materiales Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,068.06 0.00 2017-06-06 2017-08-01 2018-01-28 impresos (Brochures, cotizaciones Envelope pendiente and Support to Targeted letreros) Households PSIP-270-CP-S / (Act. 2.2.3.10) Reproduccion de Component 2. guias, cuestionarios y Strengthening of the Solicitud de Single Stage - One Ejecución manuales para la IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,893.57 0.00 2017-06-12 2017-08-07 2018-02-03 cotizaciones Envelope pendiente Implementation de los 5 and Support to Targeted ciclos de los Reportes Households Comunitarios PSIP-005-SC / (Act. 3.3.2.4) Asistencia técnica Component 3. Enhancing para la formulación y Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 15,171.77 0.00 2017-06-12 2017-08-07 2018-02-03 seguimiento a la política de cotizaciones Envelope pendiente orientation reducción de embrazo en adolescentes y desigualdad de género Page 4 DO-GCPS-87346-NC-RFQ / (Act. 3.3.3.1) Experto para la definición y aplicación de Component 3. Enhancing la metodología de la Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 8,565.65 0.00 2017-06-12 2017-08-07 2018-02-03 construcción de una Política cotizaciones Envelope pendiente orientation Publica de Vivienda para Grupos Vulnerables. (pago de pasajes y viátios) PSIP-001-SC / (Act. 3.3.9.2) Pago de 8 boletos Component 3. Enhancing aéreos de asesores Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 6,218.58 0.00 2018-08-14 2018-10-09 2019-04-07 internacionales para el cotizaciones Envelope pendiente orientation diseño de la medición y talleres de transferencia metodológica PSIP-019-CP-SNC / Component 3. Enhancing Solicitud de Single Stage - One Ejecución (Act.3.4.2.16) Transporte y IBRD / 84790 Equity and Results- Posterior Limited 5,258.04 0.00 2018-01-13 2018-03-10 2018-09-06 cotizaciones Envelope pendiente almacenaje orientation DO-GCPS-98409-NC-CDD / (Act. 1.3.1.1.1) 3ra.. Contratación de los Centros Component 1. Integrated Operativos del Sistema Participación de Area-Based Social (COS) para capacitación en IBRD / 84790 Posterior la comunidad en Open - National 2,700,000.00 0.00 En ejecución 2019-02-28 2019-03-05 2019-04-16 2019-05-16 2019-06-20 2019-12-17 Protection and Pro-poor competencias básicas y las adquisiciones Service Delivery habilidades técnicas dirigidos a los jóvenes beneficiarios del Proyecto PSIP-111-PS-CDD / (Act. 1.3.1.1.1) 2da. Contratación de los Centros Operativos Component 1. Integrated del Sistema (COS) para Participación de Area-Based Social capacitación en competencias IBRD / 84790 Previa la comunidad en Open - National 3,431,183.00 0.00 En ejecución 2017-12-15 2017-12-20 2018-01-31 2018-03-02 2018-04-06 2018-10-03 Protection and Pro-poor básicas y habilidades las adquisiciones Service Delivery técnicas dirigidos a los jóvenes beneficiarios del Proyecto DO-GCPS-104210-NC-RFQ / Servicios de Alquiler de Vehículos para continuidad Component 3. Enhancing Solicitud de Single Stage - One Ejecución del Levantamiento del IBRD / 84790 Equity and Results- Posterior Limited 76,800.00 0.00 2019-03-09 2019-03-25 2019-09-21 cotizaciones Envelope pendiente 3ESH (Regional Distrito orientation Nacional, Santo Domingo y Este) DO-GCPS-104211-NC-RFQ / Servicios de Alquiler de Vehículos para la Component 3. Enhancing Solicitud de Single Stage - One Ejecución realización de la IBRD / 84790 Equity and Results- Posterior Limited 77,200.00 0.00 2019-03-09 2019-03-25 2019-09-21 cotizaciones Envelope pendiente continuidad del orientation Levantamiento del 3ESH (Regional: Nordeste, Central, Norcentral y Noroeste) DO-GCPS-104212-NC-RFQ / Servicios de Vehículos para la realización de la Component 3. Enhancing Solicitud de Single Stage - One Ejecución continuidad del IBRD / 84790 Equity and Results- Posterior Limited 50,400.00 0.00 2019-03-09 2019-03-25 2019-09-21 cotizaciones Envelope pendiente Levantamiento del 3ESH orientation (Regional: El Valle, Enriquillo y Valdesia) DO-GCPS-104847-NC-RFQ / Component 3. Enhancing Solicitud de Single Stage - One Ejecución (Act. 3.2.1.2.4.3.1) Alquiler IBRD / 84790 Equity and Results- Posterior Limited 43,333.33 0.00 2019-04-05 2019-05-31 2019-11-27 cotizaciones Envelope pendiente de vehículo orientation Component 2. DO-GCPS-105067-NC-RFQ / Strengthening of the (Act. 2.2.1.1.5) Adquisición Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 3,000.00 0.00 2019-05-05 2019-06-30 2019-12-27 de Uniformes para oficiales cotizaciones Envelope pendiente and Support to Targeted de servicios de PS Households PSIP-11-PS-CDD / (Act. 1.3.1.1.1) 1ra. Contratación de los Centros Operativos Component 1. Integrated del Sistema (COS) para Participación de Area-Based Social Ejecución capacitación en competencias IBRD / 84790 Previa la comunidad en Open - National 505,236.83 0.00 2016-06-01 2016-06-06 2016-07-18 2016-08-17 2016-09-21 2017-03-20 Protection and Pro-poor pendiente básicas y habilidades las adquisiciones Service Delivery técnicas dirigidos a los jóvenes beneficiarios del Proyecto DO-GCPS-116956-NC-RFQ / Component 2. (Act. 2.1.3.6.1) Capacitación Strengthening of the Personal Operativo de Solicitud de Single Stage - One Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Limited 70,000.00 0.00 2019-07-05 2019-08-30 2020-02-26 PROSOLI en la Estrategia cotizaciones Envelope pendiente and Support to Targeted de Cambio de Households Comportamiento en Higiene DO-GCPS-107009-NC-RFB / Component 2. (Act. 2.1.3.6.1) Capacitación Strengthening of the Personal Operativo de Solicitud de Single Stage - One IBRD / 84790 PROSOLI CCT Program Posterior Open - National 100,000.00 0.00 Cancelado 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2020-01-17 PROSOLI en la Estrategia ofertas Envelope and Support to Targeted de Cambio de Households Comportamiento en Higiene DO-GCPS-116959-NC-RFQ / (Act. 3.2.1.2.3) Component 3. Enhancing Levantamiento de Linea de Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 100,000.00 0.00 2019-06-05 2019-07-31 2020-01-27 Base para la Evaluación del cotizaciones Envelope pendiente orientation Impacto del subcomponente 1.2 (Mejora de Vivienda) DO-GCPS-106709-NC-RFP / (Act. 3.2.1.2.3) Levantamiento de Linea de Component 3. Enhancing Pedido de Single Stage - One Base para la Evaluación IBRD / 84790 Equity and Results- Posterior Open - National 100,000.00 0.00 Cancelado 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2020-01-17 propuestas Envelope del Impacto del orientation subcomponente 1.2 (Mejora de Vivienda) DO-GCPS-116962-NC-RFQ / (Act. 3.2.1.3.2) Component 3. Enhancing Levantamiento de Linea Solicitud de Single Stage - One Ejecución IBRD / 84790 Equity and Results- Posterior Limited 100,000.00 0.00 2019-06-05 2019-07-31 2020-01-27 Base para la Evaluación cotizaciones Envelope pendiente orientation Subcomponente 1.3 (Capacitación DO-GCPS-106713-NC-RFP / (Act. 3.2.1.3.2) Levantamiento de la Component 3. Enhancing Pedido de Single Stage - One Linea Base para la IBRD / 84790 Equity and Results- Posterior Open - National 100,000.00 0.00 Cancelado 2019-03-31 2019-04-05 2019-05-17 2019-06-16 2019-07-21 2020-01-17 propuestas Envelope Evaluación del orientation Subcomponente 1.3 (Capacitación) Page 5 Component 2. DO-GCPS-119196-NC-DIR / Strengthening of the (Act. 2.2.1.3.1) Curso Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 2,600.00 0.00 2019-06-16 2019-06-17 2019-06-27 2019-12-24 Certificación Servicio al directa pendiente and Support to Targeted Cliente Households Component 2. DO-GCPS-119197-NC-DIR / Strengthening of the (Act. 2.3.6.3) Curso Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 2,600.00 0.00 2019-06-14 2019-06-15 2019-06-25 2019-12-22 Certificación en Servicio al directa pendiente and Support to Targeted Cliente Households