Procurement Plan (P 155350) Sindh Resilience Project I. General 1. Bank’s approval Date of the procurement Plan [Original: February 28, 2016]: Revision of Updated Procurement Plan, May 2017 ] 2. Date of General Procurement Notice: August 2016 3. Period covered by this procurement plan: The procurement period of project covered from year May 2017 to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project issued by SID 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce July 9, 2010 (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that July 9, 2010 will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Pakistan : Sindh Resilience Project PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2016-11-03 2019-08-23 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155350 GPN Date: 2016-10-28 Project Name: Sindh Resilience Project Loan / Credit No: IDA / 58880 Executing Agency(ies): Sindh Irrigation Department WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-SID-2961-CW-RFP / Providing stone pitching between BU Bund from mile 13/3 to 35/3 and indo bund Improving Infrastructure Open - Single Stage - One IDA / 58880 Prior Request for Bids 5,024,100.36 Signed 2016-11-25 2016-12-09 2017-01-23 2017-02-22 2017-04-07 2017-10-04 from mile 0/0 to 15/6 total and Systems for Resilience International Envelope 15 miles and 7 furlongs in Sakro Division Mirpursakro. (Baghar Circle Hyderabad). PK-SID-2963-CW-RFP / CONSTRUCTION OF BHANSAR Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 2018-01-08 SMALL/RECHARGE DAM and Systems for Resilience Envelope IN NAGARPARKAR AREA (THAR REGION) PK-SID-2964-CW-RFP / CONSTRUCTION OF SABUSAN Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 2018-01-08 SMALL/RECHARGE DAM and Systems for Resilience Envelope IN NAGARPARKAR AREA (THAR REGION) PK-SID-2965-CW-RFP / CONSTRUCTION OF SANKAR Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-03-01 2017-03-16 2017-04-27 2017-05-29 2017-07-12 2018-01-08 SMALL/RECHARGE DAM and Systems for Resilience Envelope IN NAGARPARKAR AREA (THAR REGION) PK-SID-2967-CW-RFP / CONSTRUCTION OF Improving Infrastructure Single Stage - One KONKAR IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-16 2017-09-27 2017-10-27 2017-12-08 2018-06-06 and Systems for Resilience Envelope RECHARGE/SMALL DAM IN LOWER KOHISTAN PK-SID-2968-CW-RFP / CONSTRUCTION OF Improving Infrastructure Single Stage - One KARMATIANI IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2017-08-01 2017-08-16 2017-09-27 2017-10-27 2017-12-08 2018-06-06 and Systems for Resilience Envelope RECHARGE/SMALL DAM IN LOWER KOHISTAN PK-SID-2960-CW-RFP / Recoupment of stone Apron along S.H Bund mile 1/6 to 2/1 and Repair to damage stone pitching along S.H Bund mile 1/0 to 3/0 Improving Infrastructure Single Stage - One IDA / 58880 Prior Request for Bids Open - National 1,042,222.84 Signed 2017-01-21 2017-01-26 2017-03-09 2017-04-08 2017-05-13 2017-11-09 (Different Reaches) and and Systems for Resilience Envelope widening of S.H Bund from mile 0/4 to 3/2 in Kalri Baghar Division Thatta.(Baghar Circle Hyderabad). Page 1 PK-SID-2962-CW-RFP / Stone pitching and Toe Wall along M.S Bund mile 29/2 to 29/5, 36/0 to 40/0, 45/0 to 58/2, Raising and Improving Infrastructure Single Stage - One IDA / 58880 Prior Request for Bids Open - National 0.00 Canceled 2017-01-21 2017-01-26 2017-03-09 2017-04-08 2017-05-13 2017-11-09 strengthening along M.S and Systems for Resilience Envelope Bund mile 55/4 to 58/2 in Lower Pinyari Division Sujawal. (Pinyari Circle Hyderabad). PK-SID-20260-CW-RFB / Providing Stone Pitching along M.S Bund mile 29/2 Under