DO-GCPS-119238-NC-DIR / Component 3. Enhancing (Act. 3.3.2.6) Diplomado en Adquisición Ejecución IBRD / 84790 Equity and Results- Posterior Direct 2,770.00 0.00 2019-06-14 2019-06-19 2019-07-24 2020-01-20 Análisis y Diseño de directa pendiente orientation Políticas Públicas DO-GCPS-119441-NC-RFQ / Component 2. (Act. 2.1.2.2.2) Impresiones Strengthening of the Solicitud de Single Stage - One Ejecución de Manuales para la IBRD / 84790 PROSOLI CCT Program Posterior Limited 1,665.00 0.00 2019-11-05 2019-12-31 2020-06-28 cotizaciones Envelope pendiente capacitación de los Comités and Support to Targeted Provinciales y Regionales Households DO-GCPS-77489-NC-RFB / (Act. 2.1.2.2) Diagramación, Revisión e Impresión Component 2. manuales para la creación Strengthening of the Solicitud de Single Stage - One de los comités y IBRD / 84790 PROSOLI CCT Program Posterior Limited 19,665.00 0.00 Cancelado 2018-11-04 2018-12-30 2019-06-28 cotizaciones Envelope capacitación de la estrategia and Support to Targeted Progresando Unidos y del Households funcionamiento de los comités DO-GCPS-121889-NC-DIR / Component 2. (Act. 2.2.1.4) Habilitación de Strengthening of the Punto Solidario en el Adquisición Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Direct 45,000.00 0.00 2019-07-31 2019-08-05 2019-09-09 2020-03-07 Centro de Atención directa pendiente and Support to Targeted Presidencial para el Households Ciudadano, Punto GOB Component 2. DO-GCPS-78787-NC-RFB / Strengthening of the (Act. 2.2.3.8) Publicación Solicitud de Single Stage - One IBRD / 84790 PROSOLI CCT Program Posterior Limited 6,667.00 0.00 Cancelado 2018-11-04 2018-12-30 2019-06-28 de los resultados de los cotizaciones Envelope and Support to Targeted Reportes Comunitarios Households DO-GCPS-122288-NC-RFQ / (Act. 3.2.3.3.3) Impresión de Component 3. Enhancing Solicitud de Single Stage - One Ejecución Publicaciones del IBRD / 84790 Equity and Results- Posterior Open - National 4,700.00 0.00 2019-07-15 2019-09-09 2020-03-07 cotizaciones Envelope pendiente Observatorio de Políticas orientation Sociales DO-GCPS-127345-NC-CDD / (Act. 1.3.1.1.1) 4Ta Licitación - Contratación de los Centros Operativos del Component 1. Integrated Participación de Sistema (COS, para la Area-Based Social Ejecución IBRD / 84790 Previa la comunidad en Open - National 2,670,000.00 0.00 2019-08-15 2019-09-02 2019-10-02 2019-11-01 2019-12-06 2020-06-03 capacitación en competencias Protection and Pro-poor pendiente las adquisiciones básicas y habilidades Service Delivery técnicas dirigidas a los jóvenes beneficiarios del Proyecto CONSULTING FIRMS Activity Reference No. Actual Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Process Expression of Request for Opening of Technical Evaluation of / Description Component Review Type Method Amount Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Status Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal (US$) Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PIPPS-163-2016 / Component 1. Integrated PROCESO DE AGENTE Area-Based Social Selección basada Open - IBRD / 84790 Previa 197,810.00 197,810.00 Cancelado VERIFICADOR Protection and Pro-poor en calidad International INDEPENDIENTE Service Delivery DO-GCPS-78790-CS-QCBS / Component 2. (Act. 2.3.1.2) Contratación Strengthening of the Selección basada Open - Ejecución de Firma Consultora para IBRD / 84790 PROSOLI CCT Program Posterior en calidad y 226,666.67 0.00 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2020-04-08 International pendiente mejorar la plataforma Punto and Support to Targeted costo Solidario Households DO-GCPS-78953-CS-QCBS / (Act. 3.3.2.2.5) Diseño de la Component 3. Enhancing Selección basada campaña de educación Ejecución IBRD / 84790 Equity and Results- Posterior en calidad y Open - National 80,000.00 0.00 2018-10-30 2018-11-20 2019-01-03 2019-01-31 2019-03-02 2019-04-06 2019-05-11 2020-05-10 ciudadana par la inclusión pendiente orientation costo laboral de personas con discapacidad. DO-GCPS-85684-CS-QCBS / (Act. 2.3.2.1) dquisición e Implantación de una solución tipo IVR para Component 2. enviar SMS a los Strengthening of the Selección basada Ejecución Beneficiarios, realizar IBRD / 84790 PROSOLI CCT Program Posterior en calidad y Open - National 210,120.00 0.00 2018-11-30 2018-12-21 2019-02-03 2019-03-03 2019-04-02 2019-05-07 2019-06-11 2020-06-10 pendiente encuestas de satisfacción, and Support to Targeted costo como también permitir que Households los ciudadanos puedan consultar el estatus de sus trámites, quejas, reclamos y solicitudes DO-GCPS-78802-CS-QCBS / (Act. 2.3.6.2) Implementar Component 2. un Sistema de Strengthening of the Selección basada DataWarehouse para manejo Ejecución IBRD / 84790 PROSOLI CCT Program Posterior en calidad y Open - National 190,100.00 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-04 2019-06-03 2019-07-08 2019-08-12 2020-08-11 de indicadores y cuadro de pendiente and Support to Targeted costo mando integral basado en Households la plataforma de intercambio de datos interinstitucional DO-GCPS-80902-CS-QCBS / Component 3. Enhancing Selección basada (Act. 3.2.1.2.4) Realizar la Ejecución IBRD / 84790 Equity and Results- Posterior en calidad y Open - National 307,500.00 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-04 2019-06-03 2019-07-08 2019-08-12 2020-08-11 Intervención y Monitoreo de pendiente orientation costo Intervención PSIP-182-SBCC-SC / Component 3. Enhancing Selección basada (Act.3.4.3.1) Auditoria Ejecución IBRD / 84790 Equity and Results- Posterior en calidad y Open - National 32,051.33 0.00 2016-01-03 2016-01-24 2016-03-08 2016-04-05 2016-05-05 2016-06-09 2016-07-14 2017-07-14 financiera externa fondos pendiente orientation costo del Proyecto PSIP-183-SCC-SC / (Act. Component 3. Enhancing Selección basada 3.4.3.2) Agente Verificador Open - Ejecución IBRD / 84790 Equity and Results- Previa en calidad y 199,971.00 0.00 2016-01-03 2016-01-24 2016-03-08 2016-04-05 2016-05-05 2016-06-09 2016-07-14 2017-07-14 Indpendiente de los fondos International pendiente orientation costo componente 1.1 del Proyecto Page 6 DO-GCPS-117424-CS-CQS / (Act. 3.3.2.9.1) Consultoría Component 3. Enhancing Selección basada para Elaboración del Diseño Ejecución IBRD / 84790 Equity and Results- Posterior en calificaciones Open - National 55,000.00 0.00 2019-05-31 2019-06-21 2019-08-04 2019-09-03 2019-10-08 2020-04-05 Curricular para Clases de pendiente orientation de consultores Competencia comunicativas de Español a Inmigrantes DO-GCPS-117426-CS-CQS / (Act. 3.3.2.9.2) Consultoría Component 3. Enhancing Selección basada para la Implementación de Ejecución IBRD / 84790 Equity and Results- Posterior en calificaciones Open - National 55,000.00 0.00 2019-05-31 2019-06-21 2019-08-04 2019-09-03 2019-10-08 2020-04-05 Clases de Competencias pendiente orientation de consultores Comunicativas de Español a Inmigrantes DO-GCPS-77504-CS-QCBS / Component 2. (Act. 2.1.3.4) Consultoría Strengthening of the Selección basada para la Revisión de los Open - IBRD / 84790 PROSOLI CCT Program Posterior en calidad y 35,204.96 0.00 Cancelado 2018-09-28 2018-10-19 2018-12-02 2018-12-30 2019-01-29 2019-03-05 2019-04-09 2020-04-08 procesos transversales y International and Support to Targeted costo descentralizados de Households PROSOLI DO-GCPS-122267-CS-QCBS / (Act. 3.2.1.3.3) Realizar la Component 3. Enhancing Selección basada Ejecución Intervención y Monitoreo de IBRD / 84790 Equity and Results- Posterior en calidad y Open - National 241,000.00 0.00 2019-07-31 2019-08-21 2019-10-04 2019-11-01 2019-12-01 2020-01-05 2020-02-09 2021-02-08 pendiente Intervención Subcomponente orientation costo 1.3 (Capacitación) DO-GCPS-80931-CS-QCBS / Component 3. Enhancing Selección basada (Act. 3.2.2.3.3) Desarrollo Ejecución IBRD / 84790 Equity and Results- Posterior en calidad y Open - National 130,000.00 0.00 2019-01-31 2019-02-21 2019-04-06 2019-05-04 2019-06-03 2019-07-08 2019-08-12 2020-08-11 de la Plataforma pendiente orientation costo Informática del SIME INDIVIDUAL CONSULTANTS Activity Reference No. Actual Invitation to Loan / Credit Market Contract Type Estimated Process Draft Negotiated / Description Component Review Type Method Amount Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Status Contract (US$) Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PIPPS-125-2017 / Component 1. Integrated Recontratacion directa del Area-Based Social Selección directa Personal de la Unidad IBRD / 84790 Previa Direct 0.00 49,734.34 Firmado Protection and Pro-poor de consultores Tecnica del Proyecto (UTP) Service Delivery - Gavino Severino Berroa Component 1. Integrated PIPPS-083-2016 / Area-Based Social Selección directa Recontratacion de IBRD / 84790 Previa Direct 0.00 2,977.13 Cancelado Protection and Pro-poor de consultores Digitadores Service Delivery Component 1. Integrated PIPPS-061-2016 / Area-Based Social Selección directa Recontratacion de Personal IBRD / 84790 Previa Direct 0.00 158,693.42 Firmado Protection and Pro-poor de consultores de la UTP Service Delivery PIPPS-694-2017 / Contratacion directa y Component 3. Enhancing Selección directa recontratacion del personal IBRD / 84790 Equity and Results- Previa Direct 145,659.45 189,769.00 Firmado de consultores de la Unidad Tecnica del orientation Proyecto UTP DO-GCPS-77451-CS-INDV / (Act. 1.3.2.1.5) Consultoría Individual para Adecuación Component 1. Integrated de Cursos de Capacitación Area-Based Social Ejecución de acuerdo a las familias IBRD / 84790 Posterior Individual Open 40,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Protection and Pro-poor pendiente ocupacionales con mayor Service Delivery demanda de capacitacion (en base al estudio de Demanda Laboral) DO-GCPS-77454-CS-INDV / (Act. 1.3.2.5) Consultoría Component 1. Integrated Individual para Revisión y Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 40,000.46 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Adecuación de la Oferta Protection and Pro-poor pendiente Curricular del INFOTEP Service Delivery para grupos vulnerables DO-GCPS-77458-CS-INDV / (Act. 1.3.2.6.2) Consultoría Component 1. Integrated para la Implementación de Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 20,210.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Mejoras al sistema Protection and Pro-poor pendiente Informático de PROSOLI. Service Delivery Modulo Progresando Unidos DO-GCPS-77485-CS-INDV / (Act. 1.3.3.1) Diagnóstico Component 1. Integrated sobre mejores prácticas Area-Based Social Ejecución internacionales autoempleo IBRD / 84790 Posterior Individual Open 35,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Protection and Pro-poor pendiente para la definición de una Service Delivery estrategia de micro emprendimiento DO-GCPS-78713-CS-INDV / (Act. 1.3.2.6.6.1) Asistente Contable 1 para apoyo a Component 1. Integrated la Dirección de Capacitación Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 20,800.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 de PROSOLI para gestión Protection and Pro-poor pendiente de pagos a jóvenes de los Service Delivery Centros Operativos del Sistema (COS) DO-GCPS-78714-CS-INDV / (Act. 1.3.2.6.6.2) Asistente Contable 2 para apoyo a la Component 1. Integrated Dirección de Capacitación Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 20,800.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 de PROSOLI para gestión Protection and Pro-poor pendiente de pagos a jóvenes de los Service Delivery Centros Operativos del Sistema (COS) DO-GCPS-78720-CS-INDV / (Act. 1.3.3.2.4) Apoyo Component 1. Integrated Soporte Técnico para Enlace Area-Based Social Ejecución Operativo de Santo IBRD / 84790 Posterior Individual Open 20,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Protection and Pro-poor pendiente Domingo y el Distrito Service Delivery Nacional para la implementación de proceso de capacitación. DO-GCPS-78766-CS-INDV / Component 2. (Act. 2.2.2.2.1) Apoyo Strengthening of the Técnico para la IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 50,000.00 0.00 En ejecución 2018-10-10 2018-11-28 2018-12-19 2019-01-23 2019-07-22 digitalización y la and Support to Targeted sistematización de data. Households Page 7 DO-GCPS-78782-CS-INDV / Component 2. (Act. 2.2.2.2.5)Desarrollo e Strengthening of the Implementación Piloto de Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 7,500.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Reportes Comunitarios pendiente and Support to Targeted vinculados a Puntos Households Solidarios Component 2. DO-GCPS-78789-CS-INDV / Strengthening of the Ejecución (Act. 2.2.3.11) Evaluación IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 17,500.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 pendiente de Reportes Comunitarios and Support to Targeted Households DO-GCPS-78826-CS-INDV / (Act. 3.2.2.1) Actualización Component 3. Enhancing Ejecución del inventario de los IBRD / 84790 Equity and Results- Posterior Individual Open 50,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 pendiente programas de protección orientation social. DO-GCPS-78828-CS-INDV / (Act. 3.2.2.3.1) Diseño Component 3. Enhancing conceptual de la segunda IBRD / 84790 Equity and Results- Posterior Individual Open 40,000.00 0.00 En ejecución 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 fase del SIME (tablero de orientation control, 9 entidades adscritas) DO-GCPS-78833-CS-INDV / Component 3. Enhancing (Act. 3.3.1.1) Fortalecimiento Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 40,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 de la Institucionalidad pendiente orientation social. DO-GCPS-78837-CS-INDV / (Act. 3.3.1.2) Facilitador Component 3. Enhancing Ejecución proceso consulta para la IBRD / 84790 Equity and Results- Posterior Individual Open 40,000.00 0.00 2019-02-08 2019-03-29 2019-04-19 2019-05-24 2019-11-20 pendiente reformas en protección orientation social DO-GCPS-78838-CS-INDV / (Act. 3.3.1.3) Consultores Individuales para el Component 3. Enhancing Ejecución fortalecimiento de la IBRD / 84790 Equity and Results- Posterior Individual Open 50,000.00 0.00 2018-10-29 2018-12-17 2019-01-07 2019-02-11 2019-08-10 pendiente implementacion de la orientation estrategia integral de Protección Social. DO-GCPS-78839-CS-INDV / (Act. 3.3.1.4) Diseño e Component 3. Enhancing implementación la Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 25,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 plataforma virtual del pendiente orientation inventario nacional de programas sociales DO-GCPS-78967-CS-INDV / (Act. 3.3.2.6) Asistencia Técnica para formulación y Component 3. Enhancing seguimiento de políticas Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 55,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 para cerrar brechas sociales, pendiente orientation desigualdad de genero e iniquidad de derechos humanos. DO-GCPS-78969-CS-CDS / Component 3. Enhancing Selección directa Ejecución (Act. 3.3.2.7) Taller Sobre IBRD / 84790 Equity and Results- Previa Direct 45,000.00 0.00 2018-09-28 2018-10-08 2018-12-12 2019-06-10 de consultores pendiente Teoría de Cambio orientation DO-GCPS-78974-CS-INDV / (Act. 3.3.4.3) Definición de metodología para Component 3. Enhancing Ejecución identificación y IBRD / 84790 Equity and Results- Posterior Individual Open 50,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente sistematización de buenas orientation practicas en la protección social del país DO-GCPS-78994-CS-INDV / (Act. 3.3.9.5) Contratación Component 3. Enhancing Ejecución de consultoría para IBRD / 84790 Equity and Results- Posterior Individual Open 31,512.61 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente implementación de orientation evaluación (sociólogo) DO-GCPS-78996-CS-INDV / (Act. 3.3.9.6) Contratación Component 3. Enhancing Ejecución de consultoría para IBRD / 84790 Equity and Results- Posterior Individual Open 31,512.60 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente implementación de orientation evaluación (psicólogo) DO-GCPS-80719-CS-INDV / Component 1. Integrated (Act. 1.3.2.6.3) Consultoría Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 24,700.