Improving Infrastructure Single Stage - One to 29/5, 36/0 to 40/0 to 58/2 IDA / 58880 Post Request for Bids Open - National 3,557,787.46 Implementati 2017-07-21 2017-07-21 2017-08-21 2017-08-28 2017-10-02 2018-03-31 and Systems for Resilience Envelope and Raising and on Strengthening of M.S Bund mile 55/4 to 58/2. PK-SID-29036-CW-RFB / Providing Stone Pitching along PB Bund from mile Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 4,106,231.10 Signed 2017-09-19 2017-09-22 2017-10-23 2017-10-30 2017-11-06 2018-11-05 0/0 to 8/5 and 11/4 to 15/0 and Systems for Resilience Envelope in Kalri Baghar Division Thatta. PK-SID-29042-CW-RFB / Earthwork & Repair Damaged Stone Pitching Improving Infrastructure Single Stage - One along up Stream left side IDA / 58880 Post Request for Bids Open - National 791,521.35 Completed 2017-09-19 2017-09-22 2017-10-23 2017-10-30 2017-11-06 2018-11-05 and Systems for Resilience Envelope guide bund from RD 0+000 to RD 5+700 in Kotri Barrage Division Jamshoro. PK-SID-29051-CW-RFB / Providing Stone Pitching along MS Bund from mile Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 5,527,355.70 Signed 2017-09-19 2017-09-22 2017-10-23 2017-10-30 2017-11-06 2018-11-05 0/0 to 14/0 and 22/0 to 24/7 and Systems for Resilience Envelope in Upper Pinyari Division, Hyderabad PK-SID-29055-CW-RFB / Providing Stone Pitching Improving Infrastructure Single Stage - One along BU Bund from mile IDA / 58880 Post Request for Bids Open - National 969,963.22 Signed 2017-09-19 2017-09-22 2017-10-23 2017-10-30 2017-11-06 2018-11-05 and Systems for Resilience Envelope 3/0 to 5/0 in Kalri Baghar Division Thatta. PK-SID-29086-CW-RFB / Providing Stone Pitching along Kuka Link Bund 0/0 to 20/6, Raising and Strengthening along Kuka Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 4,924,242.94 Signed 2017-09-19 2017-09-22 2017-10-23 2017-10-30 2017-11-06 2018-11-05 Wari Bund mile 3/6 to7/4 and Systems for Resilience Envelope and Kuka Wari Retarded Bund mile 0/0 to 3/0 in Lower Pinyari Division Sujawal. PK-SID-37707-CW-RFB / Recoupment of Damaged Stone Pitching & Earth Work along SM Bund from Improving Infrastructure Single Stage - One mile 123/0 to 172/0 IDA / 58880 Post Request for Bids Open - National 0.00 Canceled 2018-01-16 2018-01-19 2018-02-21 2018-03-07 2018-04-11 2019-04-10 and Systems for Resilience Envelope (Different Reaches) in Hala Irrigation Division Hala. (95 percent from counterpart funding). PK-SID-69711-CW-RFB / Construction of 2Nos: Small/Recharge Dams in Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 3,533,285.00 Signed 2018-07-16 2018-07-19 2018-08-20 2018-09-19 2018-11-02 2019-11-01 Lower Khoistan Malir and Systems for Resilience Envelope namely Karmatiani and Konkar. Page 2 PK-SID-2969-CW-RFP / CONSTRUCTION OF Improving Infrastructure Single Stage - One ARIPIR RECHARGE/SMALL IDA / 58880 Post Request for Bids Open - National 1,925,753.61 Signed 2018-07-16 2018-07-19 2018-08-20 2018-09-19 2018-11-02 2019-11-01 and Systems for Resilience Envelope DAM IN LOWER KOHISTAN. PK-SID-2966-CW-RFP / CONSTRUCTION OF JUNG Improving Infrastructure Single Stage - One SHAHI RECHARGE/SMALL IDA / 58880 Post Request for Bids Open - National 2,722,112.20 Signed 2018-07-16 2018-07-19 2018-08-20 2018-09-19 2018-11-02 2019-11-01 and Systems for Resilience Envelope DAM IN LOWER KOHISTAN PK-SID-69710-CW-RFB / Construction of 2Nos: Improving Infrastructure Open - Single Stage - One Small/Recharge Dams in IDA / 58880 Post Request for Bids 6,481,286.34 Signed 2018-07-16 2018-07-19 2018-09-03 2018-10-03 2018-11-16 2019-11-15 and Systems for Resilience