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 para la Vinculación Protection and Pro-poor pendiente Empresarial de PROSOLI Service Delivery DO-GCPS-80928-CS-INDV / (Act. 3.2.3.3.4) Consultoría Component 3. Enhancing Individual De Apoyo Técnico Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 20,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 de Investigación al pendiente orientation Observatorio de Políticas Sociales del GCPS DO-GCPS-81089-CS-INDV / (Act. 3.3.2.2.2) Apoyo al Component 3. Enhancing Ejecución desarrollo de políticas IBRD / 84790 Equity and Results- Posterior Individual Open 20,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente sectoriales de la Agenda de orientation Discapacidad PSIP-8-3CV-CI / (Act. 1.2.1.3) Apoyo a la Coordinacion Tecnica del Component 1. Integrated Proyecto de Mejoramiento Area-Based Social Ejecución de Viviendas (cambio piso IBRD / 84790 Previa Individual Limited 113,092.00 0.00 2016-01-01 2016-01-06 2016-01-27 2016-03-02 2016-08-29 Protection and Pro-poor pendiente tierra por cemento) de los Service Delivery Hogares en Extrema Pobreza en la Republica Dominicana PSIP-3CV-CI / (Act.1.2.1.5) Encargados Regionales de Component 1. Integrated Apoyo a la Unidad de Area-Based Social IBRD / 84790 Previa Individual Open 248,145.00 0.00 En ejecución 2016-01-06 2016-02-24 2016-03-16 2016-04-20 2016-10-17 Infraestructura Social (6 Protection and Pro-poor encargados - todos los lotes Service Delivery -empresas y ONGs PSIP-22-3CV-CI / (Act. Component 1. Integrated 1.3.3.2.1) Apoyo Técnico Area-Based Social Ejecución Administrativo a PROSOLI IBRD / 84790 Previa Individual Open 47,265.00 0.00 2016-03-01 2016-04-19 2016-05-10 2016-06-14 2016-12-11 Protection and Pro-poor pendiente para la implementacion del Service Delivery proceso de capacitacion Page 8 PSIP-257-3CV-CI / (Act. 2.1.2.1) Actualización del Reglamento de Component 2. Funcionamiento de los Strengthening of the Ejecución Comités Regionales y IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 10,011.00 0.00 2015-12-03 2015-12-08 2015-12-29 2016-02-02 2016-07-31 pendiente Municipales del Prosoli y and Support to Targeted Elaboración del Contenido Households de Manuales de Capacitación para los Comités PSIP-186-3CV-CI / (Act. 2.1.3.2.1) Actualización y elaboración del material de Component 2. apoyo y la guía del Strengthening of the facilitador, para la Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 20,000.00 0.00 2016-02-03 2016-02-08 2016-02-29 2016-04-04 2016-10-01 implementación de la pendiente and Support to Targeted capacitación operativa del Households personal de campo en las provincias del Proyecto Progresando Unidos PSIP-192-3CV-CI / (Act. 2.1.3.2.3.3.4) Contratacion de Component 2. 14 digitadores para el Strengthening of the Ejecución Procesamiento de la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 3,231.00 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 pendiente informacion obtenida de la and Support to Targeted ficha y alimentacion de la Households Base de datos PSIP-292-3CV-CI / (Act. 2.1.3.2.4.2) Consultor Component 2. Individual Senior para Strengthening of the Ejecución Monitoreo y Seguimiento al IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 20,000.00 0.00 2017-07-03 2017-07-08 2017-07-29 2017-09-02 2018-03-01 pendiente proceso de Capacitacion and Support to Targeted Operativa al personal de Households Campo Supervisores PSIP-293-3CV-CI / (Act.2.1.3.2.4.3) Consultor Component 2. Individual Junior para Strengthening of the Ejecución Monitoreo y Seguimiento al IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 10,000.00 0.00 2017-08-01 2017-08-06 2017-08-27 2017-10-01 2018-03-30 pendiente proceso de Capacitacion and Support to Targeted Operativa al personal de Households Campo Supervisores PSIP-040-3CV-CI / (Act. 2.2.1.3.2) Implementacion de plataforma de educacion Component 2. virtual para la capacitacion, Strengthening of the Ejecución seguimiento y desarrollo de IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 25,000.00 0.00 2017-09-01 2017-09-06 2017-09-27 2017-11-01 2018-04-30 pendiente habilidades de los and Support to Targeted representantes de servicio al Households cliente, personal soporte de los Puntos Solidarios PSIP-315-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.1.1.1.5) Pago aplicacion IBRD / 84790 Equity and Results- Posterior Individual Limited 7,865.00 0.00 2016-08-26 2016-08-31 2016-09-21 2016-10-26 2017-04-24 pendiente fichas - Piloto Estudio orientation PSIP-276-3CV-CI / (Act. 3.1.1.2.2.4.1) Consultor para Component 3. Enhancing el diseno del Plan de IBRD / 84790 Equity and Results- Posterior Individual Limited 2,974.00 0.00 En ejecución 2017-02-20 2017-02-25 2017-03-18 2017-04-22 2017-10-19 Medios de la Campana de orientation Comunicaciones ESH2017 PSIP-227-3CV-CI / (Act. 3.2.3.1.1) Consultoria individual No.1 para el Component 3. Enhancing Ejecución diseño e implementación del IBRD / 84790 Equity and Results- Posterior Individual Limited 29,418.00 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 pendiente portal WEB del orientation Observatorio de Políticas Sociales PSIP-280-CD-CI / (Act.3.3.2.1) Diseño y Component 3. Enhancing Selección directa Ejecución Elaboración del Manual IBRD / 84790 Equity and Results- Previa Direct 43,250.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 de consultores pendiente Operativo para el proyecto orientation Progresando Unidos PSIP-025-CD-SC / (Act. 3.3.4.6.1 ) Asesoria Tecnica para la Implemntacion y Component 3. Enhancing Configuracion de Dspace Selección directa Ejecución IBRD / 84790 Equity and Results- Previa Direct 5,400.00 0.00 2018-05-01 2018-05-11 2018-07-15 2019-01-11 como Plataforma Tecnologica de consultores pendiente orientation para la Creacion del Repositorio Institucional (RI) INTEC PSIP-026-3CV-CI / (Act. 3.3.4.6.2) Consultoria Component 3. Enhancing Individual Nacional de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 4,660.00 0.00 2018-06-30 2018-08-18 2018-09-08 2018-10-13 2019-04-11 Apoyo Informatico para el pendiente orientation DIseño e Implementacion del Repositorio Institucioinal PSIP-027-3CV-CI / (Act. 3.3.5.1.1) Consultoría para Component 3. Enhancing el diseño e inventario Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 8,700.00 0.00 2016-06-01 2016-06-06 2016-06-27 2016-08-01 2017-01-28 inicial del Centro de pendiente orientation Documentación de Políticas Sociales PSIP-002-3CV-CI / (Act. Component 3. Enhancing 3.3.9.4) Contratación de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 38,000.00 0.00 2018-08-28 2018-09-02 2018-09-23 2018-10-28 2019-04-26 consultoría para la pendiente orientation aplicación de la línea base. PSIP-199-CD-CI / Component 3. Enhancing Selección directa Ejecución (Act.3.4.1.3) Especialista IBRD / 84790 Equity and Results- Previa Direct 88,274.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Financiero orientation PSIP-201-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.7) Consultor en IBRD / 84790 Equity and Results- Previa Direct 43,274.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Tecnologia orientation PSIP-208-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.8) Apoyo Logistico de IBRD / 84790 Equity and Results- Previa Direct 13,332.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Oficina/Asistente Financiero orientation Component 3. Enhancing PSIP-206-CD-CI / (Act. Selección directa Ejecución IBRD / 84790 Equity and Results- Previa Direct 43,271.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 3.4.1.13) Analista Financiero de consultores pendiente orientation PSIP-010-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.18) Oficial de IBRD / 84790 Equity and Results- Previa Direct 27,160.00 0.00 2018-04-01 2018-04-11 2018-06-15 2018-12-12 de consultores pendiente Adquisiciones orientation Page 9 PSIP-013-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.22) Analista IBRD / 84790 Equity and Results- Previa Direct 19,015.00 0.00 2018-01-01 2018-01-11 2018-03-17 2018-09-13 de consultores pendiente Financiero 2 orientation PSIP-008-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.25) Asesora de IBRD / 84790 Equity and Results- Previa Direct 12,474.00 0.00 2018-03-01 2018-03-11 2018-05-15 2018-11-11 de consultores pendiente Adquisiciones BM orientation DO-GCPS-77448-CS-INDV / (Act. 1.3.2.1.4) Consultoría Component 1. Integrated Individual Internacional Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 60,000.00 0.00 2018-09-27 2018-11-15 2018-12-06 2019-01-10 2019-07-09 para Asistencia Técnica al Protection and Pro-poor pendiente INFOTEP para Estudio de Service Delivery Demanda Laboral DO-GCPS-80896-CS-INDV / (Act. 3.2.1.1) Evaluación de Component 3. Enhancing Ejecución Procesos de las IBRD / 84790 Equity and Results- Posterior Individual Open 11,250.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 pendiente Intervenciones de la orientation Estrategia territoral DO-GCPS-80724-CS-INDV / (Act. 1.3.3.2.5) Apoyo Component 1. Integrated Soporte Técnico para Enlace Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,000.00 0.00 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 Operativo en la Región Sur Protection and Pro-poor pendiente para la implementación de Service Delivery proceso de capacitacion PSIP-6-3CV-CI / (Act. Component 1. Integrated 1.2.1.2.1) Supervisores de Area-Based Social obra en apoyo a la a IBRD / 84790 Previa Individual Open 128,142.13 0.00 En ejecución 2017-01-06 2017-02-24 2017-03-17 2017-04-21 2017-10-18 Protection and Pro-poor Unidad de Infr. Social (30 Service Delivery supervisores) DO-GCPS-87196-CS-INDV / (Act. 1.3.2.3) Coordinador Component 1. Integrated Técnico para el Monitoreo y Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 24,870.92 0.00 2016-06-01 2016-07-20 2016-08-10 2016-09-14 2017-03-13 Seguimiento de las Protection and Pro-poor pendiente Actividades de capacitación Service Delivery del Subcomponente PSIP-232-3CV-CI / (Act. 1.3.3.2.2) Apoyo Tec. Component 1. Integrated Operativo a PROSOLI para Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,821.53 0.00 2016-10-11 2016-11-29 2016-12-20 2017-01-24 2017-07-23 la imp. Del proceso de Protection and Pro-poor pendiente capacitacion en la Regional Service Delivery Sto Dgo y D.N. PSIP-233-3CV-CI / (Act. 1.3.3.2.3) Apoyo Soporte Component 1. Integrated Técnico para Enlace Area-Based Social Ejecución Operativo en las gerencias IBRD / 84790 Posterior Individual Open 16,420.29 0.00 2016-10-11 2016-11-29 2016-12-20 2017-01-24 2017-07-23 Protection and Pro-poor pendiente del INFOTEP de la Regiion Service Delivery Sur para la implementacion del proceso de capacitacion PSIP- 3CV-CI / (Act. Component 2. 2.1.3.1.4) Consultoria Strengthening of the Individual Coordinadora Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 31,158.69 0.00 2017-10-12 2017-10-17 2017-11-07 2017-12-12 2018-06-10 para el Seguimiento de las pendiente and Support to Targeted Operaciones de Progresando Households Unidos Component 2. PSIP-29-3CV-CI / (Act. Strengthening of the 2.2.1.1.4.11) Consultoria Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 8,215.09 0.00 2018-03-05 2018-04-23 2018-05-14 2018-06-18 2018-12-15 Analista de Informacion pendiente and Support to Targeted para Punto Solidario Households PSIP-022-3CV-CI / (Act. 2.2.2.1.1) Consultoria Indvidual para el Apoyo Component 2. técnico a la coordinación de Strengthening of the Ejecución Actividades de la Dirección IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 19,548.47 0.00 2015-12-23 2015-12-28 2016-01-18 2016-02-22 2016-08-20 pendiente de Vinculación and Support to Targeted Interinstitucional en el Households marco del Proyecto Progresando Unidos PSIP-225-3CV-CI / (Act. 2.2.2.2.4) Diseño Conceptual Component 2. y Desarrollo de la Strengthening of the Ejecución Plataforma Informática para IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 13,912.28 0.00 2017-11-01 2017-12-20 2018-01-10 2018-02-14 2018-08-13 pendiente la recopilación, análisis y and Support to Targeted publicación de Reportes Households Comunitarios Digitales. PSIP-56-3CV-CI / (Act. 2.2.3.1) Apoyo Técnico Administrativo -- (Apoyo Component 2. Técnico y Administrativo en Strengthening of the Ejecución Actividades de Dirección de IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 15,700.00 0.00 2016-06-01 2016-06-06 2016-06-27 2016-08-01 2017-01-28 pendiente Vinculación and Support to Targeted Interinstitucional del Prosoli Households en el marco del Proyecto Progresando Unidos) PSIP-58-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo para Strengthening of the el apoyo técnico a la Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 17,165.77 0.00 2017-06-07 2017-07-26 2017-08-16 2017-09-20 2018-03-19 implementación de los pendiente and Support to Targeted Reportes Comunitarios, Households Distrito Nacional - Santo Domingo PSIP-030-3CV-CI / (Act. 2.3.1.1.1) consultoria para Component 2. elaboracion de Protocolos, Strengthening of the Ejecución Politicas, Convenios y IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 20,576.40 0.00 2016-04-01 2016-05-20 2016-06-10 2016-07-15 2017-01-11 pendiente Colaboracion and Support to Targeted Interinstitucional que Households regiran la Interoperabilidad Component 2. PSIP-71-3CV-CI / (Act. Strengthening of the 2.3.1.3.3) Contratación de Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 28,263.39 0.00 2016-08-01 2016-08-06 2016-08-27 2016-10-01 2017-03-30 consultor administrador de pendiente and Support to Targeted proyectos. Households Component 2. PSIP-71A-3CV-CI / (Act. Strengthening of the 2.3.1.3.4) Contratación de Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 26,313.93 0.00 2017-12-28 2018-01-02 2018-01-23 2018-02-27 2018-08-26 consultor administrador de pendiente and Support to Targeted proyectos. Households PSIP-035-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.1.1.2.2.5.5) Honorarios IBRD / 84790 Equity and Results- Posterior Individual Limited 276,105.50 0.00 2018-01-10 2018-01-15 2018-02-05 2018-03-12 2018-09-08 pendiente personal revisores orientation Page 10 PSIP-036-3CV-CI / Component 3. Enhancing (Act.3.1.1.2.2.5.6) Honorarios Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 1,336.24 0.00 2018-01-10 2018-01-15 2018-02-05 2018-03-12 2018-09-08 Personal Encargado pendiente orientation Supervisores PSIP-037-3CV-CI / (Act. Component 3. Enhancing 3.1.1.2.2.5.7) Personal de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 54,239.17 0.00 2018-01-10 2018-01-15 2018-02-05 2018-03-12 2018-09-08 Apoyo Administrativo y pendiente orientation Tecnico del 3ESH PSIP-129-3CV-CI / (Act. 3.2.2.3.4) Consultoria Component 3. Enhancing Individual para la Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 34,494.48 