International Envelope Tharparkar namely Sabusan and Sankar. PK-SID-83933-CW-RFB / Recoupment of Damaged Stone Pitching & Earth Work along SM Bund from mile 123/0 to 172/0 Under Improving Infrastructure Single Stage - One (Different Reaches) in Hala IDA / 58880 Post Request for Bids Open - National 0.00 Implementati 2018-10-29 2018-11-01 2018-12-03 2019-01-02 2019-01-30 2019-10-27 and Systems for Resilience Envelope Irrigation Division Hala. on (100 percent payment will be made counterpart funding through Government of Sindh). PK-SID-93082-CW-RFB / Under Package No: 14 Construction Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 2,950,660.01 Implementati 2018-12-28 2018-12-31 2019-01-30 2019-03-01 2019-03-29 2020-03-27 of Bhansar/ Rathi Small and Systems for Resilience Envelope on storage Dam. PK-SID-93083-CW-RFB / Package No: 15 Lot No. 1 Construction of Naing-II Improving Infrastructure Single Stage - One Small/Recharge Dam. IDA / 58880 Post Request for Bids Open - National 6,109,757.41 Signed 2018-12-28 2018-12-31 2019-01-30 2019-03-01 2019-03-29 2020-03-27 and Systems for Resilience Envelope Lot No. 2 Construction of Gabol and Dhal Dhoro-II Small/Recharge Dams. PK-SID-93084-CW-RFB / Package No: 16 Lot No. 1 Construction of Tikho-II and Sureshi Small/Recharge Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 5,020,897.80 Signed 2018-12-28 2018-12-31 2019-01-30 2019-03-01 2019-03-29 2020-03-27 Dams. and Systems for Resilience Envelope Lot No. 2 Construction of Upper Mole-II Small/Recharge Dam. PK-SID-93086-CW-RFB / Under Package No: 17 Construction Improving Infrastructure Single Stage - One IDA / 58880 Post Request for Bids Open - National 0.00 Implementati 2018-12-28 2018-12-31 2019-01-30 2019-03-01 2019-03-29 2020-03-27 of Nali and Qasim Tok and Systems for Resilience Envelope on Small/Recharge Dams. PK-SID-119972-CW-RFB / Package-I: Construction and Under Improving Infrastructure Single Stage - One Rehabilitation of Laboratory IDA / 58880 Post Request for Bids Open - National 0.00 Implementati 2019-06-21 2019-06-24 2019-07-24 2019-08-23 2019-10-11 2020-07-07 and Systems for Resilience Envelope Building and Trays. on 1 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3 PK-SID-2980-GO-RFQ / Improving Infrastructure Request for Single Stage - One IDA / 58880 Prior Open - National 415,398.59 Completed 2016-11-12 2017-01-07 2017-07-06 Vehciles and Systems for Resilience Quotations Envelope PK-SID-2979-GO-RFQ / Improving Infrastructure Request for Single Stage - One IDA / 58880 Post Open - National 47,647.27 Completed 2016-11-11 2017-01-06 2017-07-05 Office Furniture and Systems for Resilience Quotations Envelope PK-SID-4707-GO-RFQ / Improving Infrastructure Request for Single Stage - One IDA / 58880 Post Open - National 39,507.07 Completed 2016-12-24 2017-02-18 2017-08-17 Office Equipment and Systems for Resilience Quotations Envelope PK-SID-2978-GO-RFB / Improving Infrastructure Request for Single Stage - One IDA / 58880 Post Open - National 0.00 Canceled 2016-11-11 2017-01-06 2017-07-05 Office Equipment and Systems for Resilience Quotations Envelope PK-SID-15281-GO-RFQ / Improving Infrastructure Request for Single Stage - One Purchase of Motorcycles upto IDA / 58880 Post Open - National 1,206.08 Completed 2017-05-19 2017-06-12 2017-07-27 and Systems for Resilience Quotations Envelope 70cc PK-SID-15303-GO-RFQ / Improving Infrastructure Request for Single Stage - One Purchasing of stabilizer of IDA / 58880 Post Open - National 1,744.00 Completed 2017-05-19 2017-06-12 2017-07-27 and Systems for Resilience Quotations Envelope 11 Nos: for office use