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 Optimización el Sistema pendiente orientation Informático del Módulo Operativo del SIME PSIP-228-3CV-CI / (Act. 3.2.3.1.2) Consultoria individual No.2 para el Component 3. Enhancing diseño gráfico de elementos Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 15,383.74 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 contenidos en actividades pendiente orientation del Observatorio de Políticas Sociales, así como manejo de las redes sociales PSIP-230-3CV-CI / (Act.3.2.3.3.1) Consultoría individual No.1 Cualitativa: Component 3. Enhancing nacional para la Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 24,007.54 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 implementación y pendiente orientation funcionamiento del Observatorio de Políticas Sociales. PSIP-229-3CV-CI / (Act.3.2.3.3.2) Consultoría individual No.2 Component 3. Enhancing Cuantitativa: nacional para Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 23,573.38 0.00 2016-08-22 2016-10-10 2016-10-31 2016-12-05 2017-06-03 la implementación y pendiente orientation funcionamiento del Observatorio de Políticas Sociales. PSIP-028-3CV-CI / (Act. 3.3.6.1) Analista documental Component 3. Enhancing Ejecución para implementación del IBRD / 84790 Equity and Results- Posterior Individual Limited 10,275.82 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 pendiente centro de documentación de orientation políticas sociales PSIP-001-3CV-CI / (Act. 3.3.9.13) Creacion de Metodologia e Instrumentos Component 3. Enhancing de Actuacion de las IBRD / 84790 Equity and Results- Posterior Individual Open 39,659.89 38,907.52 Firmado 2018-07-30 2018-09-17 2018-10-08 2018-11-12 2019-05-11 Acciones de Innovacion orientation Institucional del Programa de Prevencion PSIP-198-CD-CI / (Act. Component 3. Enhancing Selección directa Ejecución 3.4.1.2) Especialista en IBRD / 84790 Equity and Results- Previa Direct 80,256.30 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 de consultores pendiente Adquisiciones orientation PSIP-207-CD-CI / (Act. Component 3. Enhancing 3.4.1.4) Analista de Registro Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 45,959.31 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 y Reportes del Proyecto pendiente orientation (Contador) PSIP-222-3V-CI / Component 3. Enhancing Ejecución (Act.3.4.1.5) Asistente IBRD / 84790 Equity and Results- Posterior Individual Limited 32,000.00 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 pendiente Financiero del Proyecto orientation PSIP-235-3V-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.6) Analista IBRD / 84790 Equity and Results- Previa Individual Limited 20,712.65 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 pendiente Adquisiciones 2 orientation Component 3. Enhancing PSIP-202-CD-CI / (Act. Selección directa Ejecución IBRD / 84790 Equity and Results- Posterior Direct 8,057.00 0.00 2017-01-01 2017-01-11 2017-03-17 2017-09-13 3.4.1.9) Conserje de consultores pendiente orientation PSIP-160-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.10) Asistente IBRD / 84790 Equity and Results- Posterior Individual Limited 24,968.77 0.00 2017-01-01 2017-01-06 2017-01-27 2017-03-03 2017-08-30 pendiente Adquisiciones orientation Component 3. Enhancing PSIP-203-CD-CI / (Act. Selección directa Ejecución IBRD / 84790 Equity and Results- Posterior Direct 6,181.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 3.4.1.11) Mensajeria de consultores pendiente orientation Component 3. Enhancing PSIP-306-3CV-CI / (Act. Selección directa Ejecución IBRD / 84790 Equity and Results- Posterior Direct 21,043.00 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 3.4.1.14) Chofer UTP de consultores pendiente orientation Component 3. Enhancing PSIP-209-3CV-CI / (Act. Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 96,673.37 0.00 2017-06-07 2017-06-12 2017-07-03 2017-08-07 2018-02-03 3.4.1.16) Enlace Operativo pendiente orientation PSIP-011-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.19) Analista de IBRD / 84790 Equity and Results- Posterior Individual Limited 13,268.75 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contratos 1 orientation PSIP-012-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.21) Auxiliar de Gestion IBRD / 84790 Equity and Results- Posterior Individual Limited 6,697.70 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente de contratos orientation PSIP-0001-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.1) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,592.72 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 1 orientation PSIP-0002-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.2) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,592.72 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 2 orientation PSIP-003-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.3) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 3 orientation PSIP-004-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.4) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 4 orientation PSIP-005-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.5) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 5 orientation Page 11 PSIP-006-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.23.6) Auxiliar IBRD / 84790 Equity and Results- Posterior Individual Limited 6,077.82 0.00 2018-01-01 2018-01-06 2018-01-27 2018-03-03 2018-08-30 pendiente Contable 6 orientation PSIP-007-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.24) Asistente Tecnico IBRD / 84790 Equity and Results- Posterior Individual Open 11,825.55 0.00 2018-03-01 2018-04-19 2018-05-10 2018-06-14 2018-12-11 pendiente (a) Coordinador de Enlace orientation PSIP-0009-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.26) Auxiliar de IBRD / 84790 Equity and Results- Posterior Individual Limited 7,961.25 0.00 2018-01-08 2018-01-13 2018-02-03 2018-03-10 2018-09-06 pendiente Adquisiciones orientation DO-GCPS-77507-CS-INDV / Component 2. (Act. 2.1.4.1) Desarrollo e Strengthening of the Implementación del sistema Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 9,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 de seguimiento de comités pendiente and Support to Targeted Municipales y Regionales Households (desarrollo informático) DO-GCPS-102454-CS-CDS / Contratación del personal de campo (pago de ficha a Component 3. Enhancing Ejecución Entrevistadores y IBRD / 84790 Equity and Results- Previa Individual Direct 779,377.20 0.00 2019-02-21 2019-03-03 2019-03-24 2019-04-28 2019-10-25 pendiente Supervisores) de la orientation continuidad del Levantamiento del 3ESH PSIP-7-3CV-CI / (Act. Component 1. Integrated 1.2.1.2.2) Encargados Area-Based Social Ejecución Regionales de Apoyo a la IBRD / 84790 Posterior Individual Open 36,283.55 0.00 2017-01-06 2017-02-24 2017-03-17 2017-04-21 2017-10-18 Protection and Pro-poor pendiente a Unidad de Infr. Social (6 Service Delivery Encargados Regionales) PSIP-581-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo para Strengthening of the Ejecución el apoyo tecnico a la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 15,736.00 0.00 2018-01-23 2018-01-28 2018-02-18 2018-03-25 2018-09-21 pendiente implementación de los and Support to Targeted Reportes Comunitarios Households Regional El Valle, Enriquillo PSIP-582-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo para Strengthening of the el apoyo tecnico a la Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 15,735.00 0.00 2018-02-15 2018-04-05 2018-04-26 2018-05-31 2018-11-27 implementación de los pendiente and Support to Targeted Reportes Comunitarios Households Regional Noroeste, Norcentral PSIP-583-3CV-CI / (Act. 2.2.3.3) Contratación Component 2. consultores de Campo para Strengthening of the Ejecución el apoyo tecnico a la IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 16,863.00 0.00 2018-09-10 2018-09-15 2018-10-06 2018-11-10 2019-05-09 pendiente implementación de los and Support to Targeted Reportes Comunitarios Households Regional Este, Valdesia Component 3. Enhancing PSIP-2091-3CV-CI / (Act. Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 47,095.00 0.00 2018-06-01 2018-06-06 2018-06-27 2018-08-01 2019-01-28 3.4.1.16) Enlace Operativo pendiente orientation PSIP-021-3CV-CI / (Act. 3.3.8.1) Component 3. Enhancing Ejecución Consultora/Encargada del IBRD / 84790 Equity and Results- Posterior Individual Direct 23,044.02 0.00 2017-06-07 2017-06-17 2017-07-08 2017-08-12 2018-02-08 pendiente Area de Documentación de orientation PROSOLI PSIP-240-CD-CI / Component 3. Enhancing Selección directa Ejecución (Act.3.4.1.12) Asistente IBRD / 84790 Equity and Results- Posterior Direct 42,406.22 0.00 2017-06-07 2017-06-17 2017-08-21 2018-02-17 de consultores pendiente Administrativo orientation DO-GCPS-80704-CS-QCBS / Component 1. Integrated (Act. 1.2.2.2) Supervisión Area-Based Social Ejecución de la rehabilitación de IBRD / 84790 Posterior Individual Open 50,198.01 0.00 2019-02-03 2019-03-24 2019-04-14 2019-05-19 2019-11-15 Protection and Pro-poor pendiente viviendas, cambio de piso Service Delivery de tierra por cemento PSIP-1601-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.10) Asistente IBRD / 84790 Equity and Results- Posterior Individual Limited 16,900.00 0.00 2018-05-14 2018-05-19 2018-06-09 2018-07-14 2019-01-10 pendiente Adquisiciones orientation PSIP-2071-3CV-CI / (Act. Component 3. Enhancing 3.4.1.4) Analista de Registro Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 32,772.00 0.00 2018-03-12 2018-03-17 2018-04-07 2018-05-12 2018-11-08 y Reportes del Proyecto pendiente orientation (Contador) PSIP-1981-3CV-CI / (Act. Component 3. Enhancing Ejecución 3.4.1.2) Especialista en IBRD / 84790 Equity and Results- Posterior Individual Limited 39,303.00 0.00 2018-04-16 2018-04-21 2018-05-12 2018-06-16 2018-12-13 pendiente Adquisiciones orientation DO-GCPS-78985-CS-INDV / (Act. 3.3.6.2) Gestor de Proyectos Sociales. Component 3. Enhancing Ejecución Asistencias técnicas a ser IBRD / 84790 Equity and Results- Posterior Individual Open 20,800.00 0.00 2018-11-21 2019-01-09 2019-01-30 2019-03-06 2019-09-02 pendiente identificadas para la orientation innovación y creación de nuevas políticas publicas. PSIP-0221-3CV-CI / (Act. 2.2.2.1.1) Consultoria Indvidual para el Apoyo Component 2. técnico a la coordinación de Strengthening of the Ejecución Actividades de la Dirección IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 22,728.00 0.00 2018-10-23 2018-10-28 2018-11-18 2018-12-23 2019-06-21 pendiente de Vinculación and Support to Targeted Interinstitucional en el Households marco del Proyecto Progresando Unidos PSIP-2281-3CV-CI / (Act. 3.2.3.1.2) Consultoria individual No.2 para el Component 3. Enhancing diseño gráfico de elementos Ejecución IBRD / 84790 Equity and Results- Posterior Individual Limited 30,428.00 0.00 2017-07-24 2017-07-29 2017-08-19 2017-09-23 2018-03-22 contenidos en actividades pendiente orientation del Observatorio de Políticas Sociales, así como manejo de las redes sociales DO-GCPS-789851-CS-INDV / (Act. 3.3.6.2) Especialista para el Analisis y Formulacion de Politicas Component 3. Enhancing Ejecución Publicas en el Sector Social. IBRD / 84790 Equity and Results- Posterior Individual Open 28,600.00 0.00 2018-11-21 2019-01-09 2019-01-30 2019-03-06 2019-09-02 pendiente Asistencias técnicas a ser orientation identificadas para la innovación y creación de nuevas políticas publicas. Page 12 DO-GCPS-104161-CS-INDV / (Act. 3.2.1.3.3.1) Asistente de Investigación para el Component 3. Enhancing Diseño e Implementación de Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 29,150.00 0.00 2019-03-29 2019-05-02 2019-05-12 2019-06-07 2019-12-04 la Evaluación de Impacto pendiente orientation del subcomponente 1.3 (Capacitación) del Proyecto Progresando Unidos DO-GCPS-104165-CS-INDV / (Act. 3.2.1.2.4.1) Asistente de Investigación para el diseño e Component 3. Enhancing Ejecución implementación de la IBRD / 84790 Equity and Results- Posterior Individual Open 29,150.00 0.00 2019-03-29 2019-05-02 2019-05-12 2019-06-07 2019-12-04 pendiente Evaluación de Impacto al orientation Subcomponente 1.2 (Mejora de Vivienda) del proyecto Progresando Unidos. DO-GCPS-104167-CS-INDV Component 2. / (Act. 2.2.1.3.2) Consultoría Strengthening of the Ejecución Ampliación del Alcance de IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 12,052.16 0.00 2019-03-29 2019-05-02 2019-05-12 2019-06-07 2019-12-04 pendiente la Plataforma de Educación and Support to Targeted Virtual. Households PSIP-13114-3CV-CI / (Act. 1.3.1.1.4) Apoyo Técnico Component 1. Integrated Operativo a PROSOLI para Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,833.00 0.00 2019-02-11 2019-03-20 2019-03-30 2019-04-25 2019-10-22 la implementación del Protection and Pro-poor pendiente proceso de Capacitación en Service Delivery la Regional Norcentral. PSIP-13115-3CV-CI / (Act. 1.3.1.1.5) Apoyo Técnico Component 1. Integrated Operativo a PROSOLI para Area-Based Social Ejecución la implementación del IBRD / 84790 Posterior Individual Open 15,833.00 0.00 2019-02-11 2019-03-20 2019-03-30 2019-04-25 2019-10-22 Protection and Pro-poor pendiente proceso de Capacitación en Service Delivery la Regional Distrito Nacional. PSIP-13116-3CV-CI / (Act.1.3.1.1.6) Apoyo Técnico Component 1. Integrated Operativo a PROSOLI para Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 15,833.00 0.00 2019-02-11 2019-03-20 2019-03-30 2019-04-25 2019-10-22 la implementación del Protection and Pro-poor pendiente proceso de Capacitación en Service Delivery la Regional Enriquillo. DO-GCPS-104832-CS-INDV Component 2. / (Act. 2.1.3.6.2) Strengthening of the Consultorías para Apoyo Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 10,000.00 0.00 2019-03-31 2019-04-14 2019-04-29 2019-05-25 2019-11-21 Técnico de Seguimiento a la pendiente and Support to Targeted Implementación del Cambio Households de Comportamiento DO-GCPS-104849-CS-INDV Component 3. Enhancing / (Act. IBRD / 84790 Equity and Results- Posterior Individual Limited 4,950.00 0.00 En ejecución 2019-03-31 2019-04-05 2019-04-26 2019-05-31 2019-11-27 3.2.1.2.4.3.3)contratación de orientation Chofer DO-GCPS-104851-CS-INDV / (Act. 3.2.1.3.3.2) Analista Junior para Gestión de la Component 3. Enhancing Ejecución Evaluación del impacto del IBRD / 84790 Equity and Results- Posterior Individual Open 20,900.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 pendiente Sub-componente 1.3 orientation (Capacitación) del Proyecto Progresando Unidos. DO-GCPS-104853-CS-INDV / (Act. 3.2.2.4.1) Consultoría Component 3. Enhancing Ejecución de apoyo y mantenimiento IBRD / 84790 Equity and Results- Posterior Individual Open 24,750.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 pendiente a la plataforma informática orientation del SIME DO-GCPS-104854-CS-INDV Component 3. Enhancing / (Act. 3.2.2.4.2) Analista de IBRD / 84790 Equity and Results- Posterior Individual Open 24,750.00 0.00 En ejecución 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 Monitoreo orientation DO-GCPS-104855-CS-INDV Component 3. Enhancing / (Act. 3.2.2.4.3) Gestora Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 22,000.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 Administrativa de Proyectos pendiente orientation Sociales DO-GCPS-104880-CS-INDV Component 3. Enhancing / (Act.3.2.5.1) Consultoría Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 27,500.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 para elaboración de Manual pendiente orientation Operativo DO-GCPS-104882-CS-INDV Component 3. Enhancing / (Act. 3.2.5.2) Consultoría Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 22,000.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 para elaboración de Agenda pendiente orientation Anual de Evaluación DO-GCPS-104883-CS-INDV / (Act. 3.2.5.3) Consultoría Component 3. Enhancing Ejecución de acompañamiento técnico IBRD / 84790 Equity and Results- Posterior Individual Open 20,900.00 0.00 2019-03-31 2019-05-04 2019-05-14 2019-06-09 2019-12-06 pendiente y gestión del Laboratorio de orientation Evidencias DO-GCPS-104900-CS-INDV / (Act. 3.3.6.3) Consultoria Individual de Auxiliar Component 3. Enhancing Ejecución Documental para el Centro IBRD / 84790 Equity and Results- Posterior Individual Limited 7,850.00 0.00 2019-03-08 2019-03-13 2019-04-03 2019-05-08 2019-11-04 pendiente de Documentacion y orientation Repositorio Institucional del GCPS DO-GCPS-105012-CS-INDV / (Act. 3.3.14) Consultoría Component 3. Enhancing Ejecución Seguimiento a la IBRD / 84790 Equity and Results- Posterior Individual Open 7,000.00 0.00 2019-04-30 2019-06-03 2019-06-13 2019-07-09 2020-01-05 pendiente Capacitación Cambio de orientation Comportamiento Senior DO-GCPS-105013-CS-INDV / (Act. 3.3.15) Consultorias Component 3. Enhancing Ejecución Seguimiento a la IBRD / 84790 Equity and Results- Posterior Individual Open 3,205.00 0.00 2019-04-30 2019-06-03 2019-06-13 2019-07-09 2020-01-05 pendiente Capacitación Cambio de orientation Comportamiento Junior. DO-GCPS-105387-CS-CDS / Component 2. (Act. 2.2.1.1.10) Realización Strengthening of the Selección directa Ejecución e Encuestas de Satisfacción IBRD / 84790 PROSOLI CCT Program Posterior Direct 4,900.00 0.00 2019-03-11 2019-03-19 2019-04-14 2019-05-14 de consultores pendiente de los Servicios de Punto and Support to Targeted Solidario. Households Page 13 DO-GCPS-109644-CS-CDS / (Act. 3.2.2.3.3.1) Consultoría Individual para Acompañar Component 3. Enhancing el Proceso de Selección directa IBRD / 84790 Equity and Results- Posterior Direct 45,000.00 0.00 En ejecución 2019-04-30 2019-05-10 2019-07-14 2020-01-10 Implementación da la 2da. de consultores orientation fase del Sistema Integrado de Monitoreo y Evaluación (SIME)". DO-GCPS-116966-CS-INDV / (Act. 2.1.3.7) Consultoría Individual Coordinador Component 2. Operativo para el Enlace de Strengthening of the Ejecución las operaciones del Proyecto IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 30,000.00 0.00 2019-05-31 2019-06-05 2019-06-26 2019-07-31 2020-01-27 pendiente Progresando Unidos, and Support to Targeted Provincias Independencia, Households Barahona, Pedernales y Bahoruco. DO-GCPS-117428-CS-INDV / (Act. 3.3.2.9.3) Consultoría Component 3. Enhancing Individual de Monitoreo y Ejecución IBRD / 84790 Equity and Results- Posterior Individual Open 30,000.00 0.00 2019-05-31 2019-07-19 2019-08-09 2019-09-13 2020-03-11 Evaluación de las Clases de pendiente orientation Competencia Comunicativa de Español a Inmigrantes DO-GCPS-118056-CS-INDV / (Act. 3.3.2.4.1) Analista para la Coordinación, Component 3. Enhancing monitoreo y seguimiento a IBRD / 84790 Equity and Results- Posterior Individual Open 25,000.00 0.00 En ejecución 2019-07-31 2019-09-18 2019-10-09 2019-11-13 2020-05-11 la implementación del Plan orientation de Reducción de Embarazos en adolescentes. DO-GCPS-119438-CS-INDV / (Act. 2.1.2.2.1) Consultoría para Diseño, Component 2. Revisión y Diagramación de Strengthening of the Manuales para la creación IBRD / 84790 PROSOLI CCT Program Posterior Individual Limited 18,000.00 0.00 En ejecución 2019-07-01 2019-07-06 2019-07-27 2019-08-31 2020-02-27 de los comités y and Support to Targeted capacitación de la estrategia Households Progresando Unidos y del Funcionamiento de los Comités. DO-GCPS-104843-CS-INDV / (Act. 3.2.1.2.4.2) Analista Junior para Component 3. Enhancing Ejecución Gestión de la Evaluación IBRD / 84790 Equity and Results- Posterior Individual Open 17,100.00 0.00 2019-07-31 2019-09-03 2019-09-13 2019-10-09 2020-04-06 pendiente del Impacto al Sub- orientation Componete 1.2 (Mejora de Vivienda) del Proyecto Progresando Unidos DO-GCPS-121826-CS-INDV / (Act. 3.2.1.2.4.3.5) Monitores Locales para la Component 3. Enhancing Evaluación de impacto del IBRD / 84790 Equity and Results- Posterior Individual Limited 20,900.00 0.00 En ejecución 2019-07-31 2019-08-05 2019-08-26 2019-09-30 2020-03-28 Subcomponente de Mejora orientation de Vivienda del Proyecto Progresando Unidos DO-GCPS-121835-CS-INDV / (Act. 2.2.3.3) Consultoría de Campo para el Apoyo Component 2. Técnico y Operativo a la Strengthening of the Implementación de los Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 16,800.00 0.00 2019-07-31 2019-09-18 2019-10-09 2019-11-13 2020-05-11 Reportes Comunitarios en el pendiente and Support to Targeted PROSOLI, Regionales Households Noroeste y Norcentral (Provincias Santiago y Monte cristi) DO-GCPS-77490-CS-INDV / Component 2. (Act. 2.1.3.1.1) Consultoría Strengthening of the individual de un Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 53,000.00 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 Coordinador Operativo para pendiente and Support to Targeted el enlace de las operaciones Households de Progresando Unido DO-GCPS-78768-CS-INDV / Component 2. (Act. 2.2.2.2.2) Analista Strengthening of the Ejecución para aplicación de Minería IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 12,382.56 0.00 2019-07-31 2019-09-18 2019-10-09 2019-11-13 2020-05-11 pendiente de Datos y Comunicación and Support to Targeted Social de Reportes Households Comunitarios DO-GCPS-77488-CS-INDV / Component 2. (Act. 2.1.1.1) Diseño del Strengthening of the instrumento del Ejecución IBRD / 84790 PROSOLI CCT Program Posterior Individual Open 14,782.44 0.00 2018-09-28 2018-11-16 2018-12-07 2019-01-11 2019-07-10 levantamiento de la oferta pendiente and Support to Targeted de servicios y compilación Households de la información. DO-GCPS-80911-CS-INDV / (Act. 3.2.1.3.3) Levantamiento de Linea de Component 3. Enhancing Base para la Evaluación IBRD / 84790 Equity and Results- Posterior Individual Open 100,000.00 0.00 Cancelado 2018-10-30 2018-12-18 2019-01-08 2019-02-12 2019-08-11 del impacto de la estrategia orientation territorial integral del proyecto. DO-GCPS-128164-CS-INDV Component 1. Integrated / (Act. 1.2.2.2) Lote 31, Area-Based Social Ejecución Fase IV "Supervisión de IBRD / 84790 Posterior Individual Open 12,996.69 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 Protection and Pro-poor pendiente pisos de tierra por pisos de Service Delivery cemento", Provincia: Azua DO-GCPS-128165-CS-INDV / (Act. 1.2.2.2) Lote 32, Component 1. Integrated Fase IV "Supervisión de Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 12,880.45 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 pisos de tierra por pisos de Protection and Pro-poor pendiente cemento", Provincia: San Service Delivery Juan de la Maguana DO-GCPS-128167-CS-INDV / (Act. 1.2.2.2) Lote 33, Component 1. Integrated Fase IV "Supervisión de Area-Based Social Ejecución IBRD / 84790 Posterior Individual Open 13,623.15 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 pisos de tierra por pisos de Protection and Pro-poor pendiente cemento", Provincia: Elias Service Delivery piña DO-GCPS-128168-CS-INDV / (Act. 3.2.3.6.1) CI- Acompañamiento técnico en Component 3. Enhancing Ejecución la actualización del Plan IBRD / 84790 Equity and Results- Posterior Individual Open 20,000.00 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 pendiente Estratégico Sectorial para la orientation Inclusión Social y Económica (PEISE) Page 14