PK-SID-16582-GO-RFQ / Supply, Installation Testing Improving Infrastructure Request for Single Stage - One IDA / 58880 Post Open - National 12,561.52 Completed 2017-06-02 2017-06-26 2017-08-10 and Commissioning Diesel and Systems for Resilience Quotations Envelope Generator 30 to 37 KVA. PK-SID-21212-GO-RFQ / Improving Infrastructure Request for Single Stage - One IDA / 58880 Post Open - National 17,121.64 Completed 2017-07-20 2017-08-14 2017-09-28 Video Conference System and Systems for Resilience Quotations Envelope PK-SID-27863-GO-RFQ / Work Station, Chairs, Fixtures and partitions in prayer area. 1. Work Stations 08 Nos. Improving Infrastructure Request for Single Stage - One IDA / 58880 Post Open - National 7,528.57 Completed 2017-09-08 2017-10-12 2017-12-11 2. Hydraulic Chairs and Systems for Resilience Quotations Envelope 08 Nos. 3. Aluminum Door with Glass 01 No. 4. Fixture/Partitions 01 No. PK-SID-92972-GO-RFQ / Improving Infrastructure Request for Single Stage - One Procurement of 2Nos: IDA / 58880 Post Open - National 994.49 Signed 2019-01-04 2019-01-14 2019-04-14 and Systems for Resilience Quotations Envelope Motorcycles for Office use. PK-SID-118848-GO-RFB / Under Improving Infrastructure Single Stage - One Hydraulic Laboratory IDA / 58880 Post Request for Bids Open - National 0.00 Implementati 2019-06-20 2019-06-27 2019-07-29 2019-08-28 2019-09-30 2020-03-28 and Systems for Resilience Envelope Equipment. on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Under PK-SID-122451-NC-RFQ / Improving Infrastructure Request for Single Stage - One IDA / 58880 Post Open - National 0.00 Implementati 2019-07-12 2019-08-02 2020-01-29 Digitization of Data and Systems for Resilience Quotations Envelope on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 PK-SID-2955-CS-QCBS / Procurement of Project Improving Infrastructure Quality And Cost- Open - Implementation Support and IDA / 58880 Prior 3,381,604.10 Signed 2016-11-03 2016-11-03 2016-12-17 2017-01-14 2017-02-13 2017-03-20 2017-04-24 2018-04-24 and Systems for Resilience Based Selection International Supervision Consultant (PISSC) PK-SID-38659-CS-CQS / Consultant Organizational Capacity Improving Infrastructure IDA / 58880 Post Qualification Open - National 244,301.97 Signed 2017-12-04 2017-12-19 2018-02-20 2018-03-23 2018-05-04 2018-10-31 Assessment of Sindh and Systems for Resilience Selection Irrigation Department. PK-SID-38661-CS-CQS / Consultant Improving Infrastructure Third Party Monitoring and IDA / 58880 Post Qualification Open - National 348,297.30 Signed 2017-12-04 2017-12-19 2018-02-20 2018-03-23 2018-05-04 2021-05-03 and Systems for Resilience Validation. Selection PK-SID-56147-CS-QCBS / River Morphological Study, Flood Hazard Mapping and Improving Infrastructure Quality And Cost- Open - Under IDA / 58880 Prior 0.00 2018-03-30 2018-04-06 2018-06-04 2018-07-04 2018-08-03 2018-08-24 2018-09-21 2020-03-14 Establishment of Decision and Systems for Resilience Based Selection International Implementation Support System for Sindh Province PK-SID-61859-CS-QCBS / Feasibility Study of 30 Nos: Improving Infrastructure Quality And Cost- Open - of Small Dams in Water IDA / 58880 Prior 0.00 Under Review 2018-05-08 2018-05-15 2018-07-12 2018-08-11 2018-09-10 2018-10-01 2018-10-29 2020-04-21 and Systems for Resilience Based Selection International Scarce Areas in Sindh Province. PK-SID-128479-CS-CQS / Consultant Hydro Metrological Hazard Improving Infrastructure Pending IDA / 58880 Post Qualification Open - National 0.00 2019-08-22 2019-09-23 2019-11-08 2019-12-08 2020-01-13 2021-01-12 Assessment of Sindh and Systems for Resilience Implementation Selection Province. PK-SID-128488-CS-CQS / Consultant Performance Evaluation of Improving Infrastructure Pending IDA / 58880 Post Qualification Open - National 0.00 2019-08-22 2019-09-23 2019-11-08 2019-12-13 2020-01-20 2020-07-18 Small Dams in the Sindh and Systems for Resilience Implementation Selection Province. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Individual PK-SID-2970-CS-INDV / Improving Infrastructure IDA / 58880 Prior Consultant Open 56,401.20 Completed 2016-11-07 2016-12-27 2017-01-17 2017-02-21 2017-08-20 Finance Consultant and Systems for Resilience Selection Individual PK-SID-2972-CS-INDV / M Improving Infrastructure IDA / 58880 Post Consultant Open 86,017.49 Signed 2016-11-07 2016-12-27 2017-01-17 2017-02-21 2017-08-20 & E Consultant and Systems for Resilience Selection Individual PK-SID-2973-CS-INDV / Improving Infrastructure IDA / 58880 Post Consultant Open 100,204.53 Signed 2016-11-07 2016-12-27 2017-01-17 2017-02-21 2017-08-20 IT/GIS Consultant and Systems for Resilience Selection Individual PK-SID-2975-CS-INDV / Improving Infrastructure IDA / 58880 Post Consultant Open 31,148.43 Signed 2016-11-07 2016-12-27 2017-01-17 2017-02-21 2017-08-20 Quality Assurance Engineer and Systems for Resilience Selection Individual PK-SID-2976-CS-INDV / Improving Infrastructure IDA / 58880 Post Consultant Open 31,029.60 Terminated 2016-11-07 2016-12-27 2017-01-17 2017-02-21 2017-08-20 Environmental Consultant and Systems for Resilience Selection Individual PK-SID-2981-CS-INDV / Improving Infrastructure Under IDA / 58880 Post Consultant Open 101,778.62 2016-11-07 2016-12-27 2017-01-17 2017-02-21 2017-08-20 Social Safeguard Consulatnt and Systems for Resilience Implementation Selection Page 5 PK-SID-7391-CS-INDV / Individual Procurement & Contract Improving Infrastructure IDA / 58880 Prior Consultant Open 108,998.08 Signed 2017-02-15 2017-04-05 2017-04-26 2017-05-31 2018-05-31 Consultant (Individual and Systems for Resilience Selection Consultant) PK-SID-2971-CS-INDV / Individual Improving Infrastructure Procurement & Contract IDA / 58880 Prior Consultant Open 0.00 Canceled 2016-11-07 2016-12-27 2017-01-17 2017-02-21 2017-08-20 and Systems for Resilience Consultant Selection PK-SID-27831-CS-INDV / Individual Hiring of Environment Improving Infrastructure IDA / 58880 Post Consultant Open 96,560.19 Signed 2017-09-08 2017-10-02 2017-10-04 2017-10-06 2018-10-06 Consultant (Individual and Systems for Resilience Selection Consultant) Individual PK-SID-47074-CS-INDV / Improving Infrastructure IDA / 58880 Prior Consultant Open 101,711.37 Signed 2018-02-01 2018-02-01 2018-02-01 2018-02-01 2018-02-01 Finance Consultant and Systems for Resilience Selection Individual PK-SID-92998-CS-INDV / Improving Infrastructure IDA / 58880 Post Consultant Open 18,993.89 Signed 2019-01-01 2019-01-28 2019-02-04 2019-02-13 2020-02-12 Fiduciary Monitoring Analyst and Systems for Resilience Selection PK-SID-114445-CS-INDV / Individual The Hiring of Improving Infrastructure IDA / 58880 Post Consultant Open 22,755.05 Signed 2019-05-10 2019-07-01 2019-07-22 2019-08-26 2020-08-24 Electro/Hydraulic Individual and Systems for Resilience Selection Consultant. PK-SID-121794-CS-INDV / The Hiring of Individual Consultant for carrying out Individual the Social & Environment Improving Infrastructure Under IDA / 58880 Post Consultant Limited 0.00 2019-07-09 2019-07-09 2019-07-11 2019-07-12 2019-09-10 Impact Assessment of and Systems for Resilience Implementation Selection Constructed Small Dams in Sindh Province Under Irrigation Department. Page 6